Cost of Capturing Co From Industrial Sources: July 15, 2022
Cost of Capturing Co From Industrial Sources: July 15, 2022
Cost of Capturing Co From Industrial Sources: July 15, 2022
This project was funded by the United States Department of Energy, National Energy
Technology Laboratory, in part, through a site support contract. Neither the United
States Government nor any agency thereof, nor any of their employees, nor the
support contractor, nor any of their employees, makes any warranty, express or implied,
or assumes any legal liability or responsibility for the accuracy, completeness, or
usefulness of any information, apparatus, product, or process disclosed, or represents
that its use would not infringe privately owned rights. Reference herein to any specific
commercial product, process, or service by trade name, trademark, manufacturer, or
otherwise does not necessarily constitute or imply its endorsement, recommendation, or
favoring by the United States Government or any agency thereof. The views and
opinions of authors expressed herein do not necessarily state or reflect those of the
United States Government or any agency thereof.
All images in this report were created by NETL, unless otherwise noted.
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
This report was peer reviewed by three independent peer reviewers with various
affiliations and from relevant scientific disciplines to ensure that information presented is
based on sound and credible science and considered technically adequate,
competently performed, properly documented, and in compliance with established
quality requirements. As a step beyond standard internal quality assurance and quality
control procedures, the U.S. Department of Energy (DOE) Office of Fossil Energy and
Carbon Management (FECM)/NETL are committed to rigorous peer review of key work
products to meet the quality standards of the research community. The following
individuals served on the peer review panel:
Richard Bohan, Portland Cement Association
Michael Matuszewski, AristoSys, LLC
Technical expert (anonymity requested)
Suggested Citation:
S. Hughes and A. Zoelle, "Cost of Capturing CO2 from Industrial Sources," National
Energy Technology Laboratory, Pittsburgh, July 15, 2022.
TABLE OF CONTENTS
List of Exhibits ................................................................................................................ vi
List of Equations ............................................................................................................. x
Acronyms and Abbreviations ...................................................................................... xi
Executive Summary ...................................................................................................... 1
1 Introduction ............................................................................................................ 9
1.1 Assumptions ...................................................................................................... 9
2 Plant Sites and CO2 End-Use ............................................................................... 11
3 Economic Analysis Overview .............................................................................. 20
3.1 Cost Estimating Methodology ...................................................................... 20
3.1.1 Capital Costs ........................................................................................... 21
3.1.2 Operation and Maintenance Costs ...................................................... 24
3.2 Capital Charge Factors ................................................................................ 25
3.3 Retrofit Factors ............................................................................................... 27
4 Equipment ............................................................................................................. 28
4.1 Compression................................................................................................... 28
4.1.1 Reciprocating Compressor .................................................................... 28
4.1.2 Centrifugal Compressor.......................................................................... 28
4.2 CO2 Capture and Purification ...................................................................... 29
4.2.1 Cansolv Post-Combustion Capture ....................................................... 30
4.2.2 ADIP-Ultra Pre-Combustion Capture ..................................................... 32
4.3 Industrial Boiler ................................................................................................ 33
4.4 Cooling Water Unit......................................................................................... 33
4.5 Heat Exchangers ............................................................................................ 34
4.6 Ancillary Equipment, Buildings, and Structures ........................................... 34
5 Cost and Performance: High Purity Sources ...................................................... 35
5.1 Ammonia ........................................................................................................ 35
5.1.1 Size Range................................................................................................ 35
5.1.2 CO2 Point Sources ................................................................................... 35
5.1.3 Design Input and Assumptions ............................................................... 36
5.1.4 CO2 Capture System............................................................................... 37
5.1.5 BFD, Stream Table, and Performance Summary .................................. 37
5.1.6 Capture Integration ................................................................................ 38
5.1.7 Power Source ........................................................................................... 38
5.1.8 Economic Analysis Results ...................................................................... 39
i
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
ii
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
iii
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
iv
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
v
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
LIST OF EXHIBITS
Exhibit ES-1. Industrial sources of CO2 case summary ............................................... 1
Exhibit ES-2. COC from industrial sources.................................................................... 3
Exhibit ES-3. Capture system BEC and amount of CO2 captured versus capture
rate ................................................................................................................................. 4
Exhibit ES-4. COC versus CO2 partial pressure and CO2 concentration ................. 5
Exhibit ES-5. U.S. industrial CO2 emissions by industry ................................................. 7
Exhibit ES-6. Representative plant COC results versus U.S. industrial CO2 emissions
........................................................................................................................................ 7
Exhibit 1-1. Process design assumptions .................................................................... 10
Exhibit 2-1. Existing CO2 pipelines and active EOR injection sites .......................... 12
Exhibit 2-2. Ammonia plant locations and existing CO2 pipelines and EOR
injection sites ............................................................................................................... 13
Exhibit 2-3. EO plant locations and existing CO2 pipelines and EOR injection sites
...................................................................................................................................... 14
Exhibit 2-4. Ethanol plant locations and existing CO2 pipelines and EOR injection
sites ............................................................................................................................... 15
Exhibit 2-5. NGP plant locations and existing CO2 pipelines and EOR injection
sites ............................................................................................................................... 16
Exhibit 2-6. Refinery hydrogen (U.S. refineries) plant locations and existing CO2
pipelines and EOR injection sites ............................................................................... 17
Exhibit 2-7. Cement plant locations and existing CO2 pipelines and EOR injection
sites ............................................................................................................................... 18
Exhibit 2-8. Steel (BOF) plant locations and existing CO2 pipelines and EOR
injection sites ............................................................................................................... 19
Exhibit 3-1. Capital cost levels and their elements .................................................. 22
Exhibit 3-2. Estimated amounts for owner’s costs .................................................... 23
Exhibit 3-3. Financial assumptions for high purity sources ....................................... 26
Exhibit 3-4. Financial assumptions for low purity sources ......................................... 26
Exhibit 4-1. Reciprocating compressor cases specifications .................................. 28
Exhibit 4-2. Integrally geared centrifugal compressor cases specifications ......... 29
Exhibit 4-3. Shell’s Cansolv CO2 capture typical process flow diagram ................ 30
Exhibit 4-4. ADIP-Ultra CO2 capture typical process flow diagram ........................ 32
Exhibit 5-1. Ammonia production via NG reforming ............................................... 36
Exhibit 5-2. Ammonia CO2 capture BFD ................................................................... 37
Exhibit 5-3. Ammonia stream table ........................................................................... 37
Exhibit 5-4. Performance summary ............................................................................ 38
Exhibit 5-5. Owner’s costs for ammonia greenfield site ........................................... 39
Exhibit 5-6. Capital costs for ammonia greenfield site ............................................ 40
Exhibit 5-7. Initial and annual O&M costs for ammonia greenfield site ................. 41
Exhibit 5-8. COC for 394,000 tonnes/year ammonia greenfield and retrofitA ....... 41
Exhibit 5-9. Ammonia plant capacity sensitivity ....................................................... 42
Exhibit 5-10. 2007 U.S. EO production facility capacities......................................... 43
vi
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
vii
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
viii
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-34. Initial and annual O&M costs for cement greenfield site with FGD
and SCR at 90 percent capture .............................................................................. 118
Exhibit 6-35. COC for 1.3 M tonnes/year cement greenfield cases (base cases
and FGD + SCR cases) ............................................................................................. 119
Exhibit 6-36. BOF iron and steel plant characteristics [52] .................................... 121
Exhibit 6-37. Braddock steel mill plot plan .............................................................. 121
Exhibit 6-38. CO2 capture BFD for COG/BFS ........................................................... 122
Exhibit 6-39. Iron/steel COG/BFS stream table with 99 percent capture ............ 123
Exhibit 6-40. Iron/steel COG/BFS stream table with 90 percent capture ............ 124
Exhibit 6-41. CO2 capture BFD for COG PPS ........................................................... 125
Exhibit 6-42. Iron/steel COG PPS stream table with 99 percent capture ............ 125
Exhibit 6-43. Iron/steel COG PPS stream table with 90 percent capture ............ 126
Exhibit 6-44. Performance summary for iron/steel COG/BFS section ................... 127
Exhibit 6-45. Performance summary for iron/steel COG PPS section ................... 127
Exhibit 6-46. Owners’ costs for iron/steel retrofit cases .......................................... 129
Exhibit 6-47. Capital costs for iron/steel COG/BFS section retrofit with 99 percent
capture ...................................................................................................................... 130
Exhibit 6-48. Capital costs for iron/steel COG PPS retrofit with 99 percent capture
.................................................................................................................................... 131
Exhibit 6-49. Capital costs for iron/steel COG/BFS section retrofit with 90 percent
capture ...................................................................................................................... 133
Exhibit 6-50. Capital costs for iron/steel COG PPS retrofit with 90 percent capture
.................................................................................................................................... 134
Exhibit 6-51. Initial and annual O&M costs for iron/steel site with 99 percent
capture ...................................................................................................................... 136
Exhibit 6-52. Initial and annual O&M costs for an iron/steel retrofit site with 90
percent capture ....................................................................................................... 137
Exhibit 6-53. COC for 2.54 M tonnes/year iron/steel retrofit cases ....................... 137
Exhibit 6-54. Iron/steel plant capacity sensitivity .................................................... 138
Exhibit 6-55. Iron/steel capture system BEC and amount of CO2 captured versus
capture rate .............................................................................................................. 139
Exhibit 7-1. COC summary ....................................................................................... 140
Exhibit 7-2. Cost and performance summary comparison – high purity cases .. 142
Exhibit 7-3. Cost and performance summary comparison – low purity cases .... 143
Exhibit 7-4. COC vs. CCF .......................................................................................... 144
Exhibit 7-5. COC vs. retrofit factor ........................................................................... 146
Exhibit 7-6. COC vs. purchased power price ......................................................... 147
Exhibit 7-7. COC vs. NG price .................................................................................. 148
Exhibit 7-8. COC vs. CF ............................................................................................. 149
Exhibit A-1. Ethanol case carbon balance ............................................................ 159
Exhibit A-2. Ammonia case carbon balance ........................................................ 159
Exhibit A-3. NGP case carbon balance.................................................................. 159
Exhibit A-4. EO case carbon balance .................................................................... 160
Exhibit A-5. CTL case carbon balance ................................................................... 160
ix
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
LIST OF EQUATIONS
Equation ES-1 ................................................................................................................. 2
Equation 1-1................................................................................................................... 9
Equation 5-1................................................................................................................. 43
Equation 5-2................................................................................................................. 52
x
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
xi
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
xii
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
EXECUTIVE SUMMARY
The objective of this report is to provide an estimate of the cost to capture carbon dioxide (CO2)
from selected industrial processes. The following nine processes were chosen for analysis due to
either the high purity of the CO2 emission source (99–100 mole percent CO2) or the large
quantity of CO2 potentially available. The processes considered in this study are summarized in
Exhibit ES-1, where “CO2 Available for Capture” represents the amount of pure CO2 in the
capture stream described in the table for each case, at a 100 percent capacity factor (CF).
Note: COG = coke oven gas; PPS = power plant stack; BFS = blast furnace stove
For each industrial process considered, available plant information, such as existing average
plant size, projected new development plant size, or existing plant operations data was used to
develop a reference plant for this study. Plant size is one factor affecting the amount of CO 2
available for capture from an industrial process. Other factors are specific to each industry. For
example, the ammonia industry captures and re-uses CO2 in urea production, and natural gas
processing (NGP) plant CO2 emissions are dependent upon the raw gas compositions entering
the facility. As such, specific assumptions related to CO2 availability are necessary to establish
each representative plant and to suggest the industry’s average CO2 emissions.
For each process, the CO2 capture cost for a greenfield facility and a retrofit facility was
calculated with the latter being calculated by applying a retrofit factor to the greenfield total
plant cost (TPC). For the iron/steel process, only a retrofit case is given since the representative
1
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
plant is a basic oxygen furnace facility, which are no longer being constructed. For the coal-to-
liquids (CTL) and gas-to-liquids (GTL) cases, no retrofit case is given, since no plants currently
exist domestically, and it is assumed that none will be constructed without CO2 capture. The
cost metric of interest is the cost of CO2 captured in U.S. dollars per tonne, as calculated in
Equation ES-1. In this report, costs are presented in December 2018 real dollars.
Where:
TOC – Total overnight costs of equipment added for the application of CO2 capture
CCF – Capital charge factor, based on industry-specific financial assumptions as detailed in
Section 3.2
FOM – Annual fixed operating & maintenance (O&M) costs
VOM – Annual variable O&M costs
PF – Purchased fuel
PP – Purchased power
The high purity emissions sources are inherently produced by their base plants at CO2
concentrations suitable for pipeline transport, requiring only compression, associated
intercooling, and, in some cases, glycol dehydration. The low purity sources considered offer
emission streams with CO2 concentrations below that which is acceptable for pipeline use, per
guidance in National Energy Technology Laboratory’s (NETL) “Quality Guidelines for Energy
System Studies (QGESS): CO2 Impurity Design Parameters” specifications. [1] As such, the
refinery hydrogen, cement, and iron/steel cases require CO2 removal systems along with
compression, associated intercooling, and glycol dehydration. For the CO2 removal systems, two
capture rates were evaluated, 90 and 99 percent, to evaluate the cost of capturing the CO2 from
the emissions streams defined in Exhibit ES-1.a
Exhibit ES-2 provides the resulting greenfield and retrofit cost of CO2 capture (COC), where
appropriate, for each case considered in this study, along with the capital, variable and fixed
O&M, purchased power and/or natural gas (NG) fuel cost components for each case. For each
case, other than those of iron/steel, the individual cost components shown (i.e., capital costs,
fixed O&M costs, variable O&M costs, and purchased power/natural gas) represent the cost
components that add to the total COC in greenfield applications. For iron/steel, those individual
cost components represent retrofit costs. In addition, each high purity source shows the total
retrofit COC, which is estimated based on methodology described in Section 3.3, except for the
CTL and GTL cases. As there are no existing CTL or GTL plants in the domestic industrial fleet, it
a This report does not consider capture of the CO2 produced by the natural gas-fired boiler used for steam generation in
the low purity cases (i.e., for solvent regeneration) or other process streams outside of those defined in Exhibit ES-1. If this
CO2 was captured, it would greatly impact the results presented herein. Such an analysis is discussed in the future work
considerations detailed in Section 9.
2
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
is assumed that future (i.e., greenfield) builds would include carbon capture (i.e., retrofit
capture applications at CTL or GTL facilities would not be expected). Further details regarding
the estimation of capital, operating, and maintenance costs are provided within the body of the
report.
Note: All values expressed in December 2018 U.S. dollars per tonne CO2.
The results show that CTL has the lowest greenfield COC, followed by GTL, NGP, ammonia,
ethylene oxide (EO), ethanol, refinery hydrogen, and finally, cement, which has the highest
greenfield COC. Retrofit applications exclude CTL and GTL, but follow the same cost pattern;
however, the highest retrofit COC is the iron/steel case.
For the low purity cases, the normalized COC ($/tonne CO2) decreases slightly with increasing
capture rate (i.e., from 90 to 99 percent capture). The cost of the capture system and associated
consumables increases at a lesser rate than that of the amount of CO2 captured (i.e., a 10
percent increase from 90 to 99 percent capture). This is the effect of accuracy ranges of the
capital cost estimates from the capture system vendor (-25/+40 percent) and the cost scaling
methodology employed in this study. [2] [3] The margin of error associated with the cost
estimate indicate that with increasing capture rate in the low purity cases, the COC is effectively
the same. The reported minor increase in capital cost with increased capture rate (up to 99
percent for sources with CO2 purity greater than 12 percent) based on vendor furnished cost
and performance estimates has been validated by independent modeling performed by the
carbon capture simulation initiative team at NETL and has been reported independently in
literature. [4] Exhibit ES-3 shows the error in the calculated capture system BEC associated with
the vendor’s quoted uncertainty rate alongside the amount of CO2 captured in the cement case
3
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
from 90 to 99 percent capture rate. Similar graphs in for the refinery hydrogen and iron/steel
cases can be found in Section 6.1.10 and Section 6.3.10, respectively.
