PROJECT TITLE:
A. Proposed 2-Storey Building Renovation and Canteen
B. Lani’s Crib_2-Storey Residential Building (Ground-up)
ADDRESS:
A. Jocelyn Forge Bldg. -56 Altoveros St, 3020 Bagbaguin Rd,
Meycauayan, Bulacan
B. Lani’s Crib - 200 Altoveros St, 3020 Bagbaguin Rd, Meycauayan,
Bulacan
I. PROJECT UNDERSTANDING
B. LANI’s CRIB
This project covers construction of a two-storey house having three
bedrooms, three toilet and baths, caretaker room, a powder room,
sauna, living, dining and kitchen areas. This house is design to create
more private and peaceful home.
II. PROCEDURE
1. MOBILIZATION
Our team will mobilize all the required project team personnel,
equipment, tools and manpower with the required skills and in sufficient
number as may be necessary for the efficient undertaking of the
project.
2. SITE PREPARATION
Site Assessment - The first step is to assess the site thoroughly. This
includes evaluating the existing structures or vegetation, and
potential environmental impacts. Understanding these factors is
essential for making informed decisions throughout the construction
process.
Prioritize safety throughout the site preparation process. Ensure that
workers have the necessary training and personal protective
equipment (PPE). Regular safety audits and risk assessments should
be conducted
Quality Control - Establish strict quality control measures to monitor
the progress and quality of site preparation work. Regular
inspections will be conducted to help identify and rectify issues
before they become major problems.
4. CONSTRUCTION METHODOLOGY
B. Structural Works
1. Formworks
2. Rebar Works
Within the yard the steel will be cut and bent into required lengths
and shapes. The reinforcement cages will be fabricated in the areas
as designated and will then be placed in the required areas.
3. Concrete Works
C. Architectural Works
All masonry walls shall start after all forms and shoring at the
ground floor has been cleared. Concrete hollow blocks to be used
shall conform to the specifications. Mortar for setting blocks shall
be in the proportion specified in the plans and specifications. All
masonry shall be laid plumb and true to line and built to the
thickness and bond required with the courses level and bond
uniform. Vertical and horizontal reinforcements shall be of standard
sizes and laid on required spacing. Sealants and compressible filler
below slab/beam soffit & concrete walls/columns will be placed.
Materials for plastering shall conform to the standard mix
proportions by volume. Base coat will be applied first prior to the
finish coat as required by the thickness.
2. Ceiling Works
3. Metal Works
INSTALLATION PROCEDURE
b. Full Welding
4. Painting Works
5. Roofing Works
Insulation
a. New insulation will be installed (10mm Double Sided Foil Insulation).
b. For Office and Canteen insulation will be installed below the framings
(c-purlins) to avoid the removal of the existing roof panels.
c. Then it will be holded by metal framings
Roofing Panel
Materials for the roof will be carefully lifted to the roof area. Position the panels
accurately on supporting frame or structure. Adjust accordingly to final
position with proper bearing before fix or fastener. After alignment is done
secure the panel using the fastener with electric drill machine with care.
Install the next roof panels in the same procedure as above, ensure the
correct orientation of each panels, anticipate the requirement for the
lapping, end trim, joint filler and sealant. Install all accessories in
accordance with vendor catalog, drawings and specification.
D. Material Testing
E. Demobilization