IBS Note
IBS Note
The traditional construction method which is commonly practiced, where based on the client
brief, the architect will produce an architectural design, and pass it to the structural engineers.
After completing the structural design, the detail specification will be passed to the quantity
surveyor to produce costs and the bill of quantities. Later, these documents will be passed to
the main contractor who will then discuss the matter with the client and in the end take
responsibility for the construction (assembly) of the building structures. The shortcoming of
this method is, high in cost of construction, inability to meet the ever-increasing huge
housing demand within a short space of time, requires a large workforce (mostly unskilled)
and failed to produce acceptable quality construction products. In an attempt to address these
issues, the Construction Industry Development Board (CIDB) tries to encourage a paradigm
industrialization perspective. One of the efforts is to actively promote the adoption of the
process of social and economic change whereby a society is transformed from pre-industrial
to industrial state. It is part of a wider modernisation process through the gainful utilisation of
The term IBS is widely used by the practitioners, researchers and the government in most
countries to represent industrialization in construction. The term, however, cover a very wide
scope which includes the application of onsite systems and one cannot distinguish it properly
with conventional practice. While other terms used to represent construction industrialization
1
Board (CIDB) includes low-tech solutions and other practices which have already become
What is Industrialisation?
The International Council for Research and Innovation in Building and Construction (CIB) in
its latest report on industrialized construction linked industrialization with the use of
mechanical power and tools, the use of computerized steering system and tools, production in
operations are mechanized and are focused on mass production and mainly factory
Industrialized Building System (IBS). IBS is defined as, “An innovative process of building
the factory or onsite within controlled environments, it includes the logistic and
assembly aspect of it, done in proper coordination with thorough planning and
integration”.
It literally means that those parts of building that are repetitive but difficult, time consuming,
labour intense to cost at site are design and detailed as standardized components at factory.
2
construction. It is important to note that in this research, IBS involves onsite casting using
Objective of industrialisation
2. Improving quality
4. Cost efficiency.
Manufacturing (OSM), Offsite Production (OSP) and Offsite Construction (OSC). These
concepts are often used interchangeably when describing the characteristics of industrialized
construction. Nonetheless, regardless of the terms, the idea is the same which refers to
Categorization of Terminologies.
3
✓ Industrialized Building
IBS CLASSIFICATION
1) Frame System (pre-cast or steel): The framed structures are defined as those structures
that carry the loads through their beams and girders to columns and to the ground
2) Panellised System: In panel system, load are distributed through large floor and wall
panels.
3) Onsite fabrication
5) Block work system: Interlocking concrete masonry units (CMU), lightweight concrete
blocks.
6) Hybrid System
7) Volumetric and Modular System: The box systems include those systems that employ
three-dimensional modules (or boxes) for fabrication of habitable units are capable of
withstand load from various directions due to their internal stability.
4
Heavy weight panel (factory Concrete
produced)
Heavy weight panel (tilt up Concrete
produced on site)
3 Box system Medium weight box Wood frame, light gage metal,
(modules) (mobile) composite
1 Closed System
A closed system can be classified into two categories, namely production based on client’s
design and production based on precaster’s design. The first category is designed to meet a
spatial requirement of the client, that is the spaces required for various functions in the
building as well as the specific architectural design. In this instance, the client’s needs are
paramount and the precaster is always forced to produce a specific component for a building.
On the other hand, the production based on precaster’s design includes designing and
producing a uniform type of building or a group of building variants, which can be produced
with a common assortments of component. Such building includes school, parking garage,
gas station, low cost housing, etc. Nevertheless these types of building arrangement can be
a) The size of project is large enough to allow for distribution of design and production costs
over the extra cost per component incurred due to the specific design.
5
b) The architectural design observes large repetitive element and standardisation. In respect
to this, a novel prefabrication system can overcome the requirement of many standardised
c) There is a sufficient demand for a typical type of building such as school so that a mass
d) There is an intensive marketing strategy by precaster to enlighten the clients and designer
on the potential benefit of the system in term of economics and noneconomic aspects.
2 Open System
In view of the limitations inherent in the closed system, an open system which allows greater
flexibility of design and maximum coordination between the designer and precaster has been
proposed. This system is plausible because it allow the precaster to produce a limited number
of elements with a predetermined range of product and at the same time maintaining
architectural aesthetic value. In spite of many advantages inherent in an open system, its
adoption experiences one major setback. For example, joint and connection problem occur
when two elements from different system are fixed together. This is because similar
3 Modular Coordination
Modular co-ordination is a co-ordinated unified system for dimensioning spaces,
components, fitting, etc. so that all elements fit together without cutting or extending even
a) to create a basis upon which the variety of types and sizes of building components can be
interchangeable with other similar ones and hence, provide a maximum degree of freedom
and choice offered to the designer. This can also be accomplished by adopting a relatively
6
large basic measurement unit (basic module) and by limiting the dimensions of building
b) to allow for easy adoption of prefabricated components to any layout and for their
interchangeability within the building. This is achieved by defining the location of each
component in the building with reference to a common modular grid rather than with a
reference to other components. The modular co-ordination for building component apply the
basic length unit or module of M=100cm. This allows the designer to apply this size or its
multiple in the production of building components. Although this concept seems to be easy
for adoption, its application involves a great degree of coordination and adjustment in the
standardised for production. Such standardisation of space and elements need prescribing
tolerances, and erection tolerances, so that the combined tolerance obtained on statistical
considerations is within the permitted limits. Production resources can be used in the most
efficient manner if the output is standardised. Then the production process, machinery, and
workers’ training can be best absorbed to the particular characteristics of the product.
