SQH - 30 Days Provisional Inspection Look Ahead-July 2024 - CIVIL

Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

SALALAH HOSPITAL PROJECT

30-Jun-2024
PROVISIONAL INSPECTION DATES

IR to be raised by NEO-
SR No. Description of Inspection Discipline Remarks
ATNM to NEO Work to be Inspected

ZONE 1 & 1A

1 Level-06 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 06-Jul-2024 07-Jul-2024 Civil 1 nos inspection in given time period
2 Level-05 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 07-Jul-2024 08-Jul-2024 Civil 1 nos inspection in given time period
3 Level-04 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 10-Jul-2024 11-Jul-2024 Civil 1 nos inspection in given time period
4 Level-03 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 13-Jul-2024 14-Jul-2024 Civil 1 nos inspection in given time period
5 Level-02 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 15-Jul-2024 16-Jul-2024 Civil 1 nos inspection in given time period
6 Level-01 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 20-Jul-2024 21-Jul-2024 Civil 1 nos inspection in given time period
7 Completion Of EIFS Texture Application Level 00-02 Courtyard 06-Jul-2024 07-Jul-2024 Civil 1 nos inspection in given time period
8 Completion Of EIFS Texture Application Level 03-Roof South Elevation 24-Jul-2024 25-Jul-2024 Civil 1 nos inspection in given time period
9 EPDM Surface Preparation For Louver Screen & Rain Screen At Level-02 03-Jul-2024 04-Jul-2024 Civil 1 nos inspection in given time period
10 EPDM Completion For Louver Screen & Rain Screen At Level-02 06-Jul-2024 07-Jul-2024 Civil 1 nos inspection in given time period
11 Level 02-03 EIFS Surface Preparation- North & South Side 07-Jul-2024 10-Jul-2024 Civil 2 nos inspection in given time period
12 Level 02-03 EIFS Rock Wool & Accessories Installation Completion- North & South Side 16-Jul-2024 17-Jul-2024 Civil 1 nos inspection in given time period
13 Level-02 Peripheral Sill Reinforcement, Formwork And Concreting 20-Jul-2024 27-Jul-2024 Civil 4 nos inspection in given time period
14 Level 02 Wall Stucco Putty 30-Jun-2024 01-Jul-2024 Civil

15 Level 02 1St Coat Paint 03-Jul-2024 04-Jul-2024 Civil

16 Riser -2Nd Coat For Fenomastic Paint 02-Jul-2024 03-Jul-2024 Civil

17 Level 01 To 03 Surface Preparation For The Sealant Application Above Screed 01-Jul-2024 30-Jul-2024 Civil

18 Level 01 Surface Preparation Prior To The Screed 01-Jul-2024 30-Jul-2024 Civil

19 Level 01 Bonding Agent And Laying Of Screed Concrete 03-Jul-2024 03-Aug-2024 Civil

20 Level - 01- 03 Glass Fixing 06-Jul-2024 07-Jul-2024 Civil 3 nos inspection in given time period
21 Curtain Wall Frame Fixing 18-Jul-2024 20-Jul-2024 Civil 1 nos inspection in given time period
22 Curtain Wall Glass Fixing 28-Jul-2024 30-Jul-2024 Civil 3 nos inspection in given time period
ZONE 2 & 2A

