Scoping Report Revised Version 1
Scoping Report Revised Version 1
Scoping Report Revised Version 1
PROPONENT:
The NATIONAL SOCIAL SECURITY FUND
P.O. Box 1322.
Tanzania Institute of Arbitrators (TIArb).
SUBMITTED TO:
NATIONAL ENVIRONMENT MANAGEMENT COUNCIL,
CONSULTANT:
SAFI CONSULTANT
CIVIL ENGENERES/STRUCTURE
ENGENERS
P. O. BOX 7302, DAR ES
SALAAM
TEL: +255 713254610
i
3.2.2 Construction Phase.............................................................................................12
3.2.3 Operation phase..................................................................................................13
3.2.4 Decommissioning Phase...................................................................................13
3.3 Utilities............................................................................................................................13
3.3.1........................................................................................................ Water
supply.......................................................................................................................13
3.3.2 Power supply........................................................................................................13
3.4 Waste Generation and Management.................................................................14
3.4.1............................................................................ Construction Phase 14
3.4.2 Operational Phase..............................................................................................15
3.5 Health and Safety Management..........................................................................16
3.6 Project EIA Boundaries............................................................................................17
3.6.1........................................................................................... Core Area 17
3.6.2 Area of Influence................................................................................................17
3.7 Life Span of the Proposed Project.......................................................................17
CHAPTER FOUR: POLICY, LEGAL AND INSTITUTIONAL ASPECTS............17
4.1Overview................................................................................................................ 17
4.2 Relevant Policies........................................................................................................18
4.3 Relevant strategies...................................................................................................18
4.4 Relevant Statutes......................................................................................................19
4.5 International Agreements and Treaties............................................................19
4.6 Administrative Framework.....................................................................................19
CHAPTER FIVE: BASELINE INFORMATION.............................................................22
5.1Introduction........................................................................................................... 22
5.2 Location and Administrative Boundaries...................................................22
5.3 Physical Characteristics..........................................................................................22
5.3.1...................................................................................................... : Climate 22
5.3.2 Topography and Soil..................................................................................22
5.3.3 Surface and Ground water Hydrology.................................................23
5.3.4 Air quality....................................................................................................... 23
5.3.5 Noise levels................................................................................................... 23
5.4 Biological Environment....................................................................................23
5.4.1 Flora.................................................................................................................. 23
ii
5.4.2 Fauna............................................................................................................... 23
5.5 Social Values........................................................................................................ 23
5.5.1 Demographic Profile...................................................................................23
5.5.2 Cultural diversity and social capital.....................................................23
5.5.3 Education........................................................................................................ 24
5.5.4 Water supply................................................................................................. 24
5.5.5 Waste Management..........................................................................................24
5.5.6 Energy and Communication....................................................................25
5.6 Economic Values................................................................................................ 25
5.6.1 Economic Conditions..................................................................................25
5.6.2 Transportation Infrastructure........................................................................27
iii
7.3.6 Water supply................................................................................................. 40
7.3.7 Solid Waste Management Alternatives......................................................41
CHAPTER EIGHT: MITIGATION MEASURES............................................................42
8.1Mitigation measures for construction phase impacts..................................42
8.2 Mitigation measures for operation phase impacts................................43
8.3 Mitigation measures for decommissioning phase impacts.......................43
CHAPTER NINE: ENVIRONMENTAL MANAGEMENT PLAN.......................45
9.1 Introduction................................................................................................................................45
CHAPTER TEN: ENVIRONMENTAL MONITORING PLAN..................................48
10.1 Introduction..............................................................................................................................48
CHAPTER ELEVEN: DECOMMISSIONING PLAN............................................................51
11.1 Introduction..............................................................................................................................51
CHAPTER TWELVE: CONCLUSION...............................................................................54
APPENDICES...................................................................................................................................55
Appendix A: Certificate of Incorporation.........................................................................55
Appendix B: Certificate of TIN............................................................................................. 56
Appendix C: Certificate of Occupancy and Leaseholder...........................................57
Appendix D: List of stakeholders consulted...........................................................................93
Appendix E: Architectural drawing............................................................................................95
iv
LIST OF FIGURES
Figure 1: The Satellite image shows Site location of the proposed project (Read
color) (Source: Google earth, February, 2022)
...................................................................................................................................................................
