Inspection and Test Plan
Inspection and Test Plan
Inspection and Test Plan
CLIENT: SPORTT
Reference No: Rev No: 01 Rev Date: Page No: 1 of 1
ITP DETAILS
MAST NUMBER:
Action by
TITLE ZEL SPORTT Inspection Report No. Date
ELECTRICALS
Removal of existing panels, cables, capacitors H M
Installation of Iterra Box System H/R R
Installation of Main Cable to Iterra Boxes H/R R
Installation of trunking along mast H M
Installation of transition panel H/R R
Installation of LED Drivers H/R R
Installation of Main Panel, contactors and breakers H/R R
Install Transient Voltage Surge Suppressors H/R R
Install wiring and cables H/R R
SPORTLIGHT INSTALLATIONS
Install Brackets on New Cradle H R
Install Sportlights on New Cradle H/R R/S
Complete Wiring on New Cradle H/R R/S
Install Grommets on New Cradle H/R R/S
TESTING
Visual Inspection - Welding H/R R/S
Visual Inspection - Electrical H/R R/S
Visual Inspection - Painting and Coating H/R R/S
Fabrication Report H/R R/S
Welding Report H/R R/S
Insulation Resistance Testing H/R R/S
Electrical Resistivity Testing H/R R/S
Testing of Sportlights H/R R/S
Note:
TORS
DAD. W.I.
[email protected]
Location: ARIMA
of 1