Project-Based Pedagogy in Interdisciplinary Building Design Adopting BIM
Project-Based Pedagogy in Interdisciplinary Building Design Adopting BIM
Project-Based Pedagogy in Interdisciplinary Building Design Adopting BIM
www.emeraldinsight.com/0969-9988.htm
ECAM
25,10 Project-based pedagogy in
interdisciplinary building design
adopting BIM
1376 Ruoyu Jin
Department of Built Environment, University of Brighton, Brighton, UK
Received 9 July 2017
Revised 2 October 2017 Tong Yang
Accepted 18 October 2017
Department of Design Engineering and Mathematics,
Middlesex University, London, UK
Poorang Piroozfar
Department of Built Environment, University of Brighton, Brighton, UK
Byung-Gyoo Kang
Department of Civil Engineering, University of Nottingham, Ningbo, China
Dariusz Wanatowski
Department of Civil Engineering, University of Leeds, Leeds, UK
Craig Matthew Hancock
Department of Civil Engineering, University of Nottingham, Ningbo, China, and
Llewellyn Tang
Department of Architecture and Built Environment,
University of Nottingham, Ningbo, China
Abstract
Purpose – The purpose of this paper is to present a pedagogical practice in the project-based assessment of
architectural, engineering and construction (AEC) students’ interdisciplinary building design work adopting
BIM. This pedagogical practice emphasizes the impacts of BIM, as the digital collaboration platform, on the
cross-disciplinary teamwork design through information sharing. This study also focuses on collecting
students’ perceptions of building information modeling (BIM) effects in integrated project design. Challenges
in BIM adoption from AEC students’ perspective were identified and discussed, and could spark further
research needs.
Design/methodology/approach – Based on a thorough review of previous pedagogical practices of
applying BIM in multiple AEC disciplines, this study adopted a case study of the Solar Decathlon (SD)
residential building design as the group project for AEC students to deliver the design work and construction
planning. In total 13 different teams within the University of Nottingham Ningbo China, each group
consisting of final year undergraduate students with backgrounds in architecture, civil engineering, and
architectural environmental engineering, worked to deliver the detailed design of the solar-powered
residential house meeting pre-specified project objectives in terms of architectural esthetics, structural
integrity, energy efficiency, prefabrication construction techniques and other issues such as budget and
scheduling. Each team presented the cross-disciplinary design plan with cost estimate and construction
scheduling together within group reports. This pedagogical study collected students’ reflective thinking on
how BIM affected their design work, and compared their feedback on BIM to that from AEC industry
professionals in previous studies.
Findings – The case study of the SD building project showed the capacity of BIM in enabling
interdisciplinary collaboration through information exchange and in enhancing communication across
different AEC fields. More sustainable design options were considered in the early architectural design stages
through the cross-disciplinary cooperation between architecture and building services engineering. BIM
Engineering, Construction and motivated AEC student teams to have a more comprehensive design and construction plan by considering
Architectural Management
Vol. 25 No. 10, 2018 multiple criteria including energy efficiency, budget, and construction activities. Students’ reflections
pp. 1376-1397 indicated both positive effects of BIM (e.g. facilitating information sharing) as well as challenges for further
© Emerald Publishing Limited
0969-9988
BIM implementation, for example, such as some architecture students’ resistance to BIM, and the lack of
DOI 10.1108/ECAM-07-2017-0119 existing family types in the BIM library, etc.
Research limitations/implications – Some limitations of the current BIM pedagogy were identified Project-based
through the student group work. For example, students revealed the problem of interoperability between BIM
(i.e. Autodesk Revit) and building energy simulation tools. To further integrate the university education and pedagogy
AEC industry practice, future BIM pedagogical work could recruit professionals and project stakeholders in
the adopted case studies, for the purpose of providing professional advice on improving the constructability
of the BIM-based design from student work.
Practical implications – To further integrate the university education and AEC industry practice, future
BIM pedagogical work could recruit professionals and project stakeholders in the adopted case study, for the
purpose of providing professional advice in improving the constructability of the BIM-based design from 1377
student work.
Originality/value – This work provides insights into the information technology applied in the AEC
interdisciplinary pedagogy. Students gained the experience of a project-based collaboration and were
equipped with BIM capabilities for future employment within the AEC job market. The integrated design
approach was embedded throughout the team project process. Overall, this BIM pedagogical practice
emphasized the link between academic activities and real-world industrial practice. The pedagogical
experience gained in this BIM course could be expanded to future BIM education and research in other themes
such as interoperability of building information exchange among different digital tools.