6
LIST OF PLATE
LIST OF TABLES
v
CHAPTER ONE: PROPOSED UNDERTAKING/DEVELOPMENT BACKGROUND
1.1 BACKGROUND
During her visit to access the progress of the project to construct a five-star hotel at
Mwanza Tourist Hotel in Mwanza, the President of the URT, H.E. Dr. Samia Suluhu
Hassan advised the Fund to consider putting up similar investments in Dodoma and
other suitable locations in the country provided that the return is justified. Thus, the
Government of the United Republic of Tanzania through National Social Security Fund
(NSSF) here referred as the proponent proposed construction of multipurpose
complex that will have office tower and a five-star hotel
Furthermore, based on the first schedule of the Environmental Management (EIA and
Audit) (Amendment) Regulations of 2018, the proposed project (Multistory buildings)
falls under type A, hence in the list for mandatory project and obliged for proponent
to comply with it. Being aware of the above, NSSF (Proponent) commissioned SAFI
1
Consultant Ltd in joint venture with EcoNat Consultants Ltd (Registered
Environmental firm) to undertake the ESIA study of the proposed project.
2
1.2 Methodology of the Study
3
Secondary data obtained from various documents such as Dodoma City
socio- economic profiles, web search, previous EIA reports, etc.
i) Meeting and discussion with Mtaa and Ward Leaders – Msangalale Mashariki
Mtaa and Dodoma Makulu Ward;
4
.
1.3 Rationale of ESIA Study
The ESIA study provides an analysis of the implications of the proposed project to
the social and biophysical environment in the project areas. The study also provides
a mitigation plan to prevent or minimize adverse impacts to be caused by different
project activities. The study addresses key Environmental and Social Aspects of the
proposed project concerning other land uses and community life in Dodoma City
Council.
The estimated cost of the project is TZS 148.40 billion and project life span is 20
years. The financial viability from the pre-feasibility study indicate the project is
viable as it is projected to generate positive Net Present Value (NPV) of TZS
37,930,052,022.72, Internal Rate of Return (IRR) of 16.24%, Average Return on
Investment(AROI) of 18.26% with Payback Period of 14 years from the beginining of
operation activities.
The sensitivity analysis has considered change in revenue and cost of construction of
the project. The result shown that a reduction of revenue by 15% while everything
remains constant, the project will not be viable. On the other hand, when cost
increase by 29%, the project will not be viable hence the project is more sensitive to
revenue than cost.
CHAPTERS DESCRIPTION
5
implementation arrangements
Chapter Project design, explains about the project components and its activities
three that will be undertaken to success the project.
Chapter Illustrates policy, legal and administrative frameworks, which are the
four relevant Tanzanian environmental policies and legislation applicable to
construction projects.
Chapter Baseline information relevant to environmental characteristics, which
five gives details concerning the Bio-physical environment and socio-
economic environment at the project area.
Chapter six Expresses the consultation exercise at the project area detailing the list
of stakeholders consulted and the issues raised.
Chapter Gives the mitigation measure for the potential negative impact of the
eight project.
Chapter Presents the decomission phas and the plan as wel as estimated
ten costs.
The Containing some key primary information collected during the study
appendices area attached at the end of this report.
6
List of consulted ministry/administration/people
7
CHAPTER TWO: PROJECT DESCRIPTION
The area for proposed investment is located at Njedengwa Hilltop, Block “F” Plot No.3
Njedengwa Investment Area, Msangalale Mashariki Mtaa, Dodoma Makulu Ward,
Dodoma City in Dodoma at -61878,358111 Region and the site can be accessed via
the UCSAF Road 24 kilometers from current Dodoma Airport and Dodoma CBD only a
mere 30 minutes’ drive from the aforementioned areas Figure 2.1.
Figure 2.1 Satellite View of Site Location (Source: Google earth, August 2024
8
2.4 Site Topography
Generally, the terrain of the area is gently sloping with rocky nature. In that regard,
during construction there will be excavation for breaking rocks which has cost impact
to construction costs. There will be cuts and fills of various point during project
construction so as to attain desired levels.
The site boundaries are clear with beacons and pins as observed during site visit
enclosing the entire area which covers 2.13 Ha which is equivalent to 21,300 sqm.
The clearance was ongoing for geotechnical survey. There were no any structures
plate 1. The proposed project site is surrounded by undeveloped plots
9
CHAPTER THREE: PROJECT DESIGN AND ACTIVITIES
11
3.2 Infrastructure, facilities and services
3.2.1 Water supply
Water supply network from DUWASA is available surrounding the site area as justified
by the natives of the area and the relevant authority. Clean water supply is important
not only by prospective occupants/users but also during the development phase of
the project.
There is no wastewater sewer near the area however, it was learned that DUWASA is
about to commence a new project of wastewater sewage which shall cross near the
area. Currently, the available wastewater pipe is approximately five (5) kilometers
away whereas its connection shall be very expensive. In that regard, the project shall
have onsite sanitation through construction of bio-digesters/ French drains.
