0% found this document useful (0 votes)
22 views15 pages

Sample Problem QP

Sample question paper bca cloud computing
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views15 pages

Sample Problem QP

Sample question paper bca cloud computing
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 15

UNIT -1: LINEAR PROGRAMMING MODELS

1. A Company is producing two products A and B. The resource requirements per unit of
each of the products and total Availability are given below. Formulate the above
Information as a LPP Model and solve it by graphical method.

Product A B Total Availability


Man Hours/Unit 6 3 200 Man Hours
Machine Hours/Unit 2 5 350 Machine Hours
Material/Unit 1kg 2kg 100kgs
Profit 20 25

2. Solve the following LPP by graphical method


Max Z = 2x1+3x2
Subjected to
x1+x2 ≤ 30
x1 ≤ 20
x2 ≤ 12
x2 ≥3 and x1,x2 ≥ 0
3. Solve the following LPP by graphical method
Maximize Z= x1+4x2
Subjected to 3x1+x2 ≤ 3
2x1+3x2 ≤ 6
4x1+5x2 ≥20 and x1,x2 ≥ 0

4. Solve the following LPP by Graphical method.

Minimize Z=4x+5y
Subjected to
x+y≥10;
2x+5y≥35 and x, y≥0.
5. Solve the following LPP by graphical method.
Max Z = 3X1 + 2X2
Subjected to
2X1 + X2 ≤ 2
3X1 + 4X2 ≥ 12 and X1, X2 ≥ 0

6. Solve the following LPP by simplex method,


Maximize Z= 6x1+9x2
Subjected to
x1+x2 ≤ 12
x1+5x2 ≤ 45
3x1+x2≤ 30 and x1, x2 ≥ 0.
7. Solve the following LPP by simplex method.
Maximize Z=3X1+2X2
Subjected to
X1+X2  4,
X1-X2≤ 2 and X1, X2 ≥0.
8. Solve the following LPP by simplex method,
Maximize Z= 6x1+9x2
Subjected to
x1+x2 ≤ 12
x1+5x2 ≤ 45
3x1+x2≤ 30 and x1, x2 ≥ 0.

9. Solve the following LPP by simplex method.


Max Z = 3X1 + 2X2
Subjected to 2X1 + X2 ≤ 2
3X1 + 4X2 ≥ 12
and X1, X2 ≥ 0

10. Solve the following problem by Big M method


Maximize Z= x1+4x2
Subjected to
3x1+x2 ≤ 3
2x1+3x2 ≤ 6
4x1+5x2 ≥20 and x1,x2 ≥ 0
11. Solve the following by Big M method.
Maximize Z=12X1+20X2.
Subjected to 6X1+8X2  100,
7X1 +12X2  120 and X1, X2  0.

12. Solve the following LPP by Big M method.


Max Z = 3X1 + 2X2
Subjected to
2X1 + X2 ≤ 2
3X1 + 4X2 ≥ 12 and X1, X2 ≥ 0
13. Solve the following problem by two-phase method
Maximize Z= x1+4x2
Subjected to
3x1+x2 ≤ 3
2x1+3x2 ≤ 6
4x1+5x2 ≥20 and x1,x2 ≥ 0

14. Solve the following LPP by Two phase method

Min Z = 12x1+20x2
Subjected to
6x1+8x2 ≥100
7x1+12x2 ≥120 and x1,x2,x3≥ 0
15. Solve the following LPP by Two phase method
Maximize Z=X1+5X2+3X3.
Subjected to X1+2X2+X3=3
2X1-X2=4 and X1, X2, X3  0.
Unit – 2: TRANSPORTATION AND ASSIGNMENT PROBLEMS

1. Find the optimum solution to the following transportation problem.

Factory Ware House Capacity


D E F G
A 1 2 1 4 30
B 3 3 2 1 50
C 4 2 5 9 20
Demand 20 40 30 10 100

2. Solve the following transportation problem


Factory Ware House Capacity
W1 W2 W3 W4
F1 11 20 7 8 50
F2 21 16 10 12 40
F3 8 12 18 9 70
Demand 30 25 35 40