23 Level-06 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 06-Jul-2024 07-Jul-2024 Civil 1 nos inspection in given time period
24 Level-05 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 07-Jul-2024 08-Jul-2024 Civil 1 nos inspection in given time period
25 Level-04 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 10-Jul-2024 11-Jul-2024 Civil 1 nos inspection in given time period
26 Level-03 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 13-Jul-2024 14-Jul-2024 Civil 1 nos inspection in given time period
27 Level-02 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 15-Jul-2024 16-Jul-2024 Civil 1 nos inspection in given time period
28 Level-01 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 20-Jul-2024 21-Jul-2024 Civil 1 nos inspection in given time period
29 Completion Of EIFS Texture Application Level 00-02 Courtyard 1 08-Jul-2024 09-Jul-2024 Civil 1 nos inspection in given time period
30 Completion Of EIFS Texture Application Level 00-02 Courtyard 2 09-Jul-2024 10-Jul-2024 Civil 1 nos inspection in given time period
31 Completion Of EIFS Texture Application Level 03-Roof South Elevation 15-Jul-2024 16-Jul-2024 Civil 1 nos inspection in given time period
32 EPDM Surface Preparation For Louver Screen & Rain Screen At Level-02 03-Jul-2024 04-Jul-2024 Civil 1 nos inspection in given time period
33 EPDM Completion For Louver Screen & Rain Screen At Level-02 06-Jul-2024 07-Jul-2024 Civil 1 nos inspection in given time period
34 Completion Of EIFS Texture Application Level 00-Roof North Elevation 20-Jul-2024 21-Jul-2024 Civil 1 nos inspection in given time period
35 Completion Of EIFS Texture Application Level 03-Roof South Elevation 24-Jul-2024 25-Jul-2024 Civil 1 nos inspection in given time period
36 Block Work Completion For Electrical Rooms At Level-06 10-Jul-2024 11-Jul-2024 Civil 1 nos inspection in given time period
37 Block Work Completion For Electrical Rooms At Level-05 13-Jul-2024 14-Jul-2024 Civil 1 nos inspection in given time period
38 Block Work Completion For Electrical Rooms At Level-04 15-Jun-2024 16-Jun-2024 Civil 1 nos inspection in given time period
39 Level 02-03 EIFS Surface Preparation- North & South Side 07-Jul-2024 10-Jul-2024 Civil 2 nos inspection in given time period
40 Level 02-03 EIFS Rock Wool & Accessories Installation Completion- North & South Side 16-Jul-2024 17-Jul-2024 Civil 1 nos inspection in given time period
41 Level-02 Peripheral Sill Reinforcement, Formwork And Concreting 20-Jul-2024 27-Jul-2024 Civil 4 nos inspection in given time period
42 Level 02 Wall Stucco Putty 01-Jul-2024 02-Jul-2024 Civil

43 Level 02 1St Coat Paint 04-Jul-2024 06-Jul-2024 Civil

44 Headroom Ceiling Painting-Stucco Putty 03-Jul-2024 04-Jul-2024 Civil

45 Headroom Ceiling Painting-Primer 06-Jul-2024 07-Jul-2024 Civil

46 Headroom Ceiling Painting-1St Coat 09-Jul-2024 10-Jul-2024 Civil

47 Headroom Ceiling Painting-2Nd Coat 12-Jul-2024 14-Jul-2024 Civil

48 Level 01 To 03 Surface Preparation For The Sealant Application Above Screed 01-Jul-2024 30-Jul-2024 Civil

49 Level 01 Surface Preparation Prior To The Screed 01-Jul-2024 30-Jul-2024 Civil

50 Level 01 Bonding Agent And Laying Of Screed Concrete 03-Jul-2024 03-Aug-2024 Civil

51 Level - 01- 05 Window Glass Fixing 11-Jul-2024 13-Jul-2024 Civil


4 nos inspection in given time period
52 Curtain Wall Frame Fixing 18-Jul-2024 20-Jul-2024 Civil
1 nos inspection in given time period
53 Curtain Wall Glass Fixing 22-Jul-2024 24-Jul-2024 Civil
1 nos inspection in given time period
ZONE 3 & 3A

54 Level-06 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 06-Jul-2024 10-Jul-2024 Civil 2 nos inspection in given time period
55 Level-05 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 07-Jul-2024 13-Jul-2024 Civil 2 nos inspection in given time period
56 Level-04 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 10-Jul-2024 14-Jul-2024 Civil 2 nos inspection in given time period
57 Level-03 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 13-Jul-2024 17-Jul-2024 Civil 2 nos inspection in given time period
58 Level-02 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 15-Jul-2024 18-Jul-2024 Civil 2 nos inspection in given time period
59 Level-01 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 20-Jul-2024 24-Jul-2024 Civil 2 nos inspection in given time period
60 Completion Of EIFS Texture Application Level 00-02 Courtyard 16-Jul-2024 17-Jul-2024 Civil 1 nos inspection in given time period
61 Completion Of EIFS Texture Application Level 03-Roof North Elevation 24-Jul-2024 25-Jul-2024 Civil 1 nos inspection in given time period
62 EPDM Completion For Louver Screen & Rain Screen At Level-02 North & South 06-Jul-2024 07-Jul-2024 Civil 1 nos inspection in given time period
63 Level 02-03 EIFS Surface Preparation- North & South Side 22-Jul-2024 23-Jul-2024 Civil 1 nos inspection in given time period
64 Level 02-03 EIFS Rock Wool & Accessories Installation Completion- North & South Side 27-Jul-2024 28-Jul-2024 Civil 1 nos inspection in given time period
65 Level-02 Peripheral Sill Reinforcement, Formwork And Concreting 18-Jul-2024 24-Jul-2024 Civil 4 nos inspection in given time period
66 Level 01 To 03 Surface Preparation For The Sealant Application Above Screed 01-Jul-2024 30-Jul-2024 Civil

