3. Quantity of Cement, Sand and Gravel for Slab and Walls per Square Meter
Area
Mixture Class
Slab
Sand Gravel
Thickness 40 kg cement 50 kg cement
cu. m. cu. m.
cm
A B C A B C
5 0.45 0.375 0.3 0.35 0.3 0.25 0.025 0.05
7.5 0.675 0.5626 0.45 0.525 0.45 0.375 0.15 0.075
10 0.9 0.7502 0.6 0.7 0.6 0.5 0.275 0.1
12.5 1.125 0.9378 0.75 0.875 0.75 0.625 0.4 0.125
15 1.35 1.1254 0.9 1.05 0.9 0.75 0.525 0.15
17.5 1.575 1.313 1.05 1.225 1.05 0.875 0.65 0.175
20 1.8 1.5006 1.2 1.4 1.2 1 0.775 0.2
22.5 2.025 1.6882 1.35 1.575 1.35 1.125 0.9 0.225
25 2.25 1.8758 1.5 1.75 1.5 1.25 1.025 0.25
27.5 2.475 2.0634 1.65 1.925 1.65 1.375 1.15 0.275
30 2.7 2.251 1.8 2.1 1.8 1.5 1.275 0.3
4. Quantity of Cement, Sand and Gravel for Post Beam and Girder Per Meter
Length
Mixture Class
50 kg Sand Gravel
Size cm. 40 kg cement
cement
A B A B cu.m. cu.m.
15 x 20 0.27 0.225 0.21 0.18 0.15 0.03
15 x 25 0.3375 0.2813 0.263 0.225 0.019 0.038
15 x 30 0.405 0.3376 0.315 0.27 0.023 0.045
15 x 35 0.4725 0.3939 0.369 0.315 0.026 0.053
15 x 40 0.54 0.4502 0.42 0.36 0.03 0.06
5. Quantity of Cement, Sand and Gravel per Meter Length of Circular Column
Col. Dia. Mixture Class Sand Gravel
40 kg cement 50 kg cement
cm.
A B A B cu.m. cu.m.
25 0.442 0.368 0.344 0.295 0.025 0.05
30 0.636 0.53 0.495 0.424 0.35 0.07
35 0.866 0.722 0.673 0.577 0.048 0.096
40 1.131 0.942 0.88 0.754 0.063 0.126
50 1.767 1.473 1.374 1.178 0.098 0.196
55 2.138 1.782 1.663 1.425 0.119 0.238
60 2.545 2.121 1.979 1.696 0.141 0.282
65 2.986 2.488 2.323 1.991 0.166 0.332
70 3.464 2.886 2.694 2.309 0.192 0.384
75 3.976 3.313 3.093 2.651 0.221 0.442
80 4.524 3.770 3.519 3.016 0.251 0.502
85 2.107 4.256 3.972 3.405 0.284 0.568
90 5.726 4.771 4.453 3.817 0.318 0.636
100 7.069 5.890 5.498 4.712 0.393 0.786
7. Quantity of Cement and Sand for Mortar and Plaster in Cubic Meter
8. Quantity of Cement and Sand for CHB Mortar per Square Meter
Size of Numbe Bags Cement Mixture
CHB in r per
cm. sq. m.
A B C D Sand cu. m.
10x20x4 0.79 0.52 0.39 0.32
12.5 0.0435
0 2 2 4 8
15x20x4 1.52 1.01 0.76 0.63
12.5 0.0844
0 6 8 3 3
20x20x4 1.12 0.93
12.5 2.26 1.5 0.125
0 5 8
9. Quantity of
Cement and Sand per One Hundred Blocks
Size of Cement in Bags 40 kg Mixture Sand
CHB in
cu. m.
cm. A B C D
10x20x40 6.336 4.176 3.152 2.624 0.348
15x20x40 12.15 8.104 6.072 5.064 0.675
20x20x40 18.072 12 9 7.504 1
10. Quantity of Cement and Sand for Plaster per Square Meter Area
11. Quantity of Cement, Sand and Gravel for CHB Footing per Meter Length
Dimension Aggregate
Cement in Bags
Centimeter s
s Class Mixture Sand Gravel
T x W A B C cu.m. cu. m.
