NEDC Distribution System Capability Statement
NEDC Distribution System Capability Statement
In addition to the required data made available annually as part of DSCS; NEDC additionally has
provided improved detailed system connectivity and additional technical data of assets, impact analysis
of Cost Reflective Tariff (CRT) on NEDC customers and an overview of the Low Carbon Technologies
(LCTs) especially the photovoltaic (PV) system penetration in the NEDC distribution system which is
gaining momentum in our licenced area as well. These additions are expected to provide customers and
other stakeholders with a transparent understanding of NEDC distribution system and operational
overview, sufficient technical parameters to undertake initial system capabilities assessment and the
overall distribution system development.
NEDC have determined this three-year plan to clarify and highlight NEDC’s key priorities over the DSCS
planning period. The plan will form the basis for the company’s investments to provide economic and
efficient system development along with serving to inform NEDC’s contributions to the Oman electricity
sector and in turn aligning with the Oman Vision 2040 goals.
PREFACE 1
LIST OF TABLES 3
LIST OF FIGURES 4
LIST OF ABBREVIATIONS 5
1. INTRODUCTION 1
1.1. WHO WE ARE & WHAT WE DO ............................................................................................................................... 1
1.2. NEDC KEY STATISTICAL DATA .............................................................................................................................. 3
1.3. PURPOSE OF STATEMENT .................................................................................................................................... 3
1.4. STRUCTURE OF THIS DSCS .................................................................................................................................. 4
3. PLANNING DRIVERS 13
3.1. BACKGROUND ...................................................................................................................................................... 13
3.2. MUSCAT GOVERNORATE..................................................................................................................................... 14
3.2.1. Wilayat Muscat ........................................................................................................................................... 14
3.2.2. Wilayat Muttrah ........................................................................................................................................... 14
3.2.3. Wilayat Amerat ........................................................................................................................................... 14
3.2.4. Wilayat Quriyat ........................................................................................................................................... 14
3.2.5. Wilayat Bousher .......................................................................................................................................... 14
3.2.6. Wilayat Seeb............................................................................................................................................... 14
3.3. SOUTH AL BATINAH GOVERNORATE AND SUAWIQ AREA................................................................................ 21
3.4. AL DAKHILIAH GOVERNORATE............................................................................................................................ 25
3.5. NORTH AL SHARQIYAH GOVERNORATE ............................................................................................................ 28
3.6. SOUTH AL SHARQIYAH GOVERNORATE ............................................................................................................ 30
3.7. AL WUSTA GOVERNORATE AND SURROUNDING AREAS. ................................................................................ 32
3.8. AL BURAYMI GOVERNORATE .............................................................................................................................. 34
3.9. AL DHAHIRAH GOVERNORATE ............................................................................................................................ 36
3.9.1. Wilayat Ibri .................................................................................................................................................. 36
3.10. NORTH AL BATINAH GOVERNORATE ................................................................................................................. 38
3.10.1. Wilayat Shinas ............................................................................................................................................ 38
3.10.2. Wilayat Sohar ............................................................................................................................................. 38
Table 6: Current Ratings of Bus Bar, Bus-section, Transformer, and Feeder Bays ............................... 8
Table 10 : South Al Batinah Governorate and Suawiq Area- Grid and Primary Substations Connectivity
.............................................................................................................................................................. 21
Table 11: Al Dakhiliah Governorate- Grid and Primary Substations Connectivity ................................ 25
Table 12 :North Al Sharqiyah Areas – Power Plant, Grid, PDO and Primary Substations Connectivity
.............................................................................................................................................................. 28
Table 13:South Al Sharqiyah Areas – Power Plant, Grid, PDO and Primary Substations Connectivity
.............................................................................................................................................................. 30
Table 14 AL Wusta Governorate and Surrounding Areas – Power Plant, Grid, PDO and Primary
Substations Connectivity ....................................................................................................................... 32
Table 16: AL Dhahirah Governorate - Grid and Primary Substations Connectivity .............................. 36
Table 17: North AL Batinah Governorate - Grid and Primary Substations Connectivity ...................... 38
Table 18: Musandam Governorate - Grid and Primary Substations Connectivity ................................ 41
Table 19: Summery of Firm Capacity and Max Load per Governorate ................................................ 42
Table 24: 2023 PV connection Applications with total installed PV capacity ........................................ 60
Figure 6 : Hourly Demand – MIS System Maximum and Minimum Day Profile ................................... 45
Figure 7 : Hourly Demand – Musandam System Maximum and Minimum Day Profile ........................ 45
Figure 9 : History of NEDC Demand Not Secured and Out of Firm PSS ............................................. 47
Figure 10 : Historical Trend in NEDC System Maximum Demand with Three Years Forecast ............ 51
APSR Authority for Public Services Regulation (formerly known as AER - Authority for Electricity
Regulation)
PV Photovoltaic
Reviewer:
Aisha Saif Al Muqarshi
Acting / Planning Manager
Zone 1
Authorisation to Issue
Corporate Affairs General Yousuf Mohammed Al Mahrooqi
Manager
Request for a copy of this DSCS, the associated system studies or for any assistance in interpreting or
clarifying any information contained within it; please contact:
Email: [email protected]
The electricity sector in the Sultanate of Oman has been extensively restructured following the law’s
implementation to regulate and privatize the electricity and related water sector (“The Sector Law”).
Royal Decree 78/2004 promulgated the Law for the Regulation and Privatisation of the Electricity and
Related Water Sector. Article 90 of the D&SL places an obligation on Distribution Companies to
undertake financing, operation, maintenance, development, and expansion of the distribution system in
a safe, economic and efficient manner and in accordance with the relevant performance and security
standards.
In 2022 a direction has been taken to marge all Distribution Companies (excluding Dhofar Governorate).
In Jun 2023 Nama Electricity Distribution Company (NEDC) has been establish and it is under the
umbrella of the Nama Group and is licensed to carry out electricity network management and related
activities such as extension and new connection work in The Sultanate of Oman, except for Dhofar
Governorate.
The company is providing the following services: Planning and extension of electricity network,
connecting new properties to the electricity network, connecting additional load to existing properties,
receiving solar projects applications, receiving requests related to the work on the electricity network,
electricity drawings approval for new properties, inspection, replacement and shifting of electricity meters
of existing properties, managing scheduled and emergency outages information, testing electricity
technicians, Issuing electricity technician license, Receiving and managing requests, queries and
complaints about electricity network, receiving customers enquiries about electricity outages in
properties. The Figure 1 shows the authorized area for NEDC.
NEDC to achieve the above services, it set vision, mission and values which are:
• Vision: Nama Distribution company is a leading reference for electricity services excellence in the
Region.
• Mission: Empower Oman through safe, reliable, sustainable, economic and customer focused
electricity.
The key statistical figures related to the existing electricity distribution network are enumerated in Table
1 below:
Overhead
Underground Distribution Primary Grid Station
line (All Customer Licensed
Asset Type Cable (All Substation Substation (220/132/33
voltage Number Area
voltage levels) (11/0.415 kV) (33/11 kV) kV)
levels)
Unit km km No. No. No. No. km2
The information in the Distribution System Capability Statement (DSCS) is published annually to fulfil
NEDC regulatory obligation under Condition 33 of its Distribution and Supply Licence (D&SL) and
Distribution planning code 4.4 of the Oman Distribution Code.
This DSCS is intended to provide an understanding of NEDC’s 33kV, 11kV and LV distribution system
along with presenting NEDC’s development plans for the 33kV and 11kV distribution system for the
years 2024-2026. This statement includes power system data for the primary substation loads, overhead
lines, cable circuits, transformers, switchgear, and capacitors which forms the NEDC distribution system
and used in the preparation of distribution system models for the power system studies. The results of
load flow, short circuit studies and system technical losses are presented thereby providing an
assessment of the capability of the distribution system.
Implementation of the system development plans is necessary to meet future forecast demand growth,
maintain and/or improve the capability in the distribution system to meet the system growth and to
address the issues of actual or forecast non-compliance with the Distribution System Security Standard
(DSSS). Implementation of these plans will enhance the available system capacity as well as potentially
The impact of NEDC’s forecast demand growth and distribution system development plans on the
Transmission System, which is owned and operated by Oman Electricity Transmission Company
(OETC), has been fully assessed in the development of NEDC’s development plans. Where appropriate
33kV load transfers from one 132/33kV grid substation (GSS) to another are feasible they have been
considered and where this option is not feasible; applications for additional 132/33kV GSS capacity have
been submitted to OETC, resulting in OETC plans to construct and build additional 132/33kV GSS
capacity within the NEDC licence area.
The following summarises the structure of this Distribution System Capability Statement:
• Chapter 1 - Introduction: An overview of the NEDC area, the main function, and the statement's
purpose. Moreover, it presents the key statistical data of NEDC to date.
• Chapter 2 - Planning philosophy and Practices: This chapter presents the governing standard
that NEDC follows in planning, designing, operating, and maintaining the network. And it illustrates
the asset characteristic, configuration, selection, and details of asset data.
• Chapter 3 - Planning Drivers: this chapter provides the overall distribution system connectivity in
each governorate with future indications projects per wilayat.
• Chapter 4 - NEDC Distribution System: provides a summary view of the distribution system,
together with details of the 2023 demand profile along with projected demand forecast, CRT impact
analysis of NEDC system, system constraints, a summary of the required technical power system
analysis of the distribution system. Furthermore, this chapter presents the power flow results for
NEDC networks by listing the study methodology and data considered. In addition, it shows the
technical losses percentage.
• Chapter 5 - Challenges and Opportunities within the System: This chapter presents the future
Low Carbon technologies that going to affect directly in the power system such as PV solar systems,
Electric vehicles, and the ambition plan of Oman for zero carbon.
• Chapter 6 - Investment Plan: The future projects, Network Suitability for New Connections and
system constraints are presented in section Six.