Keywords Integration, Simulation, Information and communication technology (ICT),
Building information modelling, Design management, Constructions education
Paper type Technical paper
1. Introduction
Building information modeling (BIM), as the emerging digital technology in the global
architectural, engineering, and construction (AEC) market, is gaining wider application in
industrial practice. The popularity of BIM as an integral concept in the AEC industry has
motivated its necessary inclusion within relevant education (Ghosh et al., 2015). BIM
movements and multiple BIM-related areas (e.g. sustainability) have resulted in a higher
demand on competent BIM professionals and college graduates with BIM skills ( Jäväjä and
Salin, 2014). Educational institutions play a significant role in providing the industry with
BIM-equipped graduates (Tang et al., 2015). However, there are still insufficient institutional
education resources to train and educate AEC students to meet industry needs in countries
like China, where the industry demand for BIM professionals is growing.
BIM education is not simply changing the pedagogical tool from 2D computer-aided
design (i.e. CAD) to 3D visualization (Tang et al., 2015), but the way of collaboration
among project team members through information management and teamwork (Sacks and
Pikas, 2013). Recent trends of AEC movements, including prefabrication in construction
and energy efficient “green” building, are gaining momentum along with BIM in some
developing economies’ AEC markets (e.g. China). These state-of-the-art practices
are interlinked. For example, BIM digital libraries could be established to incorporate the
information of various building prefabricated members (e.g. precast concrete walls), and
BIM could be used to support the building energy performance analysis through data
sharing. Nevertheless, communication, coordination and collaboration, as keys for BIM
implementation, have not been fully integrated into existing BIM training or education
through project-based or experimental learning approach.
Previous relevant pedagogical practices mostly adopted BIM in single disciplines, such
as architecture in the studies of Mathews (2013) and Solnosky and Parfitt (2015), structural
engineering in the study of Nawari (2015), and construction engineering in the studies of
Kim (2011) and Ghosh et al. (2015). So far there has been limited pedagogical practice in
recruiting all the aforementioned disciplines by exploring BIM’s capacity in enhancing
interdisciplinary project design and construction planning through information sharing and
management. This BIM pedagogical study aims to: implement the project-based approach to
adopt BIM as the digital platform to enhance the multidisciplinary project teamwork for
final year undergraduate AEC students; incorporate the real-world scenario (i.e. off-site
construction elements and solar energy) into the project team design; apply multiple criteria
ECAM in the student project work including architectural design, structural analysis, technology,
25,10 cost estimate, and construction planning; and gain insights from the feedback and reflective
thinking of AEC students on BIM’s impacts on cross-disciplinary team project. The overall
goal of this BIM pedagogical work is to provide students’ with not only BIM operational
skills, but also the initial BIM-based collaboration experience which could help their future
professional career in the AEC industry.
1378
2. Literature review
2.1 Application of information and communication technology (ICT) in AEC fields
2.1.1 ICT movement in AEC industry. Barriers and constraints of ICT implementation in
the construction industry identified by Peansupap and Walker (2006) have been overcome
and advanced towards BIM adoption in terms of technology, cultural and behavioral
change management worldwide (Benjaoran and Bhokha, 2009; Khosrowshahi and Arayici
2012; Jensen and Jóhannesson, 2013; Ding et al., 2015; Rogers et al., 2015). Gajendran and
Brewer (2007) emphasized the influence of ICT integration on the change of cultural
environment. Through a BIM experience survey in Australia (2007–2010) and Finland
(2012–2014), Singh and Holmström (2015) established the congruence between Maslow’s
motivational theory of needs and Roger’s theory of technology adoption and innovation
diffusion. Individuals and organizations have distinct aspects of adoption and
innovation-related needs for being career champions and industry leaders to meet
market demands and maintain competitive advantage.
2.1.2 Benefits of BIM adoption. BIM enables digital forensic tracking of high quality
information to support business outcomes through true collaborative effort amongst all
stakeholders such as clients, designers, contractors, building occupiers and managers
(Yang, 2017). BIM collaborative processes will significantly improve the efficiency of design,
construction and operation, and provide a platform for continuous upskilling for all (Strong
and Burrows, 2017). Focusing on commercial construction, Farnsworth et al. (2015) surveyed
executive, mid-management, and BIM practitioner level employees on application,
advantages, and methods associated with the use of BIM in the sector. Top advantages
of using BIM were identified as communication, scheduling, coordination, visualization and
clash detection. Efficiency with regards to time, resources, materials, and reduced
construction costs were also acknowledged. Companies reported a positive impact on
profitability, construction time, and marketing. The 4D and 5D capabilities of BIM in
simulations for resources, time, safety, space, risk, construction layout and buildability
analyses have been used with the outcomes of reduced cycle times, reduced request for
information, reduced wastes and increased safety in some work tasks (Aziz and Tezel, 2016).