Exhibit ES-3. Capture system BEC and amount of CO 2 captured versus capture rate
Exhibit ES-4 shows a plot of the COC versus the assumed CO2 stream partial pressure and the
assumed CO2 concentrations for each of the base cases considered in this report. The general
trend shows that as both the CO2 concentration and the CO2 partial pressure decrease, the COC
of CO2 increases. The average COC for the six processes with CO2 concentration greater than 95
percent is $17.5/tonne, while the average COC for the three processes with CO2 concentration
less than 50 percent is $62.0/tonne. The partial pressure in the high purity cases is mainly
reflective of the CO2 concentration.
4
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit ES-4. COC versus CO2 partial pressure and CO2 concentration
The trends observed in this study may not be universally applicable because the assumptions
made for each case in this study may not apply to all real-world examples of a specific industry.
Additionally, concentration trends are emphasized due to the potential misleading nature of
partial pressure values. In some instances, partial pressure can have directly recognizable effects
on the COC; higher pressures will reduce the size of and duty of compression equipment, but
this may not always be the case. For example, a stream with a total pressure of 1,000 psia, and a
concentration of 10 percent CO2, would have a partial pressure of 100 psia. For the cases in this
study, this partial pressure would be considered high, and might be expected to result in a low
COC. However, for this example, capture and/or purification would be required, and therefore
the resulting COC would not be expected to follow the partial pressure trend observed in Exhibit
ES-4.
There are also exceptions to these trends driven by economies of scale. Such a relationship is
demonstrated in Exhibit ES-4 when comparing the results of NGP and ammonia. The CO2 stream
partial pressures are equivalent, and the concentrations are also the same at 99 percent.
However, the greenfield COCs were calculated to be $16.1/tonne CO2 for NGP and $19.0/tonne
CO2 for ammonia, about an 18 percent difference. This is a result of the amount of CO2 available
for capture in each case. Based on the assumptions made for each representative plant, NGP
has 649,225 tonne/year CO2 available, while ammonia only has 486,227 tonne/year available.
Therefore, while the CO2 stream partial pressures and concentrations are equivalent, there is 33
percent more CO2 available for capture and sale at the NGP reference plant, resulting in a lower
normalized CO2 capture cost. The factors noted above in Exhibit ES-4, namely CO2 partial
pressure, concentration, and economies of scale (i.e., CO2 available at each representative
5
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
plant), result in a significant range of CO2 capture costs. The highest greenfield COC, the cement
case with 90 percent capture, is more than eleven times the price of the least expensive case
(i.e., CTL).
In addition, the assumptions regarding the quality of the CO2 emissions stream from the base
plant in each case may greatly impact the COC. For instance, the base cement case assumes that
the kiln off-gas is suitable to be sent directly for CO2 separation; however, cement industry
members suggest that the kiln off-gas may have higher-than-acceptable levels of oxides of sulfur
(SOx)/oxides of nitrogen (NOx) and would require the addition of selective catalytic reduction
(SCR) and flue gas desulfurization (FGD). A sensitivity to this case was performed to evaluate the
effect of adding these unit operations to the cement cases. The amount of SOx/NOx was not
directly characterized; instead, the FGD and SCR costs were scaled from Case B12B of Revision 4
of NETL’s “Cost and Performance Baseline for Fossil Energy Plants Volume 1: Bituminous Coal
and Natural Gas to Electricity” based on the quantity of gas to be treated (i.e., the total flow of
kiln off-gas). [5] Case B12B presents an SCR with a 78 percent NOx removal efficiency and an
FGD that removes 2,000 ppm, by volume, of SOx from the coal boiler flue gas stream. The
results of this sensitivity analysis show that the addition of a similar SCR and FGD to the cement
plant’s CO2 capture system would increase greenfield COC by 23–25 percent with a COC of
$74.8/tonne CO2 and $78.0/tonne CO2 for 99 and 90 percent capture, respectively.
While the calculation of a COC demonstrates the capture costs across different industries based
on a specific set of plant assumptions, another important consideration is the amount of CO2
available from each industry. Neglecting CO2 transportation costs, if two industries demonstrate
approximately equivalent normalized COCs, but one has a significantly larger supply, the
industry with the larger supply would offer the more effective decarbonizationb application at
the same or similar normalized cost. Exhibit ES-5 shows the CO2 emissions by industry in the
United States, while Exhibit ES-6 presents a plot of COC versus the amount of domestic CO2
emissions, both based on the Environmental Protection Agency Facility Level Information on
Greenhouse Gases Tool as of the 2020 reporting year.c [6] The COCs are those calculated in this
study for greenfield sites except for iron/steel, which is for a retrofit application. This plot shows
the cost of the source relative to the potentially capturable emissions in the United States.
b Decarbonization within the context of this report is defined as the reduction of point-source emissions from industrial
processes. Lifecycle analysis of decarbonization efforts as it relates to the CO2 capture operations evaluated in this
report is not considered but could be considered in future work opportunities.
c CO2 emissions related to EO production are not reported in Environmental Protection Agency’s Facility Level
Information on Greenhouse Gases Tool; as such, the total emissions were estimated based on the total EO production as
of 2019 [53] and an emissions factor of 1:3 CO2:EO on a molar basis, according to reaction stoichiometry as detailed in
Section 5.2.
6
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit ES-6. Representative plant COC results versus U.S. industrial CO2 emissions
Note: Only the 99 percent capture cases are shown for low purity sources in Exhibit ES-6.
Based on emissions rates, of the industrial plants with existing operations (i.e., excluding CTL
and GTL), EO is the least impactful decarbonization option given the small amount of CO2
available for capture (0.95 M tonnes/year), and cement manufacturing is the most impactful
option with the largest amount of CO2 available (66 M tonnes/year). Based on normalized COC,
NGP is the least expensive industrial source of CO2 within the existing U.S. fleet with a price of
$16.1/tonne, and iron/steel is the most expensive option with a price of $64.8/tonne.
7
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Sensitivities to CF, cost of purchased power, plant size in terms of CO2 emissions per year, and
capital charge factor (CCF) were analyzed for each greenfield case. A sensitivity to natural gas
price was also performed for the greenfield low purity cases. In these cases, natural gas is
burned in an industrial boiler, described in Section 4.3, to generate steam for solvent
regeneration in the CO2 capture process. Lastly, a sensitivity to the retrofit factor applied to
generate retrofit application costs was evaluated for each case, excluding CTL and GTL, which do
not have retrofit applications. The plant size sensitivity results for each case, evaluated across
the typical plant size ranges specific to each industry, can be found in the corresponding
sections, and all other sensitivity analyses can be found in Section 7.2.
The general results of the sensitivities evaluated are as follows:
• As CF varies from 65 to 95 percent, the COC for each case decreases, most notably in the
Refinery H2 90 percent capture case where a $18.0/tonne CO2 decrease is observed
across the sensitivity range. An 85 percent CF was assumed for the cases in this study.
• As purchased power price increases, the COC also increases. This study assumes that all
electricity requirements are provided by purchasing power from the grid. In cases
requiring additional power beyond just compression, such as power for auxiliary loads in
the CO2 separation processes, the COC increase is more dramatic. The largest increase
across the sensitivity range was observed in the iron/steel and cement cases at
$16.4/tonne.
• The sensitivity to CCF is important as different industries may have access to different
costs of capital. The CCF for each case was developed by NETL’s Energy Markets Analysis
Team based on market financial data respective to each industrial sector. Details of the
financial factors used in this study are given in Section 3.2. As CCF varies from 5 percent
to 35 percent, the capture costs can increase by up to $150.2/tonne as observed in the
refinery hydrogen case with 90 percent capture.
• The final sensitivity to natural gas price showed that as the natural gas price varied over
the range $3–10/MMBtu, the COC may rise as much as $30.6/tonne CO2 as was
observed in the iron/steel 90 percent capture case.d
This study uses the COC and CO2 supply to compare nine potential industrial CO2 sources. The
results are representative of the assumptions regarding the reference plant and its CO2
emissions stream(s). Scale and location will impact results for actual plants. Methods of CO2
transport and storage (T&S) and the associated costs are considerations that could ultimately
change the economic impact of implementing carbon capture at a specific plant. T&S costs were
not considered in this study; however, Section 2 examines the location of individual plants in
each industry relative to CO2 pipelines and current EOR sites to qualitatively identify relative
advantages or disadvantages for decarbonization in each industry, as it relates to T&S. To
estimate T&S costs, users may refer to NETL’s “Quality Guidelines for Energy System Studies
(QGESS): Carbon Dioxide Transport and Storage Costs in NETL Studies” for guidance. [7]
d This report does not consider capture of the CO2 produced by the NG-fired boiler. If this CO2 was captured, it would
impact the results presented herein greatly, due to the lower concentration of CO2 in the flue gas stream compared to
that of the low purity industrial sources considered. It would also increase the amount of CO 2 available for capture, as
NG consumption increases. Such an analysis is discussed in the future work considerations detailed in Section 9.
8
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
1 INTRODUCTION
With a global initiative to reduce greenhouse gas (GHG) emissions, several common industrial
processes have been identified as potential opportunities for carbon dioxide (CO2) capture. Of
the 9 processes considered in this report, 7 have existing operations in the United States,
contributing just under 270 M tonnes per year of CO2 emissions in 2020 based on reporting to
the Environmental Protection Agency. [6] Industrial plant CO2 emissions sources offer
advantages when considering decarbonization due to their relatively high concentrations of CO2
in emissions streams, which may lead to lower normalized capture costs. With high CO2
concentrations, separation equipment costs are minimized, or even eliminated in cases where
CO2 streams are 99–100 percent pure. This study evaluates nine representative plants with CO2
emissions sources having relatively high concentrations to determine the cost of CO2 capture.
The cost of CO2 capture (COC) in each case, as defined by Equation 1-1, considers the
equipment required for CO2 removal, if applicable, and compression, as well as the balance of
plant equipment as detailed in Section 4.3 through Section 4.6, and operation and maintenance
(O&M), purchased power, and fuel costs, as applicable. Throughout the report, “CO 2 capture”
refers to the incremental equipment required to prepare the CO2 emissions stream for pipeline
transport (i.e., compression and intercooling, auxiliary equipment, CO2 removal systems, etc.).
Where:
TOC – Total overnight costs of equipment added for the application of CO2 capture
CCF – Capital charge factor, based on industry-specific financial assumptions as detailed in
Section 3.2
FOM – Annual fixed O&M costs
VOM – Annual variable O&M costs
PF – Purchased fuel
PP – Purchased power
Estimates of financing scenarios specific to each industry were applied to the capital
costs to account for return on equity and financing costs. Financial methodology and
the resulting financial factors for each case are presented in Section 3.
1.1 ASSUMPTIONS
There are many industrial processes that produce CO2 emissions, and as such, criteria were
established to justify the inclusion of an industrial process in this report. First, an industrial plant
must be representative of either a relatively large amount of CO2 emissions (i.e., an emissions
source that could benefit from economies of scale) or of a 99–100 percent pure CO2 stream. The
9
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
second criterion for inclusion is that an industrial plant is likely to provide a relatively low
normalized COC. This condition is highly dependent upon the first criteria, as normalized COC
values are a function of CO2 availability. Power production plants are not considered in this
study, as they are evaluated in NETL’s collection of baseline studies, such as “Cost and
Performance Baseline for Fossil Energy Plants Volume 1: Bituminous Coal and Natural Gas to
Electricity.” [5] Process models were developed for each case based on guidance in NETL’s
“Quality Guidelines for Energy Systems Studies (QGESS): Process Modeling Design Parameters,”
and applicable model assumptions are shown in Exhibit 1-1. [8]
10
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
11
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 2-1. Existing CO2 pipelines and active EOR injection sites
A large percentage of ammonia plants are in close proximity to existing CO2 pipelines and EOR
injection sites, as shown in Exhibit 2-2. The bars on the chart represent gross (light blue) and net
(dark blue) ammonia production at each plant. As noted in Section 5.1.2, the representative
ammonia production in the United States was considered at gross capacity, but in some
ammonia plants, portions of gross ammonia and CO2 produced are further utilized to make
ammonia derivatives, such as ammonium nitrate or urea. Alternate use of CO2 in ammonia
plants is outside the scope of this study, but net capacities are shown alongside gross capacities
in Exhibit 2-2 for reference or future use.
12
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 2-2. Ammonia plant locations and existing CO2 pipelines and EOR injection sites
Exhibit 2-3 shows the location of EO plants and their relation to existing CO2 pipelines and EOR
injection sites. U.S. EO production is concentrated in Texas and Louisiana. Of the 15 U.S. EO
plants, 6 are located very close to existing EOR pipelines and injection sites. Therefore, from a
location standpoint, EO presents a potentially advantageous option for capture integration.
However, due to the small scale of the existing EO plants (i.e., the small amount of CO2 available
for capture), diseconomies of scale may deter implementation.
13
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 2-3. EO plant locations and existing CO2 pipelines and EOR injection sites
As shown in Exhibit 2-4, a large percentage of ethanol plant locations are not near existing CO2
pipelines or EOR injection site locations; however, most of the ethanol processing facilities are
grouped in the Midwest and could potentially realize economies of scale collectively to justify
the addition of a new CO2 pipeline for connection to existing infrastructure. This scenario falls
outside the scope of this study but could be considered in future work.
14
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 2-4. Ethanol plant locations and existing CO2 pipelines and EOR injection sites
Exhibit 2-5 shows the location of natural gas processing (NGP) facilities and their relations to
existing CO2 pipelines and EOR injection sites. Plant capacities are shown on this map; however,
given the 471 NGP facilities, each treating a different amount of natural gas (NG) with widely
varying CO2 concentrations, there may not be a direct correlation between capacity and CO2
available. This means that a large facility processing NG with low CO2 concentration may have
less CO2 available than a smaller facility processing NG with a much higher CO2 concentration.
15
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 2-5. NGP plant locations and existing CO2 pipelines and EOR injection sites
Exhibit 2-6 shows the location of U.S. refineries that produce hydrogen, and their proximity to
existing CO2 pipelines and EOR injection sites. There are many refineries near existing EOR
pipelines and injection sites. However, the map is only intended to show the relative crude
throughput capacity of the refineries, and not the amount of CO2 available. There is not
necessarily a direct relationship between refinery capacity and CO2 available for capture.
16
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 2-6. Refinery hydrogen (U.S. refineries) plant locations and existing CO 2 pipelines and EOR injection sites
Exhibit 2-7 shows the location of cement plants and their relation to existing CO2 pipelines and
EOR injection sites. Some cement plants are located relatively close to existing infrastructure
and given the typically larger scale of cement production capacity, and consequently larger
amount of CO2 emissions available, construction of a connecting pipeline for other cement
facilities may be a viable means of decarbonization in the cement industry. This is scenario is
not evaluated within the context of this study.
17
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 2-7. Cement plant locations and existing CO2 pipelines and EOR injection sites
Exhibit 2-8 shows currently operating steel basic oxygen furnace (BOF) plants and their relation
to existing CO2 pipelines and EOR injection sites. Steel does not appear to provide ease of
implementation for EOR end-use because many facilities would not be able to utilize any of the
existing EOR infrastructure. However, based on this study’s assumptions, steel plants represent
the largest amount of CO2 available among the industries considered that are currently
operating plants in the United States; therefore, construction of connecting pipelines may be a
viable means of decarbonization in the steel industry. This scenario is not evaluated in the
context of this study.
18
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 2-8. Steel (BOF) plant locations and existing CO2 pipelines and EOR injection sites
19
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
20
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
environmental concerns, weather delays) that may make construction more costly. Such
variations are not captured by the reported cost uncertainty.