NEDC has an operating philosophy that underlies the development of the distribution system at the
three-voltage level 33, 11, and 0.415 kV. Furthermore, it ensures that the whole distribution system
satisfies the following fundamental design criteria throughout the planning period:
• Sector Law Royal Decree 78/2004: Enabling legislation that established the Oman Electricity
and Water Sectors. Article 90 obligates Distribution Companies to finance, operate, maintain,
develop and expand the Distribution System safely and under the relevant performance and
security standards.
• NEDC’s license conditions 4, 32, and 33.
• Distribution Code Version 1.1 (April 2020).
• Grid Code Version 3.0 (August 2020).
• Oman Electrical Standard (OES) and international standards.
• Security of Supply standards (APSR letter 2008).
• Connection Statement Version 1 (October 2006).
• Electrical Safety Rules.
Copies of the above standards and codes are available on APSR’s website (https://apsr.om/en/home).
Moreover, the distribution system must also be capable of being operated, maintained, repaired,
extended and replaced as necessary during its life without exceeding design levels of risk to the
customers it serves.
2 Rated Frequency Hz 50 50 50
6 Voltage fluctuations % 3 3 3
1
There are different short circuit level 25 kA and 31.5 kA based on Substation design requirements.
2
There are different short circuit level 31.5 kA based on Substation design requirements.
2.2.3 Frequency Deviation: During normal operating conditions, the nominal System Frequency of the
Transmission and Distribution Systems will be 50.00 Hz and usually will be controlled by Oman
Electricity Transmission Company (OETC) between 49.95Hz and 50.05Hz. During exceptional steady-
state conditions, Frequency deviations will not exceed 49.90Hz to 50.10Hz unless disturbed
circumstances prevail. Under disturbed conditions, System Frequency could rise transiently to 51.50 Hz
or fall to 48.00 Hz.
2.2.4 Voltage Waveform Quality: The maximum total levels of harmonic distortion on the Distribution
System at 33 kV and 11 kV, from all sources under both normal, planned outage and fault outage
conditions, shall not exceed a total harmonic distortion of 2.0 % with no individual harmonics greater
than 1.5 % unless abnormal conditions prevail. At LV, the maximum levels of harmonic distortion from
all sources shall not exceed a total harmonic distortion of 2.5 %.
The maximum negative phase sequence component of the phase voltage on the Distribution System
should remain below 1.0 % unless abnormal conditions prevail. A maximum value of 2.0 % is permitted
for phase unbalance.
2.2.5 Voltage Fluctuation: Voltage fluctuations arising from fluctuating Demands Connected at a
Connection Point to the Distribution System shall not exceed 1.0% of the voltage level for step changes
that may occur repetitively. Any large voltage excursions other than step changes may be allowed up to
a level of 3.0%, provided this does not constitute a risk to the Distribution System or any Distribution
System User.
2.2.6 Distribution System Security Standard (DSSS): After the approval of Distribution System Security
Standards in November 2008, as shown in Table 4 below, NEDC is obliged to comply with the Planning
requirements of Security Standards. Since NEDC’s Distribution License grant, NEDC has started
planning its distribution network to comply with simple planning principles to supply its customers with
high-quality products.
According to the Security Class, a 33 kV feeder is considered not complying with the standards if, upon
a fault on the feeder, the Demand Group cannot be supplied within the prescribed period. A portion of
the feeder cannot be fed back, and the feeder is considered and classified as non-compliant.
For the 33/11 kV substations, two situations are of interest. In the first case, if two transformers are
installed in a substation but the total load is greater than the capacity of one transformer, then the
substation is considered non-compliant. The second situation is where only one transformer is installed,
and there is no link to a nearby substation that can take the affected demand group, then the substation
is considered non-compliant. It is worth mentioning that non-compliance is only during the summer
period. For most of the year, many feeders and substations comply with the DSSS except the radial
feeders, T-Offs, and substations with only one installed transformer. All investments in NEDC Network
are to make all substations comply with DSSS.
2.3.1 33 kV system: The 33 kV System of NEDC serves a distribution role between the OETC and the
11 kV system as direct 132/11 kV transformation is also in use. The System consists mainly of 33 kV
feeders, 33/11kV primary substations, and 33/0.415 kV transformers installed on some feeders where it
is not feasible to develop an 11 kV network due to limited demand. The 33 kV feeders from the 132/33
kV grid stations supply the 33/11 kV primary substations.
Primary substations are of two types, namely indoor and outdoor. Indoor primary substations are mainly
2x10 MVA, 2x20 MVA and 3x20 MVA with 33 kV outdoor/indoor circuit breakers and 11 kV indoor
switchgear panels. Indoor primary substations are proposed to be constructed during the coming years
to supply highly growing areas. Outdoor primary substations are installed throughout the ten
governorates of NEDC in urban and rural areas where demand usually is less than 6 MW. The regular
3
For 11kV networks in remote areas this restoration time may be extended by the time it reasonably takes for a repair crew to
reach the area with the outage as long as the total restoration time will not exceed 6 hours.
Along with the 33 kV feeders, Tees are used to connect primary substations. The entire network is
interconnected, except in a few situations where radial feeders without interconnections with other
feeders feed primary substations. The number of 33/11 kV substations and transformers in the System
up to September 2023 is shown in Table 5.
Power Governorate
Transformer North South South North
Muscat Dhakliyah Dhahirah Wusta Buraymi Musandam NEDC
Size Sharqiyah Batinah Sharqiyah Batinah
1 MVA 1 - - 8 - - 2 - 1 5 17
3 MVA 8 6 10 15 7 1 3 6 2 6 64
5 MVA 4 - - - - - - - 4
6 MVA 51 81 29 19 58 79 38 26 18 7 406
10 MVA 10 2 10 13 2 4 9 11 5 3 69
15 MVA 1 1
16 MVA 16 - - - - - - - - - 16
20 MVA 322 93 37 30 29 115 44 126 24 8 828
31.5 MVA 2 - - 7 - - - - - - 9
40 MVA 1 1
Total 414 182 86 94 96 199 96 169 50 29 1415
The 33 kV indoor switchgear is a single bus bar, totally enclosed metal-clad type with withdrawable
circuit breakers or metal-clad SF6 insulated with vacuum or SF6 circuit breakers. 11 kV and 33 kV
current ratings of the bays are shown in Table 6.
Table 6: Current Ratings of Bus Bar, Bus-section, Transformer, and Feeder Bays
Most of NEDC’s primary substations are standard two transformers with two separate 33 kV and 11 kV
busbars. In some cases where demand is much less than the capacity of two transformers, which is
expected in remote rural areas, primary substations with only one 33/11 kV transformer are installed.
The 33 kV network is designed and will be developed to meet its customer’s satisfaction and comply
with the Distribution System Security Standards (DSSS).
4
There are special cases where the thermal rating may vary.
These 11 kV feeders are generally operated as radial feeders, with the open point selected for ease of
operational access to minimize customer minutes lost while considering the need to meet security
requirements and reduce system losses and voltage drops.
Distribution substations are of two types, ground-mounted and pole-mounted. One transformer with a
rated capacity of 500 kVA or higher is commonly used for ground-mounted distribution substations,
whereas those transformers with ratings less than 500 kVA are installed on H-Pole structures. Both
substations are fed directly from the 11 kV feeders with jumpers (Pole-Mounted) or through 11 kV cables
(Ground-Mounted). Expulsion fuses protect both substations on the high voltage side, and HRC fuses
on the low-tension side. However, Ground-mounted transformers connected through HFU are protected
by HRC fuses of 125 A, 63 A and 31.5 A for 2000 kVA, 1000 kVA & 500 kVA, respectively.
NEDC has already started implementing two smaller ratings, 25 and 50 kVA, to minimize transformer
losses arising from higher ratings for loads far away less than the capacity of the transformer. The
number of distribution substations in the system up to September 2023 is shown in the below table.
Distribution Governorate
Transformer North South South North NEDC
Size Muscat Dhakliyah Dhahirah Wusta Buraymi Musandam
Sharqiyah Batinah Sharqiyah Batinah
16 KVA 5 - - 1 - - - - - - 6
25 KVA 2 60 3 1 23 8 6 103
50 KVA 20 127 253 2 407 86 129 82 43 4 1153
100 KVA 575 2345 1159 523 2102 1368 772 1427 793 218 11282
200 KVA 229 479 284 94 458 743 228 594 194 86 3389
250 KVA 8 - - - - - - - - - 8
315 KVA 503 1559 900 102 923 1358 518 2188 282 43 8376
500 KVA 1166 915 278 316 634 2428 545 740 243 315 7580
630 KVA 1 1 - 7 - - - - - - 9
750 KVA 2 - - 2 - - - - - - 4
800 KVA 3 1 11 1 16
1000 KVA 7524 1641 743 369 658 2090 789 1672 630 221 16337
1250 KVA 17 - - 7 - 4 - - - 2 30
1500 KVA 18 - - 16 2 - - 20 - 4 60
1600 KVA 214 4 - 1 5 1 13 - - 238
2000 KVA 1877 70 2 26 15 120 100 168 - 1 2379
2500 KVA 35 - - 3 - - - 6 3 - 47
NEDC Total 12199 7202 3633 1470 5223 8210 3088 6910 2188 894 51017
NEDC’s low-tension network is designed and will be developed to meet its customer’s satisfaction and
comply with the approved Distribution System Security Standards.
2.3.4 Small Scale Grid Connected Solar PV Systems: The minimum technical specifications and
connection methodologies for installation of small-scale grid connected Solar PV systems within Oman
are specified in the Technical and Connection Guidelines published by APSR in May 2017; these shall
be adhered by PV system installers and users for PV system installations. Furthermore, other national
& international standards, network codes, and other specific technical requirements of NEDC may apply
to solar PV generating plants and therefore shall be complied with.
