BOQ. 4seat (Boys)

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 6

Project: School Wash Latrine facilities

Bill of quantities improved Dry Pit Latrine for Boys (4 seats)

Item Description Unit Qty Unit price Total price


A. SUB-STRUCTURE
1. EXCAVATION & EARTHWORKS

1.1 Clear the site to remove top soil to an average depth of 20cm m2 35 300 10,500.00
Bulk excavation of ordinary soil type for latrine to a depth
1.2 not exceeding 400cm from reduced ground level m3 100 600 60,000.00
Bulk excavation of rocky soil type for latrine to a depth
1.3 exceeding 400cm from RGL m3 36 700 25,200.00

Backfill around masonry wall , pavement and ramp


with selected and non expansive material up to
a required level and well consolidated in layers
1.4 not exceeding 20cm thick m3 150 500 75,000.00

Load and cart away surplus excavated material


and deposited at an appropriate place not less
than 1 km out side the site as approved by the
1.5 Engineer m3 200 200 40,000.00

Lay and compact 250 mm thick hard basaltic ston


or equivalent stone hardcore, finished and
blinded with crushed stone under Ramp &
Pavement or as per the drawing and Engineers
1.6 recommendation m2 33 300 9,900.00
Sub Total 220,600.00
2. CONCRETE WORKS
Lay 5cm thick lean concrete in C-5 with
2.1 minimum cement content of 150kg/m3
a) Above hardcore of ramps m2 7.5 1000 7,500.00

Cast Reinforced concrete in class C-25 (with


a 28-day 150mm cube crushing strength
of 25MPa) and maximum aggregate size
of 30mm cast into formworks and vibrated
around rod reinforcement bars.( formwork &
2.2 reinforcement bars are measured separately) in: -
a) Grade beam (30cm x 30cm) m3 3.25 1000 3,250.00

b) 15cm thick floor slab, Provide openings for


vent pipes, squat hole, urine disposal pipe
and manhole's as per the drawing. When
finished the manhole cover should have
lever with the rest of floor. m3 3.15 1000 3,150.00
c)10cm thick floor slab for urenary floor , Provide openings
for urine disposal pipe as per the drawing. m3 1.35 1000 1,350.00
Provide, cut and fix in position sawn zigba
2.3 wood formwork or equivalent for; -
a) Grade beam m2
16 800 12,800.00
b) 15cm thick floor slab m2 21 800 16,800.00
Cost to supply, cut and fix Reinforcement steel
bars according to structural drawing. Price
includes cutting, bending, placing in position
2.4 and tying wires. -
a) dia. 6mm plain bar kg 16 200 3,200.00
b) dia. 8mm plain bar kg 86 200 17,200.00
c) dia. 12 mm deformed bar kg 720 150 108,000.00
Sub Total 173,250.00
3. Masonry and Block works

Construct 50cm -100cm thick, roughly dressed


hard trachytic or equivalent stone masonry
wall bedded in cement sand mortar mix of 1:3
as specified in the drawing. The price includes
Pointing for exposed surfaces or as directed by
3.1 the engineer. m3 64 1500 96,000.00
Sub Total 96,000.00
Total Carried to Summary (A)
B. SUPER-STRUCTURE
1. CONCRETE WORKS

Cast Reinforced concrete in class C-25 (with


a 28-day 150mm cube crushing strength
of 25MPa) and maximum aggregate size
of 30mm cast into formworks and vibrated
around rod reinforcement bars.( formwork &
1.1 reinforcement bars are measured separately) in:
a) In elevation columns (20cm x 20cm) m3 0.8 1000 800.00

b) In top tie beam (20cmx20cm) m3 1.2 1000 1,200.00

Provide, cut and fix in position sawn zigba


wood formwork or equivalent for columns and
1.2 top tie beams -
a) In elevation columns m2 16 1000 16,000.00
b) In top tie beams m2
18 1000 18,000.00

Cost to cut and fix Steel reinforcement steel


bars according to structural drawing. Price
includes cutting, bending, placing in position
1.3 and tying wires. -
a) dia. 6mm plane bar kg 53 200 10,600.00
b) dia. 12 mm deformed bar kg 204 200 40,800.00
Sub Total 87,400.00
2. BLOCK WORKS

20cm thick hollow concrete block (class C)


wall bedded in cement mortar 1:3 internal and
external walls left for plastering. The quality
has to be approved by the client prior to supply
2.1 of HCB. m2 64 1500 96,000.00
Ditto but 15cm thick HCB wall (class C), The
quality has to be approved by the client prior to
2.2 supply of HCB. m2 20 1500 30,000.00
Sub Total 126,000.00
3. ROOFING

Supply and fix G-32 galvanized corrugated


steel sheet roofing fixed to 5x7 cm purlins at
c/c 90 cm. Horizontal projection of roof area
3.1 shall be taken for measurement. m2 28 2000 56,000.00

Truss members of eucalyptus shall be well


seasoned, straight and free of harmful defects.
Each truss joint and members shall be firmly
connected with strips of band iron. Price shall
include approved 2 coats of anti termite paint
to truss and purlins. Truss should be fixed with
the top tie beam with Ø6 rebar and spaced at
3.2 120cm from each other. -
a) Ø 10 cm or above eucalyptus upper and
lower members ml 106 300 31,800.00
b) 5x7 cm zigba purlins , Price includes anti
termite treatment ml 36 300 10,800.00
Supply and fix 20x2.5cm kerero or equivalent
fascia board including 3 coats of weather 300
3.3 resistant paint. ml 7.2 2,160.00
Sub Total 100,760.00
4. METAL WORKS

All metal doors and windows shall be


fabricated from locally manufactured frame
1.25mm thick LTZ 38mm width, pressed metal
with the necessary iron mongory, accessories
and three coats of paint. The doors must be
fixed with simple lock inside and outside.
Price includes one coat anti rust and two coats
synthetic paint internally and externally. It also
includes provision of 40cm plastic cover at the
bottom of each door (1.5mm thick as per Amhara pipe
factory LLDPE Geomemberane sheet technical
4.1 specification).