21
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
process equipment
Bare Erected Cost
supporting facilities Engineering, Procurement
BEC
direct and indirect EPCC and Construction Cost
labor Total Plant Cost
TPC Total Overnight Cost
EPC contractor services Total As-Spent Cost
process contingency
TOC
project contingency
TASC
pre-production costs
inventory capital BEC, EPCC, TPC and TOC are
financing costs all “overnight” costs
expressed in base-year dollars.
other owner’s costs
TASC is expressed in mixed-
escalation during capital expenditure period year current dollars, spread
over the capital expenditure
interest on debt during capital expenditure period period.
e This would not be the case had a facility, area, or commodity account structure been chosen instead.
22
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
23
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
24
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
2.3 additional operators were considered for low purity cases, which is the difference in
operating labor required for a supercritical pulverized coal power plant with and without
capture, per NETL’s “Cost and Performance Baseline for Fossil Energy Plants Volume 1:
Bituminous Coal and Natural Gas to Electricity” results. [5] The average base labor rate used to
determine annual cost is $38.50/hour. The associated labor burden is estimated at 30 percent of
the base labor rate.
3.1.2.4 Consumables
The cost of consumables, including fuel, was determined based on individual rates of
consumption, the unit cost of each specific consumable commodity, and the plant annual
operating hours.
Quantities for major consumables such as NG for fuel and purchased power were taken from
technology-specific energy and mass balance diagrams developed for each plant application.
Fuel cost is $4.42/MMBtu, and power is purchased at a cost of $60/MWh. Sensitivity analyses
relating COC to purchased power price and NG price are detailed in Section 7.2.3 and Section
respectively. Other consumables were evaluated based on the quantity required using reference
data.
The quantities for initial fills and daily consumables were calculated on a 100 percent operating
capacity basis. The annual cost for the daily consumables was then adjusted to incorporate the
annual plant operating basis, or capacity factor (CF). An 85 percent CF was assumed for all
cases. Initial fills of the consumables, fuels, and chemicals may be accounted for directly in the
O&M tables or included with the equipment pricing in the capital cost.
25
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Refinery
Financial Parameter Cement Iron/Steel
Hydrogen
Fixed Charge Rate 4.39% 5.08% 6.90%
TASC/TOC Ratio 1.036 1.054 1.091
Capital Charge Factor 4.55% 5.35% 7.53%
Debt/Equity Ratio 33/67 42/58 39/61
Payback Period 30 years
Interest on Debt 5.15%
Levered Return on Equity (Asset Weighted) 0.41% 1.42% 5.02%
Capital Expenditure Period 3 years
Capital Distribution 1st year – 10%; 2nd year – 60%; 3rd year – 30 %
The result of the economic analysis is a calculated COC of CO2, which represents the cost to the
owner, per tonne of CO2 captured. This cost includes the capital expenditures, escalated at the
assumed nominal general inflation rate of two percent per year, providing the stipulated rate of
return on equity over the entire economic analysis period. Assuming all annual costs also
escalate at the same inflation rate, the COC is essentially the sum of the O&M costs and the
annualized capital cost charges, all normalized to the annual plant CO2 flow rate.
For a CO2 source with a higher flow rate (same CO2 purity and pressure), a corresponding
increase in the flow rate of the captured CO2, requirement for consumables, size of capture
equipment, etc., occurs; however, the COC is expected to be roughly equivalent or, in some
cases, lower due to the economies of scale associated with the cost of the larger
equipment. This is especially apparent when comparing the costs of each low purity case at two
26
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
different capture rates (e.g., cement at 90 percent and 99 percent capture). Ultimately, the CCF,
which is the product of the fixed charge rate and the TASC/TOC ratio, applied in each case can
have a dramatic effect on the COC calculated. A sensitivity analysis evaluating this relationship is
presented in Section 7.2.1.
The areas where these retrofit factors would be more directly applicable are the ‘Ductwork &
Stack’ accounts, which can have a retrofit factor as high as 1.6. The BEC of the ‘Ductwork &
Stack’ account in the cement case with 99 percent capture, for example, is $15,274,000.
Application of a 1.6 retrofit factor would add an additional $9,164,400 for the ‘Ductwork &
Stack’ line item. With the cement plant case having a greenfield TOC of $424,897,000
application of this 1.6 retrofit factor would represent a 2.2 percent increase in the TOC for
‘Ductwork & Stack’ alone.
Engineering judgment was used to determine a more generic factor to be applied to the cases in
this report, in lieu of those presented in the Retrofit Study. As an alternative, for high purity
cases a retrofit factor of 1.01 was applied to the TPC as a blanket retrofit cost increase, and a
retrofit factor of 1.05 was applied to the TPC of low purity cases. Without a formalized
procedure for applying the retrofit factors, it is best to consider the retrofit factor as a single
capital cost sensitivity, from which the true cost of a retrofit (which has overriding project and
site-specific considerations) can be refined as more information is available for a specific design
case. A sensitivity analysis examining the effect on COC related to the retrofit factor applied is
discussed in Section 7.2.2.
27
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
4 EQUIPMENT
4.1 COMPRESSION
Two different types of compressors are used for the cases in this study, an integrally geared
centrifugal compressor and a reciprocating compressor. The type of compressor selected for
each case is chosen based on the mass flow of CO2 to the first compression stage as well as the
suction conditions at stage one.
28
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
obtained for application in the refinery hydrogen cases. The quote data is proprietary; thus, details are not included within this
report.
D A second inlet to compression was considered as part of the compressor design (proprietary) for refinery hydrogen cases due
As mentioned, all compressors discharge at a pressure of 2,214.7 psia (2,200 psig). This is the
pipeline pressure specification assumed in this study, which is given in the QGESS for CO 2 for use
in EOR applications. [1] However, it should be noted that EOR field pressure requirements can
vary from location to location, and pressures as low as 1,200 psig could be acceptable. [14]
fMuch of the text and descriptions within this section were sourced, with permission, from data provided by Shell to NETL, unless otherwise
noted. The information relates to a CO2 removal system designed by Shell.
29
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
The performance and cost information for the AGR units employed in this study are based on
data provided by Shell in 2021. The quote provided specific cost and performance metrics at
individual capture rates (i.e., 90, 95, and 99 percent) for each representative industrial plant.
The unit cost is scaled based on CO2 product mass flow (60 percent) and inlet flow to the
adsorber (40 percent), per specifications in “QGESS Capital Cost Scaling Methodology: Revision
4 Report.” [3] Cases where an AGR is used include refinery hydrogen, iron/steel, and cement.
The CO2 removal efficiency of the AGR unit is represented at two rates, 90 percent and 99
percent, for each case. For the purposes of this study, performance and cost data for the AGR
units was obtained from Shell for the specific flue gas streams representative of the low purity
industrial sources, not scaled or applied from quotes provided for power-related capture
systems.
Exhibit 4-3. Shell’s Cansolv CO2 capture typical process flow diagram
CO2
CONDENSER
SOLVENT
TREATED GAS RECLAIMING
TO STACK REFLUX
ACCUMULATOR
WASH WATER
RICH AMINE
LEAN AMINE LEAN/RICH EXCHANGER
REFLUX PUMP
ABSORBER STRIPPER
REBOILER
INTERCOOLER
LEAN AMINE
INDUSTRIAL RICH AMINE
FEED GAS WATER VAPOR RECYCLE
4.2.1.1 Pre-scrubber
The CO2-laden gas from the industrial source (cement or iron/steel plant) is sent through a
booster fan to drive the gas through downstream equipment starting with the pre-scrubber
inlet cooling section. The cooler is operated as a direct contact cooler that saturates and sub-
cools the feed gas stream. Saturation and sub-cooling are beneficial to the system as they
improve the amine absorption capacity, thus reducing amine circulation rate. In cement or steel
30
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
applications, in or after the cooling section the feed gas is also scrubbed with caustic to capture
residual acid compounds (SO2, hydrogen chloride, etc.).
31
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
compressor at approximately 0.2 MPa (29 psia), and the remaining water is collected and
returned to the stripper as reflux.
The flow of steam to the regenerator reboiler is proportional to the rich amine flow to the
stripper; however, the flow of low-pressure steam is also dependent on the stripper top
temperature.
LOW-PRESSURE CO2
TREATED GAS
CONDENSER
TO PSA
MID-PRESSURE CO2
TREATED GAS
KNOCKOUT
RICH AMINE
REFLUX
LEAN
FLASH VESSEL ACCUMULATOR
AMINE
INTERCOOLER
COOLER
LEAN/RICH EXCHANGER
REFLUX PUMP
ABSORBER
COOLING REGENERATOR
WATER
REBOILER
32
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Treated gas exits through the top of the absorber and is sent through a second knockout vessel
to remove entrained amine droplets using a mist pad before being routed to the pressure-swing
adsorption unit for the production of high purity hydrogen. A rich solvent stream exits through
the sump of the absorber and is routed towards the amine regeneration section.
33
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Power consumption estimates for the cooling water system (i.e., circulating water pumps and
cooling tower fans) were calculated based on methodology consistent with that of BBR4 cases.
Cost estimates for the cooling water system were scaled from Case B11A-BR of NETL’s
“Eliminating the Derate of Carbon Capture Retrofits” (Derate Study) based on QGESS guidance
for capital cost scaling. [17] [3] This account was scaled from the Derate Study because Case
B11A-BR is more representative of the size range for the cooling water system associated with
the cases in this report.
34
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
5.1 AMMONIA
It is estimated that the U.S. gross ammonia production in 2019 was over 19.2 M tonnes. [19] In
all but one plant in the United States, the ammonia production process first reforms a NG
feedstock to produce hydrogen (H2), carbon monoxide (CO), and CO2. The unconverted CO from
reforming is then shifted to produce more H2 and CO2. The optimum ratio of H:N for ammonia
synthesis is 3:1; therefore, the amount of CO2 removed from the post-shift stream must be high
to optimize the H:N ratio. A portion of the CO2 removed from the post-shift stream is often
captured and reused to produce urea, by reacting ammonia with CO2. The amount of CO2
captured and reused for ammonia derivatives will vary from plant to plant based on production
capacities and market opportunities for each product. With CO2 removal inherent to the
ammonia process, coupled with the need for CO2 to convert ammonia into ammonia
derivatives, ammonia processing is a potentially low-cost option for industrial CO2 capture.
An article published by KBR Technology [22] concerning CO2 capture in the ammonia industry
stated that for an average ammonia plant producing 660,000 tonnes/year ammonia,
approximately 34 percent of CO2 emissions come from the primary reformer flue gas and 66
percent are emitted by the CO2 stripper vent. The total CO2 produced in ammonia production
(i.e., that of both the primary reformer and the CO2 stripper) is 1.87 tonnes CO2/tonne
ammonia. [22] Applying this emissions factor and the fact that 66 percent of the CO2 emissions
would be captured from the stripper vent as a high purity source, the representative 394,000
tonnes ammonia/year plant produces 486,227 tonnes CO2 vented from the CO2 stripper. It is
assumed that the stripper vent CO2 concentration is 99 percent by volume. [23] The ammonia
35
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
production process, using NG as a feedstock, is depicted in a basic BFD (Exhibit 5-1) to further
illustrate the point-sources of CO2 described in this section.
Synthesis Gas
Natural Gas Primary Secondary Shift & CO2
for Ammonia
& Steam Reformer Reformer removal
Production
In some ammonia production facilities, portions of the ammonia and the CO2 emissions are
further processed to create ammonia derivatives. For this study, it is assumed that the ammonia
produced by the representative plant is not used for derivative production, and as such, the CO 2
emitted is not needed for reprocessing within the plant. In practical applications, the amount of
CO2 available would be affected by derivative manufacturing, as well as by process
configurations and operating parameters affecting the ratio of CO2 emitted from the stripper
and the primary reformer. This would have to be evaluated on a case-by-case basis, and the
assumptions in this study are employed to present an illustrative COC in a representative
ammonia production plant.
36
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
1 2 3
V-L Mole Fraction
Ar 0.0000 0.0000 0.0000
CH4 0.0000 0.0000 0.0000
CO 0.0000 0.0000 0.0000
CO2 0.9709 0.9887 0.9995
SO2 0.0000 0.0000 0.0000
H2 0.0000 0.0000 0.0000
H2O 0.0291 0.0113 0.0005
H2S 0.0000 0.0000 0.0000
N2 0.0000 0.0000 0.0000
Total 1.0000 1.0000 1.0000
37
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
1 2 3
A
Steam Table Enthalpy (kJ/kg) 8,841 8,791 8,755
Aspen Plus Enthalpy (kJ/kg)B -9,021 -8,968 -9,195
Density (kg/m3) 3.0 2.9 630.1
V-L Molecular Weight 43.3 43.7 44.0
The performance results are based on the reciprocating compressor quote and are provided in
Exhibit 5-4.
Performance Summary
Item 394,000 tonnes ammonia/year (kWe)
CO2 Compressor 5,770
Circulating Water Pumps 60
Cooling Tower Fans 30
Total Auxiliary Load 5,860
38
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
by the compression train and the cooling water system. Purchased power cost is estimated at a
rate of $60/MWh as discussed in Section 3.1.2.4.
39
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
40
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
The initial and annual O&M costs for a greenfield site were calculated and are shown in Exhibit
5-7 while Exhibit 5-8 shows the COC for greenfield and retrofit sites for the representative
ammonia plant.
Exhibit 5-7. Initial and annual O&M costs for ammonia greenfield site
Case: Ammonia Cost Base: Dec 2018
O&M Labor
Operating Labor Operating Labor Requirements per Shift
Operating Labor Rate (base): 38.50 $/hour Skilled Operator: 0.0
Operating Labor Burden: 30.00 % of base Operator: 1.0
Labor O-H Charge Rate: 25.00 % of labor Foreman: 0.0
Lab Techs, etc.: 0.0
Total: 1.0
Fixed Operating Costs
Annual Cost
($) ($/tonnes/yr CO2)
Annual Operating Labor: $438,438 $0.90
Maintenance Labor: $239,021 $0.49
Administrative & Support Labor: $169,365 $0.35
Property Taxes and Insurance: $746,941 $1.54
Total: $1,593,765 $3.28
Variable Operating Costs
($) ($/tonnes/yr CO2)
Maintenance Material: $358,532 $0.87
Consumables
Initial Fill Per Day Per Unit Initial Fill
Water (/1000 gallons): 0 46 $1.90 $0 $27,119 $0.07
Makeup and Waste Water Treatment 0 0.1 $550.00 $0 $24,747 $0.06
Chemicals (ton):
Triethylene Glycol (gal): w/equip. 312 $6.80 $0 $658,287 $1.59
Subtotal: $0 $710,152 $1.72
Waste Disposal
Triethylene Glycol (gal): 312 $0.35 $0 $33,882 $0.08
Subtotal: $0 $33,882 $0.08
Variable Operating Costs Total: $0 $1,102,566 $2.67
Exhibit 5-8. COC for 394,000 tonnes/year ammonia greenfield and retrofitA
41
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Note: The data point for the COC at a 394,000 tonnes/year ammonia plant does not fall on the COC line due to data point
increments and plot formatting.
gFor instance, the TASC for the retrofit ammonia case is $47.5 million, which is higher in comparison to the TASC for the
greenfield ammonia case (i.e., $47.2 million) as presented in Exhibit 5-5.
42
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
It should be noted that for existing U.S. ammonia plants producing excess high purity CO 2, this
CO2 may already be processed and sold for other uses. For example, in addition to urea and
other ammonia derivative production, some ammonia plants also produce food-grade liquid
CO2 as a sellable product. This would reduce or eliminate the amount of high purity CO2
potentially available for capture as evaluated in this study. This scenario was not considered in
this study as it would need to be evaluated on a case-by-case basis.
43
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
The U.S. contains 10 major producers totaling an EO production of 3.6 M tonnes. The average
2007 U.S. plant capacity is 364,500 tonnes EO, which is representative of the majority of EO
plants and, thus, is the production capacity basis for the EO case in this study. With a 6:2 ratio of
EO:CO2, a plant with a 3.6 M tonnes annual EO production capacity would produce 121,500
tonnes CO2/year at 100 percent CF. The International Energy Agency Greenhouse Gas R&D
Programme (IEAGHG) database gives an average annual emission for the 52 worldwide EO
production sites of 150,000 tonnes CO2 per plant [24], which is within range of the assumed
emissions rate for the representative EO plant evaluated.