2.1.3 BIM applications in building design and construction. BIM can also be linked to
building sustainability. Wong and Kuan (2014) noted that BIM-based sustainability analysis
was regarded as a potentially useful vehicle for helping project stakeholders to capture
complete design and project information. The latest review of sustainability by Chong et al.
(2017) highlighted the demands of new BIM tools for assessing sustainability criteria,
improved interoperability among BIM software package and energy simulation tools.
Further impacts of BIM on various AEC practices can be found in further studies.
For example, Bråthen and Moum (2016) facilitated the use of “BIM-kiosks” for construction
site workers to obtain a better understanding of the design material, navigate to get
information about specific details or problem in the 3D model and efficiently handle complex
elements. Amuda-Yusuf and Mohamed (2015) created a building service standard method of
measurement framework for managing the cost of building services by quantity
surveyors/cost consultants. Li et al. (2015) developed a 4D automated simulation tool based
on simulation by using a game engine for construction resource planning, which was
different from traditional construction planning that relies upon the critical path method Project-based
and bar charts embedded with visualization and timing issues. These multiple studies pedagogy
indicated that BIM could play a role within different AEC fields. There could be further
work to adopt BIM to enhance interdisciplinary collaboration across AEC fields.
3. Research methods
This pedagogical research design consists of steps guided by Creswell (2014) as described in
Table I.
Details on the research design are described in the following sections, including students’
academic background, group project information, assessment approach of team design,
pedagogical strategies.
ECAM Steps Strategy
25,10
Preliminary Literature review of previous case studies in BIM pedagogy
considerations Case study approach adopting the 2018 Solar Decathlon (SD) project aiming to
incorporate the state-of-the-art practices within the AEC industries (e.g. prefabrication
construction, renewable energy facilities, and human well-being) to the BIM-based
group project
1380 Theories including Bloom’s Taxonomy (1956) and Chickering and Gamson (1987)’s
principles for good practice in undergraduate education
Purpose statement The research focuses on the BIM pedagogical practice aiming to enhance the building
project design by bridging multiple AEC disciplines
Research hypotheses AEC students could gain the experience through project-based learning on how BIM
impacts their design
The BIM pedagogy could link education to industry practice by comparing students’
perceptions towards BIM impact in project delivery to that of AEC professionals
Methods AEC student teams will be asked to perform the group design and construction
planning for the residential building by meeting pre-described project specifications
Table I. The deliverables of students’ group design included their design documents,
Research design steps presentations reflecting their experience on how BIM affects their group design, as
of BIM pedagogy well as benefits and challenges in BIM practice
As summarized in Table II, this SD project had specific requirements for adopting renewable
energy technologies and off-site construction. Students were guided on utilizing BIM as a
digital platform to perform the team design, and linking BIM into building energy simulation.
Team presentation
Desig
Project report
Re ect b
pro
vie rie
n brie
j
wo f
f
Problem-based Project-based
Simulation
learning learning
Informal group
Peer assessment
work
Strategies
Seven principles
for practice Active Bloom’s
Reflect Guide
(Chickering and Learning Taxonomy (1956)
Gamson, 1987)
Develop
Figure 2. Critical
Teaching strategies in Thinking
the BIM-based student
team project
Some of the teaching strategies and theories adopted from other educators (e.g. Bloom et al., Project-based
1956; Chickering and Gamson, 1987) are described below: pedagogy
• BIM enables simulation-related activities within the building design and construction
stages. In this team project, energy simulation was required to determine the
optimized energy efficiency design. The 4D scheduling was also encouraged to
display the assembly of prefabricated construction members on site.
• Peer assessment and informal group work were incorporated in the project design 1383
process. Peer-assessment could stimulate students to become independent learners
(Falchikov, 2005). Informal group work would enhance student collaborative work as
learning should be collaboration-based (Dolmans et al., 2005).
• The principles for good practice in undergraduate education proposed by Chickering
and Gamson (1987) were reflected in the BIM pedagogy, including encouraging active
learning, giving prompt feedback to students during different design stages of SD
project, encouraging contacts between students and faculty, as well as developing
reciprocity and cooperation among students.
