fwctCoP 2023 Part 2
fwctCoP 2023 Part 2
Code of Practice
For
Fresh Water Cooling Towers
2023 Edition
(October 2023)
2023 Edition i
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
Foreword
This Code of Practice was prepared to promote the proper use of fresh water cooling towers
with guidelines for cooling tower design, installation, testing, commissioning, operation and
maintenance in order to meet the energy efficiency objective with due consideration of the
environment and health issues. It was developed by the Task Force which comprises members
from eight government departments, three professional institutions and three trade unions on
Code of Practice for Fresh Water Cooling Towers.
Part 2 of this series of Code of Practice for Fresh Water Cooling Towers (previously known as
Code of Practice for Water-cooled Air Conditioning Systems) provides details on the operation
and maintenance of cooling towers. It should be read in conjunction and made cross-reference
with the followings:
2023 Edition ii
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
Contents
Page
Foreword ii
Definitions v
1. Introduction 1
1.1 Scope 1
1.2 Objectives 1
1.3 Applications 1
6. Reference Information 23
Appendices
Appendix 2A – Recommended Minimum Monitoring Frequency for Different Water 24
Quality Parameters for Cooling Tower System
Appendix 2B – Recommended Routine Inspection Checklist for Cooling Tower System 25
Appendix 2C – Recommended Routine and Preventive Maintenance Checklist for 26
Cooling Tower System
Appendix 2D – Recommended List of Personal Protective Equipment 27
Appendix 2E – Sample Operation and Maintenance Records for Cooling Tower System 28
Appendix 2F – Sample Independent Audit Report for Cooling Tower System 31
2023 Edition iv
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
Definitions
Bleed off (blowdown) : The removal of water from a cooling tower system to maintain the
concentration of total dissolved solids and suspended solids in an
acceptable level.
Corrosion coupon : Small strip of metal, usually placed into water circuits so that they
can easily be removed, to enable the corrosion characteristics of
the water to be assessed.
Corrosion inhibitor : Chemical which protects metals by: (a) passivating the metal by
the promotion of a thin metal oxide film (anodic inhibitors); or (b)
physically forming a thin barrier film by controlled deposition
(cathodic inhibitors).
Cycle of concentration : The ratio between the concentration of dissolved solids in the
cooling water and the concentration of dissolved solids in the
make-up water as a result of the evaporation that takes place in
the cooling tower.
Dead leg : Water pipe with length equal to or larger than one diameter of the
pipe, ending at a fitting through which water flows only when the
2023 Edition v
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
Decontamination : A process used when a cooling tower system is found with a level
of bacterial count which involves a series of actions to disinfect,
clean and re-disinfect the cooling tower system.
Drift : Water lost from the cooling tower as liquid droplets or aerosols
entrained in the exhaust air, excluding condensation.
Fan : A rotary machine which propels air continuously. This is used for
moving air in a mechanical draft tower. The fan may be of induced
draft or forced draft application.
Fill (packing) : Material placed within cooling tower to increase heat and mass
transfer between the circulating water and the air flowing through
the tower.
Heterotrophic colony : The number of viable units of bacteria per millilitre of water
count (HCC) sample. It is also known as Total Bacteria Count (TBC), Total Plate
Count or Viable Bacteria Count.
2023 Edition vi
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
Medical and health : Hospitals, general clinics, specialist clinics; community support
care premises facilities for the elderly, such as residential elderly homes, social
centre for the elderly; and establishments providing health care
and services for the sick and infirm.
Operable window : An operable window is a window that has moving parts, such as
hinges, and can be opened. If a window is permanently locked or
required special tools to be opened, that window would not be
considered as an operable window when examining the separation
distance.
Oxidising biocide : Agents capable of oxidising organic matter, e.g. cell material
enzymes or proteins which are associated with microbiological
populations resulting in death of the micro-organisms.
Plume : The visible discharge of air and moisture from a cooling tower due
to condensation. It is usually most visible in cool and humid days
when water vapour emanates from the cooling tower exhaust.