67 Level 01 Surface Preparation Prior To The Screed 01-Jul-2024 30-Jul-2024 Civil

68 Level 01 Bonding Agent And Laying Of Screed Concrete 03-Jul-2024 03-Aug-2024 Civil

69 Level - 00- 05 Window Glass Fixing 02-Jul-2024 04-Jul-2024 Civil


6 nos inspections in given time period
70 Curtain Wall Frame Fixing 13-Jul-2024 14-Jul-2024 Civil 1 nos inspections in given time period
71 Curtain Wall Glass Fixing 25-Jul-2024 27-Jul-2024 Civil
3 nos inspections in given time period
ZONE 4& 4A

72 Level-06 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 06-Jul-2024 10-Jul-2024 Civil 2 nos inspection in given time period
73 Level-05 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 07-Jul-2024 13-Jul-2024 Civil 2 nos inspection in given time period
74 Level-04 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 10-Jul-2024 14-Jul-2024 Civil 2 nos inspection in given time period
75 Level-03 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 13-Jul-2024 17-Jul-2024 Civil 2 nos inspection in given time period
76 Level-02 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 15-Jul-2024 18-Jul-2024 Civil 2 nos inspection in given time period
77 Level-01 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 20-Jul-2024 24-Jul-2024 Civil 2 nos inspection in given time period
78 Completion Of EIFS Texture Application Level 00-02 Courtyard 1 08-Jul-2024 09-Jul-2024 Civil 1 nos inspection in given time period
79 Completion Of EIFS Texture Application Level 00-02 Courtyard 2 09-Jul-2024 10-Jul-2024 Civil 1 nos inspection in given time period
80 Completion Of EIFS Texture Application Level 03-Roof South Elevation 15-Jul-2024 16-Jul-2024 Civil 1 nos inspection in given time period
81 EPDM Surface Preparation For Louver Screen & Rain Screen At Level-02 03-Jul-2024 04-Jul-2024 Civil 1 nos inspection in given time period
82 EPDM Completion For Louver Screen & Rain Screen At Level-02 06-Jul-2024 07-Jul-2024 Civil 1 nos inspection in given time period
83 Level 02-03 EIFS Surface Preparation- North & South Side 10-Jul-2024 11-Jul-2024 Civil 1 nos inspection in given time period
84 Level 02-03 EIFS Rock Wool & Accessories Installation Completion- North & South Side 16-Jul-2024 17-Jul-2024 Civil 1 nos inspection in given time period
85 Block Work Completion For Electrical Rooms At Level-06 10-Jul-2024 11-Jul-2024 Civil 1 nos inspection in given time period
86 Block Work Completion For Electrical Rooms At Level-05 13-Jul-2024 14-Jul-2024 Civil 1 nos inspection in given time period
87 Block Work Completion For Electrical Rooms At Level-04 15-Jun-2024 16-Jun-2024 Civil 1 nos inspection in given time period
88 Level-02 Peripheral Sill Reinforcement, Formwork And Concreting 18-Jul-2024 24-Jul-2024 Civil 4 nos inspection in given time period
89 Service Room Wall Ceiling Surface Preparation 03-Jul-2024 13-Jul-2024 Civil

90 Service Room Wall Ceiling Primer 04-Jul-2024 14-Jul-2024 Civil

91 Level 02& Service Room L Stucco Putty 01-Jul-2024 11-Jul-2024 Civil 5 inspections during this period
92 Level 02 & Service Room Wall 1St Coat Paint 03-Jul-2024 14-Jul-2024 Civil 5 inspections during this period
93 Headroom Ceiling Painting-Stucco Putty 03-Jul-2024 14-Jul-2024 Civil
5 inspections during this period
94 Headroom Ceiling Painting-Primer 16-Jul-2024 17-Jul-2024 Civil