• Bloom’s Taxonomy Theory defined six hierarchy levels of cognitive domain
(i.e. knowledge, comprehension, application, analysis, synthesis, and evaluation).
Students enrolled on this BIM course had all been equipped with subject-specific
skills and knowledge through their own field of core curriculums. For example, CE
students had learned and practiced building structural design, take-off estimate, and
construction scheduling; architecture students had been trained, through studio
work, in architectural design; and AEE students had been trained through their first
three years’ undergraduate study in building services design and environmental
sustainability. This project-based collaborative work was designed to apply their
own fields of knowledge to contribute to the team design adopting BIM as the
communication platform through information sharing.
Finally, students’ critical thinking was reviewed in the group project report. The critical
thinking could cover topics such as their understanding of how BIM impacted the project
delivery process compared to the traditional design approach, and existing problems in
applying BIM. The researchers also viewed students’ digital models, clash detection results, and
group presentation contents to check the consistency between their reflections and their project
design deliverables. For example, when a group claimed that BIM improved design quality with
clash detections, their clash detection reports would be checked by the researchers to verify the
detailed spatial clashes identified and how they were resolved. Similarly, when a group
described lack of family (e.g. solar PV panel) in BIM library as one challenge in using BIM, the
researchers would check the building model to pinpoint how the lack of family was acted upon
addressed. Only these consistent reflections from student group work would be considered
reliable and adopted for analysis of students’ perceptions towards BIM at later stages.
4. Results
By the end of the autumn semester in 2016, 12 undergraduate student teams and one
graduate team presented their team design proposals. Figure 3 showcases an example of
one student group’s workflow.
According to the given group work procedure described in Figure 3, the team design
started from a comprehensive understanding of the project requirements summarized in
Table I, to finally provide the design deliverables including architectural rendering, cost
estimate, construction scheduling, and integrated digital models. The key of the BIM group
design based pedagogy was AEC students’ interdisciplinary collaboration adopting BIM as
a digital platform.
ECAM Building
performance
Building
materials
25,10 analysis
Analysis of
site and end- Interdisciplinary
Start
user design in BIM
Are team
members from different
1384 disciplines satisfied with the
Yes
Building model
integration
Clash Detection
current design
Structural Architectural option?
soundness aesthetics
Satisfactory
Not
No
Cost estimate
Energy
simulation
Reflect on Clash Detection Clash Detection
project brief
Construction
scheduling
Satisfactory
1385
(c) (d)
Notes: (a) Determining the building orientation; (b) cross-ventilation; (c) 2D plan linked to 3D
visualization; (d) integration of solar panels. All the figures or images generated in this figure are Figure 4.
adopted from students’ original work in this BIM course without modification, with the purpose Interdisciplinary
collaboration in the
of demonstrating students’ interdisciplinary practice within BIM. The same rule applies to early design stage
Figures 5–15, except Figure 10 which is the researcher’s work
1386
Model Simulation
Calculate
Structure Stability
Cost
Evaluation
Clash
Figure 5. Detection
Architecture
One example of team and Structure
design with multiple Model Videos
BIM-based tools
Figure 6.
Spacing for
air conditioning
and piping
(a) (b)
Figure 7.
Interdisciplinary
collaboration in the
structural design
Notes: (a) Structural model; (b) integrated model
(a) (b)
Figure 8.
Spatial conflict
detected in
Notes: (a) Clash between pipes and structural column; (b) conflict between pipes MEP design
and structural beam
40
35
Annual Energy (MWh)
30
25
20 Building energy
demand
15 Renewable energy
generated
10
5
Figure 10.
Different teams’ 0
A B C D E F G H I J K L
simulation results
of building Student Team
energy demand Note: Only 12 teams’ simulation results are available and presented
and renewable
energy generation in this figure, the other team consisting of graduate students did not
provide the results
availability and transportation cost of prefabricated members. Among these 13 teams, six of Project-based
them chose a steel frame; three teams designed a timber frame structure, and two teams pedagogy
chose precast concrete construction. The remaining two teams chose a mixed structural
system, namely steel framing with timber roofing and flooring, and a recycled steel
container with steel framing. Figure 11 displays the visualization of the mixed structures.