44
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
of the compression train. The cost was adjusted to account for the removal of the first stage by
scaling on power requirement, resulting in a 21.4 percent reduction in cost, as compared to the
quoted value.
Desired
EO Plant 1 Compressor 2
Usage
1 2
V-L Mole Fraction
AR 0.0000 0.0000
CH4 0.0000 0.0000
CO 0.0000 0.0000
CO2 1.0000 1.0000
SO2 0.0000 0.0000
H2 0.0000 0.0000
H2O 0.0000 0.0000
H2S 0.0000 0.0000
N2 0.0000 0.0000
Total 1.0000 1.0000
45
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
1 2
V-L Mole Fraction
V-L Flowrate (lb/hr) 30,578 30,578
Temperature (°F) 96 86
Pressure (psia) 43.5 2,214.7
Steam Table Enthalpy (Btu/lb)A 3,765 3,763
Aspen Plus Enthalpy (Btu/lb)B -3,841 -3,952
3
Density (lb/ft ) 0.325 39.3
ASteam table reference conditions are 32.02°F & 0.089 psia
BAspen thermodynamic reference state is the component’s constituent elements in an ideal gas state at 25°C and 1 atm
Performance Summary
Item 364,500 tonnes/year (kWe)
CO2 Compressor 1,180
Circulating Water Pumps 10
Cooling Tower Fans 10
Total Auxiliary Load 1,200
46
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
estimated at a rate of $60/MWh as discussed in Section 3.1.2.4. Given that the EO reaction is
exothermic, and this additional heat is possibly used to generate steam, an EO plant may
already generate power on-site for other usage, and this power may be available as an
alternative to purchasing power from the grid. The availability of on-site power would need to
be evaluated on a case-by-case basis and is not considered within the scope of this report.
47
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
48
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
The initial and annual O&M costs for a greenfield site were calculated and are shown in Exhibit
5-16, while Exhibit 5-17 shows the COC for greenfield and retrofit sites for the representative EO
plant.
Exhibit 5-16. Initial and annual O&M costs for EO greenfield site
Case: Ethylene Oxide Cost Base: Dec 2018
49
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
50
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
5.3 ETHANOL
Ethanol production generates as a byproduct a high purity CO2 stream greater than 85 percent
by volume. [29] Though not a large-scale CO2 producer, the COC is assumed to be relatively low.
One project where CO2 is being captured from ethanol refining is the DOE-funded Archer
Daniel’s Midlands project in Decatur, IL. The purpose of the project is to demonstrate how the
next generation of technologies capture and store or reuse industrial CO2 emissions. [30] The
project design states a goal to capture approximately 1 M tons of CO2/year using dehydration
and compression and store the captured CO2 in the Mt. Simon Sandstone Formation saline
reservoir. [30]
Since a large portion of existing ethanol plants, 66 have smaller production capacities of 40–60
M gallons/year, the plant size chosen was 50 M gallons/year, and utilized reciprocating
compression. It was also assumed that the plant uses the dry mill process with corn as the
feedstock of choice.
51
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
fermentation off-gas stream is considered high purity and is the basis for the ethanol case in this
report. The fuel burning stream may be considered as future work, as detailed in Section 9.1.
A study by the Illinois State Geological Survey [33] investigated the inventory of stationary CO2
emissions in the Illinois Basin in 2007. The study reviewed a wide range of industrial processes,
including ethanol plants. They used the relationship given in Equation 5-2 to calculate the
amount of CO2 emissions from the fermentation point source.
𝑔𝑎𝑙 𝑙𝑏𝐶𝑂2
[𝑒𝑡ℎ𝑎𝑛𝑜𝑙 𝑝𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 ( ) ( )]
𝑡𝑜𝑛𝑛𝑒 𝑦𝑒𝑎𝑟 ∗ 𝐸𝐹 𝑔𝑎𝑙 Equation
𝐶𝑂2 𝐹𝑒𝑟𝑚𝑒𝑛𝑡𝑎𝑡𝑖𝑜𝑛 ( )= 5-2
𝑦𝑒𝑎𝑟 𝑙𝑏 𝑡𝑜𝑛
2,000 𝑡𝑜𝑛 ∗ 1.01231 𝑡𝑜𝑛𝑛𝑒
Where
𝐸𝐹 = emission factor, feedstock dependent
The generic plant assumed in the Illinois Stage Geological Survey study utilizes corn as the
feedstock, giving an EF equal to 6.31 lb CO2/gallons ethanol. The EF was formulated in the
Illinois Stage Geological Survey study through communication with representatives from existing
ethanol plants in the Illinois Basin. [33] Using this relationship, the representative ethanol plant
will generate approximately 143,042 tonnes CO2/year from fermentation (at 100 percent CF),
with a production capacity of 50 M gallons of ethanol/year.
A report published by the Global Carbon Capture and Sequestration (CCS) Institute in 2010
states that “the emission in ethanol plants arise from fermentation of biomass such as sugar
cane or corn. Fermentation results in a pure stream of CO2, which significantly reduces the cost
for applying CCS.” [34] The fermentation process occurs at a temperature of 140–180 °C (284–
356 °F). [35] Therefore, the fermentation stream is assumed to be 100 percent CO2 and may be
sent directly for cooling and compression. Other sources [30] have referenced the presence of
water in the fermentation CO2 stream. This is a possibility; however, water knockout drums
would be present in the CO2 compression train and, thus, further purification before processing
would be unnecessary.
52
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
• The end product CO2 quality is based on the EOR pipeline standard as mentioned in the
NETL QGESS for CO2 Impurity Design Parameters [1]
53
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
The trend for the ethanol industry is smaller plants, which in turn produce smaller CO 2 streams
and require compression equipment capable of handling smaller flows. This requirement is
satisfied by using reciprocating compression discussed in Section 4.1.1; however, an alternative
to smaller equipment could be to combine the emissions streams from multiple nearby plants
for a single, larger compressor to compress the aggregate CO2 for EOR use. Such a scenario is
not considered in the scope of this study but could be evaluated in future work as described in
Section 9.2.
Ethanol Desired
1 HX 2 Compressor 3
Plant Usage
1 2 3
V-L Mole Fraction
AR 0.0000 0.0000 0.0000
CH4 0.0000 0.0000 0.0000
CO 0.0000 0.0000 0.0000
CO2 1.0000 1.0000 1.0000
SO2 0.0000 0.0000 0.0000
H2 0.0000 0.0000 0.0000
H2O 0.0000 0.0000 0.0000
H2S 0.0000 0.0000 0.0000
N2 0.0000 0.0000 0.0000
Total 1.0000 1.0000 1.0000
54
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
1 2 3
V-L Mole Fraction
Density (kg/m3) 1.5 2.0 629
The performance results are based on compressor quotes discussed in Section 4.1.1 and scaled
auxiliary loads for the cooling water system as discussed in Section 4.4. The performance
summary is provided in Exhibit 5-23.
Performance Summary
Item 50 M Gal Ethanol/year (kWe)
CO2 Compressor 1,810
Circulating Water Pumps 20
Cooling Tower Fans 10
Total Auxiliary Load 1,840
55
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
56
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
57
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
The initial and annual O&M costs for a greenfield site were calculated and are shown in Exhibit
5-26, while Exhibit 5-27 shows the COC for greenfield and retrofit sites for the representative
ethanol plant.
Exhibit 5-26. Initial and annual O&M costs for ethanol greenfield site
Case: Ethanol Cost Base: Dec 2018
58
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Note: The data point for the COC at a 50 M gallon/year ethanol plant does not fall directly on the COC line due to data point
increments and plot formatting.
59
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
might be a more economical option, but further evaluation would be required to determine an
applicable COC for this alternate CO2 end-use.
h The assumptions for this study’s reference plant are not limited to the Michigan Basin. High CO2 content coupled with
large capacity processing plants may also be found in the Gulf Coast region, the Williston Basin, and the Midwest region,
referred to as the Foreland Province, according to the Gas Technology Institute database. [37]
60
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Natural Gas
Desired
Processing 1 Compressor 2 HX 3
Usage
Plant
61
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
1 2 3
V-L Mole Fraction
AR 0.0000 0.0000 0.0000
CH4 0.0000 0.0000 0.0000
CO 0.0000 0.0000 0.0000
CO2 0.9900 0.9995 0.9995
SO2 0.0000 0.0000 0.0000
H2 0.0000 0.0000 0.0000
H2O 0.0100 0.0005 0.0005
H2S 0.0000 0.0000 0.0000
N2 0.0000 0.0000 0.0000
Total 1.0000 1.0000 1.0000
The performance results are based on the centrifugal compressor discussed in Section 4.1.2 and
scaled auxiliary loads for the cooling water system as discussed in Section 4.4. The performance
summary is provided in Exhibit 5-32.
62
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Performance Summary
Item 330 MMSCFD (kWe)
CO2 Compressor 6,010
Circulating Water Pumps 70
Cooling Tower Fans 40
Total Auxiliary Load 6,120
63
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
64
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
65
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
The initial and annual O&M costs for a greenfield site were calculated and are shown in Exhibit
5-35, while Exhibit 5-36 shows the COC for greenfield and retrofit sites for the representative
NGP plant.
Exhibit 5-35. Initial and annual O&M costs for NGP greenfield site
Case: Natural Gas Processing Cost Base: Dec 2018
Representative Plant Size: 330 MMSCFD natural gas Capacity Factor (%): 85
Exhibit 5-36. COC for 330 MMSCFD NGP greenfield and retrofit
66
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
67
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
5.5 COAL-TO-LIQUIDS
Economic and national security concerns related to liquid fuels have revived national interest in
alternative liquid fuel sources. Coal-to-Fischer-Tropsch fuels production emerged as a major
technology option for many states and the DOE. The 2014 NETL report “Baseline Technical and
Economic Assessment of a Commercial Scale Fischer-Tropsch Liquids Facility” (“CTL Study”) [38]
examined the technical and economic feasibility of a commercial 50,000 barrels per day (BPD)
CTL facility. The facility employs gasification and Fischer-Tropsch (FT) technology to produce
commercial-grade diesel and naptha liquids from medium-sulfur bituminous coal. The basis for
the CTL case in this report is that of the CO2 sequestration case evaluated in the CTL Study.
68
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
1 2 3 4 5
V-L Mole Fraction
AR 0.0000 0.0000 0.0000 0.0000 0.0000
CH4 0.0000 0.0000 0.0000 0.0000 0.0000
CO 0.0000 0.0000 0.0000 0.0000 0.0000
CO2 1.0000 1.0000 1.0000 1.0000 1.0000
H2 0.0000 0.0000 0.0000 0.0000 0.0000
H2O 0.0000 0.0000 0.0000 0.0000 0.0000
H2S 0.0000 0.0000 0.0000 0.0000 0.0000
N2 0.0000 0.0000 0.0000 0.0000 0.0000
Total 1.0000 1.0000 1.0000 1.0000 1.0000
69
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
1 2 3 4 5
V-L Mole Fraction
V-L Flowrate (kgmol/hr) 13,449 7,384 1,846 22,679 22,679
V-L Flowrate (kg/hr) 91,870 324,980 81,245 498,095 498,095
Temperature (°C) 38 16 16 49 30
Pressure (MPa, abs) 1.8 1.1 2.1 15.3 15.3
A
Steam Table Enthalpy (kJ/kg) 8,759 8,759 8,758 8,755 8,753
Aspen Plus Enthalpy (kJ/kg)B -8,948 -8,961 -8,972 -9,132 -9,188
3
Density (kg/m ) 34.2 21.7 43.8 668.2 628.8
V-L Molecular Weight 44.01 44.01 44.01 44.01 44.01
The performance results are taken from the CTL Study sequestration case that considered CO2
capture. The performance summary is provided in Exhibit 5-40.
Performance Summary
Item 50,000 BPD (kWe)
CO2 Compressor 43,480
Circulating Water Pumps 100
Cooling Tower Fans 50
Total Auxiliary Load 43,630
70
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
71
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
72
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
The initial and annual O&M costs for a greenfield site were calculated and are shown in Exhibit
5-43, while Exhibit 5-44 shows the COC for a greenfield site for the representative CTL plant.
Exhibit 5-43. Initial and annual O&M costs for CTL greenfield site
Case: Coal-to-Liquids Cost Base: Dec 2018
Representative Plant Size: 50,000 BPD Fischer-Tropsch liquids Capacity Factor (%): 85
73
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
5.6 GAS-TO-LIQUIDS
Domestic FT GTL technology provides an alternative option for use of U.S. increasing supply of
domestic NG. As with CTL, GTL can create a significant economic value while increasing the
country’s energy security. In their report “Analysis of Natural Gas-to Liquid Transportation Fuels
via Fischer-Tropsch” [39] (“GTL Study”) published in 2013, NETL evaluated the cost and
performance of a 50,000 BPD FT liquids GTL facility. Of the total liquids production, 30 percent is
allocated for finished motor gasoline, and 70 percent results in low-density diesel fuel. The
74
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
system is calibrated to produce predominately liquid fuels; however, electrical power for export
is also a co-product after satisfying internal plant power consumption. In its current
configuration, the GTL plant exports 40.8 MWe to the grid. This study also considers CO2
capture and compression with associated performance and cost. The case for this report is that
of the GTL Study.
75
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
adjusted to December 2018 dollars. This will require that the amount of cooling water
necessary for interstage cooling be approximated, similar to the CTL case in this study.
Desired
GTL Facility 1 Compressor 2 HX 3
Usage
76
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
1 2 3
V-L Mole Fraction
Aspen Plus Enthalpy (Btu/lb)B -3,847 -3,929 -3,950
Density (lb/ft3) 2.14 43.0 39.3
ASteam table reference conditions are 32.02°F & 0.089 psia
BAspen thermodynamic reference state is the component’s constituent elements in an ideal gas state at 25°C and 1 atm
The performance results given are taken from the current GTL Study case that considered CO2
capture. The performance summary is provided in Exhibit 5-48.
Performance Summary
Item 50,000 BPD (kWe)
CO2 Compressor 6,700
Circulating Water Pumps 20
Cooling Tower Fans 10
Total Auxiliary Load 6,730
77
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
78
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
79
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
The initial and annual O&M costs for a greenfield site were calculated and are shown in Exhibit
5-51, while Exhibit 5-52 shows the COC for a greenfield site for the representative GTL plant.
Exhibit 5-51. Initial and annual O&M costs for GTL greenfield site
Case: Gas-to-Liquids Cost Base: Dec 2018
Representative Plant Size: 50,000 BPD Fischer-Tropsch liquids Capacity Factor (%): 85
Operating & Maintenance Labor
Operating Labor Operating Labor Requirements per Shift
Operating Labor Rate (base): 38.50 $/hour Skilled Operator: 0.0
Operating Labor Burden: 30.00 % of base Operator: 1.0
Labor O-H Charge Rate: 25.00 % of labor Foreman: 0.0
Lab Techs, etc.: 0.0
Total: 1.0
Fixed Operating Costs
Annual Cost
($) ($/tonnes/yr CO2)
Annual Operating Labor: $438,438 $0.24
Maintenance Labor: $314,687 $0.17
Administrative & Support Labor: $188,281 $0.10
Property Taxes and Insurance: $983,396 $0.53
Total: $1,924,802 $1.04
Variable Operating Costs
($) ($/tonnes/yr CO2)
Maintenance Material: $472,030 $0.30
Consumables
Initial Fill Per Day Per Unit Initial Fill
Water (/1000 gallons): 0 59 $1.90 $0 $34,632 $0.02
Makeup and Waste Water Treatment 0 0.2 $550.00 $0 $29,863 $0.02
Chemicals (ton):
Subtotal: $0 $64,495 $0.04
Variable Operating Costs Total: $0 $536,526 $0.34
80
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
81
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
82
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
83
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
compression, and cooling are necessary to create a CO2 product stream suitable for EOR end-
use. The Shell ADIP-Ultra pre-combustion AGR unit detailed in Section 4.2.2 is modeled to
represent CO2 removal at 90 and 99 percent. AGR auxiliary loads are scaled based on CO2
flowrate.