Public accessible area : An area that is accessible by the public or building occupants other
than building management/maintenance staff. Some of the
examples are pedestrian thoroughfare/ footpath, place where
people gather together for activities, accessible green
roof/garden. Restricted area with proper access control which is
only accessible by building management/maintenance staff is not
considered as a public accessible area.
Scale inhibitor : Chemicals used to control scale. They function by holding up the
precipitation process and/or distorting the crystal shape, thus
preventing the build-up of a hard adherent scale.
Slug dosing/Shock : The process of adding in a single dose a much higher amount of
dosing chemical biocide than is normally applied, with the intention of
rapidly raising the concentration of biocide in the water to a level
expected to kill most of the organisms in the water.
Spray nozzle : A device used in an open distribution system to break up the flow
of the circulating water into droplets, and effect uniform spreading
of the water over the wetted area of the tower.
Stagnant water : Pockets of motionless water within the cooling tower system that
can allow microorganisms to grow.
Total legionella count : The number of legionella colony-forming units (CFU’s) found in
one millilitre of the water sample.
1. Introduction
1.1 Scope
This Part of the Code of Practice specifies the minimum requirements and good practices for the
operation and maintenance of cooling tower systems. This outlines both prescriptive and
performance requirements to minimise the health risk posing to the public by using cooling
towers, and to optimise the system operating performance. Emphasis has been put on the
followings;
1.2 Objectives
This Part of the Code of Practice aims at providing technical guidelines to every party involved in
the operation and maintenance of cooling towers so as to achieve the following objectives:
a) Assure the public health and safety by preventing any potential risks associated with cooling
tower system;
b) Achieve better/maintain energy efficiency and operational performance of cooling tower
system;
c) Minimise nuisances caused by cooling tower systems to the public;
d) Prevent pollution and misuse of water;
e) Assure occupational safety and health of the staff concerned.
1.3 Applications
1.3.1 This Code of Practice is intended for use by personnel who are responsible for the
operation and maintenance of cooling tower systems, etc. It should be applied to both
the newly installed and the existing systems.
2023 Edition 1
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
1.3.2 This Code of Practice should be read in conjunction with any additional recommendations
provided by suppliers/ manufacturers of the water treatment chemicals/cooling tower
equipment and any relevant specification and applicable ordinances and regulations in
Hong Kong.
1.3.3 EMSD reserves the right to interpret the contents of this Code of Practice.
1.3.4 In case of conflict between the requirements of this Code of Practice and any other
relevant requirements, the following order of priority should apply:
a) All currently in force Legislation and other Subsidiary Legislation.
b) The relevant Codes of Practice and Technical Standards.
c) This Code of Practice.
2023 Edition 2
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
2.1 General
2.1.1 A comprehensive operation programme for cooling tower system that applicable
throughout the lifetime of the entire cooling tower system should be developed and
implemented by the O&M contractor of cooling tower. The operation programme should
include, but not limited to, the following actions:
Cooling tower system should be kept in regular use whenever possible. When a system is used
intermittently or installed as standby unit, it should be run at least one hour per week. Systems
with standby unit should have the cooling towers in operation on a rotational basis to avoid a unit
to be left idle for a long period. Water treatment and water quality monitoring is required to
ensure effective levels of corrosion and scale inhibitor and biocide are maintained at all times. This
should also be applied to standby unit filled with cooling water.
2023 Edition 3
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
2.3.1 If the system is intended to be out of use for more than a week, the system should either
be:
a) kept full of treated water which should be checked (for biocide levels and water
quality) and circulated once a week; or
b) fully drain off the system water and dry the system by mechanical fan, and then
cover and shut off the inlet and outlet pipes leading to the cooling tower(s) to
prevent water from entering the system.
2.3.2 For both cases, cooling tower(s) temporarily shut-down should be isolated from the main
system to avoid contamination. Drain valve should be opened at all times to prevent
accumulation of water in basin on rainy days. Full re-commissioning, including cleaning
and disinfection should be carried out before the system is brought into service again.