3.2.3 Communications
TTCL telecommunication poles were seen near the area during the visit, furthermore
by virtue of the position of the site there is reliable telecommunication network from
other service providers within the country.
Road: Being located in the city area, the site enjoys various tarmac roads
which are well maintained and passable though out the year.
12
Ventilation: the design caters for natural ventilation with equipment’s that could
facilitate circulation of natural air. For instance, windows and doors/gates which
will allow air circulation.
13
Solid Waste Management: Project proponent will ensure having adequate waste
storage facilities and contract waste handling company for collection and
disposal.
Project activities at the site will involve three to four phases which are
mobilization, construction, operation and decommissioning. Mostly, the project
activities will not affects any environmentally sensitive areas such as wetlands,
productive agricultural land, important archaeological, historical and cultural
sites, and areas containing rare or endangered flora or fauna, areas containing
unique or outstanding background among others.
The mobilization phase will mostly entail deployment of required tools and
machinery for the work and requirement of construction crew for the same.
Also, the place will involve deploy of construction materials and their
transportations from the point source to the site. A contractor will be
responsible for this phase with supervision from the proponent.
14
Table 3: Types and quantities of construction materials and equipment
Construction crew
15
It is projected that the construction phase will require about 85 workers
whereby about 55 personnel are skilled and semi-skilled and about 30 non
skilled laborers). These will depend on the Contractors choice for specific
activity. Because of the size of the project there will be construction camp for
some workers and other workers will commute from their homes in Dodoma
city. The construction workers will be getting their food from the nearby
restaurants/food vendors; First Aid facility will be available on the site for
construction workers. In case of occupational injuries and any illness
emergency, workers can be treated in hospitals around Dodoma city.
3.4 Utilities
16
sourced from the nearby TANESCO line. The project also plans to have a
standby generator in case of power blackout. Estimate electricity demand
during operation phase is expected to be 180Kwh from TANESCO and 25KVA
from standby generators. For safety and minimization of any pollution, the
generator set will have the following specifications.
17
Fully weather protected,
Service dish and placed at containment area for management the oil spills
Within the premises there will be wastes generated from various activities
during the construction and operation phases and these wastes will not be left
to pollute the environment within and around the project. The management of
these wastes will be as indicated below:
Construction wastes
Table 4 below presents the summary of the anticipated major wastes
generation associated with the project construction and the description of the
treatment disposal methods
18
Table 4: Waste generation and treatment during construction phase
Domestic Wastes
Domestic shall include liquid wastes and general refuse. About 1589.5kg per
month of domestic refuse will be generated at the site by 85 workers
(assuming generation rate of 0.83kg/person per day where workers work for
22 days a month). A temporary solid waste station will be designated by the
19
proponent to store domestic refuse before they are collected for final disposal
to authorized dumpsite (Chidaya dumpsite) by the contractor/proponent or city
trucks.
Liquid waste
Sanitation system to be used at the site will be connected into the temporary septic
tank expected be constructed at site. Whereby,
There will be 85 workers
Water consumption = 40Litre /capita/day
80% of the water consumed become wastewater
Therefore, wastewater generation per day (85 x 40 x 80%) will be 2,720 litres
Solid Wastes
The Solid wastes such as packaging materials, plastic, food wastes are
expected during operational phase. Whereby the average number of workers
will be 100 and that the generation rate is 0.83kg/person per day. Total waste
to be generated per day will be 1000 x 0.83 = 83 kg; therefore, the waste will
be 83kg/day. The generated wastes will be directed to a designated temporary
garbage collection station before disposed at authorized dumpsite (Chidaya
Dumpsite) at least twice per week.
Liquid Wastes
All the liquid wastes from toilets/bathrooms will be collected and directed
septic tank and soak away pit. It is anticipated that there are people will be at an
operation time.
Storm water
20
At the open area within the site will be paved and drainage structures will be
constructed to collect water out of site and channeled into the nearby drainage
system.
21
3.6 Health and Safety Management
Proponent and contractor are committed to protecting the health and safety of
its employees, users of its facilities and neighboring communities to ensuring
that all activities are conducted in accordance with current buildings design,
standards and applicable local legislation, in a manner that protects the
environment and people’s health. The project shall be implemented in
compliance to labor laws in Tanzania, in particular, the Occupational Health
and Safety Act No. 5 (2003). Contractor shall adhere to safety and health best
practices as per its Safety and Health Policy including procedure of the works
and construction sites. Clauses to protect and safeguard of workers shall be
included in the contract documents for implementation stage:
Use of safety gear (PPE) to all employees and any person under
construction site or and other site visitors such as helmets, industrial
boots/shoes, gloves, and reflectors is mandatory.