Although two out of the 13 teams chose a mixed structural system, both of them
implemented steel as the main structure. It could be found that the steel-based materials and 1389
structure were the dominating option to satisfy the prefabrication construction needs of this
SD project. Teams all provided a rationale for their selections. For example, those teams who
selected the steel frame stated that steel is high in strength, fitting the fast construction needs,
and is recyclable, etc. The team that proposed to use a steel container in Figure 11 explained
that the locally available supplier could prepare the building services facilities (e.g. electrical
wiring) in the containers when they are being manufactured in factory, and the floors/walls
are integrated in the container therefore achieving time saving during on-site construction.
Teams were strongly encouraged to incorporate scheduling into the site-assembly for
prefabricated construction members on-site. Typically teams used Work Breakdown
Structure (WBS) in a Gantt Chart and 4D BIM to simulate construction activities on site.
Figure 12 and Figure 13 show an example of traditional scheduling approach and 4D BIM
assisted simulation, respectively.
(a) (b)
Figure 11.
Two mixed structural
systems in SD team
design
Notes: (a) Steel framing with timber roofing; (b) steel container with steel frame
ECAM Construction Process
25,10 3.2.3 Decoration
3.2.2 Inspection
3.2.1 Set lighting
3.1.4 Set plumbing
3.1.3 Install solar panel
3.1.2 HVAC equipment
3.1.1 Roof
1390 2.2.3 Hang wallpaper
2.2.2 Ceiling
2.2.1 Paint walls
2.1.8 Wall construction
2.1.7 Install slab
2.1.6 Set joist
2.1.5 Build connection
2.1.4 Set steel beams
2.1.3 Back-fill consolidation
2.1.2 Set steel columns
Figure 12. 2.1.1 Material preparation
A demonstration 1.3 Set precast foundation
of 12-day on-site 1.2 Ground Compaction
construction 1.1 Foundation excavation
scheduling 0 1 2 3 4 5 6 7 8 9 10 11 12 13
Duration Float
4.7 Reflection
As indicated in Figure 2, this BIM course was developed to motivate students’ active
learning and to nurture their critical thinking focusing on how BIM affected their team
design and management in this SD case study project. Students were guided to share their
BIM usage experience through this SD project. Based on the qualitative analysis of the 13
teams’ project deliverables, i.e. reflective reports, building digital models and drawings,
clash detection results, and group presentation contents, both positive and negative
perceptions that teams held towards how the adoption of BIM impacted their teamwork
were categorized and counted as shown in Table III.
Table III indicates the number of teams that provided the given perception towards BIM
impacts on their team project. The most frequently perceived positive effect of BIM within
the team project was the improved collaboration and communication. As teams reflected,
BIM worked as a platform for cross-disciplinary communication starting from the
Multi-Category MEP Equipment Schedule Project-based
Family and Type Category Count
Unit Cost Total Cost pedagogy
(¥) (¥)
Solar Panel 17,820.00
Mechanical
M_Solar Panel: 750 × 1,500 mm 66 270 17,820.00
Equipment
1391
Plumbing Equipments 6,898.84
Hand Washing Sink Plumbing 2 560 1,120.00
Fixtures
Mechanical
Febricated Water Supply Tank - Equipment 1 650 650.00
Standard
Plumbing
Shower - 965 × 965 mm 2 658 1,316.00
Fixtures
M_Water Closet - Flush Tank - Plumbing
2 499 998.00
Private = 2.1 Lpf Fixtures
Figure 14.
Pipe A captured example
M_Bend - PVC - Sch 40 - DWV 59 0.26 15.34
Fittings of take-off spreadsheet
Note: Only part of cost items were displayed in this figure to show the in Excel according to
the quantity generated
example of the budget sheet, some other items (e.g. electrical facilities from Autodesk Revit
and structural members) are not captured in this figure
(a) (b)
Figure 15.
Students’ work on
editing existing
quantity take-off
functions in
autodesk revit
Notes: (a) Adding formula; (b) changing format
conceptual design to the later clash detection. There were more motivations for
collaborations among the major disciplines (i.e. architecture, structural engineering, building
services engineering, and construction management) in the BIM-driven environment,
through information sharing and coordination within the digital building models. The
second most frequently recognized BIM impact on teamwork was the improved design
quality with clash detection. Teams were able to modify their models by correcting
detections automatically identified within the BIM system. One of the fundamental
ECAM Number Number
25,10 Positive perceptions of teams Negative perceptions of teams
BIM features, 3D visualization, was also frequently listed by teams as one major impact on
project design. Besides these three major positive effects of BIM, a few teams also had
positive perceptions of the effects of using BIM in building sustainability and design
delivery. AEE students in this project were responsible for integrating solar panels into the
building service facilities and analyzing the building energy demand. BIM, up to a certain
level, assisted the building performance analysis through data sharing (e.g. building
geometric information). The interdisciplinary design approach, as stated by several teams,
enhanced the design efficiency.
