ITP-1093-201-14AB Rev00 - (JV Rev00) Lighting Tray

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 2

TAV - CCC - ARABTEC JOINT VENTURE Doc. No.

: ITP - 1093 - 201 - 14AB

Rev. No. : 00
INSPECTION AND TEST PLAN Handover Class : Finishes
FOR INSTALLATION OF LIGHTING TRAY
Page No. : 3 of 3

Inspection and Acceptance


No. Activity Description Test/Inspection requirements and Criteria Reference Documents Frequency Report Reference No.
AGC-A QC JV QC Engineer

1 Shop Drawing Drawing Review Project Specification 057000 Once H H H Approved Shop Drawing
Clause 1.6 C

2 Materials & Sample Submittals Document & Product Reviw Project Specification 057000 Once H H H MAR
Clause 1.4 & 2.13

3 Method Statement, Inspection and Test Plan Document Review Project Specification 057000 Once H H H Approved Method
Statement and MIR

4 Material Delivered on Site Inspection to confirm that approved materials Project Specification 057000 Every Delivery H H H MIR, Approved MAR
received

Mock-up Obtain Engineer's Approval of visual Mock before Project Specification 084126 WIR
5 a. Visual mock-up starting work. To set quality standards for Clause 1.5H & Once H H H Contract Document
b. In place mock-up installation Clause 1.5I

6 Site Examination & Setting-out Survey report Project Specification 057000 Each Location/area H H S Signed Survey report
Clause 3.1

7 Bracket & Steel Tubes Installation Conform to approved shop drawing & MS Project Specification 057000 Every completted area as per H H H WIR (1st Fix)
Clause 3.2 marked up location

8 Steel Frame & Cladding Installation Conform to approved shop drawing & MS Project Specification 057000 Every completted area as per H H H WIR (2nd Fix)
Clause 3.2 marked up location

9 Snaging & Handover of completed works Conform to approved shop drawing Project Specification 017700 Each Location/area H H H WIR
Clause 3.1B & 3.1C

Legend: S-Surveilance Inspection, W-Witness Inspection Point, H-Mandatory Hold Point for Inspection, R-Record Review
Form No. : FM-1093-201-14AB
Rev. No. : 00
TAV - CCC - ARABTEC Owner : ITP-1093-201-14AB
JOINT VENTURE
Handover Class : Generic
Page : 1 of 2
INSPECTION CHECK LIST FOR INSTALLATION OF LIGHTING TRAY

Note: Please tick box if verified: √ - Ok X - Not Ok N/A - Not applicable


Location: WIR No.:
System: Lighting Tray
Quality Control Inspection
INSPECTION ACTIVITIES
AGC-A QC TCAJV QC

A. Document Review
1 Shop drawing approved
2 Method Statement Approved
3 ITP Approved
4 MAR Approved
5 MIR Approved
B. INSTALLATION (1st Fix)
1 Survey Report Attached Approved
2 MEP Clearance attached
3 Installation Conform to Shop Drawing
4 Installed Materials Free of Damage
5 Completeness of work as per 1st Fix Item
C. INSTALLATION (2nd Fix)
1 Installation Conform to Shop Drawing
2 Installed Steel Frame & Cladding Free of Damage
3 Completeness of work as per 2nd Fix Item
D. SNAGING & HANDOVER OF COMPLETED WORKS
1 Review of related WIR raised on specified area
2 Snag Item Rectified

Contractor's Representative Name & Signature Date


AGC QC Engineer

JV Site Engineer

JV QC Engineer