The AGR unit requires low pressure steam at 74 psia to regenerate the amine-based solvent.
These steam needs are met with the industrial boiler discussed in Section 4.3. In addition,
cooling water is required for both the AGR unit and for compression intercooling and after-
cooler. The cooling water unit auxiliaries are scaled as described in Section 4.4.
To PSA
5 2
ADIP-Ultra
Steam Desired
CO2
Methane 1 3 Compressor 6 HX 7
Capture Usage
Reformer
System
Water KO
The stream tables for 99 and 90 percent capture in the refinery hydrogen case are presented in
Exhibit 6-3 and Exhibit 6-4, respectively.
84
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
1 2 3 4 5 6 7
V-L Mole Fraction
AR 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
CH4 0.0179 0.0000 0.0000 0.0000 0.0336 0.0000 0.0000
CO 0.0010 0.0000 0.0000 0.0000 0.0017 0.0000 0.0000
CO2 0.1268 0.8644 0.9629 0.0020 0.0023 0.9995 0.9995
SO2 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
H2 0.5020 0.0000 0.0000 0.0000 0.9427 0.0000 0.0000
H2O 0.3438 0.1356 0.0371 0.9980 0.0039 0.0005 0.0005
H2S 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
N2 0.0020 0.0000 0.0000 0.0000 0.0034 0.0000 0.0000
C2H6 0.0049 0.0000 0.0000 0.0000 0.0091 0.0000 0.0000
C3H8 0.0011 0.0000 0.0000 0.0000 0.0021 0.0000 0.0000
C4H10 0.0006 0.0000 0.0000 0.0000 0.0011 0.0000 0.0000
O2 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Total 1.0000 1.0000 1.0000 1.0000 1.0000 1.0000 1.0000
V-L Flowrate (kgmol/hr) 8,320 593 546 2,848 4,431 1,040 1,040
V-L Flowrate (kg/hr) 111,368 24,023 23,524 51,457 14,118 45,736 45,736
Temperature (°C) 39 102 40 39 55 121 29
Pressure (MPa, abs) 2.76 0.6 0.2 2.8 2.7 15.3 15.3
A
Steam Table Enthalpy (kJ/kg) 10,569 9,172 8,865 15,273 1,597 8,760 8,755
B
Aspen Plus Enthalpy (kJ/kg) -11,217 -9,144 -9,005 -15,873 -1,501 -8,952 -9,196
Density (kg/m3) 21.3 8.3 3.3 918.8 3.1 283.1 640.4
V-L Molecular Weight 13.4 40.5 43.0 18.1 3.19 44.0 44.0
V-L Flowrate (lbmol/hr) 18,342 1,308 1,205 6,279 9,768 2,292 2,292
V-L Flowrate (lb/hr) 245,524 52,962 51,861 113,443 31,124 100,830 100,830
Temperature (°F) 102 216 104 102 131 250 85
Pressure (psia) 399.9 90.8 28.3 399.9 394.4 2,215.9 2,214.7
A
Steam Table Enthalpy (Btu/lb) 4,544 3,943 3,811 6,566 686 3,766 3,764
B
Aspen Plus Enthalpy (Btu/lb) -4,822 -3,931 -3,871 -6,824 -645 -3,849 -3,954
3
Density (lb/ft ) 1.33 0.518 0.204 57.4 0.196 17.7 44.0
ASteam table reference conditions are 32.02°F & 0.089 psia
BAspen thermodynamic reference state is the component’s constituent elements in an ideal gas state at 25°C and 1 atm
85
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
1 2 3 4 5 6 7
V-L Mole Fraction
AR 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
CH4 0.0179 0.0009 0.0000 0.0000 0.0328 0.0000 0.0000
CO 0.0010 0.0000 0.0000 0.0000 0.0018 0.0000 0.0000
CO2 0.1268 0.9493 0.9629 0.0020 0.0232 0.9995 0.9995
SO2 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
H2 0.5020 0.0130 0.0000 0.0000 0.9219 0.0000 0.0000
H2O 0.3438 0.0368 0.0371 0.9980 0.0047 0.0005 0.0005
H2S 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
N2 0.0020 0.0000 0.0000 0.0000 0.0036 0.0000 0.0000
C2H6 0.0049 0.0000 0.0000 0.0000 0.0090 0.0000 0.0000
C3H8 0.0011 0.0000 0.0000 0.0000 0.0020 0.0000 0.0000
C4H10 0.0006 0.0000 0.0000 0.0000 0.0011 0.0000 0.0000
O2 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
Total 1.0000 1.0000 1.0000 1.0000 1.0000 1.0000 1.0000
V-L Flowrate (kgmol/hr) 8,320 496 492 2,848 4,524 945 945
V-L Flowrate (kg/hr) 111,368 21,076 21,170 51,457 18,375 41,572 41,572
Temperature (°C) 39 102 40 39 55 121 29
Pressure (MPa, abs) 2.76 0.6 0.2 2.8 2.7 15.3 15.3
A
Steam Table Enthalpy (kJ/kg) 10,569 8,858 8,865 15,273 2,884 8,760 8,755
B
Aspen Plus Enthalpy (kJ/kg) -11,217 -8,938 -9,005 -15,873 -3,225 -8,952 -9,196
Density (kg/m3) 21.3 8.7 3.3 918.8 4.0 283.1 640.4
V-L Molecular Weight 13.4 42.5 43.0 18.1 4.06 44.0 44.0
V-L Flowrate (lbmol/hr) 18,342 1,094 1,084 6,279 9,973 2,083 2,083
V-L Flowrate (lb/hr) 245,524 46,464 46,672 113,443 40,510 91,651 91,651
Temperature (°F) 102 216 104 102 131 250 85
Pressure (psia) 399.9 90.8 28.3 399.9 394.4 2,215.9 2,214.7
A
Steam Table Enthalpy (Btu/lb) 4,544 3,808 3,811 6,566 1,240 3,766 3,764
B
Aspen Plus Enthalpy (Btu/lb) -4,822 -3,843 -3,871 -6,824 -1,387 -3,849 -3,954
3
Density (lb/ft ) 1.33 0.542 0.204 57.4 0.250 17.7 40.0
ASteam table reference conditions are 32.02°F & 0.089 psia
BAspen thermodynamic reference state is the component’s constituent elements in an ideal gas state at 25°C and 1 atm
The performance summaries for 90 and 99 percent capture in the refinery hydrogen case are
presented in Exhibit 6-5.
86
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Performance Summary
87,000 tonnes H2/year with 90 87,000 tonnes H2/year with 99
Item
percent CO2 capture (kWe) percent CO2 capture (kWe)
CO2 Capture Auxiliaries 500 500
Steam Boiler Auxiliaries 70 80
CO2 Compressor 3,160 3,470
Circulating Water Pumps 210 240
Cooling Tower Fans 100 120
Total Auxiliary Load 4,040 4,410
87
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
$/tonnes/yr $/tonnes/yr
Description $/1,000 $/1,000
(CO2) (CO2)
Pre-Production Costs 99% Capture 90% Capture
6 Months All Labor $1,153 $3 $1,139 $3
1-Month Maintenance Materials $123 $0 $120 $0
1-Month Non-Fuel Consumables $46 $0 $42 $0
1-Month Waste Disposal $0 $0 $0 $0
25% of 1-Month Fuel Cost at 100% CF $89 $0 $78 $0
2% of TPC $2,613 $7 $2,544 $7
Total $4,024 $10 $3,923 $11
Inventory Capital 99% Capture 90% Capture
60-day supply of fuel and consumables at
100% CF $786 $2 $693 $2
0.5% of TPC (spare parts) $653 $2 $636 $2
Total $1,439 $4 $1,329 $4
Other Costs 99% Capture 90% Capture
Initial Cost for Catalyst and Chemicals $0 $0 $0 $0
Land $30 $0 $30 $0
Other Owner's Costs $19,594 $49 $19,078 $52
Financing Costs $3,527 $9 $3,434 $9
TOC $159,244 $397 $154,978 $426
TASC Multiplier (Refinery Hydrogen, 33 year) 1.036 1.036
TASC $164,929 $412 $160,510 $441
88
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-7. Capital costs for refinery hydrogen greenfield site with 99 percent capture
Case: Refinery H2 Estimate Type: Conceptual
Representative Plant Size: 87,000 tonnes H2/year Cost Base: Dec 2018
Labor Eng'g CM Contingencies Total Plant Cost
Item Equipment Material Bare Erected
Description H.O. & $/tonnes/yr
No. Cost Cost Direct Indirect Cost Process Project $/1,000
Fee (CO2)
3 Feedwater & Miscellaneous BOP Systems
3.1 Feedwater System $237 $407 $203 $0 $847 $148 $0 $199 $1,195 $3
3.2 Water Makeup & Pretreating $552 $55 $313 $0 $921 $161 $0 $216 $1,298 $3
3.3 Other Feedwater Subsystems $82 $27 $25 $0 $134 $23 $0 $32 $189 $0
3.4 Industrial Boiler Package w/Deaerator $1,090 $0 $317 $0 $1,407 $246 $0 $331 $1,985 $5
3.5 Other Boiler Plant Systems $19 $7 $18 $0 $44 $8 $0 $10 $62 $0
3.6 NG Pipeline and Start-Up System $317 $14 $10 $0 $341 $60 $0 $80 $481 $1
3.7 Waste Water Treatment Equipment $2,898 $0 $1,776 $0 $4,675 $818 $0 $1,099 $6,591 $16
3.9 Miscellaneous Plant Equipment $68 $9 $34 $0 $111 $19 $0 $26 $157 $0
Subtotal $5,265 $518 $2,698 $0 $8,481 $1,484 $0 $1,993 $11,958 $30
5 Flue Gas Cleanup
5.1 ADIP-Ultra CO2 Removal System $21,678 $9,377 $19,691 $0 $50,746 $8,881 $8,627 $13,651 $81,904 $204
5.4 CO2 Compression & Drying $7,402 $1,110 $2,475 $0 $10,987 $1,923 $0 $2,582 $15,492 $39
5.5 CO2 Compressor Aftercooler $81 $13 $35 $0 $129 $23 $0 $30 $182 $0
5.12 Gas Cleanup Foundations $0 $4 $4 $0 $8 $1 $0 $2 $11 $0
Subtotal $29,162 $10,504 $22,204 $0 $61,870 $10,827 $8,627 $16,265 $97,589 $244
7 Ductwork & Stack
7.3 Ductwork $0 $66 $46 $0 $112 $20 $0 $26 $158 $0
7.4 Stack $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
7.5 Duct & Stack Foundations $0 $157 $187 $0 $344 $60 $0 $81 $485 $1
Subtotal $0 $223 $233 $0 $456 $80 $0 $107 $643 $2
9 Cooling Water System
9.1 Cooling Towers $455 $0 $141 $0 $596 $104 $0 $140 $840 $2
9.2 Circulating Water Pumps $41 $0 $3 $0 $44 $8 $0 $10 $62 $0
9.3 Circulating Water System Aux. $744 $0 $98 $0 $843 $148 $0 $198 $1,188 $3
9.4 Circulating Water Piping $0 $344 $312 $0 $656 $115 $0 $154 $925 $2
9.5 Make-up Water System $100 $0 $128 $0 $228 $40 $0 $54 $322 $1
9.6 Component Cooling Water System $54 $0 $41 $0 $95 $17 $0 $22 $134 $0
9.7 Circulating Water System Foundations $0 $41 $68 $0 $109 $19 $0 $26 $154 $0
Subtotal $1,394 $385 $791 $0 $2,571 $450 $0 $604 $3,624 $9
11 Accessory Electric Plant
11.2 Station Service Equipment $1,527 $0 $131 $0 $1,658 $290 $0 $390 $2,338 $6
11.3 Switchgear & Motor Control $2,371 $0 $411 $0 $2,782 $487 $0 $654 $3,923 $10
11.4 Conduit & Cable Tray $0 $308 $888 $0 $1,196 $209 $0 $281 $1,687 $4
11.5 Wire & Cable $0 $816 $1,459 $0 $2,275 $398 $0 $535 $3,208 $8
Subtotal $3,898 $1,124 $2,890 $0 $7,912 $1,385 $0 $1,859 $11,156 $28
89
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-8. Capital costs for refinery hydrogen greenfield site with 90 percent capture
Case: Refinery H2 Estimate Type: Conceptual
Representative Plant Size: 87,000 tonnes H2/year Cost Base: Dec 2018
Labor Eng'g CM Contingencies Total Plant Cost
Item Equipment Material Bare Erected
Description H.O. & $/tonnes/yr
No. Cost Cost Direct Indirect Cost Process Project $/1,000
Fee (CO2)
3 Feedwater & Miscellaneous BOP Systems
3.1 Feedwater System $217 $372 $186 $0 $775 $136 $0 $182 $1,092 $3
3.2 Water Makeup & Pretreating $495 $49 $280 $0 $825 $144 $0 $194 $1,163 $3
3.3 Other Feedwater Subsystems $73 $24 $23 $0 $119 $21 $0 $28 $168 $0
3.4 Industrial Boiler Package w/Deaerator $971 $0 $282 $0 $1,254 $219 $0 $295 $1,768 $5
3.5 Other Boiler Plant Systems $17 $6 $16 $0 $39 $7 $0 $9 $55 $0
3.6 NG Pipeline and Start-Up System $298 $13 $10 $0 $320 $56 $0 $75 $451 $1
3.7 Waste Water Treatment Equipment $2,807 $0 $1,721 $0 $4,528 $792 $0 $1,064 $6,385 $18
3.9 Miscellaneous Plant Equipment $66 $9 $33 $0 $108 $19 $0 $25 $152 $0
Subtotal $4,944 $473 $2,551 $0 $7,968 $1,394 $0 $1,872 $11,234 $31
5 Flue Gas Cleanup
5.1 ADIP-Ultra CO2 Removal System $21,409 $9,260 $19,447 $0 $50,116 $8,770 $8,520 $13,481 $80,888 $222
5.4 CO2 Compression & Drying $6,991 $1,049 $2,338 $0 $10,377 $1,816 $0 $2,439 $14,632 $40
5.5 CO2 Compressor Aftercooler $75 $12 $32 $0 $120 $21 $0 $28 $169 $0
5.12 Gas Cleanup Foundations $0 $4 $4 $0 $8 $1 $0 $2 $11 $0
Subtotal $28,476 $10,325 $21,820 $0 $60,621 $10,609 $8,520 $15,950 $95,700 $263
7 Ductwork & Stack
90
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
91
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
The initial and annual O&M costs for a greenfield site were calculated and are shown in Exhibit
6-9 and Exhibit 6-10 for 99 percent and 90 percent capture, respectively, while Exhibit 6-11
shows the COC for greenfield and retrofit sites for the representative refinery hydrogen plants
at both capture rates.
Exhibit 6-9. Initial and annual O&M costs for refinery hydrogen greenfield site with 99 percent capture
Case: Refinery Hydrogen Cost Base: Dec 2018
92
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-10. Initial and annual O&M costs for refinery hydrogen greenfield site with 90 percent capture
Case: Refinery Hydrogen Cost Base: Dec 2018
Exhibit 6-11. COC for 87,000 tonnes H2/year refinery hydrogen cases
99% Capture COC, $/tonne CO2 90% Capture COC, $/tonne CO2
Component Greenfield Retrofit Greenfield Retrofit
Capital 21.3 22.2 22.8 23.8
Fixed 14.4 15.0 15.6 16.2
Variable 5.1 5.3 5.3 5.5
Purchased Power and Fuel 16.5 16.5 16.2 16.2
Total COC 57.3 58.9 59.9 61.7
93
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
As the cost of capturing CO2 is a normalized cost (i.e., $/tonne CO2), higher capture rates appear
to cost less than lower capture rates. Comparing the true capital and O&M costs (i.e., not as
normalized costs) shows that capital and O&M expenditures increase at higher capture rates.