Some negative comments on BIM effects were also provided. One main barrier for
adopting BIM during this project work was the lack of families in the exiting BIM library.
Students had to perform extra work to build the family (e.g. solar panel) within the existing
library. A few groups demanded more software skill trainings before working on this SD
project. Teams also discussed the interoperability issue when linking BIM into building
energy simulation, specifically in the information loss when sharing the data among
different software applications. Besides these comments regarding technical factors, the
factor within design management was also concerned by student teams when adopting
BIM. Some architecture students stated that their design was restricted by both AEE and
CE disciplines. For example, in one group work, the AEE students declined the architecture
teammates’ proposal of applying larger-sized glazing for a better view, as it would result in
more heat loss in the winter. On another team, one architectural student claimed that the
worst part of BIM was that the architectural design was interfered with by team members
from other disciplines.
6. Conclusions
To fill the gap of limited BIM-based interdisciplinary teaching and learning at institutional
level, this BIM pedagogical work was developed to recruit students from multiple AEC
disciplines to deliver a solar-powered residential house within the real-world scenario. BIM
was adopted as the digital platform for cross-disciplinary communication, coordination, and
collaboration. Prefabrication and renewable energy technologies were incorporated in this
residential project as part of the BIM-driven cross-disciplinary cooperation among
architectural, structural, building services, and construction engineering work. It was found
that AEC students were generally motivated in the teamwork approach assisted by
BIM-enabled visualization and information sharing. With the experiential learning
procedure, students were able to provide their perceptions and feedback which were highly
consistent to that of AEC professionals from other studies regarding BIM influences on
project design and management. Generally, BIM was found to have positive effects in terms
of enhancing team communication, improving design through clash detection, assisting
sustainable design, and providing visualization. Challenges in BIM adoption were also
identified consistently to what had been found from the industry’s standpoint, such as the
lack of interoperability among BIM-related tools, insufficient BIM library database for
design needs, and the challenges to the traditional role of architects, etc.
The AEC students in this BIM course gained not only software skills but more importantly,
the interdisciplinary collaboration experience needed before they enter the industry. The
properly designed BIM pedagogy could provide AEC students with state-of-the-art skills and
help, further at some point, saving some resources of their future employers on employees’
BIM skill training. The limitations identified from this pedagogical practice could be linked to
research needs, such as the interoperability issue. Future BIM pedagogy could involve AEC
industrial professionals to assess student teams’ feasibility in design or construction planning
by providing more constructive feedback. More project-based case studies could be provided
from the industry to continue applying the real-world scenario in the pedagogy, which in
return provides design proposals to project stakeholders for their appraisal.
References
AIA California Council (2007), “Integrated project delivery: a guide”, AIA California Council, pp. 20-30.
Amuda-Yusuf, G. and Mohamed, S.F. (2015), “Essential features of a building services standard
method of measurement in Malaysia”, Engineering, Construction and Architectural
Management, Vol. 22 No. 6, pp. 749-770.
Azhar, S. (2010), “BIM for sustainable design: results of an industry survey”, Journal of Building
Information Modeling, Vol. 4 No. 1, pp. 27-28.
Aziz, Z. and Tezel, A. (2016), “Lean and BIM – a synergistic relationship”, UK Construction Excellence,
No. 1, p. 40.
Benjaoran, V. and Bhokha, S. (2009), “Enhancing visualization of 4D CAD model compared to Project-based
conventional methods”, Engineering, Construction and Architectural Management, Vol. 16 No. 4, pedagogy
pp. 392-408.
Bloom, B., Englehart, M.F.E., Hill, W. and Krathwohl, D. (1956), “Taxonomy of educational objectives:
the classification of educational goals”, Handbook I: Cognitive domain, David McKay Company,
New York, NY.
Bråthen, K. and Moum, A. (2016), “Bridging the gap: bringing BIM to construction workers”, 1395
Engineering, Construction and Architectural Management, Vol. 23 No. 6, pp. 751-764.
Chickering, A.W. and Gamson, Z.F. (1987), “Seven principles for good practice in undergraduate
education”, American Association for Higher Education & Accreditation Bulletin, Vol. 39 No. 7,
pp. 3-7, available at: www.aahea.org/bulletins/articles/sevenprinciples1987.htm (accessed
December 18, 2016).