2.3.5 Electric Vehicles (EV) Charging Technical Requirements: In July 2023, APSR published the EV
Charging Technical Requirements Guidelines. The guidelines include the required technical
specifications and connection methodologies for installation of EV charging within Oman. NEDC is in
process of setting up the code of practice and the policy to be followed for EV applications.
The choice of network assets suitable to connect a specific demand is subject to many factors, including
the following:
• Geographical location.
• Size and nature of the demand.
• Available network voltage level within the vicinity of the demand area.
• Spread of demand distribution (load density).
Based on NEDC technical specifications, standards, and regulations, the size and rating of network
assets have been determined and can be summarized network common assets as per below Table 8:
20 MVA
16 MVA
10 MVA
33 Power Transformer
6 MVA
5 MVA
3 MVA
1 MVA
SF6 GIS
Switchgear
AIS
3C X 240 Sq.mm
Under Ground XLPE Insulated Copper Cable
3C X 185 Sq.mm
2000 KVA
1000 KVA
500 kVA
11
315 kVA
Distribution Transformer
200 kVA
100 kVA
50 kVA
25 kVA
Oil RMU
Switchgear
SF6 RMU
120 Sq.mm
Over Headline XLPE Covered Aluminium Conductor
70 Sq.mm
4C X 120 Sq.mm
NEDC detailed assets list and evolution in Appendixes B.1, B.2, B.3, B.4 and B.5, while the below link
presents the geographical maps of the 10 governorates under NEDC service area showing the locations
of Interface points with OETC, NEDC primary substations, 11 kV feeders, and distribution transformers.
https://mzgisportal.mzec.co.om/portal/apps/webappviewer/index.html?id=dfb78b59fc294e308
2ed3c213ee360e45
5
The Username and password to be provided upon request.
3.1. Background
NEDC’s electricity distribution system serves around 1,267,808 customers cover Muscat, South Batinah,
Dakhiliah, North Al Sharqiyah, South Al Sharqiyah, Al Wusta, North Batinah, Musandam, AL Buraymi
and Al Dhahirah Governorates. The characteristics of the distribution system within the NEDC licence
areas differ mainly because of three major parameters:
The 2023 maximum demand recorded for NEDC MIS system was 6995.5 MW 6 (on Thursday – 22nd
June 2023 at 15:11 Hrs) and Musandam Area was 89.2 MW 7 on Sunday 16th July 2023 at 13:43. For Al
Wusta Area the Non-coincident peak was 155.47 MW.
As of 2023 peak period, the total existing number of 132/33kV grid substations is 101, 33/11.5kV primary
substations connected to the NEDC distribution system is 686 with a Total Firm Capacity of
11,075.2 MVA. The tables identifying each Primary Substation capacity and current demand can be
found in Appendix B.
1. A summary of the individual Governorate built up and the planning drivers for each Governorate.
2. It also provides an overview of the complete current NEDC system connectivity including
governorate classification of the primary substation.
6
MIS Transmission peak excluding of transmission technical losses and Grid Stations auxiliary load
7
Including 7 MW of isolated Madha load
The Muscat Governorate includes Wilayat Muscat, Muttrah, Amerat, Quriyat, Bousher and Seeb. The
number of customers served in the Muscat Governorate region is 448,509 which is approximately 35%
of the total customer population within NEDC. Table 9 shows all existing primary substations with their
installed and firm capacity within Muscat Governorate.
Wilayat Muscat is considered as one of the saturated areas within Muscat Governorate except Yitti Area.
The Yitti Tourism Development is one of the major projects. Moreover, the plan is to construct two
numbers of PSSs; one is under commissioning stage and the other one is in the planning Stage.
Wilayat Muttrah has circa zero growth for the last two years. There is one project for Mutrah Development
as bulk load customer, and it is still within the planning stage.
Amerat has seen the highest demand growth for the last 5 years within Muscat Governorate validating
for a significant demand growth forecasted for the current planning horizon.
Quriyat has an average of 3% load growth for the next three years and there is no major project in the
area.
Bousher Height Smart City is one of the biggest projects in Wilayat Bousher. As load demand the area
has low growth with an average of 1%.
Seeb has seen growing demand for the last 5 years within Muscat Governorate specially Mabelah area.
Moreover, Mabelah area is one of the largest commercial and residential areas. In addition, Rusail
industrial area is earmarked for some significant development projects by Public Establishment for
Industrial Estates (PEIE).
Falaj[G23] GSS
Falaj P178 2 x 16 16
Darsait P018 2 x 20 20
Jibrooh P041 3 x 20 40
P.D.O P144 3 x 20 40
Mutrah[G21] GSS
Riyam P099 2 x 20 20
Waljah P130 2 x 20 20
Amerat 1 P005 2 x 16 16
Wattaya P131 2 x 20 20
Jahloot[G03] GSS
Al Hajir P031 2 x 20 20
Yiti[G08] GSS
Quriyat[G05] GSS
Quriyat P091 2 x 20 20
Al Shahbari P092 2 x 20 20
Amerat[G10] - A GSS
Amerat 3 P179 3 x 20 40
Amerat[G10] - B GSS
Al Nahdah P006 3 x 20 40
MSQ[GP06] - A GSS
Intercontinental P109 2 x 20 20
MSQ[GP06] - B GSS
Al Khuwair 25 P053 2 x 20 20
MSQ 1 P083 2 x 20 20
Qurum[G06] GSS
Qurum 1 P093 2 x 20 20
Qurum 2 P094 2 x 20 20
Lulai P095 2 x 20 20
MSQ 2 P155 3 x 20 40
Bousher 2 P163 3 x 20 40
Al Muna P084 2 x 20 20
Al Ansab 1 P007 2 x 20 20
Ghala[G11] - A GSS
Ghala 1 P015 3 x 20 40
Ghala[G11] - B GSS
Ghala 2 P156 3 x 20 40
Al Ansab 2 P008 2 x 20 20
SQU 1 P122 3 x 16 32
SQU 2 P123 2 x 16 16
Rusail08(KOM) P164 3 x 20 40
SQU 3 P160 3 x 20 40
Misfah[G04] GSS
Al Misfah P080 3 x 20 40
Al Awabi P139 3 x 20 40
Barka[G02] GSS
Manomah P067 2 x 20 20
Mabelah C P064 3 x 20 40
PalmMall P168 3 x 20 40
Mabelah A P063 3 x 20 40
Mawaleh C P072 2 x 20 20
Rusail B P101 2 x 10 10
Mawaleh B P071 3 x 20 40
Al Khoudh[G25]- A GSS
Mawaleh A P070 3 x 20 40
Al Khoudh[G25]- B GSS
Dhagmar [GP11] GSS It is 132/11 kV Grid Station. So, no PSS is connected in this Grid.
South Batinah Governorate and Suawiq Area includes Barka, Musanah, Nakhal, Rustaq, Wadi Mawel,
Awabi and Suawiq. The number of customers served in South Batinah Governorate is 145,043. There
are 14 Grid stations (132/33 & 220/33 kV) and 103 primary substations (33/11 kV) are feeding the
governorate. Barka area has the largest growth among other areas in South Batinah governorate and
there are many NEDC Investments in the area to cover the need of load demand. One of the major
projects is new primary substation in Khazaen Economic City which is part of Oman Vision 2020-
2040.The below table provides a list of primary substations in the South Al Batinah Governorate and
Suawiq Area. Table 10 shows all existing primary substations with their installed and firm capacity within
South Al Batinah Governorate.
Table 10 : South Al Batinah Governorate and Suawiq Area- Grid and Primary Substations Connectivity
Rustaq Grid
Nakhal Grid
Barka Grid
Barka-3 PS
Madinat Barka-A
Madinat Barka-B
Khadra-A
Khadra-B
MIS
Suwaiq
Muladah-A
Muladah-B
Blue City
Al Dakhiliah Governorate includes Sumail, Izki, Nizwa, Bahla, BidBid, Manah, Hamra, Jabal Akhader
and Adam. The number of customers served in the Al Dakhiliah Governorate region is 148,882. There
are 98 Grid stations (132/33 & 220/33 kV) and 88 primary substations (33/11 kV) are feeding the
governorate. One of the tourism areas in Al Dakhiliah governorate is Jabal Akhader, new two double
circuits 33 kV feeders is under construction to secure the electricity need of new tourism investments.
Table 11 below provides list of primary substations in Al Dakhiliah Governorate.
Adam Grid
Bahla Grid
Jabrin Grid
Nizwa Grid
8
Excluding AL Rusail Indst. Grid as it is considered within Muscat Zone
Izki Grid
Samail A Grid
Samail B Grid
9
The GSS counted as number in Muscat Governorate
The North Al Sharqiyah Governorate includes Mudhaibi, Ibra, Dima Wa Taiyyin, Wadi Bani Khalid, Qabil
and Bidiyah. The number of customers served in the North Al Sharqiyah Governorate region is 25,836.
There are 6 Grid Station (132/33 & 220/33 kV) and 47 primary substations (33/11 kV) are feeding the
governorate. Table 12 below provides a list of primary substations in North Al Sharqiyah Governorate.
Table 12 :North Al Sharqiyah Areas – Power Plant, Grid, PDO and Primary Substations Connectivity
Samad Grid
Mudhaibi Grid
Hadeetha - 3x6 12
Sinaw Grid
Mudhairib Grid
Ibra Grid
Bidiyah Grid
The South Al Sharqiyah Governorate includes Sur, Jalan Bani Bu Hassan, Kamil wa Wafi, Musirh and
Jalan Bani Bu Ali. The number of customers served in the North Al Sharqiyah Governorate region is
84,805. There are 4 Grid Station (132/33 & 220/33 kV) and 48 primary substations (33/11 kV) are feeding
the governorate. Jalan Bani Bu Ali and Jalan Bani Bu Hassan areas have the highest growth in the
governorate, two 2x20 MVA primary substations are under construction to cover the high growth. Table
13 provides a list of existing primary substations in South Al Sharqiyah Governorate.