10 x 30 0.27 0.225 0.18 0.015 0.3
10 x 35 0.315 0.263 0.21 0.018 0.35
10 x 40 0.36 0.3 0.24 20 0.4
10 x 50 0.45 0.375 0.3 0.025 0.05
15 x 40 0.54 0.45 0.36 0.3 0.06
15 x 45 0.612 0.51 0.048 0.034 0.068
15 x 50 0.675 0.563 0.55 0.038 0.076
15 x 60 0.81 0.675 0.54 0.045 0.09
12. Quantity of Decorative Blocks Cement and Sand per 100 Blocks
Cement in Bags at 40 kg Sand
Class mixture per
Size in cm Number 100
per sqm A B Blocks
5 x 10 200 0.18 0.12 0.01
5 x 15 133 0.27 0.18 0.015
5 x 20 100 0.36 0.24 0.02
5 x 25 80 0.45 0.3 0.025
10 x 20 50 0.72 0.48 0.04
10 x 25 40 0.9 0.6 0.05
10 x 30 33 1.08 0.72 0.06
13. Quantity of Cement and Sand for Various Types of Bricks per 100 Blocks
14. Quantity of Cement and Sand for Adobe Mortar per Square Meter
15. Quantity of Abode Stone Cement and Sand for Buttresses and Footings
Buttress and Footing Cement per Meter ht.. Sand
Number of
Buttress Cross No. of
stone per M. A B C cu.m.
Section Course
ht.
30 x 45 2 12 0.233 0.156 0.117 0.013
45 x 45 3 18 0.35 0.233 0.175 0.019
45 x 60 4 24 0.468 0.312 0.234 0.026
45 x 75 5 30 0.583 0.389 0.292 0.032
45 x 95 6 36 0.702 0.468 0.351 0.039
* Mortar at an average thickness of 16 mm
16. Quantity of Cement and Sand for Plastering Adobe Stone per Square Meter
Cement in Bags 40 kg
Mixture Sand
Side
cu. m.
B C D
One Face 0.24 0.18 0.15 0.02
Two Faces 0.48 0.36 0.3 0.04
*Cement Plaster at an average thickness of 20mm
17. Quantity of Cement and Sand on a Stone Rip-Rap per Cubic Meter
Cement in Bags
Stone Class Grout Mixture Sand cu. m.
A B C
Class-A 2.574 1.716 1.287 0.143
Class-B 2.448 1.62 1.214 0.135
Class-C 2.232 1.488 1.116 0.124
Class-D 1.944 1.296 0.972 0.108
Class A - Stone ranging from 15 to 25 kg with at least 50% of the stones weighing more
than 20kg
Class B- Stone ranging from 30 to 70 kg. With at least 50% of the stones weighing
more than 50kg.
Class C- Stone ranging from 60 to 100 kg. With at least 50% of the stones weighing
more than 80kg.
Class D- Stone ranging from 100 to 200 kg. With at least 50% of the stones weighing
more than 150kg.
Vertical Horizontal
Reinforcement Reinforcememnt
Spacin
Spacin Length of bars in Length of Bars in
g
g meter meter
Layer
Per Per Sq . Per Per Sq .
Block M. Block M.
40 0.235 2.93 2 0.264 3.3
60 0.171 2.13 3 0.172 2.15
80 0.128 1.6 4 0.138 1.72
23. No. G.I. Tie Wire for CHB Reinforcement per Square Meter
Bar No.
Inches mm .
Designation
2 1/4 6
3 3/8 10
4 1/2 12
5 5/8 16
6 3/4 20
7 7/8 22
8 1 25
9 1 1/8 28
10 1 1/4 31
11 1 3/8 35
12 1 1/2 38
13 1 5/8 41
14 1 3/4 44
16 2 50
18 2 1/4 65
25. Number of Lateral Ties in One Steel Bar and Quantity per Meter Length of
Column
Number Length
Lateral of of Ties Number of Cut in One Steel Bar Length
Ties Lateral with
Spacing tiesper Hoow & 5 M. 6 M. 7.5 M. 9 M. 12 M.