3. Find the optimal solution to the following transportation problem.


Warehouse
Factory W1 W2 W3 W4 Capacity
F1 6 8 8 5 30
F2 5 11 9 7 40
F3 8 9 7 13 60
Demand 35 28 32 25

4. Find the optimal solution to the following problem

D1 D2 D3 Availability
O1 2 7 4 5
O2 3 3 1 8
O3 5 4 7 7
O4 1 6 2 14
Requirements 7 9 18
5. Find the optimal solution to the following transportation problem

D1 D2 D3 D4 Availability
O1 6 4 1 5 14
O2 8 9 2 7 16
O3 4 3 6 2 5
Demand 6 10 15 4

6. Find the optimal solution to the following transportation problem

D1 D2 D3 Availability
S1 6 10 15 2
S2 4 6 16 5
S3 12 5 8 9
Requirements 1 8 7

7. Find the optimal solution to the following transportation problem


D1 D2 D3 Availability
S1 1 2 6 7
S2 8 4 2 12
S3 3 7 5 11
Requirements 10 10 10

8. Solve the following assignment problem.

Jobs
J1 J2 J3 J4
W1 10 15 24 30
Workers

W2 16 20 28 10
W3 12 18 30 16
W4 9 24 32 18

9. The assignment costs of four operators to four machines are given in the following table.
What are the operator assignments which minimizes the total cost?

Operators
I II III IV
A 10 5 13 15
Machines

B 3 9 18 3
C 10 7 3 2
D 5 11 9 7
10. A Salesman has to visit five cities A, B, C, D, and E. The distances (in hundred
kilometers) between the five cities are shown in table below. If the salesman starts
from city A and has to come back to city A, which route should he select so that total
distance travelled is minimum?

A B C D E
A - 3 6 2 3
B 3 - 5 2 3
C 6 5 - 6 4
D 2 2 6 - 6
E 3 3 4 6 -

11. Find the optimal solution to the following Assignment problem.

J1 J2 J3 J4
A 10 15 24 30
B 16 20 28 10
C 12 18 30 16
D 9 24 32 18

12. Solve the travelling salesman problem with the following cost matrix

Cities
A B C D
A ∞ 46 16 40
B 41 ∞ 50 40
Cities

C 82 32 ∞ 60
D 40 40 36 ∞

13. Solve the following Assignment problem.

J1 J2 J3 J4 J5
A - 4 10 14 2
B 12 - 6 10 4
C 16 14 - 8 14
D 24 8 12 - 10
E 2 6 4 16 -
14. Solve the following Assignment problem

J1 J2 J3 J4 J5
A - 3 6 2 3
B 3 - 5 2 3
C 6 5 - 6 4
D 2 2 6 - 6
E 3 3 4 6 -

15. A sales man has to visit five cities A,B,C,D, and E. The distances (in 100 km) between
any two cities are given in the following table. The sales man starts from A and has to
come back to A after visiting all other cities in a cycle. Which route he has to select in
order that the total distance traveled by him is minimum?

A B C D E
A - 4 7 3 4
B 4 -` 6 3 4
C 7 6 - 7 5
D 3 3 7 - 7
E 4 4 5 7 -
Unit – 3: Network Models and Sequencing Models
1. For a certain project the data is given below. Draw the network diagram, identify the
critical path and compute the minimum time required to complete the project.

Activity 1-2 1-4 1-7 2-3 3-6 4-5 4-8 5-6 6-9 7-8 8-9
Expected time 2 2 1 4 1 3 8 4 3 3 5
(in months)

2. A small project is composed of seven activities whose time estimates in weeks are
given below. Draw the network and find the critical path. What is the probability that
the project will be completed at least four weeks earlier than expected?