The cost of the capture system and associated consumables increases at a lesser rate than that
of the amount of CO2 captured (i.e., a 10 percent increase from 90 to 99 percent capture). The
margin of error associated with the financial assumptions and cost scaling methodology
employed in this study indicate that with increasing capture rate in the low purity cases, the
COC is effectively the same. The reported minor increase in capital cost with increased capture
rate (up to 99 percent for sources with CO2 purity greater than 12 percent) has been validated
by independent modeling performed by the carbon capture simulation initiative (CCSI) team at
NETL and has been reported independently in literature. [4] Exhibit 6-13 shows the error in the
calculated capture system BEC associated with the vendor’s quoted uncertainty rate (-25/+40
percent) alongside the amount of CO2 captured in the refinery H2 case from 90 to 99 percent
capture rate.
94
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-13. Refinery H2 capture system BEC and amount of CO2 captured versus capture rate
95
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
6.2 CEMENT
Concrete is formed with a mixture of sand, gravel, water, and cement. Cement, when activated
with water, is the binder that holds the concrete mixture together. In 2020, the U.S. cement
industry produced approximately 89.3 M tonnes of Portland cement (PC) and masonry cement,
with sales at approximately $12.7 billion (B). [43] In the same year, the U.S. apparent
consumption of cement was 102 M tonnes of cement, meaning that imported cement filled the
production gap. The United States Geological Survey (USGS) asserts in their 2021 Minerals
Commodity Summary that U.S. cement production growth has been continuously constrained in
recent years “by closed or idle plants, underutilized capacity at others, production disruptions
from plant upgrades, and relatively inexpensive imports.” Production trends for cement, as
reported by the USGS, are shown in Exhibit 6-14. [43]
There are two processes for producing PC: wet kiln and dry kiln. The number of the more
energy-intensive wet process kilns in the United States has declined by 96 percent from 234, in
1974, to 10, in 2019, while the number of dry process kilns was reduced from 198 to 110 over
the same period. [44] Since 2008, approximately 85 percent of U.S. cement is produced using
the dry-kiln process. [45]
Both the dry- and wet-kiln processes utilize a multitude of different fuels to provide the heat
necessary for drying, calcination, and sintering. Shown in Exhibit 6-15 is a breakdown of the fuel
type consumed for 2019 as reported by the Portland Cement Association. [44] The values are
given as a percentage of Btu consumed.
96
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Fuel burning to provide kiln heat is one of two CO2 emissions sources, with the second resulting
from the calcinations of calcium carbonate to form calcium oxide/calcium silicate species during
the manufacturing process itself. PC is manufactured by crushing limestone and clay/shale raw
materials to a powder, and then feeding in dry or slurry form to a kiln. Inside the kiln, the raw
materials are heated to 2,600–3,000°F (1,430–1,650°C) and a chemical reaction takes place,
fusing the raw materials into PC clinker, thus, generating CO2. The clinker exits the kiln, is
cooled, and is ground with gypsum to form PC. [46] Exhibit 6-16 shows the traditional PC
production process, as adapted from Hassan (2005). [47]
97
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
For this study, the main point source of CO2 available for capture is the kiln off-gas, and the
concentrations given for the St. Mary’s cement plant are assumed as representative. It is
assumed that the kiln off-gas requires only CO2 removal and compression and no other clean-
up; however, it is possible that other treatment of the off-gas would be necessary prior to AGR.
A study done by the IEAGHG in 2009 estimated the cost per tonne of CO2 avoided and the cost
per tonne of cement product when adding CO2 capture to a reference cement plant. [49] Their
analysis points out that for post-combustion CO2 capture to be implemented, there are several
issues that must be addressed, as operational problems may arise from: the SO2 concentration
98
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
in the off-gas stream, which is dependent on the sulfide concentration in the raw meal; NO2
concentration in the off-gas stream, which may cause solvent degradation; and dust present in
the off-gas, which will reduce the efficiency of the post-combustion capture process. These
issues are not considered in this study’s base case; rather, the kiln off-gas is assumed suitable
for post-combustion amine capture. However, a sensitivity case is evaluated to account for
these issues with the addition of a selective catalytic reduction (SCR) unit to treat NOx and flue
gas desulfurization (FGD) to remove oxides of sulfur (SOx).
99
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Cansolv
Kiln CO2 Desired
1 2 Compressor 3 HX 4
Off-gas Capture Usage
System
1 2 3 4 5
V-L Mole Fraction
AR 0.0000 0.0000 0.0000 0.0000 0.0000
CH4 0.0000 0.0000 0.0000 0.0000 0.0000
CO 0.0000 0.0000 0.0000 0.0000 0.0000
CO2 0.2240 0.9885 0.9995 0.9995 0.0032
SO2 0.0000 0.0000 0.0000 0.0000 0.0000
H2 0.0000 0.0000 0.0000 0.0000 0.0000
H2O 0.0720 0.0115 0.0005 0.0005 0.0205
H2S 0.0000 0.0000 0.0000 0.0000 0.0000
N2 0.6810 0.0000 0.0000 0.0000 0.9444
O2 0.0230 0.0000 0.0000 0.0000 0.0319
Total 1.0000 1.0000 1.0000 1.0000 1.0000
100
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
1 2 3 4 5
V-L Mole Fraction
AR 0.0000 0.0000 0.0000 0.0000 0.0000
CH4 0.0000 0.0000 0.0000 0.0000 0.0000
CO 0.0000 0.0000 0.0000 0.0000 0.0000
CO2 0.2240 0.9887 0.9995 0.9995 0.0302
SO2 0.0000 0.0000 0.0000 0.0000 0.0000
H2 0.0000 0.0000 0.0000 0.0000 0.0000
H2O 0.0720 0.0113 0.0005 0.0005 0.0207
H2S 0.0000 0.0000 0.0000 0.0000 0.0000
N2 0.6810 0.0000 0.0000 0.0000 0.9181
O2 0.0230 0.0000 0.0000 0.0000 0.0310
Total 1.0000 1.0000 1.0000 1.0000 1.0000
101
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
The performance summary for both 90 and 99 percent capture cases is provided in Exhibit 6-21.
Performance Summary
1.3 M tonnes cement/year with 1.3 M tonnes cement/year with
Item
90 percent CO2 capture (kWe) 99 percent CO2 capture (kWe)
CO2 Capture Auxiliaries 3,100 3,500
Steam Boiler Auxiliaries 330 370
CO2 Compressor 9,570 10,460
Circulating Water Pumps 980 1,040
Cooling Tower Fans 500 540
Total Auxiliary Load 14,480 15,910
102
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
$/tonnes/yr $/tonnes/yr
Description $/1,000 $/1,000
(CO2) (CO2)
Pre-Production Costs 99% Capture 90% Capture
6 Months All Labor $1,986 $2 $1,922 $2
1-Month Maintenance Materials $319 $0 $304 $0
1-Month Non-Fuel Consumables $257 $0 $240 $0
1-Month Waste Disposal $11 $0 $11 $0
25% of 1-Month Fuel Cost at 100% CF $391 $0 $355 $0
2% of TPC $6,779 $6 $6,457 $6
Total $9,742 $8 $9,289 $9
Inventory Capital 99% Capture 90% Capture
60-day supply of fuel and consumables at 100% CF $3,550 $3 $3,239 $3
0.5% of TPC (spare parts) $1,695 $1 $1,614 $1
Total $5,245 $4 $4,853 $4
Other Costs 99% Capture 90% Capture
Initial Cost for Catalyst and Chemicals $0 $0 $0 $0
Land $30 $0 $30 $0
Other Owner's Costs $50,842 $42 $48,431 $44
Financing Costs $9,152 $8 $8,718 $8
TOC $413,960 $346 $394,192 $362
TASC Multiplier (Cement, 33 year) 1.054 1.054
TASC $436,252 $364 $415,418 $381
103
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-23. Capital costs for cement greenfield site with 99 percent capture
Case: Cement Estimate Type: Conceptual
Representative Plant Size: 1.3 M tonnes cement/year Cost Base: Dec 2018
Item Equipment Material Labor Bare Erected Eng'g CM Contingencies Total Plant Cost
Description
No. Cost Cost Direct Indirect Cost H.O. & Fee Process Project $/1,000 $/tonnes/yr (CO2)
3 Feedwater & Miscellaneous BOP Systems
3.1 Feedwater System $658 $1,127 $564 $0 $2,349 $411 $0 $552 $3,311 $3
3.2 Water Makeup & Pretreating $1,633 $163 $925 $0 $2,722 $476 $0 $640 $3,837 $3
3.3 Other Feedwater Subsystems $305 $100 $95 $0 $500 $87 $0 $117 $704 $1
3.4 Industrial Boiler Package
$4,061 $0 $1,181 $0 $5,242 $917 $0 $1,232 $7,391 $6
w/Deaerator
3.5 Other Boiler Plant Systems $73 $27 $67 $0 $167 $29 $0 $39 $235 $0
3.6 NG Pipeline and Start-Up System $654 $28 $21 $0 $703 $123 $0 $165 $992 $1
3.7 Waste Water Treatment
$3,003 $0 $1,840 $0 $4,843 $848 $0 $1,138 $6,829 $6
Equipment
3.9 Miscellaneous Plant Equipment $98 $13 $50 $0 $161 $28 $0 $38 $227 $0
Subtotal $10,485 $1,458 $4,743 $0 $16,686 $2,920 $0 $3,921 $23,527 $20
5 Flue Gas Cleanup
5.1 Cansolv CO2 Removal System $58,671 $25,377 $53,292 $0 $137,340 $24,034 $23,348 $36,944 $221,667 $185
5.4 CO2 Compression & Drying $17,147 $2,572 $5,733 $0 $25,452 $4,454 $0 $5,981 $35,887 $30
5.5 CO2 Compressor Aftercooler $137 $22 $59 $0 $218 $38 $0 $51 $307 $0
5.12 Gas Cleanup Foundations $0 $65 $57 $0 $122 $21 $0 $29 $172 $0
Subtotal $75,955 $28,036 $59,141 $0 $163,132 $28,548 $23,348 $43,006 $258,033 $215
7 Ductwork & Stack
7.3 Ductwork $0 $1,608 $1,117 $0 $2,725 $477 $0 $640 $3,842 $3
7.4 Stack $7,699 $0 $4,474 $0 $12,174 $2,130 $0 $2,861 $17,165 $14
7.5 Duct & Stack Foundations $0 $172 $204 $0 $376 $66 $0 $88 $530 $0
Subtotal $7,699 $1,779 $5,795 $0 $15,274 $2,673 $0 $3,589 $21,537 $18
9 Cooling Water System
9.1 Cooling Towers $1,426 $0 $441 $0 $1,867 $327 $0 $439 $2,632 $2
9.2 Circulating Water Pumps $147 $0 $10 $0 $157 $27 $0 $37 $221 $0
9.3 Circulating Water System Aux. $1,895 $0 $251 $0 $2,146 $376 $0 $504 $3,025 $3
9.4 Circulating Water Piping $0 $876 $794 $0 $1,670 $292 $0 $392 $2,355 $2
9.5 Make-up Water System $207 $0 $265 $0 $472 $83 $0 $111 $666 $1
9.6 Component Cooling Water
$137 $0 $105 $0 $241 $42 $0 $57 $340 $0
System
9.7 Circulating Water System
$0 $97 $161 $0 $258 $45 $0 $61 $363 $0
Foundations
Subtotal $3,811 $973 $2,027 $0 $6,811 $1,192 $0 $1,600 $9,603 $8
11 Accessory Electric Plant
11.2 Station Service Equipment $2,650 $0 $227 $0 $2,878 $504 $0 $676 $4,058 $3
11.3 Switchgear & Motor Control $4,114 $0 $714 $0 $4,828 $845 $0 $1,135 $6,808 $6
11.4 Conduit & Cable Tray $0 $535 $1,541 $0 $2,076 $363 $0 $488 $2,927 $2
104
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-24. Capital costs for cement greenfield site with 90 percent capture
Case: Cement Estimate Type: Conceptual
Representative Plant Size: 1.3 M tonnes cement/year Cost Base: Dec 2018
Item Equipment Material Labor Bare Erected Eng'g CM Contingencies Total Plant Cost
Description
No. Cost Cost Direct Indirect Cost H.O.& Fee Process Project $/1,000 $/tonnes/yr (CO2)
3 Feedwater & Miscellaneous BOP Systems
3.1 Feedwater System $616 $1,056 $528 $0 $2,199 $385 $0 $517 $3,101 $3
3.2 Water Makeup & Pretreating $1,543 $154 $874 $0 $2,571 $450 $0 $604 $3,626 $3
3.3 Other Feedwater Subsystems $280 $92 $87 $0 $459 $80 $0 $108 $647 $1
3.4 Industrial Boiler Package
$3,731 $0 $1,085 $0 $4,816 $843 $0 $1,132 $6,790 $6
w/Deaerator
3.5 Other Boiler Plant Systems $67 $25 $61 $0 $153 $27 $0 $36 $216 $0
3.6 NG Pipeline and Start-Up System $624 $27 $20 $0 $671 $117 $0 $158 $946 $1
3.7 Waste Water Treatment
$2,872 $0 $1,760 $0 $4,632 $811 $0 $1,088 $6,531 $6
Equipment
3.9 Miscellaneous Plant Equipment $96 $13 $49 $0 $157 $27 $0 $37 $221 $0
Subtotal $9,829 $1,366 $4,464 $0 $15,659 $2,740 $0 $3,680 $22,079 $20
5 Flue Gas Cleanup
5.1 Cansolv CO2 Removal System $55,656 $24,073 $50,554 $0 $130,284 $22,800 $22,148 $35,046 $210,278 $193
5.4 CO2 Compression & Drying $16,242 $2,436 $5,430 $0 $24,108 $4,219 $0 $5,665 $33,993 $31
5.5 CO2 Compressor Aftercooler $127 $20 $54 $0 $201 $35 $0 $47 $284 $0
5.12 Gas Cleanup Foundations $0 $65 $57 $0 $122 $21 $0 $29 $172 $0
105
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
106
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
The initial and annual O&M costs for a greenfield site were calculated and are shown in Exhibit
6-25 and Exhibit 6-26 for 99 percent and 90 percent capture, respectively, while Exhibit 6-27
shows the COC for greenfield and retrofit sites for the representative cement plants at both
capture rates.
Exhibit 6-25. Initial and annual O&M costs for cement greenfield site with 99 percent capture
Case: Cement Cost Base: Dec 2018
107
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-26. Initial and annual O&M costs for cement greenfield site with 90 percent capture
Case: Cement Cost Base: Dec 2018
99% Capture COC, $/tonne CO2 90% Capture COC, $/tonne CO2
Component Greenfield Retrofit Greenfield Retrofit
Capital 21.8 22.6 22.8 23.7
Fixed 10.6 11.0 11.1 11.6
Variable 5.9 6.0 6.1 6.3
Purchased Power and Fuel 22.6 22.6 22.6 22.6
Total COC 60.8 62.4 62.7 64.3
108
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
As the cost of capturing CO2 is a normalized cost (i.e., $/tonne CO2), higher capture rates appear
to cost less than lower capture rates. Comparing the true capital and O&M costs (i.e., not as
normalized costs) shows that capital and O&M expenditures increase at higher capture rates.
The cost of the capture system and associated consumables increases at a lesser rate than that
of the amount of CO2 captured (i.e., a 10 percent increase from 90 to 99 percent capture). The
margin of error associated with the financial assumptions and cost scaling methodology
employed in this study indicate that with increasing capture rate in the low purity cases, the
COC is effectively the same. The reported minor increase in capital cost with increased capture
rate (up to 99 percent for sources with CO2 purity greater than 12 percent) has been validated
by independent modeling performed by the CCSI team at NETL and has been reported
independently in literature. [4] Exhibit 6-29 shows the error in the calculated capture system
BEC associated with the vendor’s quoted uncertainty rate (-25/+40 percent) alongside the
amount of CO2 captured in the cement case from 90 to 99 percent capture rate.