Table 13:South Al Sharqiyah Areas – Power Plant, Grid, PDO and Primary Substations Connectivity
Sur Grid
Ayjah Grid
The Al Wusta Governorate and its Surrounding areas are supplied with power from various sources,
including PDO, Diesel Power Plants, and Marafiq. These power sources serve the entire Al Wusta
Governorate as well as the rural areas in Al Dhahirah and South Sharqiyah Governorates. However,
those systems are scattered through areas isolated from each other with long-distance separation, with
limited or no interconnection between them. The total number of customer services in these areas
amounts to approximately 25,225. Table 14 shows all existing primary substations with their installed
and firm capacity within Al Wusta Governorate.
Table 14 AL Wusta Governorate and Surrounding Areas – Power Plant, Grid, PDO and Primary Substations
Connectivity
AL Buraymi Governorate includes Wilayat AL Buraymi, Mahadah and Sunaynah. The number of
customers served in AL Buraymi Governorate region is 42,509 which is approximately 3.4% of the total
customer population within NEDC. There are 5 Grid Station (132/33 kV), and 27 primary substations
(33/11 kV) are feeding the governorate. Table 15 provides a list of existing primary substations in AL
Buraymi Governorate.
Buraimi_A GSS
MAHDAH GSS
10
The PSS feeding from two Sources, the other feeder from SOHAR SFZ Tx3 & Tx4 GSS
AL Dhahirah Governorate includes Wilayat Ibri, Dank and Yanqul. The number of customers served in
AL Dhahirah Governorate region is 65,192 which is approximately 5.1% of the total customer population
within NEDC. There are 6 Grid Stations (132/33 & 220/33 kV) and 42 primary substations (33/11 kV)
are feeding the governorate. Table 16 shows all existing primary substations with their installed and firm
capacity within AL Dhahirah Governorate.
The load at Ibri Grids is forecasted to increase and NEDC is planning to replace old assets and manage
load between grid stations by reconstructing the 33kV portion of Ibri Old Grid and moving AL Akhdar
PSS from Ibri Grid to Ibri old Grid. The Project is currently in the execution stage. Moreover, a future
expansion project is under execution including the new proposed 3X20 MVA PSS “Named as Hellat Al
Nahadah”, Upgrade AL Akhdar PSS from 2x10 to 2x20 and upgrading Baat PSS from 2X6 MVA to 2X20
MVA. In addition, NEDC will rearrange the 33kV network between Dreez & AL Hail Grid Stations where
Hugermat & Kahant PSSs will be transferred to AL Hail Grid Station & Provide second feeding source
to each of AL Mahual & Kahanat PSSs. Furthermore, there is a new 2X6 MVA primary substation will
be constructed for the new Ibri Industrial Area “MADAYN” by 2025 to provide the power supply for the
new expected industrial load in the area.
DANK GSS
ALHAIL GSS
DREEZ GSS
YANQUL GSS
North AL Batinah Governorate includes Wilayat Shinas, Liwa, Sohar, Saham and Al Khabourah. The
number of customers served in North AL Batinah Governorate region is 174,751 which is approximately
13.8% of the total customer population within NEDC There are 14 Grid Station (132/33 & 220/33 kV)
and 82 primary substations (33/11 kV) are feeding the governorate. Table 17 shows all existing primary
substations with their installed and firm capacity within North AL Batinah Governorate.
Shinas has average of 3% load growth for the next three years and there one major project on area
where AL Wajajah PSS will be upgraded from 2X3 MVA to 2X6 MVA with connecting a new 33kV feeder
from MD Shinas Grid to supply Ajeeb and AL Wajajah PSSs.
Sohar has seen growing with demand for the last 5 years within North AL Batinah Governorate where
Sohar downtown area is one of the largest commercial and residential areas. In addition, Sohar Free
Zone, Sohar Industrial Port and Sohar Industrial Estate area are earmarked for some significant
development projects in the area.
Overall load growth in Al Khabourah remains constant with average growth of 3%. there is one a major
project in Al Khabourah under design stage where Sana Bani Gafer PSS will be upgraded from 2x6
MVA to 2x20 MVA.
Table 17: North AL Batinah Governorate - Grid and Primary Substations Connectivity
MD SHINAS GSS
11
The PSS feeding from two Sources, the other feeder from UWAYNAT Tx3 & Tx4 GSS
Musandam Governorate includes Wilayat Khasab, Madha, Dibba and Bakha. The number of customers
served in Musandam Governorate region is 16,730 which is approximately 1.3% of the total customer
population within NEDC. Musandam Governorate's overall demand growing slowly until recently when
development in the major cities of Khasab, Bakha and Dibba have seen steadily increasing growth in
the form of new residential and commercial loads. Table 18 shows all existing primary substations with
their installed and firm capacity within Musandam Governorate.
NEDC will Upgrading Siwi PSS from 2X6 MVA to 2X20 MVA with installing new 33kV feeder from
Khasab Grid Station and Adding Backup Transformer to secure the PSS. These two projects are under
the Execution stage. In addition, there are two projects under Planning Stage: New Khasab Port PSS
(2X20 MVA) with two 33kV Feeders and Modification to secure Musandam Network.
KHASAB GSS
TIBAT GSS
DIBBA GSS It is 132/11 kV Grid Station. So, no PSS is connected in this Grid.
4.1. Introduction
NEDC is authorized to undertake all regulated activities of electricity distribution business at 33kV and
below across the whole area of Sultanate of Oman excluding Dhofar Governate.
The distribution system has three nominal voltages, i.e., 33kV, 11kV and 415V. Most customers connect
at LV (415 Volt) and there are bulk customers connected at 11kV and 33kV. Similarly, there are large
customers connected on the OETC 132kV side but are NEDC customers for the purposes of energy
supply and billing.
During 2023, the total Firm capacity for all governorates is circa 11,100 MVA, where the maximum load
(non-coincident) is around 7,353 MVA which is 66% utilization. The below table and figure present these
data.
Table 19: Summery of Firm Capacity and Max Load per Governorate
Governate Name (2023) Max Load (MVA) Firm Capacity (MVA) Utilization %
Al Sharqiyah South
North Al Sharqiyah
South Batinah
Dakhiliah
Musandam
North AL Batinah
AL Dhahirah
Buraimi
Muscat
Utilization %
System maximum demand has occurred generally during summer period; although there seems to be
no exact co-relation on the exact timing as expected. There are various parameters which affect the
occurrence of the system maximum demand hence the future forecast; we expect more parameters in
the upcoming future especially due to the macro-economic condition of the Oman economy and due to
the developments in newer technologies. Few of the significant parameters which have impacted NEDC
distribution system growth in 2023 and future are:
This can result in a lack of consistent predictability as to the precise date of future system peaks,
although provides a good indication in general of the period and pattern. For this reason, associated
demand transfers are operationally planned to occur before May period each year to ensure NEDC are
in the best position possible to meet regulatory requirements and ensure quality and security of supply
to consumers.
Figure 3 below shows the historical data [2018-2023]; the system MIS maximum demand and % growth
excluding Al Wusta and Musandam. In addition, Al Wusta and Musandam Governorate historical data
are illustrated in Figure 4 and Figure 5.
9000
14.%
8000
12.%
7000
10.%
6000
5000 8.%
(MW)
4000 6.%
3000 4.%
2000 2.%
1000 0.%
0 -2.%
2018 2019 2020 2021 2022 2023
System Max Demand (MW) MIS Growth %
180.0
14.%
160.0
12.%
140.0
10.%
120.0
100.0 8.%
(MW)
80.0 6.%
60.0 4.%
40.0 2.%
20.0 0.%
0.0 -2.%
2018 2019 2020 2021 2022 2023
120.0
14.%
100.0 12.%
10.%
80.0
8.%
(MW)
60.0 6.%
40.0 4.%
2.%
20.0
0.%
0.0 -2.%
2018 2019 2020 2021 2022 2023
10000
8000
MW
6000
4000
2000
Hours
Figure 6 : Hourly Demand – MIS System Maximum and Minimum Day Profile
100.00
80.00
MW
60.00
40.00
20.00
0.00
Hours
Min [MW] Max [MW]
Figure 7 : Hourly Demand – Musandam System Maximum and Minimum Day Profile
The Maximum load profiles for NEDC taken on Thursday, 22nd June 2023, the day of NEDC Peak, were
plotted and presented in Figure 6. The highest load was reached at 14:30 hours; on this day, the load
recorded was 7181MW12.
12
Transmission System peak
In October 2016, The Regulator announced that the Council of Ministers had approved the introduction
of a new tariff for high value customers called the Cost Reflective Tariff (CRT) and implemented fully in
2017. The new tariff is designed to reflect the actual costs of providing a supply of electricity more
accurately to large government, commercial and industrial customers without government subsidy. Till
2020 the approval for CRT implementation is for application only to the high value customers who
consume 150 MWh and above in a year, for the above-mentioned customer categories.
In 2021, CRT was revised, and the current approval is for application to the high value customers who
consume 100 MWh and above in a year and the new tariff is designed to all the customer category
except residential customers.
As the full 2023 cycle hasn’t been completed yet, an impact analysis was undertaken on 2022 NEDC
customers base to understand the full year impact of CRT on the NEDC distribution system and
described as below.
The number of CRT customers in 2023 was 19,435, circa 1.6% of the total connected customers. Figure
8 below shows some of highly loaded customers load profile during peak day and the direct effect of
CRT tariff during 2023 peak hours.
300
Peak
250 Hours
200
150
100
50
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
-50
As per the licence condition, NEDC is obliged to comply with the DSSS and moreover one of our major
investment drivers for the CAPEX programme is to meet the N-1 operational capability for each Primary
Substation.
Figure 9 below provides a trend of the NEDC Demand Not Secured (DNS) MVA performance as a
measure to show DSSS compliance improvement along with number of Primary Substations contributing
to the DNS. In the recent years the DNS performance in consistently improving and the audited 2022
DNS for NEDC realised is 356.90MVA which is a circa 8% reduction compared to 2021 DNS value of
384.90MVA.
