Document 2
Document 2
TENDER NOTICE
Sealed bid for items under the following categories, addressed to the Director General (IPWM), Poonch
House, Multan Road, Lahore, are invited under PPRA Rules 2014 (amended) through the e-Pak
Acquisition and Disposal System (ePADS). The bidder participating must not be blacklisted by the
procuring agency or by the PPRA in whole Punjab. Bidder must have registered with relevant Tax
Departments of the Govt. of Pakistan.
Sr.# Description Quantity Estimated Last Date & Time Date & Time for
Cost of for submission of Opening of
Tender Tender Tender
Category: 1 (IT Equipment)
01. Laptop 06 1500000 09.12.2024 09.12.2024
02 Printer 05 650000 10.30 AM 11.00 AM
Category: 2 (Furniture Items)
01. Revolving Office 06 348000 09.12.2024 09.12.2024
Chairs 10.30 AM 11.00 AM
02. Work Stations 06 690000
03. Drawers 06 204000
04. Cabinets 02 190000
05. Meeting Table 02 300000
06. Visitor Chair 18 450000
07. Office Sofa Set 01 300000
Category: 3 (Machinery & Equipment)
01. LED TV 01 400000 09.12.2024 09.12.2024
02 Split Air 02 540000 10.30 AM 11.00 AM
Conditioner
1. Interested eligible bidders may download the bidding document containing detailed terms &
conditions and quantities with specifications free of cost from the websites of the Punjab
Procurement Regulatory Authority i.e., www.ppra.gov.pk
2. Single stage-Two envelope bidding procedure shall be applied as specified in PPRA Rules, 2014
(amended).
3. Participating in bidding process through (ePADS) portal is compulsory for all the bidders.
4. The intending bidders shall submit their profiles including technical & financial bids online through
(EPADS) portal. Moreover, bid security @ 2% of estimated tender cost in shape of (CDR/Bank
Guarantee/Pay Order) in favor of Director General (IPWM), Punjab will also be submitted
separately in sealed envelope at the office of Director General (IPWM), Poonch House, Multan
Road, Lahore before closing date and time.
5. Separate bids (lot-wise of) for each category will be required to be submitted.
6. Technical bids will be opened on the same day at 11.00 AM on ePADS in the presence of
purchase committee.
7. Successful bidder will deposit performance guarantee @ 5% in shape of (CDR/Bank
Guarantee/Pay Order) in favor of Director General (IPWM), Punjab.
8. Director General (IPWM), Punjab will not be responsible for any cost or expense incurred by
bidders in relation to the preparation or submission of bids.
9. In case the date of opening is declared a public holiday by the Government or a non-working
day for any reason, the next official working day will be considered as the new date for opening
of tenders. The time and venue will remain unchanged.
10. All assessment and procurement procedures, including uploading on ePADS, downloading/
receiving, opening, evaluating and awarding, shall be governed by the Punjab Procurement
Rules-2014.
042-99211528-29
Important Note
In order to conduct the procurement process in a fair & transparent manner and to bring value for
money to the Procuring Agency i.e., Directorate General (IPWM), Lahore through open competitive
bidding, Tenderer/ Bidder(s) (who intend to take part in the instant tender) are required to submit
the requisite information and documents mentioned in the Bidding Documents through ePADS.
SPECIFICATIONS
Category: 1
IT Equipment
INVITATION TO BID
Punjab Procurement Rules 2014 (amended), which may be downloaded from the
website of the Public Procurement Regulatory Authority, will be strictly followed
(http://ppra.punjab.gov.pk). In this document, unless otherwise mentioned to the contrary,
"Rule" means a Rule made under Punjab Procurement Regulatory Authority Act 2009 with
reference to Punjab Procurement Rules 2014 (amended).
As per Rule 38,2 (a), Single Stage - two Envelopes Bidding Procedure shall be strictly
followed. The said procedure is comprehended as follows:
(i) The bid shall be a single package comprising two envelopes marked as “Technical
Proposal” and “Financial Proposal” clearly with official seal.
(ii) The bidding process will be managed through EPAD system and bid will be opened in
public at the date and time advertised in the Bidding Document / communicated to
the bidders.
(iii) First technical bid will be opened and evaluated by the Tender Committee/ Purchase
Committee on the basis of the product specification mentioned above.
(iv) The technical bid found as per specifications and complete in all respects will proceed
further for the financial bid and the lowest evaluated bid shall be accepted for further
process of sampling.
5. INSTRUCTIONS TO BIDDER(S)
I. The bids complete in all respect as prescribed and required under this Tender
Document, must be uploaded through EPADS not later than 10:30 am on last date
of submission of bids i.e. 09.12.2024.
II. Bids submitted late / not in accordance with advertised terms and conditions shall not
be considered/entertained.
III. Bid Security (Earnest Money) @ 2% according to the category wise in favor of
Director General (IPWM), Punjab must be attached with bid, as part of the financial
bid and as per provisions contained in Clause “Bid Security” of the 6 Terms and
Conditions of the Tender in this bidding document mentioned hereinafter.
IV. The bids shall be publicly opened in the office of Director (ID), Poonch House, Multan
Road, Lahore at 11.00 AM on 09-12-2024.
V. Alternative bids shall not be considered. Bidder(s) must read the provisions/instructions
of this Tender Document contained in Clause regarding invoking i. “Determination of
Responsiveness of Bid” and “Rejection/Acceptance of the Tender” for making bids
substantially responsive to the requirements of the Bidding Document.