2.3.3 The shut-down procedures for 2.3.1 a), closing without draining, should be as follow:
a) Where disinfection has not been done within 2 weeks or arised problems with
temperature or biocide levels, consider carrying out a full system disinfection with
flushing through to all outlets to achieve 50ppm free residual chlorine or equivalent
biocide* for at least an hour.
b) Flush through, refill and check whether biocide is at the highest normal operating
level at furthest outlets.
2.3.4 Procedures before system re-operation for 2.3.1 a), closing without draining, should be as
follow:
a) Carry out a full system disinfection, flushing through to all outlets to achieve 50ppm
free residual chlorine and equivalent biocide* for at least an hour.
b) Flush out and refill system to achieve highest normal operating levels of disinfection.
c) Monitor biocide levels and adjust where necessary. Take water samples for test after
at least 48 hours to allow the system to restabilize.
2.3.5 Systems fully drained might have pocket of water remained, which poses a risk of
microorganism growth, including Legionella. Procedures before system re-operation for
2.3.1 b), fully drain off system, should follow clause 2.3.4.
2023 Edition 4
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
2.3.6 If cooling tower(s) are shut down for more than four (4) months, cleaning, desludging and
disinfection should be carried out.
2.4 Control
2.4.1 Bleed-off is required to maintain the concentration of total dissolved solids (TDS),
insoluble precipitates, other chemical constituents and pH value of cooling water at an
acceptable level. Bleed-off is preferred to be performed automatically by a conductivity
sensor. Bleed-off immediately after chemical dosage should be avoided to minimise
chemicals wastage. Timer control or manual bleed-off is not preferred unless automatic
bleed-off by a conductivity sensor is not practicable.
2.4.2 The minimum cycle of concentration should not be less than six (6) for cooling tower
system.
2.5.1 General
The water treatment programme should aim at controlling the fouling of cooling tower
system due to corrosion, scale and microbial growth in order to maintain efficient heat
and mass transfer, to ensure free flow of cooling water throughout the system, and to
control the proliferation of bacteria in the system. Details of water treatment methods
should refer to the Code of Practice for Fresh Water Cooling Towers – Part 3: Water
Treatment Methods .
2023 Edition 5
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
Table 2.1: Indicative cooling water quality criteria for fresh water cooling tower(s)
Parameters Cooling Water Quality Criteria
Heterotrophic colony count Less than 100 000 cfu/mL
Total legionella count Less than 10 cfu/mL
Conductivity Less than 1 500 µS/cm
Total dissolved solids Less than 1 000 ppm
Suspended solids Less than 150 ppm
Calcium hardness as CaCO
Less than 500 ppm CaCO 3 3
pH 7 – 10
Total alkalinity as CaCO
80 – 500 ppm CaCO 3 3
Oxidising biocide Follow manufacturers’ specifications
Inhibitor level Follow manufacturers’ specifications
Temperature Optimal temperature for the system design
and current operating conditions
Chloride as mg/L Cl Less than 200 mg/L
Sulphate as mg/L SO4 Less than 200 mg/L
Total iron as mg/L Fe Less than 1.0 mg/L
Free Residual Cl* 0.5 – 1.0 mg/L
5-day Biochemical oxygen demand Refer to EPD’s Technical Memorandum on
(BOD5) Standards for Effluent Discharged into
Chemical Oxygen Demand (COD) Drainage and Sewerage Systems, Inland and
Metal ions Costal Waters
* Operators could decide the suitable concentration with due consideration of existing
pipe conditions.
2023 Edition 6
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
2.5.3.2 Information shown in the above tables is the indicative ranges which may vary
with specific cooling tower location and configuration. Also, the use of
metallic corrosion coupons in water circuit can provide an effective index of
the corrosive nature of the water. Recommended minimum monitoring
frequency for different parameters to determine the cooling water quality can
be referred to Appendix 2A.