95 Headroom Ceiling Painting-1St Coat 19-Jul-2024 21-Jul-2024 Civil

96 Headroom Ceiling Painting-2Nd Coat 23-Jul-2024 24-Jul-2024 Civil

97 Bmu/Façade ,Equipment Foundation Prepour&Anchor Bolt Setting-Level 05 03-Jul-2024 04-Jul-2024 Civil

98 Riser -Primer Completion 30-Jun-2024 01-Jul-2024 Civil

99 Riser -1St Coat For Fenomastic Paint 03-Jul-2024 04-Jul-2024 Civil

100 Riser -2Nd Coat For Fenomastic Paint 06-Jul-2024 07-Jul-2024 Civil

101 BMus/Façade ,Equipment Foundation Prepour&Anchor Bolt Setting-Level 06 01-Jul-2024 02-Jul-2024 Civil

102 Level 01 To 03 Surface Preparation For The Sealant Application Above Screed 01-Jul-2024 30-Jul-2024 Civil

103 Level 01 Surface Preparation Prior To The Screed 01-Jul-2024 30-Jul-2024 Civil

104 Level 01 Bonding Agent And Laying Of Screed Concrete 03-Jul-2024 03-Aug-2024 Civil

105 Level - 00- 05 Glass Fixing 15-Jul-2024 20-Jul-2024 Civil 4 nos inspections in given time period
106 Curtain Wall Frame Fixing 03-Jul-2024 06-Jul-2024 Civil
2 nos inspections in given time period
107 Curtain Wall Glass Fixing 20-Jul-2024 22-Jul-2024 Civil 3 nos inspections in given time period
ZONE 5

108 Level-04 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 10-Jul-2024 11-Jul-2024 Civil 1 nos inspection in given time period
109 Level-03 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 13-Jul-2024 14-Jul-2024 Civil 1 nos inspection in given time period
110 Level-02 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 15-Jul-2024 16-Jul-2024 Civil 1 nos inspection in given time period
111 Level-01 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 20-Jul-2024 21-Jul-2024 Civil 1 nos inspection in given time period
112 Completion Of EIFS Texture Application Level 03-Roof South Elevation 24-Jul-2024 25-Jul-2024 Civil 1 nos inspection in given time period
113 Level 02-03 EIFS Surface Preparation- North Side 07-Jul-2024 08-Jul-2024 Civil 1 nos inspection in given time period
114 Level 02-03 EIFS Rock Wool & Accessories Installation Completion- North Side 16-Jul-2024 17-Jul-2024 Civil 1 nos inspection in given time period
115 Level-02 Peripheral Sill Reinforcement, Formwork And Concreting 08-Jul-2024 13-Jul-2024 Civil 4 nos inspection in given time period
116 Level 02& Service Room L Stucco Putty 03-Jul-2024 13-Jul-2024 Civil

117 Level 02 & Service Room Wall 1St Coat Paint 04-Jul-2024 14-Jul-2024 Civil

118 Headroom Ceiling Painting-Stucco Putty 01-Jul-2024 11-Jul-2024 Civil

119 Headroom Ceiling Painting-Primer 03-Jul-2024 14-Jul-2024 Civil

120 Headroom Ceiling Painting-1St Coat 03-Jul-2024 15-Jul-2024 Civil

121 Headroom Ceiling Painting-2Nd Coat 17-Jul-2024 18-Jul-2024 Civil

122 BMus/Façade ,Equipment Foundation Prepour&Anchor Bolt Setting-Level 05 02-Jul-2024 03-Jul-2024 Civil

123 Solar Foundation Prepour 15-Jul-2024 16-Jul-2024 Civil

124 Level 01 To 03 Surface Preparation For The Sealant Application Above Screed 01-Jul-2024 30-Jul-2024 Civil

125 Level 01 Surface Preparation Prior To The Screed 01-Jul-2024 30-Jul-2024 Civil

126 Level 01 Bonding Agent And Laying Of Screed Concrete 03-Jul-2024 03-Aug-2024 Civil

127 Level - 00-05 Window Frame Fixing 13-Jul-2024 15-Jul-2024 Civil


2 nos inspection in given time period
128 Level - 00- 05 Glass Fixing 16-Jul-2024 19-Jul-2023 Civil 2 nos inspection in given time period
129 Curtain Wall Glass Fixing 23-Jul-2024 25-Jul-2024 Civil
1 nos inspection in given time period
ZONE 6