109
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-29. Cement capture system BEC and amount of CO 2 captured versus capture rate
110
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
to be included with equipment purchase, but catalyst makeup cost is calculated on a 3-year
replacement cycle. The auxiliary requirements for the FGD and SCR are scaled linearly from the
BBR4 Case B12B, adding 672 kW to the auxiliary load requirements for capture integration in
the representative cement plant. O&M costs for each cement sensitivity case are shown in
Exhibit 6-33 and Exhibit 6-34 for 99 and 90 percent capture cases, respectively, while owner’s
cost summaries for both cases are shown in Exhibit 6-32.
111
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-30. Capital costs for cement greenfield site with FGD and SCR and 99 percent CO 2 capture
Case: Cement with FGD and SCR Estimate Type: Conceptual
Representative Plant Size: 1.3 M tonnes/year Cost Base: Dec 2018
Item Equipment Material Labor Bare Erected Eng'g CM Contingencies Total Plant Cost
Description
No. Cost Cost Direct Indirect Cost H.O. & Fee Process Project $/1,000 $/tonnes/yr (CO2)
3 Feedwater & Miscellaneous BOP Systems
3.1 Feedwater System $658 $1,127 $564 $0 $2,349 $411 $0 $552 $3,311 $3
3.2 Water Makeup & Pretreating $1,633 $163 $925 $0 $2,722 $476 $0 $640 $3,837 $3
3.3 Other Feedwater Subsystems $305 $100 $95 $0 $500 $87 $0 $117 $704 $1
3.4 Industrial Boiler Package
$4,061 $0 $1,181 $0 $5,242 $917 $0 $1,232 $7,391 $6
w/Deaerator
3.5 Other Boiler Plant Systems $73 $27 $67 $0 $167 $29 $0 $39 $235 $0
3.6 NG Pipeline and Start-Up
$654 $28 $21 $0 $703 $123 $0 $165 $992 $1
System
3.7 Waste Water Treatment
$3,003 $0 $1,840 $0 $4,843 $848 $0 $1,138 $6,829 $6
Equipment
3.9 Miscellaneous Plant Equipment $98 $13 $50 $0 $161 $28 $0 $38 $227 $0
Subtotal $10,485 $1,458 $4,743 $0 $16,686 $2,920 $0 $3,921 $23,527 $20
4 Cement Kiln Accessories
4.1 Selective Catalytic Reduction
$5,660 $0 $3,225 $0 $8,885 $1,555 $0 $2,088 $12,528 $10
System
Subtotal $5,660 $0 $3,225 $0 $8,885 $1,555 $0 $2,088 $12,528 $10
5 Flue Gas Cleanup
5.1 Cansolv CO2 Removal System $58,671 $25,377 $53,292 $0 $137,340 $24,034 $23,348 $36,944 $221,667 $185
FGD Absorber Vessels &
5.2 $64,703 $0 $13,834 $0 $78,537 $13,744 $0 $18,456 $110,737 $92
Accessories
5.3 Other FGD $290 $0 $327 $0 $617 $108 $0 $145 $870 $1
5.4 CO2 Compression & Drying $17,147 $2,572 $5,733 $0 $25,452 $4,454 $0 $5,981 $35,887 $30
5.5 CO2 Compressor Aftercooler $137 $22 $59 $0 $218 $38 $0 $51 $307 $0
5.12 Gas Cleanup Foundations $0 $65 $57 $0 $122 $21 $0 $29 $172 $0
Subtotal $140,948 $28,036 $73,302 $0 $242,286 $42,400 $23,348 $61,607 $369,640 $309
7 Ductwork & Stack
7.3 Ductwork $0 $1,608 $1,117 $0 $2,725 $477 $0 $640 $3,842 $3
7.4 Stack $7,699 $0 $4,474 $0 $12,174 $2,130 $0 $2,861 $17,165 $14
7.5 Duct & Stack Foundations $0 $172 $204 $0 $376 $66 $0 $88 $530 $0
Subtotal $7,699 $1,779 $5,795 $0 $15,274 $2,673 $0 $3,589 $21,537 $18
9 Cooling Water System
9.1 Cooling Towers $1,426 $0 $441 $0 $1,867 $327 $0 $439 $2,632 $2
9.2 Circulating Water Pumps $147 $0 $10 $0 $157 $27 $0 $37 $221 $0
9.3 Circulating Water System Aux. $1,895 $0 $251 $0 $2,146 $376 $0 $504 $3,025 $3
9.4 Circulating Water Piping $0 $876 $794 $0 $1,670 $292 $0 $392 $2,355 $2
9.5 Make-up Water System $207 $0 $265 $0 $472 $83 $0 $111 $666 $1
112
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-31. Capital costs for cement greenfield site with FGD and SCR and 90 percent CO2 capture
Case: Cement with FGD and SCR Estimate Type: Conceptual
Representative Plant Size: 1.3 M tonnes/year Cost Base: Dec 2018
Item Equipment Material Labor Bare Erected Eng'g CM Contingencies Total Plant Cost
Description
No. Cost Cost Direct Indirect Cost H.O. & Fee Process Project $/1,000 $/tonnes/yr (CO2)
3 Feedwater & Miscellaneous BOP Systems
3.1 Feedwater System $616 $1,056 $528 $0 $2,199 $385 $0 $517 $3,101 $3
3.2 Water Makeup & Pretreating $1,543 $154 $874 $0 $2,571 $450 $0 $604 $3,626 $3
3.3 Other Feedwater Subsystems $280 $92 $87 $0 $459 $80 $0 $108 $647 $1
3.4 Industrial Boiler Package
$3,731 $0 $1,085 $0 $4,816 $843 $0 $1,132 $6,790 $6
w/Deaerator
3.5 Other Boiler Plant Systems $67 $25 $61 $0 $153 $27 $0 $36 $216 $0
3.6 NG Pipeline and Start-Up
$624 $27 $20 $0 $671 $117 $0 $158 $946 $1
System
113
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
114
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
115
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-32. Owners’ costs for cement cases with FGD and SCR
$/tonnes/yr $/tonnes/yr
Description $/1,000 $/1,000
(CO2) (CO2)
Pre-Production Costs 99% Capture 90% Capture
6 Months All Labor $2,484 $2 $2,420 $2
1-Month Maintenance Materials $436 $0 $421 $0
1-Month Non-Fuel Consumables $366 $0 $349 $0
1-Month Waste Disposal $11 $0 $11 $0
25% of 1-Month Fuel Cost at 100% CF $391 $0 $355 $0
2% of TPC $9,269 $8 $8,948 $8
Total $12,958 $11 $12,505 $11
Inventory Capital 99% Capture 90% Capture
60-day supply of fuel and consumables at 100% CF $3,768 $3 $3,457 $3
0.5% of TPC (spare parts) $2,317 $2 $2,237 $2
Total $6,086 $5 $5,694 $5
Other Costs 99% Capture 90% Capture
Initial Cost for Catalyst and Chemicals $0 $0 $0 $0
Land $30 $0 $30 $0
Other Owner's Costs $69,521 $58 $67,113 $62
Financing Costs $12,514 $10 $12,080 $11
TOC $564,581 $471 $544,839 $500
TASC Multiplier (Cement, 33 year) 1.054 1.054
TASC $594,983 $497 $574,178 $527
116
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-33. Initial and annual O&M costs for cement greenfield site with FGD and SCR at 99 percent capture
Case: Cement with FGD and SCR Cost Base: Dec 2018
117
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-34. Initial and annual O&M costs for cement greenfield site with FGD and SCR at 90 percent capture
Case: Cement with FGD and SCR Cost Base: Dec 2018
118
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
The COC for the greenfield FGD + SCR sensitivity cases at 99 and 90 percent capture are
presented in Exhibit 6-35 alongside corresponding values for the base case cement plants.
Exhibit 6-35. COC for 1.3 M tonnes/year cement greenfield cases (base cases and FGD + SCR cases)
The result of this sensitivity is that the total COC increases by $14.0/tonne CO2 and $15.3/tonne
CO2 for 99 and 90 percent capture, respectively, with the addition of FGD and SCR systems for
flue gas treating prior to AGR. At $78.0/tonne CO2, this cement sensitivity case with 90 percent
capture is the highest COC of any of the processes considered in this report. This COC sensitivity
is an approximation, as actual plant SOx/NOx concentrations were not available, and it is not
clear whether this sensitivity would be common occurrence in U.S. cement plants, or a special
isolated case due to raw materials used in a specific plant or region.
119
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
For plants with SOx and/or NOx contaminants above that which is acceptable at the inlet of the
AGR, an FGD and/or SCR system would be required to purify the stream before entering the CO2
capture unit. An approximation of the additional cost of adding these systems showed an
increase in greenfield COC by 23–25 percent. This approximation does not account for actual
SOx/NOx concentrations in the kiln off-gas, and could be substantially higher or lower,
depending on off-gas conditions and specific requirements of the AGR system deployed.
6.3 IRON/STEEL
According to the Environmental Protection Agency, in 2019 the industrial sector emitted 1.51 B
tonnes of CO2, representing 23 percent of U.S. GHG emissions. [50] The Iron and Steel industry
accounted for 4.8 percent or about 72 M tonnes of CO2 emissions in 2019. [6] Due to the large
amounts of emissions available for capture from the iron and steel industry, these facilities
present a great opportunity for the consideration of industrial decarbonization.
120
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Of the eight CO2 point sources listed by the Wiley Study, five have CO2 concentrations that
would have capture costs comparable to those in a typical coal-fired power plant flue gas
stream and are not included in this analysis. Only the three higher CO2 concentration streams,
the PPS, COG, and BFS are evaluated, as shown in Exhibit 6-36.
Personal communication with a former U.S. Steel Braddock, PA, facility employee indicated that
while the coke ovens are approximately five miles from the blast furnace, the COG is circulated
back to the blast furnace to preheat the incoming air. Therefore, these two streams are located
relatively close to one another and may be combined. Exhibit 6-37 is a simplified BFD of the plot
plan description of the Braddock steel mill.
5 Mile Distance
COKE BLAST
COKE OVEN GAS FOR PREHEATING AIR COG/BFS
OVENS FURNACE
121
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
• The representative BOF integrated steel mill has a production capacity of 2.54 M
tonnes/year
• The CO2 generated is 3,738,928 tonnes CO2/year at 100 percent CF
• There are three high purity point sources: COG, BFS, and COG PPS. The COG and BFS will
be combined into one stream due to plot plan and totals 1,864,388 tonnes CO2/year (at
100 percent CF); COG PPS will utilize its own separation and compression facility and
generates 1,874,540 tonnes CO2/year at 100 percent CF
• Since there are two separate capture systems, 4.6 operators are considered (i.e., 2.3
operators per capture system)
• As a low purity source, separation, compression, and cooling are required. Separation is
accomplished using a Cansolv AGR unit
• CO2 capture rates of 90 percent and 99 percent are evaluated
• The CO2 quality is based on the EOR pipeline standard as mentioned in the NETL QGESS
for CO2 Impurity Design Parameters [1]
COG 1 Cansolv
Stream CO2 Desired
3 4 Compressor 5 HX 6
Mixer Capture Usage
BFS 2 System
122
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
1 2 3 4 5 6 7
V-L Mole Fraction
AR 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
CH4 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
CO 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
CO2 0.2700 0.2100 0.2346 0.9879 0.9995 0.9995 0.0034
SO2 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
H2 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
H2O 0.0500 0.1000 0.0795 0.0121 0.0005 0.0005 0.0237
H2S 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
N2 0.6700 0.6800 0.6759 0.0000 0.0000 0.0000 0.9588
O2 0.0100 0.0100 0.0100 0.0000 0.0000 0.0000 0.0141
Total 1.0000 1.0000 1.0000 1.0000 1.0000 1.0000 1.0000
V-L Flowrate (kgmol/hr) 8,443 12,173 20,616 4,845 4,788 4,788 14,533
V-L Flowrate (kg/hr) 269,106 370,224 639,331 211,692 210,637 210,637 405,309
Temperature (°C) 100 300 219 31 80 30 38
Pressure (MPa, abs) 0.10 0.1 0.1 0.2 15.3 15.3 0.1
Steam Table Enthalpy (kJ/kg)A 3,700 3,593 3,638 8,793 8,758 8,755 309.0
Aspen Plus Enthalpy (kJ/kg)B -3,638 -3,217 -3,394 -8,961 -9,042 -9,195 -240.1
Density (kg/m3) 1.0 0.6 0.8 3.5 432.5 630.1 1.1
V-L Molecular Weight 31.9 30.4 31.0 43.7 44.0 44.0 27.9
V-L Flowrate (lbmol/hr) 18,613 26,837 45,450 10,681 10,555 10,555 32,041
V-L Flowrate (lb/hr) 593,278 816,205 1,409,483 466,701 464,375 464,375 893,553
Temperature (°F) 212 572 426 88 177 86 100
Pressure (psia) 14.7 14.7 14.7 28.9 2,216.9 2,214.7 14.8
Steam Table Enthalpy (Btu/lb)A 1,591 1,545 1,564 3,780 3,765 3,764 132.8
Aspen Plus Enthalpy (Btu/lb)B -1,564 -1,383 -1,459 -3,852 -3,887 -3,953 -103.2
Density (lb/ft3) 0.065 0.040 0.048 0.217 27.0 39.3 0.069
ASteam table reference conditions are 32.02°F & 0.089 psia
BAspen thermodynamic reference state is the component’s constituent elements in an ideal gas state at 25°C and 1 atm
123
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
1 2 3 4 5 6 7
V-L Mole Fraction
AR 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
CH4 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
CO 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
CO2 0.2700 0.2100 0.2346 0.9881 0.9995 0.9995 0.0322
SO2 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
H2 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
H2O 0.0500 0.1000 0.0795 0.0119 0.0005 0.0005 0.0237
H2S 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000
N2 0.6700 0.6800 0.6759 0.0000 0.0000 0.0000 0.9303
O2 0.0100 0.0100 0.0100 0.0000 0.0000 0.0000 0.0137
Total 1.0000 1.0000 1.0000 1.0000 1.0000 1.0000 1.0000
V-L Flowrate (kgmol/hr) 8,443 12,173 20,616 4,405 4,354 4,354 14,978
V-L Flowrate (kg/hr) 269,106 370,224 639,331 192,516 191,573 191,573 424,582
Temperature (°C) 100 300 219 31 80 30 38
Pressure (MPa, abs) 0.10 0.1 0.1 0.2 15.3 15.3 0.1
Steam Table Enthalpy (kJ/kg)A 3,700 3,593 3,638 8,793 8,758 8,755 691.0
Aspen Plus Enthalpy (kJ/kg)B -3,638 -3,217 -3,394 -8,960 -9,042 -9,195 -636.8
Density (kg/m3) 1.0 0.6 0.8 3.5 432.5 630.1 1.1
V-L Molecular Weight 31.9 30.4 31.0 43.7 44.0 44.0 28.3
V-L Flowrate (lbmol/hr) 18,613 26,837 45,450 9,712 9,599 9,599 33,021
V-L Flowrate (lb/hr) 593,278 816,205 1,409,483 424,424 422,347 422,347 936,044
Temperature (°F) 212 572 426 88 177 86 100
Pressure (psia) 14.7 14.7 14.7 28.9 2,216.9 2,214.7 14.8
Steam Table Enthalpy (Btu/lb)A 1,591 1,545 1,564 3,780 3,765 3,764 297.1
Aspen Plus Enthalpy (Btu/lb)B -1,564 -1,383 -1,459 -3,852 -3,887 -3,953 -273.8
Density (lb/ft3) 0.065 0.040 0.048 0.217 27.0 39.3 0.070
ASteam table reference conditions are 32.02°F & 0.089 psia
BAspen thermodynamic reference state is the component’s constituent elements in an ideal gas state at 25°C and 1 atm
In the same manner, the COG PPS stream is sent to the Cansolv CO2 capture system. Water and
solids recovered from the AGR process are sent to waste treatment. The CO2 stream is then
compressed with interstage cooling and after-cooled before reaching the EOR pipeline. Exhibit
124
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
6-41 shows the BFD for this process, and Exhibit 6-42 and Exhibit 6-43 show the stream table for
this process with 99 percent and 90 percent capture, respectively.
