ITP Installation of Glass Door

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

DOC. NO.

: ITP-1093-201-14N
TAV-CCC-ARABTEC JOINT VENTURE
REV. NO. : 0.0

MIDFIELD TERMINAL BUILDING HANDOVER CLASS : Finishes


ABU DHABI INTERNATIONAL AIRPORT
PAGE NO. : 2 of 3

INSPECTION AND TEST PLAN

ITP-1093-201-14N

FOR INSTALLATION OF FIRE RATED GLASS DOORS

MIDFIELD TERMINAL BUILDING


ABU DHABI INTERNATIONAL AIRPORT

ABU DHABI-UAE

Mohammad.
0 For Approval 25-MAR-2014 Maged Yassa Dennis Dixon Ali Hydar Ozak
A Imam

Rev. Description Date Prepared By Reviewed By Approved By


DOC. NO. : ITP-1093-201-14N
TAV-CCC-ARABTEC JOINT VENTURE
REV. NO. : 0.0

MIDFIELD TERMINAL BUILDING HANDOVER CLASS : Finishes


ABU DHABI INTERNATIONAL AIRPORT
PAGE NO. : 2 of 3

FORMS INDEX
LIST OF ATTACHED FORMS

Reference Rev Description


FM-1093-201-14N 00 INSPECTION CHECKLIST FOR
INSTALLATION OF FIRE RATED
GLASS DOORS

LIST OF REFERENCES

Reference Rev Description


MS-1093-201-14N 00 INSTALLATION OF FIRE RATED
GLASS DOORS

NOTE

The Inspection Forms are controlled outside of this ITP and


are included for information purposes only during the Review
and Approval cycle.

The latest revision of an Inspection Form as approved with the


controlling document shall be used during work execution.
DOC. NO. : ITP-1093-201-14N
TAV-CCC-ARABTEC JOINT VENTURE
REV. NO. : 0.0

MIDFIELD TERMINAL BUILDING HANDOVER CLASS : Finishes


ABU DHABI INTERNATIONAL AIRPORT
PAGE NO. : 2 of 3
TAV-CCC-ARABTEC JOINT VENTURE
DOC. NO. : ITP-1093-201-14N

INSPECTION AND TEST PLAN REV. NO. : 0.0

HANDOVER CLASS : Finishes


FOR INSTALLATION OF FIRE RATED GLASS DOORS
PAGE NO. : 3 of 3

Inspection and Acceptance


No. Activity Description Test / Inspection Requirements and Reference Documents Report Reference No.
Frequency AGC-A JV QC Engineer
Criteria
QC

Method statement inspection and material Project Specification 084124 Approved Method statement and
1 Document Review Once H H H
approval approved MAR

Project Specification 084124


2 Shop Drawing Drawing Review Once H H H Approved Shop Drawings

3 Material delivered on site Inspection to confirm that approve material H H H


Project specification 084124 Once per area MIR approved MAR
Received

WIR
Comply with approved drawings and survey Each location
4 Setting out / Survey Report Project Specification 084124 H H H FM-1093-201-14N
report/ to make sure proper alignment
Survey

Drilling Process / bracket fixing Anchor


Bolts/fixation/ screws fixing, installation of Project Specification 084124 Once per area
5 Fixation as per approved MS H H S FM-1093-201-14N
steel frames / fixation of outer frame, fire clause no 3.2
rated silicone application.

WIR
Glass door installation and glazing work Project Specification 084124 Once per area
6 Visual for each area H H H FM-1093-201-14N
/alignment clause no 3.2

7 Cleaning and protection Project specification 084124 H S R


To be ensure the cleaning and protection Once per area FM-1093-201-14N
clause no 3.5

Legend: S – Surveillance Inspection W – Witness Inspection Point H – Mandatory Hold Point for Inspection R – Record Review