2.5.4.2 In case that the bleed-off water is reused for flushing, the quality of flushing
water should be checked and closely monitored. Water Supplies Department’s
Water Quality Objectives of Saltwater for Flushing Supply are shown in Table
2.2 for reference. The bleed-off water should be treated to achieve the stated
water quality criteria for flushing supply at distribution when necessary.
2023 Edition 7
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
2023 Edition 8
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
a) Cultured samples
Water samples are cultured on special buffered charcoal yeast extract (BCYE) culture
media. Selective isolation processes to eliminate other microbial overgrowth can
determine the number of cfu of legionella pneumophila per millilitre of water.
Cultured samples can also be analysed to identify specific serogroups. Testing
procedures should comply with the current editions of AS/NZS 3896 – Water –
Examination for Legionellae including Legionella pneumophila and BS 6068-4.12/ ISO
11731 Section 4.12 Detection, and enumeration of legionella or equivalent
international standards.
2023 Edition 9
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
2023 Edition 10
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
2023 Edition 11
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
2.7.1.2 Cooling tower systems installed at medical and health care premises should be
monitored more closely. Water sampling for cooling tower systems installed in
these locations should be carried out at least once a month for both total
legionella count and heterotrophic colony count tests.
2023 Edition 12
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
Cooling tower systems should be inspected regularly. Inspection should include all mechanical
equipment, water tanks, water treatment facilities and major components such as fill, drift
eliminator etc. Water in cooling tower basin should be checked for clarity, odour, surface debris
and temperature. Cleanliness of every component in cooling towers, including fan, fill, drift
eliminator, water distribution and nozzle, basin, etc, should be ensured. Recommended checklist
and frequency for routine inspection of cooling tower system is shown in Appendix 2B for
reference.
3.2.1 General
Routine maintenance is required to ensure cooling tower system operating in a good
condition. Integrity and physical conditions of all components, including ladders, rails and
platforms, etc. must be inspected as well as regularly maintained to prevent breakage or
failure. Purging of dead legs during weekly inspection is required and the stagnant water
in dead legs, if any, should be drained by manual purging for at least 15 minutes.
Recommended routine and preventive maintenance checklist is described in Appendix 2C
for reference.
2023 Edition 13
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
3.3.2 On-line disinfection procedure for cooling tower systems are as follows:
a) Add biodispersant and circulate through the cooling tower system prior to on-line
disinfection (dosage as recommended by a water treatment services provider.
b) Dose a biocide of different chemical composition, or similar composition at a higher
concentration, to the cooling tower system in addition to that of the regular water
treatment programme.
c) Circulate the biocide through the cooling tower systems for the time specified by the
biocide manufacturer.
d) Return the system to normal operation.
3.4.1 Cooling tower systems should be regularly cleaned, desludged and disinfected at least
every 6 months.
3.4.3 Cleaning and disinfection of cooling tower system should be carried out by an O&M
contractor of cooling tower, water treatment services provider or a person with sufficient
relevant experience and trainings. Water treatment programme should be reinstated
before the systems are brought into service again. The cleaning and disinfection
procedures should be as follows:
a) Circulate biodispersant throughout the system before disinfection. (dosage as
recommended by the water treatment service provider)
b) Chlorinate the water and circulate for 6 hours, maintaining a minimum level of free
residual chlorine at 5 mg/L (ppm) through the entire fresh water cooling tower
system water circuit.
2023 Edition 14
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
c) If pH value is greater than 8.0, higher free residual chlorine level of 15 – 20 mg/L
(ppm) is required to achieve the disinfection performance.
d) Drain the entire water circuit, including the make-up tank.
e) Manually clean the cooling towers, sump, fill, drift eliminator, make-up tank and
water recirculation circuit. Accessible areas of the cooling towers and its fill should
be adequately washed. If cleaning method involves high pressure water spraying,
windows in the vicinity should be closed, air inlets blanked off and the working area
to be tended. The working area should be isolated to avoid nuisance to the
neighbourhood.
f) Refill with water, rechlorinate and recirculate for at least 6 hours, maintaining a
minimum level of free residual chlorine at 5 mg/L (ppm).
g) Drain and flush the system. Refill with water and dose with the appropriate start-up
level of treatment chemicals.
h) Re-commission the system.