Accident Prevention and Management Measure
- Ensuring that the project site is always safe and secure as per
rules and regulations covering special risks pertaining to the
building and construction industry.
- Restriction of unauthorized persons to entry at project site to
prevent accidents
- Keep safe working environment on site, put clear signs and/or
guard rails on dangerous spots.
- Ensure good housekeeping in the project site and always prevent
scattering of debris around the site.
- Reporting and keeping records of all accidents/incidents during
construction/installation and operation period.
- To ensure all issues indicated on design are followed
The assembly point should be placed at the site as well as first aid services
Firefighting mechanisms systems will be installed to the proposed project. The
system will comprise the following components; - Fire detection system,
22
fire hydrant system, fire and rescue service contacts, sprinkler system and
portable fire extinguishers.
Core area including the Plot size of 2.13 Ha which is equivalent to 21,300
square meters of land acquired for establishment of the proposed office tower
and hotel tower buildings.
23
CHAPTER FOUR: POLICY, LEGAL AND INSTITUTIONAL ASPECTS
4.1 Overview
Like other construction projects, the proposed activities will create several
environmental impacts that need to be managed throughout the project's
duration. The project owner must also adhere to different policies and legal
regulations related to environmental management. Given that a project of
this nature in Dodoma City affects multiple sectors, compliance with various
policies and laws is necessary, including those concerning land, water, and
other areas. This chapter summarizes the national and sector-specific legal
frameworks that regulate the environmental and social aspects of the
project's planning and execution.
25
4.6 Administrative Framework
The Environmental Management Act (Cap 191) and the Environmental
Impact Assessment (EIA) and Environmental Audit (EA) Regulations of 2005
assign various functions and responsibilities to different parties involved in
the EIA process for any proposed development. Table 5 below provides a list
of institutions and organizations and activities that have a bearing on this
project.
26
Table 5: Key Institutions to the ESIA Process
Village/street level
Msangalale Provide information on local situation
Mashariki Watchdog for the environment, security and other
mtaa community matters
The Proponent
28
CHAPTER FIVE: BASELINE INFORMATION
5.1 Introduction
The section describes prevailing situation of the study area in terms of physical
and biological environment and social environment. The information is based
on the information collected from the secondary and primary sources including
documentary review, interview with key informants, observation and
consultant meeting with the community. Information provided in this chapter
will be overlaid onto the project concept and components for impact
identification, evaluation and suggestion of mitigation measures.
district in the West and it lies between Latitudes 6.000 and 6.300 South, and
5.3.1 : Climate
The project site experiences semi-arid condition (like any other places in
Dodoma City) which characterized by a marked seasonal rainfall distribution
with a long dry and short wet season, an average annual rainfall of about 550 –
1000mm per year, which falls between December and April each year. The
average temperature varies from 200C in July to 300C in November each year.
29
The average wind speed is at 10 km/h above the ground with direction from
east to west of project site.
5.3.2 Site Topography and soil
Generally, the area is located on hills, the terrain of the area is gently sloping with
rocky nature. In that regard, during construction there will be excavation for breaking
rocks and there will be cuts and fills of various point so as to attain desired levels.
The soil at project area is characterized with silty-sandy mixes with a trace of clay,
lightly permeable and no-plastic.
5.4.2 Fauna:
There were no large animals reported or observed at the project site. The main
fauna reported by locals include: reptiles/lizards and butterfly.
30
31
5.5 Social Values
The total population in Dodoma city had increased from 410,956 persons in 2012 to
765,179 persons in 2022; this is an increase of 86.2 percent for period of 10 years.
This resulted from the increasing number of males from 203,931 persons in 2012 to
373,440 persons in 2022 as well as increasing number of females from 206,013
persons in 2012 to 391,739 persons in 2022. The general observation made on the
population increase reasons is due to rapid growth of population in the city due to
transfer of national capital city from Dar es Salaam to Dodoma City. This has
influenced more expansion of economic activities as well as business activities in
the city
32
disposal can lead to reduce health risk. The city together with solid waste
contractors’(privet sector) using vehicles, tractor and a wheel loader to remove
the generated solid waste in the center
The wastewater management at large areas in Dodoma city are practice onsite
treatment such as septic tank and soak-away pits and few areas are served
with the sewerage network (Offsite treatment). The project site will adapt the
onsite waste water management until the large project of sewer to be
accomplished after construction of waste stabilization pond at Nzuguni
The residents at project area like others in Tanzania depend on different sources of
energy such as electricity, kerosene, charcoal, fire wood, solar energy for domestic
and non-domestic consumption. The main source of power at Njedengwa area is
electricity which generated, transmitted and supplied by a sole utility agent,
Tanzania Electricity Supply Company Limited (TANESCO). There are also dependable
postal services and digital telecommunication services. The city enjoys modern
landline telephone system provided by Tanzania Telecommunication Company Ltd
[TTCL]. Mobile phones are also provided at a stiff competitive level. The competing
companies include VODACOM [TZ], Airtel, tIGO, Halotel and Zantel. The main Energy
for project site will be sourced from TANESCO and Generator.