5. Mass Production
The investment in equipment, human recourses, and facilities associated with an
observed. Such volume provides a distribution of the fixed investment charge over a large
6. Specialisation
Large production output and standardisation of precast elements allow a high degree of
labour specialisation with the production process. The process can be subdivided into a large
7
number of small homogenous tasks. In such working condition, workers are exposed to their
7. Good Organisation
High production volume, specialisation of work, and centralisation of production requires an
coordination and control function with respect to production and distribution of the products.
8. Integration
In order to obtain an optimal result, a high degree of coordination must exist between various
relevant parties such as designer, manufacturer, owner, and contractor. This is achieved
through an integrated system in which all these functions are performed under a unified
authority.
9. Production Facility
The initial capital investment for setting up a permanent factor is relatively experience. Plant,
equipment, skilled worker, management resources need to be acquired before production can
be commenced. Such huge investment can only be breakeven if there is sufficiently demand
for the products. On the other hand, a temporary casting yard or factory can be established at
10. Transportation
It is found that casting of large-panel system can reduce labour cost up to 30 percent.
However, these cost savings are partially offset by the transportation costs. The transportation
of large panels is also subject to the country’s road department requirement. These limitations
BENEFITS OF IBS
8
Industrialised building system has the following benefits when compared to the conventional
construction method.
a) The repetitive use of system formwork made of steel, aluminium, etc and scaffolding
c) Prefabrication takes place at a centralised factory, thus reducing labour requirement at site.
d) An industrialised building system allows for faster construction time (less than half of the
time taken in conventional cast in-situ construction) because casting of precast element at
factory and foundation work at site can occur simultaneously. This provides earlier
system provide opportunities for designers and builders to explore creative designs using the
IBS
attainable through careful selection of materials, use of advanced technology and strict
SHORTCOMINGS OF IBS
The adoption of IBS is not without its limitations. Below are the shortcoming of an IBS
system.
9
a) An IBS system can only be acceptable to practitioners if its major advantage can
information.
b) Standardisation of building elements face resistance from the construction industry due to
aesthetic reservation and economic reason. One good example of this is when a 300mm thick
modular standardised floor slab has to be used although a 260mm thick floor slab can achieve
introduce modular co-ordination, its acceptance has received poor responses for the building
industry. As a result, even partial introduction of IBS such as lintels, staircase, etc has not
been possible.
d) A general decline in demand and volatility of the building market for large public housing
projects in most developed countries makes an investment in IBS more risky when compared
with the conventional labour intensive methods. This reason is substantiated by a cheap
standardisation cause monotonous “barrack like” complexes that very often turned into
dilapidated slums within several years. This shortcoming is further reinforced by production
defects in building components which are quite frequent in the initial stages of prefabrication.
Such defects resulting from lack of technical expertise and poor quality control cause
aesthetic and functional faults, such as cracks, blemishes, moisture penetration, and poor
10
f) Prefabricated elements are considered inflexible with respect to changes which may be
required over its life span. This may occur when small span room size prefabrication is used.
g) At university level, students are less exposed to technology, organisation and design of
industrialised building system. The academic curriculum seldom includes courses that
incorporate a thorough and methodological manner, the potential and the limitations
connections and jointing methods which are very sensitive to errors and sloppy work. Also,
standardisation of joint and connection detail may impede the evolution of new technology.
Hence, requires an initial immense investment cost. This is cited as one of the greater
design, standard, volume and consistency. The philosophy of IBS is based on volume or mass
production focusing on the modular system and quality of finished products resulting in the
reduction in the cost of production. Unfortunately, most housing projects in rural and urban
areas were constructed in relatively small and medium scales and there is a general decline in
federal and state government large scale housing development. In addition, IBS construction
also requires specialized equipment and machinery. Since most of the machineries and
materials used in fabricating IBS components are imported from developed countries, the
11
costs of producing IBS components and assembling them are not competitive for local
contractors.
IBS requires high construction precision. Previous studies have indicated that most local
professionals are not fully conversant with modular co-ordination and standardization
concept associated with IBS design and assembling procedures and contractors lack technical
knowledge and experience in the IBS. The skill level of IBS workers is more demanding
compared to the conventional construction methods. Under this system, the demand for on-
site semi-skilled workers, particularly carpenters, bar benders and concreters becomes less.
The system demands more machine-oriented skills, both on sites and in factories. Thus, this
the IBS components before delivering these components to construction sites. As such
contractors are required to help foot this initial bill. However, the current practice of paying a
contractor between 10% and 25% of the total amount of the contract value as mobilization
fee by the client, before a construction starts is grossly inadequate. The only way for a
guarantee to be deposited with the IBS manufacturer. Unfortunately for some contractors,
especially those new to the field, they face problem(s) in securing such bond. This may well
Lack of Guideline
12
Lack of specific IBS building regulations or standard guidelines for contract documents or
This lack of structured information will not only affect construction professionals because of
misunderstanding and misinterpreting regulations but also for authorities in terms of project
approval.
components need to be standardized and therefore standard plans and standard component
drawings are required, particularly to aid the production process. This is cited as one of the
example, poor jointing of prefabricated walls with other prefabricated or in-situ elements may
give rise to water seepage problem in IBS high-rise buildings, especially during a heavy
downpour. This problem worsens if finishes are not chosen and done properly. This may
result in, for example, high moisture movement, incompatible with the other materials like
13