Before water containing high residual free chlorine is discharged to drain, it should be de-
chlorinated. The usual procedure is to add sodium thiosulphate, sodium sulphite or sodium
bisulphate as a neutraliser. The level of residual free chlorine can be determined by testing and
the quantity of sodium salt can then be calculated.
3.6.1 Under the following circumstances, emergency decontamination of fresh water cooling
tower system should be carried out.
a) If total legionella count is detected to be 1 000 cfu/mL or more; or
b) If heterotrophic colony count is detected to be 5 000 000 cfu/mL or more; or
c) If on-line disinfection, as well as, cleaning and disinfection are not effective in
controlling legionella and heterotrophic colony count in cooling tower water.
3.6.2 The procedures for emergency decontamination of fresh water cooling tower system are
as follows:
a) Take water samples for laboratory investigation before any further action.
b) Prohibit entering the vicinity of cooling towers.
c) Circulate biodispersant throughout the system before disinfection (dosage as
recommended by the cooling tower system services providers).
2023 Edition 15
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
d) Add sodium hypochlorite to the system water to obtain a measured free residual
chlorine concentration of 50mg/L (ppm).
e) Circulate the system water with the fans off for a period of at least 6 hours.
f) Maintain the free residual chlorine level at an absolute minimum of 20 mg/L (ppm)
at all times.
g) After 6 hours, de-chlorinate and drain the system.
h) Clean thoroughly the basin, fill, drift eliminator, fan and water distribution system.
i) Refill with fresh water and add sodium hypochlorite.
j) Recirculate without using the fan, at 20mg/L (ppm) of free residual chlorine for 6
hours.
k) De-chlorinate and drain the system.
l) Refill, recirculate and take water samples for testing.
m) Re-commission system when total legionella count and HCC levels are detected
within acceptable range.
3.7.1 Sufficient personal protective equipment should be provided to the personnel responsible
to carry out inspection and maintenance work of a cooling tower system. Recommended
list of personal protective equipment required related to different job nature is shown in
Appendix 2D.
3.7.2 Training in safe work procedure, including the use and maintenance of protective
equipment should be provided to the personnel carrying out cooling tower system
commissioning.
3.7.3 Water treatment may involve the application of relatively aggressive and toxic chemicals
in an environment, which is difficult to control. Safety of plant and personnel is the major
concern. All personnel involved must be fully conversant with the safe handling of the
products, which form part of the water treatment regime. Water treatment chemicals
should be handled with care according to the manufacturer’s instructions.
3.7.4 Material safety data sheet (MSDS) and relevant recognised data sheet for the chemicals
used in water treatment process should be provided by water treatment services
providers and included in the operation and maintenance manual. MSDS and relevant
warning/safety label should be provided on the surface of water treatment chemical
bucket. The MSDS and labels should be properly protected against water and chemical
damage.
2023 Edition 16
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
3.7.5 Workers should practice with a high standard of personal hygiene. Adequate washing
facilities should be provided and made easily accessible.
3.7.6 Water treatment programme for a cooling tower system should be established by a
competent service provider and complied with the requirements specified in the CoP.
3.7.7 Eye wash bottles or washing basin with fresh water tap should be provided adjacent to
water treatment chemicals tanks or any appropriate location for emergency use.
However, the water contained in the eye wash bottle should be replaced periodically.
3.7.9 Electrical fittings and luminaries serving water treatment chemical storage area should be
weather-proof and corrosion resistant type.
3.7.10 Warning signs should be erected to alert for operation and maintenance personnel of the
potential hazard caused by cooling towers; and to restrict the unauthorised access to
cooling towers.
3.7.11 Workers exposed to hazardous substances and engaged in processes of cleaning and
disinfection and water treatment should undergo regular health surveillance with a
medical personnel. In the event that the worker develops respiratory, cutaneous and
other symptoms when exposed to hazardous chemicals, immediate medical attention
should be sought.