130 Level-04 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 11-Jul-2024 13-Jul-2024 Civil 1 nos inspection in given time period
131 Level-03 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 14-Jul-2024 15-Jul-2024 Civil 1 nos inspection in given time period
132 Level-02 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 16-Jul-2024 17-Jul-2024 Civil 1 nos inspection in given time period
133 Level-01 MEP Shafts Wind post& Lintel Reinforcement/Formwork & Prepour Checking 17-Jul-2024 18-Jul-2024 Civil 1 nos inspection in given time period
134 Completion Of EIFS Texture Application Level 03-Roof South Elevation 24-Jul-2024 25-Jul-2024 Civil 1 nos inspection in given time period
135 Level 02-03 EIFS Surface Preparation- North Side 10-Jul-2024 11-Jul-2024 Civil 1 nos inspection in given time period
136 Level 02-03 EIFS Rock Wool & Accessories Installation Completion- North Side 14-Jul-2024 15-Jul-2024 Civil 1 nos inspection in given time period
137 Level-02 Peripheral Sill Reinforcement, Formwork And Concreting 10-Jul-2024 16-Jul-2024 Civil 4 nos inspection in given time period
138 Hydrotherapy Wall Rebar 04-Jul-2024 05-Jul-2024 Civil

139 Hydrotherapy Trench Base Prepour 07-Jul-2024 08-Jul-2024 Civil

140 Hydrotherapy Trench Wall Prepour 11-Jul-2024 12-Jul-2024 Civil

141 Service Room Wall Ceiling Surface Preparation 01-Jul-2024 11-Jul-2024 Civil

142 Service Room Wall Ceiling Primer 03-Jul-2024 13-Jul-2024 Civil

143 Level 02& Service Room L Stucco Putty 03-Jul-2024 13-Jul-2024 Civil 5 inspections during this period
144 Level 02 & Service Room 1St Coat Paint 04-Jul-2024 14-Jul-2024 Civil 5 inspections during this period
145 Headroom Ceiling Painting-Stucco Putty 01-Jul-2024 11-Jul-2024 Civil

146 Headroom Ceiling Painting-Primer 03-Jul-2024 15-Jul-2024 Civil

147 Headroom Ceiling Painting-1St Coat 03-Jul-2024 15-Jul-2024 Civil

148 Headroom Ceiling Painting-2Nd Coat 17-Jul-2024 18-Jul-2024 Civil

149 BMus/Façade ,Equipment Foundation Prepour&Anchor Bolt Setting-Level 05 02-Jul-2024 03-Jul-2024 Civil

150 Solar Foundation Prepour 15-Jul-2024 16-Jul-2024 Civil

151 Level 01 To 03 Surface Preparation For The Sealant Application Above Screed 01-Jul-2024 30-Jul-2024 Civil

152 Level 01 Surface Preparation Prior To The Screed 01-Jul-2024 30-Jul-2024 Civil

153 Level 01 Bonding Agent And Laying Of Screed Concrete 03-Jul-2024 03-Aug-2024 Civil

154 Level - 00- 05 Glass Fixing 11-Jul-2024 14-Jul-2024 Civil 3 nos inspection in given time period
155 Curtain Wall Frame Fixing 20-Jul-2024 22-Jul-2024 Civil
1 nos inspection in given time period
156 Curtain Wall Glass Fixing 28-Jul-2024 30-Jul-2024 Civil 1 nos inspection in given time period
ANNEX BUILDING

157 Auditorium Block Work Completion Level 01 06-Jul-2024 07-Jul-2024 Civil 1 nos inspection in given time period
158 Auditorium Block Work Completion Level 00 10-Jul-2024 11-Jul-2024 Civil 1 nos inspection in given time period
159 Level-02 Wall Sealant Completion 01-Jul-2024 02-Jul-2024 Civil 1 nos inspection in given time period
160 Level-01 Wall Sealant Surface Preparation 01-Jul-2024 02-Jul-2024 Civil 1 nos inspection in given time period
161 Level-01 Wall Sealant Completion 7/6/2024 07-Jul-2024 Civil 1 nos inspection in given time period
162 Level-00 Wall Sealant Surface Preparation 08-Jul-2024 09-Jul-2024 Civil 1 nos inspection in given time period
163 Level-00 Wall Sealant Completion 13-Jul-2024 14-Jul-2024 Civil 1 nos inspection in given time period
164 External EIFS Insulation & Groove/Corner Bead Fixing- South Side 03-Jul-2024 04-Jul-2024 Civil 1 nos inspection in given time period
165 Level-03 MEP Shafts Wind post Reinforcement/Formwork & Prepour Checking 07-Jul-2024 10-Jul-2024 Civil 2 nos inspection in given time period
166 Headroom Ceiling Surface Preparation For Pva Primer 06-Jul-2024 07-Jul-2024 Civil

