Annex 1 - SoW

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

Scope of Works

Construction of a 6 classroom school in Hamediya village, Sub of Namrud


Ninawa Gov.

1. PROJECT BACKGROUND

a. Project description:
The objective construction of this 6-classroom Hamediya primary School is to restore
primary education to the children in Hamediya Village. The building is owned and
operated by Dept. of Education, Ninawa Governorate.

b. Direct and indirect beneficiaries:


i. Direct beneficiaries: 12 Teachers employed (6 males and 6 female) with 150 students

ii. Indirect beneficiaries: 650 houses with a population of around 5,000 people (2,750
males and 2,250 female).

c. Impact after completion


Restoration of basic education to the students of Hamediya Village with the surrounding
areas and prepare them for secondary education. Providing education for 150 students.

2. LOCATION:
The project is located at Hamediya primary School in Hamediya Village - Sub of Namroud
Education - Ninawa Gov. Coordinates GPS (36.013328, 43.36612)

3. BUILDING CONSTRUCTION DESCRIPTION:


The Hamediya primary School is a one-story construction, with 6 classrooms, bathrooms,
and two management offices. The school is located inside a walled compound, with one
shift per day.

4. WORKS IN BRIEF:
The construction work includes civil, sanitary and electrical works.
 The civil part of the works includes but not limited to Remove all the classrooms,
administration rooms and sanitary facilities that made from the sandwich panel ,site
preparation, Backfilling by Sub-base , Excavation Works , Foundation Concrete,
Under DPC Wall, Blinding Concrete , Concrete works (Yard), Solid concrete block
walls , Reinforced Concrete for Slabs and Beams, Mosaic tiles, Skirting, Exterior
Surround Sidewalk, PVC windows with Burglar, Main gate foundation and columns,
plastering ,Steel doors, PVC doors , PVC windows, Painting, crystal clear glass and
suspended ceiling as indicated on the BoQ.
Scope of Works

 The sanitary works includes but not limited to water tank installation, ceramic
lavatory pedestal, Eastern toilet with siphon, Building of Drinking Bench, Septic
Tank, Water network, drainpipes, PPR water pipes maintain and water pump as
indicated on the BoQ.
 The electrical works includes but not limited to main distribution board, sub
distribution boards, power cable, ceiling fan, fluorescent fixture, switches, brackets,
outdoor lighting, split Unit Air-Conditioning (2 ton), Pipe Earthing System, Solar
Water Heater and electrical water boiler as indicated on the BoQ.

5. DURATION OF THE PROJECT


240 Calendar days