2023 Edition 17
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
The operation and maintenance (O&M) manual of the cooling tower system should be prepared by
the O&M contractor of cooling tower and kept by the owner of the system. The O&M manual
should at least consist of the followings:
a) Technical details of all equipment in a cooling tower system, including drawings of the plant,
equipment and systems;
b) System schematic and layout plan showing the locations of cooling towers and the nearby
openings in the building and the adjacent buildings;
c) Manufacturers’ recommendations on operation and maintenance of all equipment in the
cooling tower system;
d) A programme for routine chemical treatment, cleaning, desludging and disinfection of the
cooling towers;
e) Details of chemicals used for water treatment;
f) Recommended cleaning methods and dismantling instructions;
g) Start-up, operating and shut-down procedures; and
h) Procedure for emergency operation.
4.2.1 Log books to record system operation, routine inspection, water sampling results and
maintenance activities should be kept properly by the operation personnel. Details of log
books should include at least the following information:
a) Date and result of visual inspection;
b) Date and result of water sampling;
c) Date of cleaning, desludging and disinfection;
d) Date of chemical treatment with details on the treatment carried out;
e) Method of bleed-off and details of the automatic bleed-off controls;
f) Date, item of plant, equipment or system and nature of service (routine, preventive
and emergency maintenance) being performed;
g) Details of defects found and rectification procedure undertaken; and
h) The name of the person and company performing the service.
4.2.2 A sample operation and maintenance record form is enclosed in Appendix 2E for proper
minimum records of routine operation, inspection, water sampling and maintenance of
fresh water cooling tower systems.
2023 Edition 18
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
4.2.3 Operation and maintenance manuals and records should be kept by authorized personnel
and readily available for inspection upon request. The operation and maintenance
records should be kept for at least 2 years. Defects identified in any reports should notify
the plant owner/occupier, manager or their nominated representative immediately.
4.2.4 Any information change related to the cooling tower installation, including the ownership
and system components, should be reported to EMSD. Records as listed in section 4.2
should also be available for inspection by EMSD upon request.
2023 Edition 19
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
Submits to Auditor
Auditor issues an audit report to owner of Auditor submits audit a report to EMSD for
cooling towers for record and follow up checking
actions
2023 Edition 20
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
2023 Edition 21
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
5.1 Where an existing cooling tower system is no longer required for operation, the following
actions should be taken to decommission the installation:
a) Drain the water of the cooling tower system to sewage, in accordance with any
advice from the Environmental Protection Department, Drainage Services
Department and Electrical and Mechanical Services Department;
b) Remove chemical dosing tanks;
c) Disconnect power supply to the systems;
d) Disconnect water supply to the systems;
e) Remove the tower and preferably the other components of the systems;
f) Deliver the dismantled components (if recyclable) to material recycling plant.
5.2 In case it is not practical to demolish the system immediately in the decommissioning
period, the system should be kept dry and signage should be erected on the cooling tower
indicating that the system must not be re-activated. The water basin of the tower should
be dismantled in order not to allow rainwater accumulated in the tower. The owner of
cooling tower system should notify EMSD that the cooling tower system has been
decommissioned.
5.3 Owner of Building should be responsible to demolish the abandoned cooling tower system
if the owner of the cooling systems cannot be contacted.