167 Headroom Ceiling Pva Primer 10-Jul-2024 12-Jul-2024 Civil

168 Headroom Ceiling Antifungal First Coat 14-Jul-2024 16-Jul-2024 Civil

169 Headroom Ceiling Antifungal 2Nd Coat 18-Jul-2024 20-Jul-2024 Civil

170 Ahu Foundation Prepour 15-Jul-2024 19-Jul-2024 Civil

171 Riser -Primer Completion 06-Jul-2024 07-Jul-2024 Civil

172 Riser -1St Coat For Fenomastic Paint 09-Jul-2024 12-Jul-2024 Civil

173 Riser -2Nd Coat For Fenomastic Paint 15-Jul-2024 16-Jul-2024 Civil

174 Service Room Pva Primer 06-Jul-2024 11-Jul-2024 Civil

175 Service Room Stucco Putty 09-Jul-2024 16-Jul-2024 Civil

176 Service Room 1St Coat Paint 11-Jul-2024 18-Jul-2024 Civil

177 Level 01 To 03 Surface Preparation For The Sealant Application Above Screed 01-Jul-2024 30-Jul-2024 Civil

178 Level 01 Surface Preparation Prior To The Screed 01-Jul-2024 30-Jul-2024 Civil

179 Level 01 Bonding Agent And Laying Of Screed Concrete 03-Jul-2024 03-Aug-2024 Civil

180 Level - 00 Window Frame Fixing 08-Jul-2024 10-Jul-2024 Civil 1 nos inspection in given time period
181 Level - 00- 02 Glass Fixing 20-Jul-2024 22-Jul-2024 Civil 3 no's inspection in given time period
182 Curtain Wall Glass Fixing 21-Jul-2024 23-Jul-2024 Civil
2 nos inspection in given time period
GUARD HOUSE

183 Wall Sealant Completion-Main Guard House 03-Jul-2024 04-Jul-2024 Civil 1 nos inspection in given time period
184 Wall Sealant Completion-Royal Guard House 03-Jul-2024 04-Jul-2024 Civil
1 nos inspection in given time period
185 EIFS Completion Of Texture Application -Main Guard House 10-Jun-2024 11-Jun-2024 Civil 1 nos inspection in given time period
186 EIFS Completion Of Texture Application -Royal Guard House 14-Jun-2024 15-Jun-2024 Civil
1 nos inspection in given time period
187 Curtain Wall Glass Fixing 11-Jul-2024 13-Jul-2024 Civil 1 no's inspection in given time period
188 Royal Guard House-Curtain Wall Glass Fixing 13-Jul-2024 16-Jul-2024 Civil
1 nos inspection in given time period
GENERATOR COMPOUND-2

189 Completion of EIFS texture application 10-Jun-2024 11-Jun-2024 Civil 1 nos inspection in given time period
WATERTANK BUILDING

190 Lintel Reinforcement/Formwork & Concrete-Fuel Pump Room 1 03-Jul-2024 04-Jul-2024 Civil
1 nos inspection in given time period

191 EIFS Surface Preparation 10-Jul-2024 11-Jul-2024 Civil


1 nos inspection in given time period

192 EIFS Rock Wool & Accessories Installation Completion 14-Jul-2024 15-Jul-2024 Civil
1 nos inspection in given time period
193 Roof Cutout Closing-Prepour 15-Jul-2024 17-Jul-2024 Civil
1 inspection during this period
194 Final Water Leakage Test 15-Jul-2024 30-Jul-2024 Civil 04 inspection during this period
195 Completion Of Steel Structure Erection For Access Platform 02-Jul-2024 02-Jul-2024 Civil

COMBO WATERPROOFING (ZONE 01,02,03,04,08&09- ROOF)

196 Surface Preparation 01-Jun-2024 30-Jun-2024 Civil 01 inspection during this period
197 Water Leakage Test 01-Jun-2024 30-Jun-2024 Civil 3 inspection during this period
198 Screed Prepour 01-Jun-2024 30-Jun-2024 Civil 3 inspection during this period
199 Screed Joint Treatment Surface Preparation 01-Jun-2024 30-Jun-2024 Civil 2 inspection during this period
FUEL YARD