NEDC distribution system predominantly is an urban dense interconnected network and as part of
network design optimum effort is made to maintain that level of interconnection leading to majority of the
11kV feeders except minor rural feeders having no single but multiple interconnections. Hence majority
of the 11kV feeders will come under the Class A and Class B categories. Typically, with the assistance
of these 11kV interconnections, the supply can be generally restored within the allowed DSSS time
frame.
1200
963.20 992.90
1000
Demand Not Secured [MVA]
965.95
800
600
464.50
384.90
356.90
400
204 179
200 151
84 71 69
0
2017 2018 2019 2020 2021 2022
Figure 9 : History of NEDC Demand Not Secured and Out of Firm PSS
As detailed in the Appendix B-5, 15 number 11kV feeders were observed in 2023 which exceeded the
derated thermal loading limit under normal operational configuration; these will be solved by appropriate
11kV load transfers, reinforcement schemes and/or automation in 2023 itself shown in Table 20 below.
The maximum loadings of all the 11kV feeders are attached in Appendix B-5
Amerat[G10] - A GSS
Amerat Heights P152 KLN04 400 350 353.18 Internal Load Shifting
Mabelah South PH-4 P062 KLN04 400 350 380.47 Internal Load Shifting
Mabelah[GP04] GSS
Sur Al Hadid P116 KLN01 400 350 363.41 Internal Load Shifting
South Batinah
Madinat Barka-A
150 A (3 MW) will be transferred to
Saqsuq 33L5 400 350 396
new feeder from Saqsuq PSS in 2024.
Muladah-B
70 A (1.3 MW) will be transferred to
Uwayd 22L5 400 350 356
Musanah Ind PSS in 2024
Dakhiliah
Nizwa Grid
Al Sharqiyah South
Bidiyah Grid
150 A (3 MW) will be transferred to
Mintrib 31L5 400 350 359
new 11 kV feeder from Mintrib PSS
Accurate and realistic load demand forecasting is critical for the effective operation of the distribution
system and is the principal driver for capital expenditure. Realistic assumptions must be made for
inherent uncertainties in forecasting and the underlying socio-economic factors, such as the sustained
low oil price, population growth and impact of Oman wide customer tariff reforms.
Load growth can vary from year-to-year and is not uniform across the whole system. It is not unusual to
find parts of the system growing at significantly higher rates than for the system, while other parts of the
system can experience periods of low growth or demand reduction.
The forecast model has inputs data from different sources as follows:
• Population data for the area served by NEDC has been taken from data published by the Oman
Information and Statistics Centre.
• Data and projections on Oman's GDP economic development are taken from the International
Monetary Fund published in its World Economic Outlook Database.
• GIS (Geographic Information System) and CRM (Customer Relationship Management) provide
customer account details internally in the company. These two systems offer the customer
account numbers with the energy consumption and the primary substations connected to these
accounts.
• SCADA provides internally the primary substation's peak loads (Supervisory Control and Data
Acquisition).
Then the model will have several calculations using the input data to reach the load growth of each
primary substation applied in this capability statement.
NEDC considers the following features are necessary to produce an accurate demand forecast in line
with best practice:
• Accurate and unbiased actual demand data – careful management of data and forecasting
model construction based on sound theoretical grounds that closely fits the sample data.
At the time of writing this DSCS, the volume of grid connected PV systems is expected to make minor
impact at system level forecast (including future years as it stands); hence the impact of PV systems is
not included in the forecast for this DSCS. With the development of our new regression-based Load
Forecasting tool, NEDC will monitor the uptake of all low carbon technologies including PV and include
the impact of these on forecast in future appropriately.
To address the various uncertainties impacting the forecasting in recent times and going forward as
mentioned above; NEDC has an econometric forecast modelling tool rather than historically used
Compound Annual Growth Rate (CAGR%) method. The model uses regression analysis to identify
relationships between historic system data and historic economic variables. The primary economic
variables considered are population growth and the growth in GDP (broken down by economic activity).
These two drivers are commonly accepted as being key descriptive drivers of future growth in underlying
RUD and CA and by combining the historic regression-based relationship data to forecasts of the
economic variables, projections of CA growth and RUD growth can be made (with average consumption
per customer also identified).
Moreover, the tool can capture the Low Carbon Technology (LCT) impacts on load growth can also;
these will be considered in future forecasts as these impacts on system demand become significant in
future. In addition to the above, the impact of individual large investment projects is also considered
separately. These projects are projected to bring around a one-off increase in demand, which is not
captured by the economic forecast model. By undertaking sensitivity analysis, the model provides a
complete envelope of extremes for the forecasted parameters rather than relying on one-point values.
Historical data indicates that the demand rate of growth across NEDC distribution system has slowed in
recent years. This is mainly attributed to the sustained low price, general macro-economic factors and
exceptional events around the world. The average load growth for the forecasted three years, using the
Regression model, is 5.4%. Table 21 shows the actual and forecasted NEDC expected peak demand
including and excluding the direct connected customer load.
Figure 10 shows the historical trend in NEDC system maximum demand with the forecast maximum
demand over the period 2024 to 2026. Despite the general slowing in demand growth at the system
level, there are areas within the system where maximum demand is forecast to grow well beyond the
system average level, while other parts of the system are forecast to experience no load growth or a
small reduction in maximum demand.
Furthermore, the direct connected customers peak demand expected to increase by 955 MW 13 in 2026
considering the application received from customers that planning to connect through 220kV and 132kV
systems in the major industrial areas such as AL Duqum, Sohar Free Zone and Sohar Industrial Port.
Figure 10 : Historical Trend in NEDC System Maximum Demand with Three Years Forecast
13
Based on the received applications and customer forecast without implementing CRT tariff effect.
There are two sperate networks In Musandam Governorate: Main network which consists of three Grid
Stations (Tibat, Khasab and Dibba Grid Stations). This network is supplying around 99% of Musandam
Governorate. The second network is Madha network. Madha is a small Wilayat surrounded by the UAE
therefore the power system there consists of 6-11kV diesel generators (with total capacity of 11.3 MW)
located in Madha Primary Substation. In 2023 summer, recorder peak load of Madah substation was
around 7 MW and it is forecasted to remain almost the same for the period of 2024 to 2026 as there is
no expectation for new major development in Madha. Overall Musandam load growth expected to grow
within the limit of 6% as seen in Figure 11 below.
Currently, most of the distribution networks in the Al Wusta Governorate and rural areas in other
governorates are powered by diesel-fuelled power plants, which operate as isolated systems in different
areas. There are 11 power plants distributed throughout the whole of Al Wusta and surrounding areas.
NEDC has a plan to reconfigure these networks' power sources to be connected to the Main
Interconnection System (MIS) and align with the OETC Interconnection Plan in the Phases I & II of
“Rabt” project. Table 22 below displays the NEDC plan and the target date for the interconnection with
MIS.
Masirah Q4,2026
Hijj Q4,2023
Al-Khuwaima Q4,2026
Dhafrat Q1,2024
Khalouf Q2,2025
Najdah Q1,2024
Sarab Q2,2025
Duqm Q4,2023
Masrooq Q4,2026
Khadra Q4,2026
Hitam Q4,2026
In 2023, The peak load in the Al Wusta Governorate and its surrounding areas has reached 155.47 MW,
including the PDO source connection. It is anticipated that the load will increase to 178 MW by 2026.
Overall, Al Wusta load growth expected to be within 4.8% between 2024 to 2026 as seen in Figure 12
below.
NEDC maintains up-to-date models of its power system for assessing distribution system performance
via power system studies, bulk loads modelling, and undertaking customer connection studies where
required; to ensure the distribution system operates in a safe and an efficient manner along with
providing the required security of supply to its connected customers.
The planning tool utilised for system modelling and studies are PSS®SINCAL (Power System
Simulator® Siemens Network Calculation), ETAP (Electrical Transient and Analysis Program) and
DIgSILENT (Digital Simulation and Electrical Network calculation program). The models for each grid
substation with their respective connected primary substations are established by representing the 33kV
system on an electrical connectivity basis. The system models contain network topology and details in
terms of nameplate data for transformers and their tap changers, capacitor banks and their controllers,
conductor types along with associated lengths and parameters and the non-coincident demand data on
individual primary substations.
The load demands are modelled as lumped loads connected to the main 11kV bus bars and segregated
into motoric and non-motoric load types for load flow and fault current calculations. Likewise, the existing
connected solar PV plants are also modelled as lumped generation on 11kV bus bars from this year
onwards. The recorded maximum (summer) demands on each primary substation; derived from NEDC
SCADA system as of 2023 have been used to update the power system models on non-coincidental
load basis. Forecasting principles for load determination as mentioned in the previous sections have
been adopted to forecast the future year (2024-2026) maximum demands.
Load flow analysis is undertaken for maximum demand scenarios to define the performance of NEDC
distribution system. The analysis determines the active and reactive power flows in the system,
percentage loadings for transformers and 33kV circuits along with the voltage profile at the 11kV and
33kV busbars of the primary substations under normal circuit operation. Simulations are carried out for
the existing (2023) and future 3 years (2024-2026) for system maximum loadings. All short circuit results
have been listed in a downloadable excel sheet files as following:
From the studies, it is possible to identify where the system is strong and has spare capacity and
conversely, where additional mitigation and/or reinforcement, before new connections, potentially needs
The power factor values for maximum demand scenarios have been determined based on the actual
available information from NEDC SCADA. For maximum demand conditions, the actual recorded power
factor data is employed, where available. For the remaining substations, where power factor values are
not available via SCADA, a calculated system average is considered for maximum demand scenarios
in accordance with the company’s defined practice.
The load flow study results are summarised in tabular form in Appendix B and available in a
downloadable excel files that supplements this Distribution System Capability Statement.
The simulation results demonstrate the following within the period of this DSCS:
• Voltage drop under maximum demand scenario remains within the statutory limits of - 6% on all
33kV busbars/nodes.
