0% found this document useful (0 votes)
17 views

PERT Problem Sample

Sample problem on PERT

Uploaded by

Abdul Nazar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF or read online on Scribd
0% found this document useful (0 votes)
17 views

PERT Problem Sample

Sample problem on PERT

Uploaded by

Abdul Nazar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF or read online on Scribd
You are on page 1/ 3
Network Analysis (PERT/CPM) 793 Example 2 : A certain project is composed of nine activities where time estimates are given below : Activity Expected duration (week) : | optimistic | most itely | Pessimiscie_| 7 (a) Draw the project network and trace all the possible paths from it. What is the expected. Project length ? [UP TECH MBA 2004-05] . (b) Calculate the variance and standard deviation of the project length. (© What is the probability that the project will be completed : (@ at least 4 weeks earlier than expected time. (ii) no more than 4 weeks later than expected time. (@) Ifthe project date is 29 weeks, what is the probability of not meeting the due date ? (©) What due date has about 99% chance of completing the project ? Solution : (a) Project Network diagram. Fig. 19.48 Here all possible paths are (1-2=5=7; 4=2=5-6-7; 1-3-5-%; 1-3-5-6-7; 1-4-6-7. The expected activity time and variance of each activity i — j are calculated in the following table : 794 Operations Research Table 19.5 1-2 1 1 7 2 1 1-3 3 5 aT 5 0.45 1-4 | 2 2 8 3 1 2-8 1 1 1 2 0 355 | 3 6 9 6 1 4-6 2 5 8 5 z 5-6 4 6 14 t 2.79 5-7 3 7) wi 7 1.77 6-7 6 8 10 8 0.45 To find expected earliest start time E;, for tail event of each activity i Taking E, = 0, we have Ey =E, +tg, =0+2=2 Ey ttag =0+5=5 E4 =E, +teyq =0+3=3 {Ej + tej = +e oe {Bi eis) Bom MexdBit tag) = Max {E2 +t¢95,E3 +tegs} = Max {Eq +teqg.Es +teso} = Max. {2+1, 5+ 6} =11 = Max {3+5,11+7} =18 Ey = Maxey +tei7} = Max {Es +t,57,E6 +teg7} = Max {11+7, 18+ 8} = 26 To find expected latest finish time L, for head event of each activity i — j Taking L, = Ey = 26, We have Lg = Ly ~tegy = 26-8 = 18 Ug = Mini {Lj ~te5j} = Mini (bg ~tes6:L7 ~tes7}s Jn =Mini {18-7,26-7}=11 Lg = Lg ~tegg = 18-5 = 13 Ly =Lg ~tegs =11-6=5 La = Ls ~teg =11-1=10 L =a {Lj ~taj} = Mini {Lz -ta, Lz —ta3,L4 ~taad Mini (10-2, 5-5, 13-3} =0 L3,Es =Ls,Eg=Lgand Ey = Ly, alsoforthese activities I; 80, the activities 1- 3, 3-5, 5~6 and 6~7 are critical activities. v Network Analysis (PERT/CPM) 795, ‘The critical path is 1-3-5-6-7 and expected project length, T, = 26weeks. (b) For the project length, variance = 6? = sum of variances for critical activities,1 - 3, 3-5, 5- 6 and 6-7 = 0.45 +1+ 2.79 + 0.45 = 4.69 weeks «. standard deviation = 6, = 469 = 2.17 weeks. , © 0 The probability of completing the project, 4 weeks earlier than expected time ie, in time T, = 26~ 4 = 22 weeks is given by Prob. z< te = Prob 2< 22 -1.84) 2.17 = 0.5~ 0.4671 = 0.1329 (From normal distribution table) ie. 13.29% (ii) And probability of completing the project 4 weeks later than expected time ie,, in time T, = 26+ 4= 30weeks, is given by = 0.5 + 0.4671 = 0.9671 (From normal distribution table) ie, 96.71% (d) fT, = 29 weeks, then prob of completing the work by due date is given by T,- r Prob. }Z < Prob {z < 22=28 - 1 39 2.17 = 0.5 + 0.4162 = 0.9162 (From normal distribution table) i.e, 91.62% Hence the probability of not meeting the project date of 29 weeks = 1—0.9162 = 0.0838 i.e. 8.38% (©) IFT, is the project time when the due date has about 99% chance, then T.-Te T, - 26] Prob. {Z < =+—}=0: .) { a | 99 (appr.) a T, -26 ‘ cm 2.33 (from normal distribution table) => T, = 26+ 2.17 x 2.33 = 26+ 5.06 = 31.06 weeks = 31 weeks (appr.)

You might also like