RCC Road Quotation
RCC Road Quotation
2024
Sl. Particulars Qty Unit rate Material Unit rate Service H.R.C
No. Unit Material Cost Service Cost Comments
Dismantling of existing road of carpeting & 218.7 0 4800 1049760 Cost of shift by
1
subbase course, dispose from Bepza. Truck included
Cum
Earth Excavation after existing subbase course 72.88 0 1100 80168 Cost of shift by
2
removal. Dispose from Bepza. Truck included
Cum
Preparation of sub grade with proper camber by 109.32 10500 1147860 1400 153048 Sub-grade
excavating earth equal to depth of pavement Base Type-I
thickness, consolidation with roller. Compaction
3
with Sand(Minimum F.M=0.8) & 40mm
downgraded brick chips. Compacted by Roller
Machine. Sub-base Thickness=150mm. Cum
Providing and laying double layer polythene 729 45 32805 15 10935
4
sheet under reinforced concrete. sqm
Reinforcement cement concrete works having 145.76 14500 2113520 1400 204064 Ready Mix-
specified compressive strength minimum Shah Cement
f'c=3500 psi or 25 MPa (*for normal concrete) at RMC
5 28 days cylinder strength. All complete
including cost of testing materials and concrete
& other charges as per direction of the engineer Cum
in charge.
Roller Machine rental & compaction works for 4 0 32000 128000
6
sub-base preparation. Days
Supplying, fabrication, and fixing to details as 13355 103 1375565 19 253745 Rod Brand:
per design M.S deformed bar as reinforcement
of required size and length for all RCC work in/c Made by EAF
straightening the rod, removing rusts, cleaning, technology like
7 cutting, hooking, bending, binding with 24 no. AKS, GPH
GI wire, placing the bars in position, in/c
lapping, spacing and securing them in position
by concrete blocks, metal chairs, etc. (Grade 500 Kg
(Rd 500/ 500W)
Total Bill(S/N=01-07) = Materials 4669750 Service 1879720
Completion Time:
Total 45 days (if can work continuously after work order. 60 days if cannot work on Friday & other holidays
Yours Faithfully
Mohaiminul Islam
Project Manager
_______ ______
For: M/S. H.R. Construction