Chong, H., Lee, C. and Wang, X. (2017), “A mixed review of the adoption of building information
modelling (BIM) for sustainability”, Journal of Cleaner Production, Vol. 142 No. Part 4,
pp. 4114-4126.
CIBSE (2016), “GVA/15 CIBSE guide A: environmental design 2015”, The Chartered Institution of
Building Services Engineers (CIBSE), ISBN 9781906846541.
Clevenger, C., Glick, S. and Puerto, C.L.D.P. (2012), “Interoperable learning leveraging building
information modeling (BIM) in construction education”, International Journal of Construction
Education and Research, Vol. 8 No. 2, pp. 101-118.
Creswell, J.W. (2014), Research Design: Qualitative, Quantitative, and Mixed Methods Approaches,
Sage publications.
Ding, Z., Zuo, J., Wu, J. and Wang, J.Y. (2015), “Key factors for the BIM adoption by architects: a China
study”, Engineering, Construction and Architectural Management, Vol. 22 No. 6, pp. 732-748.
Dolmans, D.H., De Grave, W., Wolfhagen, I.H. and Van Der Vleuten, C.P. (2005), “Problem-based
learning: future challenges for educational practice and research”, Medical education, Vol. 39
No. 7, pp. 732-741.
Falchikov, N. (2005), Improving Assessment Through Student Involvement: Practical Solutions for
Aiding Learning in Higher and Further Education, Routledge & Falmer, London.
Farnsworth, C.B., Beveridge, S., Miller, K.S. and Christofferson, J.P. (2015), “Application, advantages,
and methods associated with using BIM in commercial construction”, International Journal of
Construction Education and Research, Vol. 11 No. 3, pp. 218-236.
Gajendran, T. and Brewer, G. (2007), “Integration of information and communication technology:
influence of the cultural environment”, Engineering, Construction and Architectural
Management, Vol. 14 No. 6, pp. 532-549.
Ghosh, A., Parrish, K. and Chasey, A.D. (2015), “Implementing a vertically integrated BIM curriculum
in an undergraduate construction management program”, International Journal of Construction
Education and Research, Vol. 11 No. 2, pp. 121-139.
Jäväjä, S.S.P. and Salin, J. (2014), “BIM education: implementing and reviewing ‘opebim’ – BIM for
teachers. Computing in Civil and Building Engineering”, ©ASCE 2014, pp. 2151-2158.
Jensen, P.A. and Jóhannesson, E.I. (2013), “Building information modelling in Denmark and Iceland”,
Engineering, Construction and Architectural Management, Vol. 20 No. 1, pp. 99-110.
Jin, R., Hancock, C.M., Tang, L., Chen, C., Wanatowski, D. and Yang, L. (2017), “Empirical study of BIM
implementation-based perceptions among Chinese practitioners”, Journal of Management in
Engineering, Vol. 33 No. 5, 04017025.
Jin, R., Tang, L., Hancock, C.M. and Allan, L. (2016), “BIM-based multidisciplinary building design
practice-a case study”, 7th International Conference on Energy and Environment of Residential
Buildings, Brisbane, November 20–24.
Khosrowshahi, F. and Arayici, Y. (2012), “Roadmap for implementation of BIM in the UK construction
industry”, Engineering, Construction and Architectural Management, Vol. 19 No. 6, pp. 610-635.
ECAM Kim, J. (2011), “Use of BIM for effective visualization teaching approach in construction education”,
25,10 Journal of Professional Issues in Engineering Education and Practice, Vol. 138 No. 3, pp. 214-223.
Kriegel, E. and Nies, B. (2008), Green BIM: Successful Sustainable Design with Building Information
Modeling, John Wiley & Sons, Hoboken, NJ.
Lee, N. and Hollar, D.A. (2013), “Probing BIM education in construction engineering and
management programs using industry perceptions”, 49th ASC Annual International
1396 Conference Proceedings, San Luis Obispo, CA.
Li, H., Chan, G., Skitmore, M. and Huang, T. (2015), “A 4D automatic simulation tool for construction
resource planning: a case study”, Engineering, Construction and Architectural Management,
Vol. 22 No. 5, pp. 536-550.
Mathews, M. (2013), “BIM collaboration in student architectural technologist learning”, Journal of
Engineering, Design and Technology, Vol. 11 No. 2, pp. 190-206.
Nawari, N.O. (2015), “The role of BIM in teaching structural design.” Structures Congress,
pp. 2622-2631.