Mining
Most of the mining activities include construction minerals like sand, gravel
33
and clay which are highly required in the City because of fast growing
population, investments and development activities performed in Dodoma
region as a capital city.
Agriculture
Basically, agriculture is the back bone of the economy of the people in the city;
it employs over 90% of the rural people. The sector has a role of providing
extension services to rural farmers to ensure food security in the district, it
also links between the researchers, NGOS and governments (central and local
governments). The main cropes includes grapes, sorghum, groundnuts etc.
Fisheries
There are no potential natural surface water bodies (rivers, lakes and other
minor waters) that could form potential sources for fishing activities. Hombolo
dam which is manmade water body was constructed in 1958 basically to
provide water for livestock and other domestic uses. Hombolo dam is now used
for fishing and irrigation, the common fish found includes oreochromis species,
cat fishes and fresh water prawns. The Hombolo dam is surrounded with 3
villages of Ipala, Zepisa and Hombolo Bwawani, the number of fishermen
ranges between 1000 and 150 using about 40 dugout canoes. However, the
city community uses tap water or harvested rain water to establish fish pond
34
for home use in order to raise fish in small scale to get source of protein and
income.
35
Livestock
The main objective of the livestock sector is to stimulate development of
livestock industry in the municipality taking due regard of the environment.
Also to promote livestock keeping activity from a tradition to a
commercial/business oriented for the purpose of improving the livestock
keeping and protecting resources used for fodder by encouraging farmers to
plant forages, to preserve grasses to feed livestock indoors and encourage
zero grazing.
The road infrastructures are facilitating economic activities within the city. The
main roads are divided into four main roads that is Arusha Road, Singida road,
Morogoro road and Iringa Road. The construction of ring road may reduce
congestion of cars in the city after decommissioning. There are other many
roads which connect on the mentioned road and the project site is accessible
through tarmac road
Railway Transport
There are regular passengers and cargo trains on the central railway line and
Standard Gauge Railway between Dar- es- salaam, Morogoro, Tabora, Mwanza,
Kigoma and Mpanda where these lines proceed to Dodoma in the Western and
East.
Air Transport
The city has airport located within where light charter aircraft accesses it. The airport
for heavy aircraft is constructed at Msalato area.
36
CHAPTER SIX: STAKEHOLDERS CONSULTATION AND ENGAGEMENT
6.1 Overview
37
6.2 Uses of Proposed Project Site
Through the meeting with the local government officials, the Consultants were
informed that the project area is owned by the city council of Dodoma and the
proponent is leased the land for construction of proposed project.
Based on the concerns raised, an analysis was carried out and issues ranked
based on the frequency of mention (see Table 7). Stakeholders expect that the
proponent will take their views into consideration in the planning, designing
and implementation of the project.
38
to workers and other site visitors
39
Road Safety /Accidents
Stakeholders insisted that during construction and operation period there will
be an increase of vehicle movement hence road safety procedures should
highly be followed to avoid unwanted accidents.
Waste water management
The member questioned about the management of waste including waste
water and solid waste where they recommended to employ the commpany
which will make sure everyday removal of the waste
Cultural values
During construction and operation many people will be comming to the site
with their culture hence inssted regular involvement of local leaders to
different activities undertaken at the site.
Environment degradation
Destruction of environment due to raw matereals to be used in the
construction of the environment where insisted to have the matereals from
registered and qualified suppliers found in or outside the city
41
Table 9: Stakeholders’ Concerns
S/N Institution/ Issue raised Response
Position
1. Ministry of -All rating requirements of Consultation will be
Natural five-star hotel should be made by the
Resources and considered proponent
Tourist -During designing or Before
implementation the
consultation must be made
with the ministry especially
Hotel rating department
2. PO-RALG This will be a good The rated (five-star
investment and the first hotel) will be
one in the city hence maintained
attract the tourist from in
and outside the city
-Rated by East Africa Rating
department after
construction should be
maintained
42
designing stage (rainfall,
temperature and wind)
Proper electricity system The proper electricity
REGIONAL should be considered system will be
5. MANAGER especially in the designing considered
TANESCO
DODOMA
REGIONAL Parking issues must be The design will
MANAGER considered consider provision of
6.