200 Backfilling 15-Jul-2024 16-Jul-2024 Civil

201 Antitermite Treatment 18-Jul-2024 19-Jul-2024 Civil

202 Blinding Work 21-Jul-2024 22-Jul-2024 Civil

GENERATOR COMPOUND 1/CUB

202 Coal Tar Epoxy Surface Preparation 30-Jun-2024 01-Jul-2024 Civil

203 Coal Tar Epoxy Completion 03-Jul-2024 04-Jul-2024 Civil

204 Backfilling 06-Jul-2024 07-Jul-2024 Civil

205 Antitermite Treatment 06-Jul-2024 07-Jul-2024 Civil

206 Blinding Work 10-Jul-2024 11-Jul-2024 Civil

207 Footing Prepour 20-Jul-2024 21-Jul-2024 Civil

DRYWALL PARTITION SYSTEM(MAIN BUILDING-LEVEL01,03,04,05,06 & ANNEX BUILDING)

208 Setting Out (Level 01,03&04-Zone 01,02,03,04/ Annex Building- Level 00, 01&02) 01-Jul-2024 31-Jul-2024 Civil
16 inspection during this period
209 Installation Of Framing For Drywall Partition & Lining 01-Jul-2024 31-Jul-2024 Civil
15 inspection during this period
EXTERNAL WORK

210 Existing Level Cutting 01-Jul-2024 02-Jul-2024 Civil

211 Pcc-Foul And Storm Water Manhole 03-Jul-2024 04-Jul-2024 Civil

212 Wall Reinforcement-Foul And Storm Water Manhole 07-Jul-2024 08-Jul-2024 Civil

213 Formwork & Prepour Concrete--Foul And Storm Water Manhole 09-Jul-2024 10-Jul-2024 Civil

214 Surface Preparation For Caol Tar Epoxy-Foul And Storm Water Manhole 11-Jul-2024 14-Jul-2024 Civil

215 Completion Of Coal Tar Epoxy-Foul And Storm Water Manhole 15-Jul-2024 16-Jul-2024 Civil

216 Excavation For Pipe Trenches 22-Jul-2024 23-Jul-2024 Civil

217 Pipeline Laying-Foul And Storm Water 24-Jul-2024 25-Jul-2024 Civil

218 Pipeline Fixing-Foul And Storm Water 28-Jul-2024 28-Jul-2024 Civil

219 Backfilling-Pipe Trenches 29-Jul-2024 30-Jul-2024 Civil

220 Pipe Encasement 31-Jul-2024 2024-aug-03 Civil

221 Installation Of Kerbstone 01-Jul-2024 02-Jul-2024 Civil

222 Kerbstone-Pcc 03-Jul-2024 04-Jul-2024 Civil

223 Pcc-Street Light Foundation 07-Jul-2024 08-Jul-2024 Civil

224 Footing- Street Light Foundation 09-Jul-2024 10-Jul-2024 Civil

225 Pedestal Casting- Street Light Foundation 11-Jul-2024 14-Jul-2024 Civil

226 Excavation- Lifting Station 18-Jul-2024 21-Jul-2024 Civil

227 Pcc- Lifting Station 22-Jul-2024 23-Jul-2024 Civil

228 Footing Reinforcement- Lifting Station 24-Jul-2024 25-Jul-2024 Civil

229 Formwork And Concrete- Lifting Station 28-Jul-2024 28-Jul-2024 Civil

230 Wall Reinforcement- Lifting Station 29-Jul-2024 30-Jul-2024 Civil

231 Wall Formwork And Concrete- Lifting Station 31-Jul-2024 03-Aug-2024 Civil

232 Excavation-Main Boundary Wall 01-Jul-2024 02-Jul-2024 Civil

233 Pcc- Main Boundary Wall Footing 03-Jul-2024 04-Jul-2024 Civil

234 Footing Reinforcement-Main Boundary Wall 07-Jul-2024 08-Jul-2024 Civil

235 Formwork And Concrete- Main Boundary Wall 09-Jul-2024 10-Jul-2024 Civil
236 Column Reinforcement- Main Boundary Wall 11-Jul-2024 14-Jul-2024 Civil

237 Column Formwork And Concrete- Main Boundary Wall 15-Jul-2024 16-Jul-2024 Civil

238 Surface Preparation For Coal Tar Epoxy- Main Boundary Wall 18-Jul-2024 21-Jul-2024 Civil

239 Completion Of Coal Tar Epoxy-Main Boundary Wall 22-Jul-2024 23-Jul-2024 Civil

240 Backfilling-Main Boundary Wall 22-Jul-2024 23-Jul-2024 Civil

ZONE 08 - STAIRCASE CORE WALL

241 Rush Coat Application 01-Jul-2024 03-Jul-2024 Civil 3 times inspection will be raised
242 Completion Of Plastering 07-Jul-2024 08-Jul-2024 Civil