Peansupap, V. and Walker, D.H.T. (2006), “Information communication technology (ICT)
implementation constraints: a construction industry perspective”, Engineering, Construction
and Architectural Management, Vol. 13 No. 4, pp. 364-379.
Porwal, A. and Hewage, K.N. (2013), “Building information modeling (BIM) partnering framework for
public construction projects”, Automation in Construction, Vol. 31, pp. 204-214.
Rogers, J., Chong, H. and Preece, C. (2015), “Adoption of building information modelling technology
(BIM): perspectives from Malaysian engineering consulting services firms”, Engineering,
Construction and Architectural Management, Vol. 22 No. 4, pp. 424-445.
Sacks, R. and Pikas, E. (2013), “Building information modeling education for construction engineering
and management. I: industry requirements, state of the art, and gap analysis”, Journal of
Construction Engineering and Management, Vol. 139 No. 11, p. 04013016.
Sebastian, R. (2010), “Changing roles of the clients, architects and contractors through BIM”,
Engineering, Construction and Architectural Management, Vol. 18 No. 2, pp. 176-187.
Sebastian, R., Haak, W. and Vos, E. (2009), “BIM application for integrated design and engineering in
small-scale housing development: a pilot project in the Netherlands”, International Symposium
CIB-W096 Future Trends in Architectural Management, pp. 2-3.
Shanbari, H., Blinn, N. and Issa, R.R.A. (2016), “Using augmented reality video in enhancing masonry
and roof component comprehension for construction management students”, Engineering,
Construction and Architectural Management, Vol. 23 No. 6, pp. 765-781.
Singh, V. and Holmström, J. (2015), “Needs and technology adoption: observation from BIM
experience”, Engineering, Construction and Architectural Management, Vol. 22 No. 2,
pp. 128-150.
Solnosky, R.L. and Parfitt, M.K. (2015), “A curriculum approach to deploying BIM in architectural
engineering”, AEI, pp. 651-662.
Spon’s Architectures’ and Builders’ Price Book (2015), Edited by AECOM, 140th ed., CRC Press, Taylor
& Francis Group, Boca Raton, FL.
Strong, D. and Burrows, V. (2017), A Whole-System Approach to High-Performance Green Buildings,
Artech House, Norwood, MA, p. 281.
Tang, L., Jin, R. and Fang, K. (2015), “Launching the innovative BIM module for the architecture and
built environment programme in China”, Building Information Modelling (BIM) in Design,
Construction and Operations, Vol. 149, WIT Transactions on The Built Environment,
WIT Press, pp. 145-156.
The British Standards Institution (2013), “Specification for information management for the capital/
delivery phase of construction projects using building information modelling”, PAS 1192-2,
Incorporating Corringendum No. 1, BSI Standards Limited.
Thomsen, A. (2010), “The role and influence of the Architect in industrialized building”, Second cycle, Project-based
A2E. Alnarp: SLU, Landscape Management, Design, and Construction. pedagogy
Udeaja, C. and Aziz, Z. (2015), “A case study of fostering multidisciplinary in built environment using
BIM”, in Raidén, A.B. and Aboagye-Nimo, E. (Eds), Procs 31st Annual ARCOM Conference,
Association of Researchers in Construction Management, Lincoln, pp. 701-710.
Wong, J.K. and Kuan, K. (2014), “Implementing ‘BEAM Plus’ for BIM-based sustainability analysis”,
Automation in Construction, Vol. 44, pp. 163-175.
1397
Yang, T. (2017), “A whole-system approach to high-performance green buildings”, Intelligent Buildings
International, Vol. 9 No. 3, pp. 177-178.
Zhao, D., McCoy, A.P., Bulbul, T., Fiori, C. and Nikkhoo, P. (2015), “Building collaborative construction
skills through BIM-integrated learning environment”, International Journal of Construction
Education and Research, Vol. 11 No. 2, pp. 97-120.
Further reading
Jin, R., Tang, L. and Fang, K. (2015), “Investigation of the current stage of BIM application in China’s
AEC industries”, WIT Transactions on the Built Environment, Vol. 149, pp. 493-503.
Corresponding author
Ruoyu Jin can be contacted at: [email protected]
For instructions on how to order reprints of this article, please visit our website:
www.emeraldgrouppublishing.com/licensing/reprints.htm
Or contact us for further details: [email protected]
Reproduced with permission of copyright owner. Further
reproduction prohibited without permission.