Chapter 4 - Quantity Take-Off
Chapter 4 - Quantity Take-Off
1
Lecture Content
❑ Definition
❑ Calculations
2
Lecture Objectives
3
Quantity Take Off>> Definitions
❑ The estimation of quantities for a contract from plans and drawings which are then recorded in
❑ The process by which a cost estimator reviews a set of plans during preconstruction in order to
❑ While performing a quantity takeoff, estimators “take off” information from common contract
site water reticulation and drainage drawings, electrical drawings, and HVAC drawings.
4
Quantity Take Off>> Definitions
1. Define takeoff scope: An estimator must thoroughly answer the question “What needs to be taken
off or measured?” by study plans and specs. If any details are unclear, the estimator should as the
2. Measure each item: Once the scope of the takeoff is understood, the estimator should use the
3. Record quantities: An estimator then makes detailed references as to which sheet the items were
5
Quantity Take Off>> Definitions
❑ For larger projects, a more comprehensive strategy is necessary to manage the sheer
❑ In these instances, an estimator should divide the project into smaller more manageable
❑ The way an estimator chooses to break up a project into manageable pieces depends on
the type of project. High rise projects, as one example, are most easily divided into floors
or groups of floors. Some projects can be divided into zones, phases or even separate
buildings.
6
Quantity Take Off >> Calculations
❑ Each and every material to be used in the project has to be calculated. Example: every door
knob, floor tile, hinge, pipe, carpeting, length of steel, insulation, or any other fittings.
❑ Unit count
Items like lights, pipe fittings, hinges, doors, or power points are materials counted in units. With
items like nails, a unit consists of 500 or a unit can be an individual object, like air conditioners,
or windows.
❑ Linear length
Although you can count pipes, electrical wiring, or pieces of steel, suppliers sell them according
to length. 7
Quantity Take Off >> Calculations
❑ Surface area
To calculate the amount of material to cover an area, like carpet, the space’s length and width is
❑ Cubic volume
When filling space, such as with concrete, the measurements required are length x width x height.
❑ Physical weight
Materials like sand or backfill come in weight measurements, such as a ton of sand.
8
Quantity Take Off >> Calculations >> Example
• Weight is needed.
❑ Concrete Calculations
• Volume is needed in m3
• WxLxD
9
Quantity Take Off >> Calculations >> Example
❑ Concrete Footing
• Volume is needed in m3
• WxLxD
❑ Roof Covering
L • Area is needed in m2
• WxL
10
Quantity Take Off >> Calculations >> Example
• How much concrete is needed for 4 x 4 x 0.3 m Slab?
• Volume is needed
• = 4 x 4 x 0.3
• =4.8 m3 of concrete is needed. 11
Quantity Take Off >> Calculations >> Example
Objective: Calculate the quantities of concrete, steel reinforcement, and formwork required for a reinforced concrete beam.
Given Data:
•Beam Dimensions: Typical Beam x
•Length = 6 meters
•Width = 0.3 meters
•Depth = 0.5 meters
•Reinforcement:
•Main bars: 4 bars of 16 mm diameter x
•Stirrups: 10 mm diameter @ 200 mm center-to-center spacing
•Concrete Mix: M25 grade
•Unit weight of steel (16 mm) = 1.58 kg/m
•Unit weight of steel (10 mm) =0.99 kg/m
Section x-x
12
Problem Statement
• Calculate the quantities of concrete, steel reinforcement, and formwork required
for a reinforced concrete beam.
• Beam Dimensions:
• - Length = 6 meters
• - Width = 0.3 meters
• - Depth = 0.5 meters
• Reinforcement:
• - Main bars: 4 bars of 16 mm diameter
• - Stirrups: 10 mm diameter @ 200 mm center-to-center spacing
Step 1: Concrete Volume Calculation
• Formula:
• Volume of concrete = Length × Width × Depth
• Calculation:
• Volume = 6 m × 0.3 m × 0.5 m = 0.9 m³
Step 2: Reinforcement Calculation
• Main Bars:
• Number of bars = 4, Diameter = 16 mm
• Total weight = 4 × 6 m × 1.58 kg/m = 37.92 kg
• Stirrups: 2x(0.5+0.3)
• Number of stirrups = 31
• Total weight of stirrups = 31 × 1.6mx 0.99 kg = 49.10 kg
Objective: Calculate the quantities of concrete, steel reinforcement, and formwork required for a reinforced concrete footing.
Given Data:
•Footing Dimensions:
•Length = 0.8 meters
•Width = 0.6 meters
•Depth = 0.4 meters
• Bottom Reinforcement:
• Top Reinforcement:
• Calculation:
• Volume = 0.8 m × 0.6 m × 0.4 m = 0.192 m³
Step 2: Reinforcement Calculation
• BOTTOM REINFORCEMENT:
• Long Span:
• Short Span:
• Short Span:
22
Steel Structure
Quantity Takeoff
Ground Floor Plan
5m 4m
1 1
5m 1 2 3
2 2
6m 1 2 3
3 3
First Floor Plan
5m 4m
5m 1 2
2 1
6m 1 2 3
3 2
5m 4m
4m
4m
Elevation
IPE 500 ➔ 90.7 kg/m
IPE 500 ➔ 90.7 kg/m
First Floor
Blue Color Beams
3x5x90.7= 1360.7 kg
Total= 5442.4 kg
IPE 500 ➔ 90.7 kg/m
Second Floor
Blue Color Beams
3x5x90.7= 1360.7 kg
Total= 4625.9 kg
5m 4m
4m
4m
Elevation
HE 500 B ➔187 kg/m
Ground Floor Columns
HE 500 B ➔187 kg/m
C1 C2 C3
The total number of columns on
the 1st floor is 9 and all columns
are built with the same section.
The height of columns on the 1st
floor is 4 m. The total weight of
the columns can be calculated as
follows:
C4 C5 C6
9X4X187= 6372 kg
C7 C8 C9
First Floor Columns
HE 500 B ➔187 kg/m
C1 C2
The total number of columns on
the 2nd floor is 8 and all columns
are built with the same section.
The height of columns on the 2nd
floor is 4 m. The total weight of
the columns can be calculated as
follows:
C3 C4 C5
8X4X187= 5984 kg
C6 C7 C8
Footing and Link Beams
5m 4m
1m 1m
5m
0.5 m
1 1
0.3 m
1 2
5m 3
0.5 m
2 2
1 1
Blue Color Link Beams
3x5x0.5x0.3= 2.25 m3
1 2
5m 3
Blue Color Link Beams
3x4x0.5x0.3= 1.8 m3
2 2
Blue Color Link Beams
3x6x0.5x0.3= 2.7 m3
6m
1 2
Blue Color Link Beams
3
3x5x0.5x0.3= 2.25 m3
………….
Construction Phase
…………..
35
Questions
36