Activity 1-2 1-3 1-4 2-5 3-5 4-6 5-6


Optimistic time 1 1 2 1 2 2 3
Most likely time 1 4 2 1 5 5 6
Pessimistic time 7 7 8 1 14 8 15

3. A Project consists of the following activities and time estimation

Activity Estimated Duration in Weeks


Optimistic Most Likely Pessimistic
(1,2) 1 1 7
(1,3) 1 4 7
(1,4) 2 2 8
(2,5) 1 1 1
(3,5) 2 5 14
(4,6) 2 5 8
(5,6) 3 6 15
a) Draw the network.
b) Find the expected time and variance for each activity.
c) What is the probability that the project will be completed 4 weeks earlier than the
expected time.
4. For a certain project the data is given below. Draw the network diagram, identify the
Critical path and compute the project duration (in months) and also find the total float.
Activity 1-2 1-4 1-7 2-3 3-6 4-5 4-8 5-6 6-9 7-8 8-9
2 2 1 4 1 3 8 4 3 3 5
Time
5. A small project is composed of seven activities whose time estimates in weeks are
given below. Find the critical path. What is the probability that the project will be
completed at least four weeks earlier than expected?

activity 1-2 1-3 1-4 2-5 3-5 4-6 5-6


Optimistic time 1 1 2 1 2 2 3
Most likely time 1 4 2 1 5 5 6
Pessimistic time 7 7 8 1 14 8 15

6. A Project consists of the following activities and time estimation. Draw the network
and Find the minimum time required to complete the project.

duration Activity duration


Activity weeks weeks
(1,2) 2 (5,8) 5
(2,3) 7 (6,7) 8
(2,4) 3 (6,10) 4
(3,4) 3 (7,9) 4
(3,5) 5 (8,9) 1
(4,6) 3 (9,10) 7

7. A project is composed of the following activities whose time estimates in weeks are
given below. Draw the network, identify the critical path and compute the minimum
time required to complete the project.
Activity A B C D E F G H
Immediate predecessor(s) - A A B C C D,E F,G
Duration in weeks 3 4 2 5 1 2 4 3

8. A project is composed of the following activities whose time estimates in days are
given below. Draw the network, identify the critical path and compute the minimum
time required to complete the project.
Activity A B C D E F
Immediate predecessor(s) - A A B C D,E
Duration in weeks 2 5 1 1 6 1
9. A book binder has one printing press, one binding machine and manuscripts of 7
different books. The times required for performing printing and binding operations for
different books are shown in table below. Decide the optimum sequence of processing
of books in order to minimize the total time required to bring out all the books.

Book 1 2 3 4 5 6 7
Printing time
20 90 80 20 120 15 65
in hours
binding time in
25 60 75 30 90 35 50
hours

10. Determine the optimal sequencing of the following 7 jobs on two machines, Machine 1
and Machine 2. Also find the makespan, idle time of Machine 1& 2.

Job 1 2 3 4 5 6 7
Machine 1 3 12 15 6 10 11 9
Machine 2 8 10 10 6 12 1 3
UNIT – 4 Game Theory
1. Mr Girish wants to invest Rs 10,000 in one of the three options A, B and C.
The pay-off for his investment depends on the nature of the economy (inflation (E1),
recession (E2) or no change (E3)). The possible returns under each economic situation
are given below:
Strategies Nature of economy
E1 E2 E3
A 2000 1200 1500
B 3000 800 1000
C 2500 1000 1800

What course of action has he to take according to:


(i) Maximin criterion (ii) Maximax (iii) Hurwicz criterion with alpha = 0.6 and
(iv) Laplace criterion?

2. A company wants to introduce a new product in place of an old one. It is to be


decided whether the price is to be fixed as very high, moderate or slightly increased (H,
M or S). Three possible outcomes are expected, viz. increase in sales, no change in sales
or decrease in sales (I, N or D). The expected sales are given in the following table (in
lakhs of rupees)

Strategies Events
I N D
H 70 30 15
M 50 45 0
S 30 30 30
Which alternative should be chosen according to (i) Maximin criterion (ii) Maximax (iii)
Hurwicz criterion with alpha = 0.7 and (iv) Laplace criterion?
3. Solve the following game by dominance principle.

Strategies (Player B
B1 B2 B3 B4
A1 3 2 4 0
Strategies A2 3 4 2 4
(Player A) A3 4 2 4 0
A4 0 4 0 8
4. Solve the following game graphically..