TANROADS parking lots
DODOMA
Design must include a Design will
proper firefighting system accommodate all
Safety signboards with an firefighting systems
independent source of and all safety
power must be installed requirements in the
FIRE RESCUE All firefighting equipment detailed design.
7.
FORCE DODOMA ie, portable fire
extinguishers, fire hydrants,
horsing pipe and smoke
alarm detection system
must be available
Appendix 1
8. DUWASA-DODOMA Location of septic tanks All utilities
should consider future use companies will be
of the sewer consulted and
identify all
infrastructures
allocation before
construction
43
9 WAMI- RUVU There is the scacity of The proponent will
BASIN water in the underground work closely with the
before construction/drilling basin and fullfill the
of bore hall the consultation requrements
of basin should be made
44
14 Solid wastes generated All solid waste
should be properly generated will be
ENVIRONMENTAL disposed of at the Landfill disposed in the
MANAGEMENT The design should consider dumpsite and the
OFFICER CCD rainwater harvest proponent will be
advised to consider
rainwater harvest
15. COMMUNITY The construction phase The labourers will be
DEVELOPMENT has to ensure labourers are obtained within the
OFFICER CCD sourced from locals to bring community
a sense of ownership. The sensitization on
The gender based violence GBV, HIV AIDS will
and HIV AIDS should be be conducted
considered in the whole All issues of social
community will be considered
-The design should consider
disabled people
Source: Consultant, August ( 2024)
45
CHAPTER SEVEN: ENVIRONMENTAL IMPACTS AND PROJECT
ALTERNATIVES
7.1 Overview
The magnitude and probability of the impact, as well as its spatial and
temporal scope
46
7.2.1 Mobilization P h a s e
Neither environmental nor social impacts are expected from this phase.
47
d) Noise Levels - Increased auditory disturbance resulting from construction
activities.
The construction activities need labor from skilled, semi-skilled and non-
skilled ones. The project through contractor will employ laborers for the
increased workforce and thus be able to execute assignment thus local
people can be offered employments and improve their life standards This is
positive and continuous impact to the local community throughout the
construction phase.
On the other hand, since the project do not offer in house catering services
to construction workers, it had been an opportunity for local food vendors
(Mama lishe) who have been providing food to the work force since
48
commencement of construction activities. This is positive and continuous
impact to the local community throughout the construction phase.
49
7.2.3 Operation phase
a) Fire Risk
This project, like all buildings in the city, is vulnerable to fire hazards.
Additionally, the building’s proximity to other structures increases the risk
that a fire originating elsewhere could easily spread to it. A fire is an
uncontrolled combustion process that occurs with no regard to time or
space, producing large amounts of heat, smoke, and toxic gases. The heat
generated can further accelerate the fire’s spread.
Human exposure to smoke and gases such as CO2, CO, and H2S can pose
several dangers: high temperatures may cause internal burns from inhaling
hot gases; smoke can obstruct visibility, complicating evacuation efforts;
reduced oxygen levels can lead to asphyxiation (ambient air usually contains
21% oxygen, which drops significantly during a fire); and the combustion
products themselves are toxic.
Flames can reach temperatures between 600°C and 1200°C, causing
immediate burns upon contact. For buildings, the impacts include structural
damage, destruction of contents, and the associated repair costs. Although
fire hazards are an ever-present risk in daily life, measures should be
implemented during the design and operational phases of the project to
minimize this risk and ensure the safety of the building and its occupants.
The consequences of fire are considered to be severe, long-lasting, and of
significant concern.
d) Waste generations
During the operational phase, the project will produce various types of
waste, including solid wastes such as food scraps and recyclable materials
(e.g., plastic bottles and bags), as well as liquid wastes like wastewater.
Improper handling of these wastes could lead to land and water pollution, as
well as visual and odor issues. This impact is direct, negative, long-term, and
of high significance with a high probability of occurrence.
e) Traffic congestion
d) Loss of Revenues
The decommissioning of the project will result in a loss of revenue for both
the proponent and the government. This impact is direct, negative, long-
term, and permanent, with moderate significance and a high probability of
occurrence.
