PM CH5
PM CH5
• Additional concepts
• Learning curve theory states that when many items are produced
repetitively, the unit cost of those items decreases in a regular pattern as
more units are produced
• Reserves are dollars included in a cost estimate to mitigate cost risk by
allowing for future situations that are difficult to predict
• Contingency reserves allow for future situations that may be partially planned for
(sometimes called known unknowns) and are included in the project cost baseline
• Management reserves allow for future situations that are unpredictable (sometimes
called unknown unknowns)
Advice for Young Professionals
• The first step in project cost management is planning how the costs
will be managed throughout the life of the project
• The project team uses expert judgment, analytical techniques, and meetings
to develop the cost management plan
• Cost management plan includes:
• Level of accuracy
• Units of measure
• Organizational procedure links
• Control thresholds
• Rules of performance measurement
• Reporting formats
• Process descriptions
Estimating Costs (1 of 4)
Information 24 31 35 13 13 116
systems
Marketing 3 3 3 3 3 15
systems
Reservations 12 29 33 9 7 90
Contractors 2 3 1 0 0 6
Totals 41 66 72 25 23 227
Activity Week 1
Table 7-3 Earned value calculations for one activity after week 1
Earned Value Management (EVM) (3 of 5)
Term Formula
• Important concepts
• Cost variance (CV) is the earned value minus the actual cost
• Schedule variance (SV) is the earned value minus the planned value
• Cost performance index (CPI) is the ratio of earned value to actual cost
• Schedule performance index (SPI) is the ratio of earned value to planned
value
• Estimate at completion (EAC) is an estimated cost of completing a project
based on performance to date
• To-complete performance index (TCPI) is a measure of the cost performance
that must be achieved with the remaining resources to meet a specific goal
Earned Value Management (EVM) (5 of 5)
Global Issues (1 of 2)