• Voltage drop under maximum demand scenario remains within the statutory limits of - 6% on all
11kV busbars/nodes.
• 33kV circuit loadings assessed for the worst-case maximum demand scenario; across the
system are within the acceptable circuit ratings.
From the results it can be observed that 20 primary substations are facing voltage drop below the
statutory limit of +/-6% at the 33kV busbars. However, the 11kV busbars are complying with the statutory
voltage limits with consideration of operating the capacitor banks and the transformer tap-changer at the
suitable tap position. By 2026, the number of primary substations facing voltage drop at the 33kV busbar
will be reduced to 18 as a results of network expansion where new 33kV lines will be introduced in the
system. NEDC will continue monitoring these primary substations to ensure keeping the 11kV network
within statutory voltage limit of +/-6%. Moreover, NEDC and will keep in consideration to improve the
33kV voltage through providing new 33kV lines or installing new Grid connection points whenever is
possible.
NEDC carries out short circuit calculation studies to establish the capability of equipment to withstand
three phase maximum prospective fault current levels. All short circuit results have been listed in a
downable excel sheet file in Appendix B-4.
The principal source of fault currents is the generation assets connected to the transmission system with
the fault current contribution onto the NEDC distribution system via the 132/33kV GSS transformers.
The fault current infeed from the OETC source have been updated in our power system models
according to the data provided by the OETC’s 2023 Capability Statement which covers up the
transmission system developments up to 2027.
• All existing and new 2x20 MVA PSSs are simulated for operation with the 11kV bus-section
circuit breaker in the “normally closed” position 14.
• All existing and new 3x20 MVA PSSs are simulated for operation with one 11kV bus-section
circuit breaker as “normally closed” and one as “normally opened” (i.e., in N or N-1 scenario, it
represents a 4 out of 5 ‘normally closed’ circuit breakers scenario) with an auto transfer
scheme (ATS)15.
• All existing 2x20 MVA PSSs and 3x20 MVA PSSs are simulated for operation of 33kV bus-
section circuit breakers within the PSSs (wherever present) 16 as “normally open”.
• All existing and new outdoor primary substations (3x6MVA, 2x6 MVA, 2x3 MVA and 2x1 MVA)
are simulated for operation with the 11kV bus-section circuit breaker in the “normally open”
position.
The design short circuit breaking ratings of the 11kV switchgear component a new and upgraded primary
substations are designed to 18.4 kA or higher based on short circuit requirement to comply with system
requirements.
Currently, in the absence of accurate fault level contribution data from low voltage (LV) side, a worst-
case allowance is made for LV motor fault contribution majorly due to the nature of the air conditioning
load prevalent across the NEDC’s distribution system. A motoric to static load type ratio of 80/20 (in
percentage) is considered using the system maximum demand values. System modelling for fault
current calculations have been performed in accordance with the principles of the “IEC 60909-Short
Circuit Currents in 3 Phase AC Systems” standard.
The maximum prospective fault current values are tabulated in the tables in Appendix B-4. The
calculation of maximum prospective fault current is compared against the rated breaking capability of
the primary equipment.
The maximum prospective (initial symmetrical) fault current is calculated to be still under but approaching
(i.e., >95% and <100%) the rated breaking capacity of the primary 33kV equipment (switchgear) at the
following primary substations:
• Wadi Adai-P175 (23.98 kA in 2024 and then within 97% of 25kA rating)
14
Except for few locations where the 33kV feeders for the individual transformers are connected from two different GSSs in which case, the 11kV
bus-section circuit breaker is kept “normally open” for the respective year(s).
15
If the fault levels are within limits for this worst-case scenario’s then on bus-coupler open scenarios of existing primaries the fault level’s will be
even lower.
16
For new PSS, the 33kV configuration excludes the 33kV bus-section circuit breakers at the PSS.
However, at the following primary substation(s), minor excursions beyond the rated breaking capacity
of the 33kV equipment (switchgear) are observed:
Where it marginally exceeds above the switchgear rating; hence NEDC shall monitor this PSS closely
and create mitigation plans in form of operational restrictions if required based on the monitoring results.
It is to be noted that all the above primary substations are in close electrical vicinity of the grids
substations where these results are based on non-coincident maximum demand fault contributions to
represent worst case scenarios of the connected PSSs.
The maximum prospective (initial symmetrical) fault current levels at 11kV busbars of all the primary
substations are within their rated breaking capacities except for the following primary substations:
The technical losses in the NEDC distribution system are a factor of the configuration of the system,
type and specification of equipment, percentage utilisation of assets and customer energy consumption.
Technical losses are attributed to load and no-load losses in the 33kV feeders and 33/11.5kV primary
transformers, 11kV feeders and distribution transformers and the LV distribution system. In line with
standard international practice for utilities where the distribution system is not fully modelled, we
calculate the losses for specific network elements (transformers, overhead lines and cables) across the
different voltage levels (33kV, 11kV and LV) and then summate the total losses to obtain a percentage
technical loss for each primary substation.
The percentage technical losses are then apportioned according to the proportion of total system energy
supplied by each substation. A summation of all apportioned technical losses is then presented as the
system percentage technical losses. The summated technical losses based on the 2023 distribution
system operation is calculated to be 4.88%. The breakdown of technical losses by voltage level is shown
in Table 23 below.
Zone 2 Zone 3
System Component Zone 1 % Total
(with Al Wasta) (with Musandam)
Implementation of Low carbon technologies (LCTs) like Solar PV, Electrical Vehicles (EV), energy
efficiency and battery storage are few of the major LCTs successfully being implemented around the
globe to achieve sustainability of natural resources and protect the environment. This philosophy is also
the cornerstone for Oman as demonstrated in the Oman Vision 2040 Environment and Natural
Resources Objective17. To achieve the above and other sustainable goals of the Sultanate National
Energy Strategy for 2040 recommended that around 20% of Oman’s generation mix should come from
renewable energy sources (RES)—primarily onshore wind and solar—by 203018. Lastly the CRT and
customer tariff reforms introduced by Oman 2017 onwards are accelerating the adoption of these LCTs.
NEDC recognise that the nature of electricity generation and use is changing. We envisage that recent
policy initiatives will result in an increase in photovoltaic (PV) generation on our distribution system.
Unlike other utilities in different regions, Oman has not seen significant uptake in electric vehicle charging
thus, the associated demand characteristics for electric vehicles (EV) are not considered to be a
contributing factor to our system planning in the short-term planning horizon. However, this will be closely
monitored to check the penetration rate of EV and PV in general.
In accordance with the above, the LCT with significant impact to the NEDC system as of 2023 is Solar
PV. In 2017, Authority for Public Services Regulation (APSR) revised the existing regulatory framework
to facilitate the adoption of small-scale grid connected solar PV systems by customers in Oman. The PV
guidelines detail the following:
• Establishing the minimum technical standards required for small scale grid connected PV
systems.
• Detailing the connection process including the installation, metering and operation/maintenance.
• Allowing the distribution companies to act as agents for OPWP (the current single buyer of
electricity) to buy PV-generated electricity from customers.
With the introduction of Sahim-I initiative by the APSR since May 2017, there has been an increasing
uptake of small grid connected PV systems for households and business as evident from the PV
connections list in Appendix B. NEDC does foresee challenges and opportunities in the way we will plan
and operate our system. Whilst PV may have the impact of reducing transmission and distribution
17
https://isfu.gov.om/2040/Vision_Documents_En.pdf
18
https://www.apsr.om/en/renewableenergy
NEDC are responsible for ensuring power quality according to the regulations under which we operate.
However, with the addition of intermittent, consumer-owned and non-dispatchable PV units, current
standard procedures for guaranteeing power quality might not be as effective as they are without PV.
Overvoltage is one of the main reasons for limiting the capacity (active power) of non-dispatchable PV;
that can be connected to a low voltage Distribution System. During high PV generation and low load
periods; there is a possibility of reverse power flow and consequently voltage rise in the HV & LV feeder.
We envisage that this will be most prominent during the winter period. For this reason, NEDC believe
that if uptake is significant, it will impact investment decision making for reinforcement and asset
replacement. Consideration of tap range, optimum dispatch of capacitor banks and conductor sizing
may be necessary should PV penetration become high.
In accordance with the above NEDC continuous to witness an increase in applications for connecting
solar PV systems of various sizes. As end of September 2023, NEDC have received in total 654 PV
applications with total requested generation capacity of 72.56 MW, 425 no. applications are connected
equating to 43.15 MW and 141 initial applications submitted equating to 11.51 MW YTD.
Table 24 and Figure 13 and Figure 14 below shows these customer classifications for the applications
in the category.
350
300
250
200
150
100
50
0
Commercial Government Residential Agricultural
30.00
25.00
20.00
MW
15.00
10.00
5.00
0.00
YTD 2023 As End Sep 2023
Connected Generation
In accordance with the current Oman regulations the solar PV systems are required to be firstly installed
for self-consumption basis before any excess generation is exported to the distribution system for the
consumption of other customers. Net metering allows Residential, Government and Commercial
customers who generate their own electricity from solar power, to sell the surplus electricity back into
the grid.
NEDC has prepared a plan for the new investments required in 2024-2026 to reinforce the 33 kV network
and ensure compliance with the security standards. Many substations and feeders will start moving
toward compliance situation. However, the NEDC investment plan updates annually to cover other
substations and feeders that need more investments. NEDC has taken various steps to tackle any
bottlenecks in the project management cycle, and with these interventions, our capabilities to deliver all
the required capital expenditures will undoubtedly improve.
Table 25 show the summary of planned 33 kV projects in the NEDC network per governorate in the
different stages, the details are illustrated in Appendix C.