VI. It is the sole responsibility of the Bidder(s) that to read and understand all provisions,
instructions, terms & conditions contained in this Tender Document before submitting
the Bid. Neither any claim whatsoever including those of financial adjustments in case
the contract is awarded under this Bid Process will be entertained by the Purchaser
nor any time schedule, nor financial adjustments arising thereof shall be permitted on
account of failure by the Bidder(s).
VII. Instructions, Terms & Conditions, and Specifications are devised for strict compliance
and enforcement.
VIII. The successful Bidder(s) will be responsible for all the deliveries and deliverables to
the Purchaser within the stipulated time at Directorate General (IPWM), Poonch
House, Multan Road, Lahore or otherwise locations described as per provision
regarding delivery time or execution schedule of the Tender Document;
IX. Bidder(s) shall communicate all queries via Caretaker Cell of DG (IPWM), Punjab.
X. Bidder(s) are required to state clearly, in their proposals, the name, title, contact
number (landline, mobile), fax number and e-mail address of the Bidder(s)’s
authorized representative through whom all communications shall be directed until
the process has been completed or terminated.
XI. The Purchaser will not bear any cost or expense incurred by Bidder(s) in connection
with the preparation or submission of bids.
The Purchaser shall, prior to the Tender evaluation, determine the substantial
responsiveness of the Bid to the Tender Documents. A substantially responsive Tender is one which:
i. Meets the eligibility criteria given in Tender Documents for provision of Items;
ii. Meets the Technical Specifications for the Items against each Item/service of BOQ.
A material deviation or reservation is one that affects the scope, quality or performance
of the Goods or limits the Purchaser's rights or the Bidder(s)'s obligations under the Contract. The
Tender determined as not substantially responsive shall not subsequently be made responsive by
the Bidder(s) by correction or withdrawal of the material deviation or reservation.
The Purchaser may reject all bids or proposals at any time prior to the acceptance of a bid or proposal.
The Purchaser shall upon request communicate to any Bidder(s), the grounds for its rejection of all
bids or proposals, but shall not be required to justify those grounds. The Purchaser shall incur no
liability, solely, by virtue of invoking discretion provided under sub-rule (1) of Rule-35 of Punjab
Procurement Rules, 2014 (amended) towards the Bidder(s). However, prospective Bidder(s) shall be
informed in due course about the rejection of the bids if any (As per Rule 35 of Punjab Procurement
Rules, 2014(amended).
The Tender shall be rejected if it is:
8. Tender Cost
The Bidder(s) shall bear costs/expenses with regard to the preparation and submission of the
Tender(s) and the Purchaser shall not be responsible/liable for those costs/ expenses.
A prospective Bidder requiring any clarification(s) on the Tender Documents may notify the Purchaser
in writing. The Purchaser shall respond in writing to any request for clarification(s) of the tender
documents, which it receives no later than ten (10) days prior to the deadline for the submission of
bids prescribed in the Invitation for Bids.
The Purchaser may, at any time prior to the deadline for submission of the Tender, at its own initiative
vested with exclusive discretion or in response to a clarification requested by the Bidder(s), amend
the Tender Document, on account of any reason, either to extend the deadline for the submission of
Bid or otherwise which shall be notified to all prospective Bidder(s) where after all such amendment(s)
shall be considered part of the Tender Document and binding on the Bidder(s) as per Punjab
Procurement Rules, 2014 (amended) Rule 25(4).
a. Best/final/fixed and valid until completion of all obligations under the Contract i.e. not subject to
variation/escalation;
i. in Pak Rupees;
ii. Inclusive of all taxes, duties, levies, insurance, freight, etc.
iii. Including all charges up to the delivery point at Directorate General (IPWM), Poonch House,
Multan Road, Lahore
b. If not specifically mentioned in the Tender(s), it shall be presumed that the quoted price is as per
the above requirements.
The Procuring Agency reserves the right at the time of contract award to increase or decrease
the quantity of goods and services originally specified in the Schedule of Requirements without any
change in unit price or other terms and conditions, on the analogy of rule-59 (c)(iv) of PPR-14 (not
more than 15%).
Note:
The successful bidder will be bound to provide a 5% performance guarantee of the contract amount
in favor of Director General (IPWM), Punjab within 24 hours of the acceptance of tender for placement
of final work order.
CERTIFICATE
i) We hereby confirm to have read carefully the description of the stores and all the terms and
conditions of your tender Enquiry No. ____________________________ due for opening on
______________ for supply of _________________________________________ in additions to
the conditions laid down in PPRA, 2014 and also all the special instructions attached to the said
tender enquiry, we agree to abide by all those instructions/conditions.
ii) We also hereby categorically confirm that the stores offered by us are exactly to the particulars
and specifications as laid down in your tender enquiry in all respects.
iii) The stores offered by us are of local/foreign origin.
iv) We accept that if the required Earnest Money is not furnished or our offer is found lacking in any
of the requirements of tender enquiry, the competent authority has the right of rejection.
v) We hereby confirm to adhere to the delivery period required in the tender enquiry as given in the
contract and which will be strictly adhered. In case of delay we have bond to pay 2% of bid per
month as fine.
vi) Certified that the prices quoted to the Department, against Tender No.
_______________________________ are not more than the prices charged from any other
Purchasing Agencies in the country and in case of any discrepancy, the tenderer hereby undertakes
to refund the price charged in excess.
2. Name of Tenderer__________________________________________________________
4. Designation ______________________________________________________________
5. Seal _____________________________________________________________________
WITNESS
Date _____________________________________________________________