M. ht. Bend
15 6.7 60 X 10 X 15 20
0.7 7 X x X 17
20 5.15 80 6 X X 11 15
85 X 7 X X 14
25 4.13 90 x X 8 10 13
95 5 x X X X
30 3.43 100 5 6 X 9 12
105 X x 7 x X
35 3 110 X X X 8 X
115 X 5 X X x
40 2.64 120 4 5 X X 10
125 4 X 6 X X
45 2.36 130 X X X X 9
135 X X X X X
50 2.14 140 X 4 X x X
145 X 4 5 6 X
55 1.96 150 X 4 5 6 8
160 3 X X X X
60 1.81 170 X X X 5 7
180 X X 4 5 X
190 X 3 X x 6
200 X 3 X X 6
26. Number of Spiral Reinforcing Bars per Meter Height
No. of
Column Pitch Number of Steel Bars from a
Turn
per Meter
Dia . cm . cm . 6.00 m . 9.00 m . 12.00 m .
ht
5 21 2.604 1.706 1.269
30 6.25 17 2.108 1.381 1.027
7.5 14.3 1.778 1.165 0.866
5 21 2.894 1.896 1.41
32.5 6.25 17 2.342 1.535 1.141
7.5 14.3 1.975 1.294 0.962
5 21 3.183 2.085 1.55
35 6.25 17 2.577 1.688 1.255
7.5 14.3 2.172 1.423 1.058
5 21 3.472 2.275 1.692
37.5 6.25 17 2.811 1.842 1.393
7.5 14.3 2.37 1.524 1.154
5 21 3.762 2.465 1.833
40 6.25 17 3.045 1.995 1.484
7.5 14.3 2.567 1.682 1.251
5.00 21 4.051 2.654 1.974
42.5 6.25 17 3.281 2.149 1.598
7.5 14.3 2.765 1.812 1.347
5 21 4.34 2.844 2.115
45 6.25 17 3.513 2.302 1.712
7.5 14.3 2.962 1.94 1.443
5 21 4.63 3.033 2.256
47.5 6.25 17 3.748 2.455 1.826
7.5 14.3 3.159 2.07 1.539
5 21 4.919 3.223 2.397
50 6.25 17 3.982 2.609 1.94
7.5 14.3 3.357 2.199 1.635
5 21 5.498 3.602 2.678
55 6.25 17 4.525 3.017 2.253
7.5 14.3 3.752 2.524 1.888
5 21 6.077 3.981 2.96
60 6.25 17 4.919 3.223 2.396
7.5 14.3 4.146 2.717 2.02
70 6.25 17 5.856 3.837 2.853
7.5 14.3 4.936 3.234 2.405
5 21 8.391 5.498 4.088
80 6.25 17 6.793 4.451 3.31
7.5 14.3 5.726 3.752 2.79
5 21 9.549 6.256 4.652
90 6.25 17 7.73 5.064 3.766
7.5 14.3 6.366 4.171 3.101
5 21 10.706 7.014 5.216
100 6.25 17 8.667 5.678 4.222
7.5 14.3 7.137 4.676 3.477
28. Quantity of Tie Wire on a One-Way Reinforced Concrete Slab in kg per sqm.
6M 7.5M 9M 12M
Bar
Spacing
in cm 0.3 0.4 0.3 0.4 0.3 0.4 0.3 0.4
29. Quantity of Steel Bars in a Two-Way Reinforced Concrete Slab per sqm.
Bar of
Numbe per
Spacing Steel Meter
r Square
in Bars
Centimeter
6.00 M 7.50 M 9.00 M 12.00M
s
10 4.369 3.337 2.772 2.022
12.5 3.603 2.662 2.245 1.535
15 3.221 2.296 1.921 1.39 :
17.5 2.647 2.025 1.65 1.196
20 2.36 1.775 1.461 1.056
22.5 2.168 1.601 1.312 0.907
25 1.977 1.466 1.217 0.862
Sources:
“Simplified Construction Estimate, Third Edition” by Max B. Fajardo Jr.