B4.

Provide Oversight (Review and Adjust)

1. Appropriate management arrangements and oversight mechanisms need to be established at


programme and project levels to ensure UNDP’s accountability for activities, results and the use of
resources, while at the same time fostering national ownership and alignment to national
processes. Minimum requirements for such management and oversight arrangements include the
elements or functions described below and illustrated in Figure 1. To the extent possible, existing
structures—national, regional and global, UN pooled fund and others—should be used to fulfil
management arrangement functions.

Oversight Mechanisms
2. All UNDP programmes and projects must be governed by a multi-stakeholder board or committee
established to review performance based on monitoring and evaluation, and address
implementation issues to ensure quality delivery of results. In crisis contexts where constraints
prevent the government from being able to participate in relevant programme and/or project
boards, the Regional Bureau can grant approval for modified oversight mechanisms, taking risks
and stakeholders into account.
3. Programme oversight occurs through the country programme board, which is typically the joint
national/UN steering committee used to monitor the Cooperation Framework but may be a
dedicated board for the UNDP country programme. The board is a mechanism for consultation and
consensus-based decision-making on programme issues. It is responsible for oversight of UNDP
country programme implementation as well as its contribution to the Cooperation Framework. The
board, at a minimum, comprises the heads (or their designated representatives) of the government
coordinating agency and UNDP Resident Representative or head of office. If consensus cannot be

Page 1 of 3 05/06/2018 v. 5.0


reached within the joint national/UN steering committee, final authority on programmatic and
financial decisions rests with the Resident Representative.
4. If the country does not have a Cooperation Framework, a national mechanism for programme
oversight should be used, if one exists. In all other cases, including for global and regional
programmes, a UNDP programme board must be set up for programme oversight.
5. To acknowledge the national ownership of all development results, the programme board must
coordinate with relevant national mechanisms where possible, and partner within a coordinated
mechanism covering all initiatives relevant to the corresponding outcome. Parallel mechanisms
should not be set up for coordination where national ones exist.
6. Project oversight is done through a project board, a multi-stakeholder governance mechanism that
may also called a project steering committee or joint programme steering committee. The project
document will state the required frequency of project reviews. Multiple projects in a portfolio may
use the same board/committee for oversight, and existing mechanisms may be used, as long as the
required composition and oversight functions are met. Joint results group boards may also be used,
as long as individual projects are reviewed.
7. The engagement facility and provision of services are governed through programme management
oversight, and do not require separate oversight arrangements. For the provision of services, UNDP
participates in any relevant oversight mechanisms of partners in accordance with signed
partnership agreements.

Functions of Oversight Mechanisms


8. Programme and project boards meet at designated decision points, at least once per year for an
annual review, or as necessary. The purposes are to:
a. Provide overall guidance and direction and agree on adjustments within provided tolerance
levels (see Manage Change);
b. Assess the achievement of results in the context of the Cooperation Framework and national
results/outcomes;
c. Assess the quality of programming against the quality criteria for Cooperation Framework
and UNDP programming;
d. Assess risks to the programme or project, and agree on management actions and resources
to address them effectively; and
e. Identify and address operational issues of programme and project implementation, including
those that could lead to revisions of the Cooperation Framework, or country programme or
project if required.
9. In crisis settings, programme and project boards may meet virtually, through an exchange of
letters, or remotely through teleconference.

10. Assurance is the responsibility of each board member. The assurance role supports respective
board members in carrying out oversight and monitoring functions. This role ensures appropriate
management milestones are managed and completed.
11. An annual review meeting should take place at the time of year most effective for reviewing results
and making decisions. It should verify that the recommendations of the previous review were
appropriately followed up and make recommendations to overcome any new issues or seize

Page 2 of 3 05/06/2018 v. 5.0


opportunities identified. Recommendations also support the preparation of inputs into the UNDP
Results-Oriented Analysis Report and other reporting required by stakeholders/donors. Changes
that could adversely impact the achievement of already approved results or that could result in a
(re)allocation of earmarked resources are considered amendments that must be submitted to the
regional bureau for review.
12. The project board is responsible for making management decisions by consensus when required,
including the approval of project plans and revisions, and the project manager’s tolerances. It
reviews evidence on project performance based on monitoring, evaluation and reporting, including
progress reports and the combined delivery report. The project quality assurance report and donor,
UN pooled fund or vertical fund reports should be discussed with the board, along with
management actions to improve quality. Board decisions are made in accordance with standards to
ensure management for development results: best value for money, fairness, integrity,
transparency and effective international competition. In case a consensus cannot be reached within
the board, a final decision shall rest with the UNDP programme manager, the Resident
Representative or staff member with delegated authority as the programme manager.
13. The project board is consulted when a project manager's tolerances (normally in terms of time and
budget) have been exceeded. There is a tolerance for failure, as long as it: (a) results in timely
course correction that improves the design of the project, and (b) leads to explicit learning that is
shared within UNDP and among external partners. The board authorizes any major deviation from
the approved multi-year workplan and decides on project changes through appropriate revisions. It
ensures that required resources are committed, arbitrates any conflicts in the project, and
negotiates any issues between the project and external bodies. In addition, it approves the
appointment and responsibilities of the project manager and any delegation of project assurance
responsibilities. Potential members of the project board are reviewed and recommended for
approval during the project appraisal committee meeting. Representatives of other stakeholders
can be included on the board as appropriate.

Project Board Roles


14. Project boards contain four roles:
a. Project director (also called executive): Represents project ownership and chairs the group.
The director is normally the national counterpart for nationally implemented projects but can
also be from UNDP.
b. Development partners (also called supplier): Individuals or groups representing the interests
of the parties concerned that provide funding and/or technical expertise to the project. This
typically includes implementing partners, UNDP and donors.
c. Beneficiary representative: Individuals or groups representing the interests of those who will
ultimately benefit from the project. Their primary function within the board is to ensure the
realization of project results from the perspective of project beneficiaries. Often civil society
representative(s) can fulfil this role.
d. Project assurance: Project assurance is the responsibility of each project board member;
however, UNDP has a distinct assurance role for all UNDP projects in carrying out objective
and independent project oversight and monitoring functions. Project assurance has to be
independent of the project manager. A UNDP programme or monitoring and evaluation
officer typically holds the project assurance role on behalf of UNDP. For GEF- and GCF-
financed projects, project assurance is undertaken as per the requirements of the vertical
funds, and these services are covered by the fee provided by the vertical fund.

Page 3 of 3 05/06/2018 v. 5.0