2023 Edition 22
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
6. Reference Information
6.1 The following Ordinances, Technical Memorandum and Code of Practice should be
complied with in the operation and maintenance of cooling towers:
• Waterworks Ordinance (WWO) (Cap. 102)
• Buildings Ordinance (BO) (Cap. 123)
• Sewage Services Ordinance (SSO) (Cap. 463)
• Water Pollution Control Ordinance (WPCO) (Cap. 358)
• Air Pollution Control Ordinance (APCO) (Cap. 311)
• Noise Control Ordinance (NCO) (Cap. 400)
• Occupational Safety and Health Ordinance (OSHO) (Cap. 509)
• Public Health and Municipal Services Ordinance (PHMSO) (Cap. 132)
• Buildings Energy Efficiency Ordinance (BEEO) (Cap. 610)
• Technical Memorandum on Standards for Effluent Discharged into Drainage and
Sewerage System, Inland and Coastal Waters, EPD
• Technical Memorandum for the Assessment of Noise from Places other than Domestic
Premises, Public Places or Construction Sites, EPD
• Fresh Water Cooling Towers Scheme, EMSD
• Code of Practice for Prevention of Legionnaires’ Disease, PLDC
2023 Edition 23
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
Appendix 2A
Recommended Minimum Monitoring Frequency for Different Water
Quality Parameters for Cooling Tower System
2023 Edition 24
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
Appendix 2B
Recommended Routine Inspection Checklist for Cooling Tower System
Procedures Inspection
Frequency
1. Check condenser water pumps Weekly
2. Check cooling water quality Monthly
3. Check internal surfaces of cooling towers/evaporative condenser for scale, Monthly
rust, sludge and biofilm accumulation
4. Check cooling water for clarity, odour, surface debris and temperature. Weekly
5. Check strainers Weekly
6. Check drains Weekly
7. Check float valves Weekly
8. Check water treatment system, including water treatment dosing equipment, Weekly
controller, conductivity sensors, and other sensors, etc.
9. Check water treatment chemicals for adequacy and safety Weekly
10. Check condition/cleanliness of fill pack/tubes Monthly
11. Check condition/cleanliness of drift eliminators Monthly
12. Check condition/cleanliness of distribution troughs/spray headers and Monthly
nozzles
13. Check fans, drives and gearbox Weekly
14. Check water level of basin Weekly
15. Check bleed-off valve Weekly
16. Check for system leakage and overflow from cooling towers Monthly
17. Check air inlets and fan screens Weekly
18. Calibrate sensors As recommended
by equipment
manufacturer or
annually
whichever is
shorter
Note: The above checklists are for reference only. The owners of the cooling tower systems should develop their own water
quality monitoring schedules to suit their systems.
2023 Edition 25
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
Appendix 2C
Recommended Routine and Preventive Maintenance Checklist for
Cooling Tower System
Checklists Maintenance
Frequency
1. Tighten all fasteners Every 6 months
2. Clean strainers Monthly
3. Clean water basin and all internal surfaces of cooling towers Every 6 months
4. Adjust and lubricate pumps and pump motors Quarterly
5. Adjust and lubricate fans and fan motors Quarterly
6. Remove drift eliminators and fills for cleaning Every 6 months
7. Adjust and lubricate valves Quarterly
8. Clean water distribution pipework, including nozzles Quarterly
9. Remove end cap in each header for cleaning Every 6 months
Note: The above checklists are for reference only. The owners of the cooling tower systems should develop their own routine
and preventive maintenance checklist for their systems.
2023 Edition 26
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
Appendix 2D
Recommended List of Personal Protective Equipment
2023 Edition 27
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
Appendix 2E
Sample Operation and Maintenance Records for Cooling Tower System
A. System Description
Record Details
Building Name & Building Address
Cooling tower type
Number of cooling towers in system
Heat rejection capacities of the cooling towers
Building owner’s name/contact details*
Owner of cooling towers’ name and contact details*
O&M contractor of cooling towers‘ name and details*
Water treatment services provider’s name and contact
details*
Water sampling/laboratory contractor’s name and contact
details*
* To include company name, contact person’s business and after office hours telephone numbers
2023 Edition 28
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
2023 Edition 29
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
2023 Edition 30
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
Appendix 2F
Sample Independent Audit Report for Cooling Tower System
Cooling Tower EMSD Registration No. PS- ___ No. ____________ to _____________
A. System Description
Record Details
Building Name and Building Address
Cooling tower type
Number of cooling towers in system
Heat rejection capacities of the cooling towers
Building owner’s name/contact details
Owner of cooling towers’ name and contact details
Designer of cooling towers’ name and contact details
O&M contractor of cooling towers’ name and contact
details
Water treatment services provider’s name and contact
details
* To include company name, contact person’s business and after office hours telephone numbers
B. Documents Checking
Records
Documents available Recommendation
Yes No
Operation & maintenance manual
Testing & commissioning records
System schematic and layout drawings
Routine inspection records
Routine maintenance records
Routine cleaning and disinfection records
Monthly heterotrophic colony count (HCC) results
Monthly/Quarterly* total legionella count results
Routine water quality monitoring records (if available)
* Delete as appropriate
2023 Edition 31
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
C. Visual Inspection
Acceptable
Items Recommendation
Yes No
General cleanliness of cooling tower system
Integrity of components including ladders, rails and
platforms
Operation condition of cooling towers and pumps
Operation condition of water treatment equipment
Cleanliness of plant area
Drift loss control
D. Risk Identification
Recommendation/
Assessment of Cooling Tower System remedial action
required
System alteration Any system addition, alteration and improvement work
carried out in the previous year?