The summary below (Table 10) shows the impacts which have occurred or
expected to occur and level of their severity and predicted impacts upon
decommissions of the projects.
liquid
waste
Auditory nuisance Irreversi Direct, Seconda Negati 1
due to bl e temporary ry ve
construction
works
noise
52
Air quality Irreversi Direct, Seconda Negati 1
degradation as a bl e temporary ry ve
result of gaseous
and dust emissions
Auditory nuisance Irreversi Direct, Seconda Negati
due to bl e temporary ry ve
construction
works
noise
Indiscriminate Irreversibl Direct, Primary Negativ 2
e temporary e
disposal
of solid waste
Exposure to health Reversib Direct, Primary Negativ 3
and le Temporary e
safety hazards
Employment Reversib Direct, Primary Positive 3
le Temporary
and indirect benefits
to small
scale entrepreneurs
53
2 Increase in theft Irreversible Direct and Primary Negative 1
cases in the area temporary
(Decrease in
safety and
security of
renters)
Fire Accident Irreversibl Direct and Primary Negativ 2
e temporary e
le Permanent v
54
Exposure Reversibl Direct and Primary Positiv 3
e temporary e
to
Occupational
health and
safety hazards
Sources; consultant august 2024.
Legend:
0 – No impact
+3 very high positive impacts -1 Minor negative impact
+2 High positive impacts -2 High negative impact
+1 Minor positive impact -3 Very severe negative impact
Short term: 0 – 4 years Long term: 5 years and above
Advantages:
Disadvantages:
Advantages:
Disadvantages:
Conclusion:
57
Groundwater extraction is another option for water supply at the project site.
It can serve as a supplementary source during times of water shortage.
However, before using groundwater, a thorough investigation of its quantity
and quality must be conducted to ensure its suitability.
Alternative Three: Rainwater Harvesting
Rainwater harvesting is also considered. This method involves collecting
rainwater from roofs and designing a rainwater harvesting system for
storage and use.
Conclusion:
The proponent has chosen to connect to the DUWASA water supply system
due to its reliability and consistent service. To address potential supply
interruptions, a rainwater harvesting system will also be implemented, and
water storage tanks will be installed to ensure a stable water supply.
The proposed project will generate solid waste during both construction and
operation phases (from shops and workers). An integrated solid waste
management system will be implemented to handle this waste effectively.
Waste Transportation
Waste will be stored in temporary containers and then transferred to waste
collection trucks operated by a licensed waste handling company. The
company will transport the waste to an approved dump site for final disposal.
Source Reduction
Priority will be given to reducing waste at the source. This approach involves
minimizing material use and waste generation through an awareness
program on solid waste management.
Recycling
The second priority will be recycling, reusing, and composting the waste.
This option requires a source separation program to be established.
Recyclable materials will be sold to local waste buyers in the surrounding
areas.
Conclusion:
An integrated approach combining source reduction, recycling, and proper
waste transportation will be employed to manage the solid waste generated
by the project efficiently.
58
59
CHAPTER EIGHT: MITIGATION MEASURES
construction phase
Sewage Management
Waste
phase impacts
decommissioning phase
62
CHAPTER NINE: ENVIRONMENTAL MANAGEMENT PLAN.
9.1 Introduction
- Adequate sanitary
facilities with
appropriate
arrangements will be
provided for workers.
Auditory
nuisance -Workers will be Noise levels will Contractor
caused by provided with noise not exceed 85
noise from protection gear, dBA during an 8-
construction including ear muffs hour day shift
works and ear plugs. and will be kept
below 35 dBA
-Noisy construction during nighttime
activities will be hours.
restricted to normal
working hours (8
a.m. - 5 p.m.).
Pollution of 0 liters of
environmenta -Sewage will be wastewater are Contractor
l bodies directed to the discharged
caused by septic tank and randomly.
improper soak-away pit on
management site. Regular
of liquid maintenance of the
waste building systems
and cleaning of the
toilets will also be
carried out.
- Workers will be
informed about the
importance of using
the sanitary
facilities.
64
- Wastewater will
be directed into the
temporary septic
tank.
Risk to - All proposed
workers' -Appropriate signs mitigation - Contractor
health and will be installed at measures are
safety the site. implemented.
- No accidents
-A well-equipped occur at the site.
first aid kit and a
trained individual to
handle site
emergencies will be
available at the site.
-Only workers
trained to operate
specific machines
and equipment will
be engaged.
65
µg/Nm³.
-For nitrogen
dioxide (NO₂),
the limit is 120
µg/Nm³ over 8
hours.
OPERATION PHASE
Traffic The project
congestion at proponent will No traffic jams Proponent
the site and in provide an or accidents will
the adequate occur due to
surrounding number of project
areas parking spaces operations.
for the project
to minimize the
impact.