Ditto but 70x30 window with weir mesh and


4.1.1 metallic frame as shown on the drawing No 4 8000 32,000.00

Ditto but 100x210 (100cm is clear opening).


Opening of this door is as shown on the
drawing and has emergency door exit for
4.1.2 disabilities latrine as shown on the drawing No 1 15000 15,000.00
Ditto but 70x210 (70cm is clear opening).
Opening of this door is as shown on the
4.1.3 drawing. No 3 15000 45,000.00
4.1.4 Door lock with key No 4 1000 4,000.00
Sub Total 96,000.00
5. FINISHING
Cost for Finishing works which shall include
all surface pre-cleaning. Preparation and
application of finishing and cleaning at the end
5.1 of finishing works
Three coats of plastering in cement sand
mortar of ratio 1:3 to HCB walls reinforced
5.1.1 concrete beams & columns as per the drawing m2 114 100 11,400.00
Pointing to HCB wall and exposed masonry
walls in cement sand mortar of ratio 1:3 as per
5.1.2 the drawing m2 50 200 10,000.00
30 mm thick cement screed floor finishing in
5.1.3 cement sand mortar of 1:3 m2 36 200 7,200.00

Install 110mm PVC vent pipe as per the


drawing. The price includes providing opening
hole in the CIS for passage, minimum two
bracket support with HCB wall and fixing PVC
5.1.5 with truss support & Truss. pcs 4 200 800.00

Provide trough Boys urinal made of HCB.


The HCB and the floor should be plastered
with smooth finish. Cost includes all works
including provision of Ø50mm PVC pipe
connected to the pit latrine as per the detail of
5.1.6 the drawing and supervisors/Engineer's recommendation. Ls 1 200 200.00

Supply and install seat for disable as per the


drawing. The seat should be suitable for using
and smooth. The price includes 1" GS pipe for
5.1.7 handrail. Ls 2 200 400.00

Supply and install hand rail for ramp made


of 1" GS pipe with bracers as shown in the
drawing & direction by supervisor. The price
includes all the necessary works for embedding
the hand rail on the ramp & provision of
5.1.8 materials thereto as per the drawing. -

a) Supply and fix 1'' galvanized steel pipe or equivalent


material hand rail. ml 24 200 4,800.00

b) Supply and place 25cm hardcore on the rump entrance of


the latrine providing a maximum of 6% slope . m2 7.5 200 1,500.00

c) Place 10cm thick mass concrete , 150 kg cement/m3 of


concrete. m2 7.5 200 1,500.00

Supply and fix precast Reinforcemen concrete manhole cover


as per the detail of the drawing and supervisors
5.1.9 recommendation. No 2 200 400.00
Supply and Install 1000lt water tanker as
shown in the drawing to be seat on a masonry
platform. Cost includes the construction of
masonry water tanker seat pointed to a good
finish, pipe laying, supply and connect all
5.1.10 necessary fittings as per the drawing and/engineer's order. Ls 2 200 400.00

Supply and construct handwash basin


connected to the latrine wall as shown on the
drawing/engineer's order.. Price includes 1/2" faucet, Ø50mm
drainage PVC pipe connected to soak away pit,
1" PPR pipe connected from elevated tanker's.
The soak away pit located a minimum of 10m
5.1.11 away from the latrine. Ls 1 200 200.00

a) Supply and construct HCB wall or equivalent stone


masonry structure for hand washing above ground level
bedded in cement mortar (1:3) in full joints m2 2 200 400.00

b) Apply three coats of plastering to the exposed surface of


the structure m2 6 200 1,200.00

c) Supply and install 1/2'' faucet connected to the pipe line


from elevated Tanker. No 8 200 1,600.00

d) Supply and install 50 mm uPVC or eqivalent drain pipe


connect to the sock away pit Price includes all accessories.
As per recommendation of supervise Enginner m 12 200 2,400.00
Apply wall paint to plastered external beams
5.1.12 and columns surfaces as per engineer's order. m2 12 200 2,400.00

Provide foot rest on each seat made of concrete as specified


on the drawing or as directed by the engineer.. The price
5.1.13 includes all necessary works there to. pcs 6 200 1,200.00
Sub Total 48,000.00
Total Carried to Summary (B)
Total A+B
hanamekat p.s

Project: School Wash Latrine facilities


Summary of cost for Dry Pit Latrine for Boys (4 seats)
Bill.no DESCRIPTION WORKS Unit Amount
A. SUB-STRUCTURE
1 Excavation & earthworks Birr 220,600.00
2 Concrete works Birr 173,250.00
3 Masonry and Block works Birr 96,000.00
Sub total .A Birr 489,850.00
B. SUPER-STRUCTURE
1 Concrete works Birr 87,400.00
2 Block works Birr 126,000.00
3 Roofing works Birr 100,760.00
4 Metal works Birr 96,000.00
5 Finishing works Birr 48,000.00
Sub total .B Birr 458,160.00
Total (A+B) Birr 948,010.00
15% VAT Birr 142,201.50
GRAND Total With VAT Birr 1,090,211.50