Muscat 4 3 3 8
Dakhiliah 0 1 0 4
South Sharqiyah 1 6 0 2
North Sharqiyah 0 0 0 3
South Batinah 1 4
North Batinah 3 2 0 2
DHAHIRAH 1 2 0 5
Musandam 2 0 0 2
Wusta 2 2 0 6
NEDC 13 17 3 36
Moreover, Table 26 show the summary of sponsored projects in the NEDC network per governorate in
the different stages, the details are illustrated in Appendix D.
Dakhiliah 0 0 0 6
South Sharqiyah 0 0 0 3
North Sharqiyah 0 0 0 3
South Batinah 0 2 0 4
NEDC 0 2 1 16
Since January 2023 up to end of September NEDC connected 21,723 applications with worth of 777
MW for both simple and complex connections. The table below shows the statistic for all governorates
for both connections. From the table below it was noted that the for the simple connection the average
connected load per customer is 0.03 MW, however the average connected load per customer for the
complex customer is around 5.2 MW.
These connections already implemented in the load forecast and power system analysis. All
reinforcement or investment have been considered in the future investment plan as illustrated in the
previse sections.
The required reinforcements and equipment loadings are shown in Appendixes C, D and E give a clear
picture of the anticipated constraints that may be imposed on the 33 kV network. The load flow results
shown for the years 2024, 2025, and 2026 were obtained assuming that the current ongoing projects
(CWIP) are expected to be completed on time and that the planned reinforcements are financed to bring
them into operation. Failure to fund these reinforcements or delay in timely completion will constrain the
network for three years.
1. The licensee shall, within 12 months of the grant of this licence, and thereafter, on an annual basis,
prepare a statement, in a form approved by the authority, showing, in respect of each of the three
succeeding financial years, circuit capacity, forecast power flows and loading on each part of its
distribution system and fault levels for each transmission node, together with:
• information on the status of distribution circuit capacity and the anticipated future requirements
of such capacity, including (i) applications for new Connections; and (ii) applications to Connect
Generation capacity to its Systems;
• a commentary prepared by the Licensee indicating the Licensee's views as to those parts of its
Distribution System most suited to new Connections and Distribution of further quantities of
electricity
• information on what constraints are foreseen on the Licensee's Distribution System and where;
• information relating to progress of ongoing investment in its Distribution System;
• such further information as shall be reasonably necessary to enable any Person seeking to
Connect to or use the Licensee's Distribution System to identify and evaluate the opportunities
for so doing;
• an assessment of technical losses from the Licensee's Distribution System; and
• such other matters as shall be specified in directions issued by the Authority from time to time
for the purposes of this Condition,
• provided that the Authority may, upon application of the Licensee, relieve the Licensee from the
obligation to prepare any such statement in respect of any period and any part or parts of its
Distribution System specified in directions issued to the Licensee by the Authority from time to
time for the purposes of this Condition.
2. The Licensee shall include in every statement prepared in accordance with paragraph 1 above the
information required by that paragraph except that the Licensee may with the prior consent of the
Authority omit from any such statement any details as to the capacity, flows, loading or other
information, disclosure of which would, in the view of the Authority, seriously and prejudicially affect
the commercial interests of the Licensee or any third party.
3. The Licensee may periodically revise the information set out in and, with the approval of the
Authority, alter the form of the statement prepared in accordance with paragraph 1 and shall, at
least once in every year this Licence is in force, revise such statement in order that the information
set out in the statement shall continue to be accurate in all material respects.
4. The Licensee shall, when preparing the statement referred to in paragraph 1 of this Condition,
ensure that the statement takes due account of information required to be provided to it by Persons
bound by the Distribution Code.
5. The Licensee shall send a copy of the statement prepared in accordance with paragraph 1 and of
each revision of such statement in accordance with paragraph 3 to the Authority. Each such revision
shall require to be approved by the Authority and shall not become effective until approved by the
Authority.
6. The Licensee shall, subject to paragraph 6, give or send a copy of the statement prepared in
accordance with paragraph 1 or (as the case may be) of the latest revision of such statement in
Appendix B presents the following series of tables, for each grid substation power system model, which
show the expected performance of the distribution network under maximum and minimum demand
scenarios for each year from 2023 to 2026.
The maximum demand with real and reactive power loads at the PSS individual peak time in 2023
planning cycle and as accordingly forecasted for the period from 2024 to 2026. Percentage loading is
calculated based on the Firm Capacity of the PSS. This data was used in the load flow and fault level
studies for maximum demand scenario presented in this section of this DSCS. Below web link drives
directly to all Primary Substations Maximum demand tables:
https://mzgisportal.mzec.co.om/portal/apps/webappviewer/CapabilityStatment2024-2026.xlsx
The resulting maximum demand in MVA on 33kV circuits/feeders, calculated for the individual non-
coincident maximum loads of the PSS(s) connected to these feeders for the period 2023 to 2026.
Percentage loading is calculated based on the de-rated capacity of the circuits. Below web link drives
directly to all 33kV feeders loading tables:
https://mzgisportal.mzec.co.om/portal/apps/webappviewer/33kVFeedersLoading2023to2026.xlsx
The resulting voltage value (expressed in percentage of the nominal 33kV and 11kV) on the busbars of
the PSSs, corresponding to maximum and minimum demand scenarios. Below web link drives directly
to the voltage non-compliance tables:
https://mzgisportal.mzec.co.om/portal/apps/webappviewer/VoltageNon-Compliances2023to2026.xlsx
The resulting 3 phase maximum fault current level on the busbars of the PSSs, corresponding to
maximum demand scenarios. The rated breaking fault ratings of the switchgear are also specified. Below
web link drives directly to all Primary Substation 3-Phase Fault Current Levels tables:
https://mzgisportal.mzec.co.om/portal/apps/webappviewer/ShortCircuitLevels(kA)_SimulationResults.x
lsx
Below web link drives to the actual maximum demand in (Amp) on 11kV circuits/feeders for 2023 tables:
https://mzgisportal.mzec.co.om/portal/apps/webappviewer/11kVFeedersloading(Actual2023).xlsx
1. 1TX in Firm Capacity means primary substation has single 33/11 kV transformer (i.e., zero N-1
capacity and firm capacity equivalent to 11kV interconnection capacity);
2. Standby PSS means primary substation having 33kV and 11kV busbars energized with 11kV
outgoing feeders (i.e., loads) disconnected. The load on these PSSs is expected to be connected
occasionally, depending on requirement.
In the above-mentioned tables, a “-“(dash) appears in relevant years due to any of the following reasons,
as may be applicable:
Expected
No. PIAD No. Project Name Wilayat Completio Project Status Project Purpose
n Year
Muscat
1 D/06/2019 New Mabelah South 9 - P184 Seeb 2023 Execution stage To relieve loads from Mabelah Area
To relieve loads from Airport Height area and
2 D/02/2021 New Airport Height 6 PSS P195 Bousher 2023 Execution stage
accommodate the new load
MEDC/AMD/2/20
3 Replacement of al Hamriyah PSS (P035) Al Hamriyah 2023 Execution stage Old asset replacement
18
To relieve loads from Al Hail Area and
4 D/07/2019 Upgrading Al Hail North 1(P027) Seeb 2023 Execution stage
accommodate the new load
Different
5 D/03/2021 Installation of 33Kv Capacitor Bank in different Grids locations 2023 Execution stage Enhance the Network reliability and efficiency
Locations
Madinat Al Nahdha PSS - 33kV Load Shifting to Amerat Grid from Balance the load between the GSS and making
6 D/05/2018 Amerat 2023 Execution stage
Jahloot Grid the two 33kV feeders from the same GSS
Different
7 D/06/2022 11kV Capacitor Banks at Primary Substations 2023 Designing Stage Enhance the Network reliability and efficiency
Locations
PIAD/REP/2019/1 Old asset replacement and upgrading the PSS
8 Construction of 2X20MVA Ruwi Valley (P174) PSS. Muttrah 2024 Execution stage
/1 to relieve loads from the area
9 D/01/2020 Upgrading Sarooj Shati Al Qurum (P110) PSS Bousher 2024 Execution stage To relieve loads from Al Sarooj - Al Qurum Area
10 PIAD/REP/2022/2 Asset Replacement at Rusail Industrial 1 P103 Seeb 2024 Tendering Stage Old asset replacement
To relieve loads from Al Hail Area and
11 D/03/2022 Upgrading Al Hail North 2 Upgrade P (028) Seeb 2024 Tendering Stage
accommodate the new load
12 D/04/2022 Bousher Ansab Height[P202] PSS Bousher 2024 Tendering Stage To relieve loads from AL Ansab Area
13 PIAD/REP/2022/4 Aziba South-1A P014 replacement of 11kV SWG Bousher 2024 Designing Stage Old asset replacement
14 - Muttrah Store P085 replacement of 33kV SWG Muttrah 2024 Designing Stage Old asset replacement.
15 - Quriyat 2025 Planning Stage To relieve loads from Quriyat Area and
Upgrading Al Shahbari P092 3x220MVA
accommodate the new load
16 - Amerat 2025 Planning Stage Old Asset Replacement and to relieve loads
Upgrading Amerat 1 P005, 2x20MVA
from Amerat Area
17 - New Misfah Phase 2 PSS 3x20MVA Seeb 2026 Planning Stage To relieve loads from Misfah Area
18 - New Mabelah South 10 PSS Seeb 2026 Planning Stage To relieve loads from Mabelah Area
Al Batinah South
Internal Note:
1 Upgrading Khazaen PSS from 1x6 MVA to 2x6 MVA Nakal 2023 Execution stage cover the new loads
Date: 25/04/2021
Constructing Hai Asem 3x20MVA substation with three 33kV To relieve loads from Rumais Primary
2 SB-07/2013 Barka 2024 Execution stage
feeders from Hai Asem Grid Substation
Construction of 2x20 MVA PSS Shuaybah South at Al Musanah To relieve loads from Jamma Temp Primary
4 SB-04/2013 Musanah 2025 Execution stage
in Batinah South with 33 kV and 11 kV feeders. Substation
Construction of 2x20 MVA PSS Nakhal Wasit at Nakhal in To relieve loads from Afi, MPF and Taww
5 SB 01/2022 Nakhal 2026 Designing Stage
Batinah South with 33 kV and 11 kV feeders. Primary Substations.