Yes No
If yes, has operation and maintenance programme been
reviewed?
Yes No
External Is there any newly occupied building regarded as high
environment risk designation located in vicinity to the system?
Yes No
If yes, has operation and maintenance programme been
reviewed?
Yes No
Is there any construction site found nearby?
Yes No
If yes, has operation and maintenance programme been
reviewed?
Yes No
Is the separation between the cooling towers and the
nearest opening(s) maintained to meet the separation
requirements as stipulated in Section 4.1 of Code of
Practice Part 1?
Yes No (please specify in details)
System Has fouling of cooling towers system occurred in the
performance previous year?
Yes No
If yes, has appropriate rectify work been carried out?
Yes No
Water treatment Has HCC results exceeded 100 000 cfu/mL during the
programme previous year?
performance Yes No
2023 Edition 32
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
Recommendation/
Assessment of Cooling Tower System remedial action
required
If yes, has appropriate rectified work, including cleaning
and disinfection and water treatment programme
review been carried out?
Yes No
Has total legionella count results exceeded 10 cfu/mL
during the previous year?
Yes No
If yes, has appropriate rectified work, including cleaning
and disinfection and water treatment programme
review been carried out?
Yes No
Compliance of Is the system complied with the Code of Practice?
Code of Practice Yes No
for Fresh Water
Cooling Towers
Potential risk
identified during
walk-through
inspection
F. Other recommendation
2023 Edition 33
Code of Practice for Fresh Water Cooling Towers
Part 2: Operation and Maintenance
G. Personal declaration
#Remark
Part I: To be completed by Auditor
*I, (Full name of Auditor), Registered Professional Engineer (*Building
Services / Mechanical Discipline), RPE Registration No: , have carried out annual independent
audit for the above cooling tower system in according to section 4.3 of the Code of Practice for Fresh
Water Cooling Towers, Part 2. And I am not involved in any O&M activities of this cooling tower
systems.
OR
*I, (Full name of Auditor), holder of
(Qualification of Auditor), issued by
(Institute issue the Qualification), have carried out annual independent
audit for the above cooling tower system in according to section 4.3 of the Code of Practice for Fresh
Water Cooling Towers, Part 2. And I am not involved in any O&M activities of this cooling tower
systems.
(* delete as appropriate)
#Remark: The Auditor should have relevant operation and maintenance experience on cooling tower systems and possess
either one of the following qualifications:
(a) Registered Professional Engineer in Building Services or Mechanical discipline, or
(b) Higher Certificate or above in building services engineering or mechanical engineering or air-conditioning
system, plus at least five years of operation and maintenance experience on cooling tower systems.
Note: The above formats are for reference only. The auditors of the cooling tower systems should develop their own formats
for their systems.
2023 Edition 34
機電工程署 能源效益事務處
香港九龍灣啟成街三號
Energy Efficiency Office
Electrical and Mechanical Services Department
3 Kai Shing Street, Kowloon Bay, Hong Kong
電話 Tel: (852) 3912 0642
傳真 Fax: (852) 2890 6081
網址 Website: https://www.emsd.gov.hk
電郵 Email: [email protected]