ZONE 04 - STAIRCASE COREWALL

243 Surface Preparation And Accessories Fixing 06-Jul-2024 10-Jul-2024 Civil 3 times inspection will be raised
244 Rush Coat Application 15-Jul-2024 18-Jul-2024 Civil 3 times inspection will be raised
245 Completion Of Plastering 24-Jul-2024 25-Jul-2024 Civil

AUDITORIUM FIRE PROOF PAINTING

245 Level 00 Base Coat Completion 02-Jul-2024 06-Jul-2024 Civil

246 Level 01 Base Coat Completion 04-Jul-2024 08-Jul-2024 Civil

247 Level 02 Base Coat Completion 06-Jul-2024 10-Jul-2024 Civil

248 Level 00 Hard Top XP Coat Final Inspection 04-Jul-2024 08-Jul-2024 Civil

249 Level 01 Hard Top XP Coat Final Inspection 08-Jul-2024 12-Jul-2024 Civil

250 Level 02 Hard Top XP Coat Final Inspection 10-Jul-2024 14-Jul-2024 Civil

LINER PANNEL INSTALLATION

251 Halter And Rockwool Completion 10-Jul-2024 12-Jul-2024 Civil

252 Standing Seam Sheet Installation 18-Jul-2024 20-Jul-2024 Civil

253 Zone 01 Level 03 Surface Preparation For Multi Coat Rendering 28-Jul-2024 30-Jul-2024 Civil

ZONE 02 LEVEL 03 SURFACE PREPARATION FOR MULTI COAT RENDERING

254 Zone 03 Level 03 Surface Preparation For Multi Coat Rendering 02-Jul-2024 03-Jul-2024 Civil

255 Zone 04 Level 03 Surface Preparation For Multi Coat Rendering 04-Jul-2024 07-Jul-2024 Civil

256 Zone 05 Level 03 Surface Preparation For Multi Coat Rendering 09-Jul-2024 13-Jul-2024 Civil

257 Zone 05 Level 03 Surface Preparation For Multi Coat Rendering 14-Jul-2024 17-Jul-2024 Civil
258 Royal Guard House Surface Preparation For Multi Coat Rendering 18-Jul-2024 21-Jul-2024 Civil

259 Main Guard House Surface Preparation For Multi Coat Rendering 22-Jul-2024 25-Jul-2024 Civil

260 Royal Guard House Surface preparation for multi coat rendering 27-Jul-2024 29-Jul-2024 Civil

261 Main Guard House Surface preparation for multi coat rendering 31-Jul-2024 02-Aug-2024 Civil

ZONE 01 - STAIRCASE COREWALL

263 Surface Preparation And Accessories Fixing 10-Jun-2024 12-Jun-2024 Civil 3 times inspection will be raised
264 Rush Coat Application 15-Jun-2024 17-Jun-2024 Civil 3 times inspection will be raised
ZONE 03 - STAIRCASE COREWALL

264 Surface Preparation And Accessories Fixing 12-Jun-2024 14-Jun-2024 Civil


3 times inspection will be raised
265 Rush Coat Application 17-Jun-2024 19-Jun-2024 Civil 3 times inspection will be raised
ZONE 03A SUB STATION - 01 TRENCH WALL

266 Wall Reinforcement 06-Jul-2024 08-Jul-2024 Civil


3 times inspection will be raised
267 Wall Formwork And RCC 11-Jul-2024 31-Jul-2024 Civil 3 times inspection will be raised
ZONE 02A SUB STATION - 02 TRENCH WALL

268 Wall Reinforcement 08-Jul-2024 10-Jul-2024 Civil 3 times inspection will be raised
269 Wall Formwork And RCC 13-Jul-2024 28-Jul-2024 Civil
3 times inspection will be raised
ZONE 07 SUB STATION - 03 TRENCH WALL

270 Wall Reinforcement 10-Jul-2024 14-Jul-2024 Civil


3 times inspection will be raised

271 Wall Formwork And RCC 16-Jul-2024 31-Jul-2024 Civil


3 times inspection will be raised
WATER TANK LV ROOM SUB STATION - 04 TRENCH WALL

272 Wall Reinforcement 10-Jul-2024 14-Jul-2024 Civil 3 times inspection will be raised
273 Wall Formwork And RCC 16-Jul-2024 26-Jul-2024 Civil 3 times inspection will be raised