Al Dakhiliah
Construction of Adam Bashaer 33 kV feeder from Adam grid To secure the 33 kV supply for Adam Bashaer
1 DH-07/2013 Nizwa 2024 Execution stage
station to supply Adam Bashaer primary substation primary substation
Construction of Sumail Industrial 132/33 kV grid station 2x125 Relieve the load form existing Sumail New grid
2 DH 06/2012 Sumail 2024 Execution stage
MVA with 33 kV feeders station
Construction of Birkat Al Mouz 132/33 kV grid station 2x125 MVA Relieve the load form existing Izki and Nizwa
3 DH-08/2013 Nizwa 2024 Execution stage
with 33 kV feeders grid stations
Construction of Jabel Al Akhder one 33 kV feeder from Izki grid To secure the 33 kV supply for Jabel Al Akhder
4 DH-02/2013 Nizwa 2024 Execution stage
station to supply Jabal Al Akhdher New primary substation primary substation
Relieve the load form existing Karsha, Maara
5 DH 01/2019 Construction of Maemeer 2x20 MVA Substation in Nizwa Nizwa 2026 Designing Stage
temp and Mamad primary substations
North Sharqiyah
Construction of New Sinaw C 3x20 MVA primary substation with Relieve the load from existing Sinwa A & B
1 SH 05/2012 Mudhaibi 2024 Execution stage
11 kV feeders and 33 kV feeders from Al Mudhaib grid station primary substations
Construction of Al Dreez 2x20 MVA substation with two 33 kV Relieve the load from existing Al Mudhairib
2 NSH 01/2019 Ibra 2024 Execution stage
feeders interlink with Mudhairib-3 and Mudhairib-4 primary substation
Construction of New 33 kV feeder from Samad Grid station to Mudhaibi-
3 ASS-DK 1/2022 2024 Execution stage Feeder Sumrah PSS from Samad Grid
Sumrah 3x6 MVA primary substation Sumail
South Sharqiyah
Relieve the load from existing Tawi Aishah,
Jalan Bani
1 SSH 01/2016 Construction of Wafi 2x20 MVA primary substation 2024 Execution stage Hadri Bilad and Kamil Water Pump primary
Bu Hassan
substations
Jalan Bani Relieve the load from existing Jalan Bani Bu Ali
2 SH 01/2012 Construction of JBB Ali-2 2x20 MVA primary substation 2024 Execution stage
Bu Ali grid and Jalan Bani Bu Ali primary substations
Jalan Bani Relieve the load from existing Jalan Bani Bu Ali
3 SSH 02/2019 Construction of Jawabi Grid 33 kV busbar and 33 kV switchgear 2025 Designing Stage
Bu Ali Grid Station
Construction of Al Ashkhara-2 2x 20 MVA substation with two 33 Jalan Bani Relieve the load from existing Ashkhara
4 SSH 03/2016 2025 Designing Stage
kV incomers from BB Hassan Grid Station Bu Ali primary substations
Modification of Sur Filayj 1x6 + 1x6 MVA substation to 2x6 MVA
5 TS-SSH 2/2022 Sur 2025 Designing Stage To comply with DSSS
with additional 33 kV Tapping from feeder 15L5 Sur Grid Station
Interconnection of the Masirah distribution system with MIS by Shutdown the Masirah Power Plant and
8 - Masirah 2026 Designing Stage
interlinked Switching Station to the Masirah Grid. reduce the OPEX cost
Interconnection of the Khuwaima distribution system with MIS by Shutdown the Khuwaima Power Plant and
9 - Khuwaima 2026 Designing Stage
constructing 2x20MVA reduce the OPEX cost
Al Wusta
Interlink of Rural Area Electricity (33 KV) Network in Wilayat Shutdown the Hijj Power Plant and reduce the
1 Tanweer 38/2021 Duqum 2023 Execution stage
Mahout with (400 KV) main Transmission Network OPEX cost
Design, Supply & Installation for Upgrading the SCADA System Duqm.Maho
6 Tanweer 19/2021 2024 Execution stage To integration of Duqm System to SCADA
at Wilayat Duqm in Al Wusta Governorate ut, Masirah
9 - Upgrade the Dhare PSS Duqm 2025 Planning Stage To comply with DSSS
10 - Extension of 33KV feeder to Um Qurshreb Village. Mahout 2026 Planning Stage Power Supply to Um Qurshreb Village.
AL Dhahirah
Reconstruction of 33 kV Portion of Ibri Old Grid Station- 33kV Replacing old assets and managing load
1 2017-01 IBRI 2024 Execution stage
Feeders Interlinks between grid stations
Construct New Hilat Al Nahdha PSS 3X20 with 33kV feeder from Cover the new loads and to relieve loads from
2 2021-2 IBRI 2024 Execution stage
Ibri Grid Mazra Bani Khater Primary Substation
Upgrading Baat PSS from 2X6 MVA to 2X20 MVA with 33kV
3 2021-5 Dreez 2024 Execution stage Cover the new loads
feeder from Dreez Grid
Rearrangement of 33kV network between Dreez & AL Hail Grid To manage Grid Stations loading and provide
4 2021-6 Stations (transfer Hugermat & Kahant to AL Hail Grid & Provide IBRI 2024 Execution stage second 33kV feeding source to AL Mahual and
second feeding source to AL Mahual & Kahanat PSS) Kahanat PSSs
Interconnection of the Hamra Al Doroa distribution system with To meet the demand and to rid of generation
5 - Ibri 2025 Designing Stage
MIS by constructing two 33KV circuits to distribution system. rental
6 2022-1 Construction of Ibri Industrial 2x6 MVA Primary Substation IBRI 2025 Execution stage Providing secure supply to new Industrial Area
Upgrade AL Akhdar PSS from 2x10 to 2x20 and Shift from Ibri
8 2021-2 IBRI 2026 Designing Stage Cover the new loads
TX1 & TX2 Grid Station to IBRI Old Tx3 & Tx4
33kV feeder interlinks to provide second feeding source for Wadi Providing second feeding source to comply
5 - Sohar 2025 Designing Stage
Ahin, Hail Al Asskareen , wadi Al Hilti and Hay Al Rafaa PSSs. with DSSS
Upgrading Siwi PSS from 2X6 MVA to 2X20 MVA with installing
1 2019-4 Khasab 2023 Execution stage Cover the new loads
new 33kV feeder from Khasab Grid Station
3 - New Khasab Port PSS (2X20 MVA) with Two 33kV Feeders Khasab 2025 Planning Stage Securing Khasab loads
4 - Modfication to secure Musandam Network Khasab 2025 Planning Stage Securing Khasab loads
Expected
No. Reference No. Project Name Wilayat Completion Project Status Purpose
Year
Muscat
The connection will be made by tapping on the existing
33kV cables passing near the AFH which are fed from
Improve Reliability at MOD MAM-B PS By Adding One
1 - Seeb 2024 Tendering Stage Rusail Industry Grid(G13) and feeding Rusail B PSS
New 33kV Feeder
and adding circa 1km of new 33kV sections form the
tapping points.
Al Batinah South
Construct 2x6 MVA substation to supply the sponsor
1 CC/10/2016 Nakhal 2023 Execution stage To meet Customer load required
project of STF Wadi Al Mawel complex.
Construction of two 11 kV feeders from Saqsuq
2 CC/6/2017 Substations to South Batinah Pumping Station Oman Barka 2023 Execution stage To meet Customer load required
Logistic
Construction of Al Hazam Water Pump 2x6 MVA
3 CC/5/2017 Musanah 2024 Execution stage To meet Customer load required
substation with 33 kV feeders from Muladah Grid
4 CC/2/2018 Construction of Hay Al Sharq 2x20 MVA substation Barka 2024 Execution stage To meet Customer load required
construction new 11 kV feeder from Khazaen temp
5 MZ22IC00910 PSS Tx 2 & tapping from DSSS:2378 as backup Nakhal 2024 Designing Stage To meet Customer load required
feeder to Khazaen fruit & vegetable
6 MZ23IC04116 Al Nakheel Integrated Tourism Complex Barka 2026 Designing Stage To meet Customer load required
Al Dhakilyah
Construction of 3x20 MVA ROP College primary
1 CC/20/2018 Nizwa 2024 Execution stage To meet Customer load required
substation
CC/10/2018 Construction of 2x10 MVA Al Ain Water Pump primary
2 Samail 2024 Execution stage To meet Customer load required
(CC/26/2017) substation
CC/11/2018 Construction of 2x10 MVA Hub 2 Water Pump primary
3 Samail 2024 Execution stage To meet Customer load required
(CC/27/2017) substation
CC/9/2018 Construction of 2x20 MVA Hameem Water Pump
4 Samail 2024 Execution stage To meet Customer load required
(CC/25/2017) primary substation
Construction of 2x33 kV feeder from Samail Industrial
MZ23IC03209-
5 132/33 kV grid station 2x125 MVA for Al Thail Metal Samail 2024 Execution stage To meet Customer load required
ND/D/1081/2023
Recycling LLC
MZ23IC03842- Construction of Two 11 kV feeder for Oman Data Park
6 Nizwa 2024 Execution stage To meet Customer load required
ND/M/1282/2023 S.A.O.C
Construction 11 kV feeder from Liwariyah PSS 2x6 Wadi Bani To supply the requested load of Wadi Bani Khalid water
2 CC/17/2018 2024 Execution stage
MVA to Wadi Bani Khalid water pump ststion Khalid pump station
Construction of 11 kV feeders from Sur Ind substation To supply Al Ghaith Chemical Industries LLC factory in
3 MZ22IC03732 Sur 2024 Execution stage
to supply Al Ghaith Chemical Industries LLC factory Sur Ind Area