B1 B2
A1 -6 7
A2 4 -5
A3 -1 -2
A4 -2 5
A5 7 -6
5. Solve the following game graphically.

B1 B2 B3 B4
A1 2 1 0 -2
A2 1 0 3 2

6. Solve the following game by dominance principle.

Strategies (Player B
B1 B2 B3 B4
A1 5 -10 9 0
Strategies A2 6 7 8 1
(Player A) A3 8 7 15 1
A4 3 4 -1 4

7. Solve the following game by dominance principle.

Strategies (Player B
B1 B2 B3 B4
A1 19 6 7 5
Strategies A2 7 3 14 6
(Player A) A3 12 8 18 4
A4 8 7 13 -1
8. Solve the following game by dominance principle.

Strategies (Player B
B1 B2 B3 B4
A1 1 7 3 4
Strategies
A2 0 2 7 8
(Player A)
A3 5 1 6 7
9. Describe the following terms: saddle point, minimax criteria, dominance principle,
strategy, zero sum game.

10. Solve the following game by dominance principle.

Strategies (Player B
B1 B2 B3 B4
A1 2 -2 4 1
Strategies A2 6 1 12 3
(Player A) A3 -3 2 0 6
A4 2 -3 7 1
UNIT – 5: QUEUEING THEORY

1. At a cycle repair shop on an average, a customer arrives every 5 minutes and on an


average the service time is 4 minutes per customer. Suppose that the inter arrival time
follows Poisson distribution and the service times are exponentially distributed. Find L s,
L q, Ws,, W q, shop busy and idle. Assuming that there is only one server.
2. In railway yard goods trains arrive at the rate of 30 trains per day. Assuming that the
service time follows exponential distribution with an average of 36 minutes, find
a) The probability that the number of trains in the yard exceeds 10.
b) The average number of trains in the yard.
3. In a store with one server,9 customers arrive on an average of 5 minutes. Service is done
for 10 customers in 5 minutes. Find
a) The average number of customers in the system.
b) The average queue length.
c) The average time a customer spends in the store.
d) The average time a customer waits before being served.
4. In a telephone booth, the arrivals follow Poisson distribution with an average of 9
minutes between two consecutive arrivals. The duration of a telephone call is exponential
with an average of 3 min.
a) Find the probability that a person arriving at the booth has to wait.
b) Find the average queue length
c) Find the fraction of the day, the phone will be in use
d) The company will install a second booth if a customer has to wait for phone, for at
least 4 minutes. If so, find the increase in the flow of arrivals in order that another booth
will be installed.
5. A T.V repairman finds that the time spent on his jobs has an exponential distribution with
mean 30 minutes. If the repairs sets in the order in which they come, and if the arrival of
sets is approximately poisson with an average rate of 10 per 8 hour day. The is
repairman`s expected idle time each day? How many jobs are ahead of the average set
just brought in?
6. A foreign bank is considering opening a drive-in window for customer service.
Management estimates that customers will arrive for service at the rate of 12 per hour.
The teller whom it is considering to staff the window can serve customers at the rate of
one every three minutes. Assuming Poisson arrival and exponential service, find: (a)
Utilization of teller (b) average number of customers in the system (c) average waiting
time in the line (d) average waiting time in the system.
7. At a railway station only one train is handled at a time. The yard can accommodate only
two trains to wait. Arrival rate of trains is 6 per hour and the railway station can handle
them at the rate of 12 per hour. Find the steady state probabilities for the various number
of trains in the system. Also find the average waiting time of a newly arriving train.
8. The capacity of a queuing system is 4. Inter-arrival time of the units is 20 minutes and the
service time is 36 minutes per unit. Find the probability that a new arrival enters into
service without waiting. Also find the average number of units in the system.
9. Patients arrive at a clinic at the rate of 30 patients per hour. The waiting hall cannot
accommodate more than 14 patients. It takes 3 minutes on the average to examine a
patient.
a) Find that probability that an arriving patient need not wait.
b) Find the probability that an arriving patient finds a vacant seat in the hall.
c) What is the expected duration of time a patient spends in the clinic?
.

You might also like