Pollution of -Sewage will be
environmenta directed to the 0 L of Proponent
l bodies septic tank and wastewater will
resulting from soak away pit be discharged
improper on site. carelessly.
sewage Additionally,
management regular
maintenance of
the building
system and
cleaning of
toilets will be
performed.
DECOMMISSIONING PHASE
- Noisy
demolition
activities will
be restricted to
normal working
hours (8 a.m. to
5 p.m.).
-For nitrogen
dioxide (NO₂),
the limit is 120
µg/Nm³ over 8
hours.
Source: Consultant august 2024.
10.1 Introduction
68
Monitoring involves the systematic collection of data through repeated
measurements over an extended period to provide information on the
characteristics and functioning of environmental and social variables in
specific areas over time. The developer should collaborate closely with
NEMC and other construction authorities to ensure that all impacts are
managed according to the proposed mitigation measures. Monitoring
parameters, frequencies, target levels/standards, and institutional
arrangements will be formulated accordingly.
Paramet
Potential er Monitorin Target Level/ Responsibilit
Impacts g standard y
to
Frequency
be
Monitor
ed
CONSTRUCTION PHASE
-Noise Noise level Every day Noise levels will not Contractor
Level: throughout exceed 85 dBA during an
Auditory construction 8-hour day period and
nuisance phase 35 dBA during the night.
due to
construction
work
TBS
Air quality Dust levels, At least twice -Particulate matter: The daily
degradati smoke, CO, during the average of hourly values shall Contracto
on due to NOx, and decommissio not exceed 0.10 µg/Nm³, and r/
dust and PM ning phase the hourly values shall not proponen
gas emissions exceed 0.20 µg/Nm³. t
emissions from -For nitrogen dioxide (NO₂)
motorized and NOx: The concentration
equipment shall not exceed 120
µg/Nm³ over an 8-hour
period.
-For carbon monoxide (CO):
The daily average of hourly
values shall not exceed 10
mg/kg, and the average of
hourly values over eight
consecutive hours shall not
exceed 20 mg/kg.
71
CHAPTER ELEVEN: DECOMMISSIONING PLAN
11.1 Introduction
The decommissioning plan is significantly shaped by the priorities of both
the surrounding communities and the Nation. For this project, the proponent
will ensure improved communication with all relevant stakeholders
throughout every stage. The decommissioning plan will be considered a
"living document," subject to ongoing revisions during the project's
operational life. It will be periodically reviewed and updated to incorporate
any changes in project construction or operation that could impact
decommissioning. Initially, the proponent has proposed a closure plan with
the following objectives:
iii. Establish clear accountability and allocate sufficient resources for the
implementation of the closure plan.
vi. Ensure that the interests of all stakeholders are considered during the
project closure.
2) Permitting: The developer shall obtain all necessary permits for the
removal of the project, including those from the NEMC, Pension Fund,
District Council, and any other relevant authorities.
3) Interim Protective Actions: This phase will address any interim
protective measures required to safeguard human health and the
environment, if necessary.
4) Project Removal: As mentioned previously, the removal of the project
will be completed within twelve months.
5) Post-Removal Activities: Post-project removal monitoring will extend
for one year.
Project removal will commence six months after closure and will proceed for a duration
of twelve months. During the six months following closure, the developer will inventory
all components that need to be removed or disposed of. This inventory will aid in
preparing the final decommissioning plan for NEMC approval. A summary of the closure
plans for the proposed project is outlined in Table 13 below.
74
Contaminated Proponent 30 8,000,000/
-Potential for Regular Phase
soils discovered
environmental monitoring /NEMC days
during the survey
will be effectively pollution,
treated for including air and
decontamination. noise pollution
Demolition of all -Potential for
existing structures health and safety
will be carried out
risks
to ensure that all
potential wastes
are properly
disposed of.
A site survey will
be conducted to
identify any
contaminated
soils around
buildings and
structures at the
closure period.
Source: Consultant August 2024.
75
CHAPTER TWELVE: CONCLUSION.
The analysis of the project concludes that all phases of the proposed
project will have significant positive impacts on both the local
community and the country as a whole. These impacts will include job
creation for local residents, increased availability of moderate housing
estates (residential buildings), and a rise in government revenue.
However, despite these positive impacts, the project will also result in
some negative effects, such as air quality degradation from dust and
gaseous emissions produced by motorized construction equipment, as
well as the generation of solid and liquid waste. Various mitigation
measures have been proposed to address these issues. With proper
implementation and monitoring of these measures, the negative impacts
are expected to be minimal, supporting the case for the project's
approval and implementation.
76
APPENDICES
77
78
79
Appendix B: Stakeholders consultation meeting minutes at Ward level:
80
81
82
83