Cansolv
COG CO2 Desired
1 2 Compressor 3 HX 4
PPS Capture Usage
System
Exhibit 6-42. Iron/steel COG PPS stream table with 99 percent capture
1 2 3 4 5
V-L Mole Fraction
AR 0.0000 0.0000 0.0000 0.0000 0.0000
CH4 0.0000 0.0000 0.0000 0.0000 0.0000
CO 0.0000 0.0000 0.0000 0.0000 0.0000
CO2 0.2323 0.9875 0.9995 0.9995 0.0034
SO2 0.0000 0.0000 0.0000 0.0000 0.0000
H2 0.0000 0.0000 0.0000 0.0000 0.0000
H2O 0.0808 0.0125 0.0005 0.0005 0.0242
H2S 0.0000 0.0000 0.0000 0.0000 0.0000
N2 0.6768 0.0000 0.0000 0.0000 0.9581
O2 0.0101 0.0000 0.0000 0.0000 0.0142
Total 1.0000 1.0000 1.0000 1.0000 1.0000
125
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
1 2 3 4 5
V-L Mole Fraction
Temperature (°F) 572 88 177 86 100
Pressure (psia) 14.7 28.9 2,216.9 2,214.7 14.8
Steam Table Enthalpy (Btu/lb)A 1,561 3,781 3,765 3,764 135.1
Aspen Plus Enthalpy (Btu/lb)B -1,415 -3,853 -3,887 -3,953 -105.1
Density (lb/ft3) 0.041 0.217 27.0 39.3 0.069
ASteam table reference conditions are 32.02°F & 0.089 psia
BAspen thermodynamic reference state is the component’s constituent elements in an ideal gas state at 25°C and 1 atm
Exhibit 6-43. Iron/steel COG PPS stream table with 90 percent capture
1 2 3 4 5
V-L Mole Fraction
AR 0.0000 0.0000 0.0000 0.0000 0.0000
CH4 0.0000 0.0000 0.0000 0.0000 0.0000
CO 0.0000 0.0000 0.0000 0.0000 0.0000
CO2 0.2323 0.9878 0.9995 0.9995 0.0319
SO2 0.0000 0.0000 0.0000 0.0000 0.0000
H2 0.0000 0.0000 0.0000 0.0000 0.0000
H2O 0.0808 0.0122 0.0005 0.0005 0.0243
H2S 0.0000 0.0000 0.0000 0.0000 0.0000
N2 0.6768 0.0000 0.0000 0.0000 0.9300
O2 0.0101 0.0000 0.0000 0.0000 0.0138
Total 1.0000 1.0000 1.0000 1.0000 1.0000
126
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
1 2 3 4 5
V-L Mole Fraction
Temperature (°F) 572 88 177 86 100
Pressure (psia) 14.7 28.9 2,216.9 2,214.7 14.8
Steam Table Enthalpy (Btu/lb)A 1,561 3,781 3,765 3,764 297.3
Aspen Plus Enthalpy (Btu/lb)B -1,415 -3,853 -3,887 -3,953 -273.7
Density (lb/ft3) 0.041 0.217 27.0 39.3 0.070
ASteam table reference conditions are 32.02°F & 0.089 psia
BAspen thermodynamic reference state is the component’s constituent elements in an ideal gas state at 25°C and 1 atm
The performance summary for both 90 and 99 percent capture cases in the COG/BFS section of
the steel mill is provided in Exhibit 6-44, while that of the COG PPS section is shown in Exhibit
6-45.
Performance Summary
2.54 M tonnes steel/year with 90 2.54 M tonnes steel/year with 99
Item
percent CO2 capture (kWe) percent CO2 capture (kWe)
CO2 Capture Auxiliaries 4,800 5,400
Steam Boiler Auxiliaries 510 560
CO2 Compressor 14,660 16,120
Circulating Water Pumps 1,480 1,610
Cooling Tower Fans 770 830
Total Auxiliary Load 22,220 24,520
Performance Summary
2.54 M tonnes steel/year with 90 2.54 M tonnes steel/year with 99
Item
percent CO2 capture (kWe) percent CO2 capture (kWe)
CO2 Capture Auxiliaries 4,900 5,400
Steam Boiler Auxiliaries 520 570
CO2 Compressor 14,750 16,210
Circulating Water Pumps 1,490 1,620
Cooling Tower Fans 770 830
Total Auxiliary Load 22,430 24,630
127
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
128
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
for a hypothetical greenfield plant but could be estimated for each account by applying a
retrofit factor TPC as described in Section 3.3. As some O&M and owner’s costs are estimated
based on TPC, the retrofit TPC value was used to estimate the owner’s costs and O&M costs
presented in Exhibit 6-46 through Exhibit 6-52; thus, those values are indicative of a retrofit
installation.
$/tonnes/yr $/tonnes/yr
Description $/1,000 $/1,000
(CO2) (CO2)
Pre-Production Costs 99% Capture 90% Capture
6 Months All Labor $5,095 $3 $4,776 $3
1-Month Maintenance Materials $902 $0 $827 $0
1-Month Non-Fuel Consumables $802 $0 $750 $0
1-Month Waste Disposal $33 $0 $32 $0
25% of 1-Month Fuel Cost at 100% CF $0 $0 $0 $0
2% of TPC $19,171 $10 $17,151 $10
Total $26,003 $14 $23,536 $14
Inventory Capital
60-day supply of fuel and consumables at 100% CF $1,327 $1 $1,243 $1
0.5% of TPC (spare parts) $4,793 $3 $4,394 $3
Total $6,120 $3 $5,637 $3
Other Costs
Initial Cost for Catalyst and Chemicals $0 $0 $0 $0
Land $0 $0 $0 $0
Other Owner's Costs $143,780 $78 $131,820 $78
Financing Costs $25,880 $14 $23,728 $14
TOC $1,160,313 $627 $1,063,524 $632
TASC Multiplier (Iron/Steel, 33 year) 1.091 1.091
TASC $1,266,188 $684 $1,160,567 $690
129
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-47. Capital costs for iron/steel COG/BFS section retrofit with 99 percent capture
Case: Iron/Steel COG/BFS Section Estimate Type: Conceptual
Representative Plant Size: 2.54 M tonnes steel/year Cost Base: Dec 2018
Item Equipment Material Labor Bare Erected Eng'g CM Contingencies Total Plant Cost
Description
No. Cost Cost Direct Indirect Cost H.O. & Fee Process Project $/1,000 $/tonnes/yr (CO2)
3 Feedwater & Miscellaneous BOP Systems
3.1 Feedwater System $886 $1,519 $760 $0 $3,165 $554 $0 $744 $4,463 $2
3.2 Water Makeup & Pretreating $2,239 $224 $1,269 $0 $3,732 $653 $0 $877 $5,263 $3
3.3 Other Feedwater Subsystems $448 $147 $139 $0 $734 $128 $0 $173 $1,035 $1
3.4 Industrial Boiler Package
$5,968 $0 $1,735 $0 $7,703 $1,348 $0 $1,810 $10,861 $6
w/Deaerator
3.5 Other Boiler Plant Systems $108 $39 $99 $0 $246 $43 $0 $58 $347 $0
3.6 NG Pipeline and Start-Up
$808 $35 $26 $0 $869 $152 $0 $204 $1,226 $1
System
3.7 Waste Water Treatment
$4,113 $0 $2,521 $0 $6,633 $1,161 $0 $1,559 $9,353 $5
Equipment
3.9 Miscellaneous Plant
$109 $14 $56 $0 $179 $31 $0 $42 $253 $0
Equipment
Subtotal $14,680 $1,979 $6,604 $0 $23,263 $4,071 $0 $5,467 $32,801 $18
5 Flue Gas Cleanup
5.1 Cansolv CO2 Removal System $81,899 $35,424 $74,391 $0 $191,714 $33,550 $32,591 $51,571 $309,426 $168
5.4 CO2 Compression & Drying $22,324 $3,349 $7,464 $0 $33,136 $5,799 $0 $7,787 $46,722 $25
5.5 CO2 Compressor Aftercooler $196 $31 $84 $0 $312 $55 $0 $73 $440 $0
5.12 Gas Cleanup Foundations $0 $89 $78 $0 $166 $29 $0 $39 $234 $0
Subtotal $104,419 $38,893 $82,017 $0 $225,328 $39,432 $32,591 $59,470 $356,822 $193
7 Ductwork & Stack
7.3 Ductwork $0 $2,303 $1,600 $0 $3,903 $683 $0 $917 $5,503 $3
7.4 Stack $7,869 $0 $4,573 $0 $12,442 $2,177 $0 $2,924 $17,543 $10
7.5 Duct & Stack Foundations $0 $176 $209 $0 $386 $68 $0 $91 $544 $0
Subtotal $7,869 $2,479 $6,382 $0 $16,731 $2,928 $0 $3,932 $23,590 $13
9 Cooling Water System
9.1 Cooling Towers $1,990 $0 $615 $0 $2,605 $456 $0 $612 $3,673 $2
9.2 Circulating Water Pumps $213 $0 $15 $0 $228 $40 $0 $54 $321 $0
9.3 Circulating Water System Aux. $2,489 $0 $329 $0 $2,818 $493 $0 $662 $3,974 $2
9.4 Circulating Water Piping $0 $1,151 $1,042 $0 $2,193 $384 $0 $515 $3,092 $2
9.5 Make-up Water System $255 $0 $328 $0 $583 $102 $0 $137 $823 $0
9.6 Component Cooling Water
$179 $0 $138 $0 $317 $55 $0 $74 $447 $0
System
9.7 Circulating Water System
$0 $124 $207 $0 $331 $58 $0 $78 $467 $0
Foundations
Subtotal $5,126 $1,275 $2,674 $0 $9,076 $1,588 $0 $2,133 $12,797 $7
11 Accessory Electric Plant
11.2 Station Service Equipment $3,192 $0 $274 $0 $3,466 $606 $0 $814 $4,887 $3
130
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-48. Capital costs for iron/steel COG PPS retrofit with 99 percent capture
Case: Iron/Steel COG PPS Section Estimate Type: Conceptual
Representative Plant Size: 2.54 M tonnes steel/year Cost Base: Dec 2018
Item Equipment Material Labor Bare Erected Eng'g CM Contingencies Total Plant Cost
Description
No. Cost Cost Direct Indirect Cost H.O.& Fee Process Project $/1,000 $/tonnes/yr (CO2)
3 Feedwater & Miscellaneous BOP Systems
3.1 Feedwater System $890 $1,525 $763 $0 $3,177 $556 $0 $747 $4,480 $2
3.2 Water Makeup & Pretreating $2,249 $225 $1,274 $0 $3,748 $656 $0 $881 $5,284 $3
3.3 Other Feedwater Subsystems $450 $148 $140 $0 $738 $129 $0 $173 $1,040 $1
3.4 Industrial Boiler Package
$5,998 $0 $1,744 $0 $7,741 $1,355 $0 $1,819 $10,915 $6
w/Deaerator
3.5 Other Boiler Plant Systems $109 $40 $99 $0 $248 $43 $0 $58 $349 $0
3.6 NG Pipeline and Start-Up System $811 $35 $26 $0 $872 $153 $0 $205 $1,229 $1
3.7 Waste Water Treatment Equipment $4,144 $0 $2,540 $0 $6,683 $1,170 $0 $1,571 $9,424 $5
3.9 Miscellaneous Plant Equipment $109 $14 $56 $0 $179 $31 $0 $42 $253 $0
Subtotal $14,759 $1,986 $6,641 $0 $23,387 $4,093 $0 $5,496 $32,975 $18
5 Flue Gas Cleanup
5.1 Cansolv CO2 Removal System $81,456 $35,233 $73,989 $0 $190,678 $33,369 $32,415 $51,292 $307,755 $166
5.4 CO2 Compression & Drying $22,399 $3,360 $7,489 $0 $33,249 $5,819 $0 $7,813 $46,881 $25
131
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
132
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-49. Capital costs for iron/steel COG/BFS section retrofit with 90 percent capture
Case: Iron/Steel COG/BFS Section Estimate Type: Conceptual
Representative Plant Size: 2.54 M tonnes steel/year Cost Base: Dec 2018
Item Equipment Material Labor Bare Erected Eng'g CM Contingencies Total Plant Cost
Description
No. Cost Cost Direct Indirect Cost H.O. & Fee Process Project $/1,000 $/tonnes/yr (CO2)
3 Feedwater & Miscellaneous BOP Systems
3.1 Feedwater System $830 $1,423 $711 $0 $2,964 $519 $0 $697 $4,179 $2
3.2 Water Makeup & Pretreating $2,116 $212 $1,199 $0 $3,527 $617 $0 $829 $4,972 $3
3.3 Other Feedwater Subsystems $411 $135 $128 $0 $674 $118 $0 $158 $951 $1
3.4 Industrial Boiler Package
$5,483 $0 $1,594 $0 $7,077 $1,238 $0 $1,663 $9,979 $6
w/Deaerator
3.5 Other Boiler Plant Systems $100 $36 $90 $0 $226 $40 $0 $53 $319 $0
3.6 NG Pipeline and Start-Up
$772 $33 $25 $0 $830 $145 $0 $195 $1,170 $1
System
3.7 Waste Water Treatment
$3,935 $0 $2,412 $0 $6,346 $1,111 $0 $1,491 $8,948 $5
Equipment
3.9 Miscellaneous Plant
$107 $14 $54 $0 $175 $31 $0 $41 $247 $0
Equipment
Subtotal $13,753 $1,853 $6,214 $0 $21,819 $3,818 $0 $5,127 $30,765 $18
5 Flue Gas Cleanup
5.1 Cansolv CO2 Removal System $71,707 $31,016 $65,134 $0 $167,857 $29,375 $28,536 $45,154 $270,921 $161
5.4 CO2 Compression & Drying $21,067 $3,160 $7,044 $0 $31,272 $5,473 $0 $7,349 $44,093 $26
5.5 CO2 Compressor Aftercooler $182 $29 $78 $0 $288 $50 $0 $68 $406 $0
5.12 Gas Cleanup Foundations $0 $89 $78 $0 $166 $29 $0 $39 $234 $0
Subtotal $92,956 $34,294 $72,333 $0 $199,583 $34,927 $28,536 $52,609 $315,655 $188
7 Ductwork & Stack
7.3 Ductwork $0 $2,303 $1,600 $0 $3,903 $683 $0 $917 $5,503 $3
7.4 Stack $7,883 $0 $4,581 $0 $12,464 $2,181 $0 $2,929 $17,575 $10
7.5 Duct & Stack Foundations $0 $175 $208 $0 $384 $67 $0 $90 $541 $0
Subtotal $7,883 $2,478 $6,389 $0 $16,751 $2,931 $0 $3,936 $23,619 $14
9 Cooling Water System
9.1 Cooling Towers $1,874 $0 $580 $0 $2,454 $429 $0 $577 $3,460 $2
9.2 Circulating Water Pumps $199 $0 $14 $0 $213 $37 $0 $50 $301 $0
9.3 Circulating Water System Aux. $2,370 $0 $314 $0 $2,684 $470 $0 $631 $3,784 $2
9.4 Circulating Water Piping $0 $1,096 $993 $0 $2,089 $365 $0 $491 $2,945 $2
9.5 Make-up Water System $246 $0 $316 $0 $562 $98 $0 $132 $792 $0
9.6 Component Cooling Water
$171 $0 $131 $0 $302 $53 $0 $71 $426 $0
System
9.7 Circulating Water System
$0 $119 $198 $0 $317 $55 $0 $74 $446 $0
Foundations
Subtotal $4,860 $1,215 $2,544 $0 $8,619 $1,508 $0 $2,026 $12,153 $7
11 Accessory Electric Plant
11.2 Station Service Equipment $3,060 $0 $262 $0 $3,322 $581 $0 $781 $4,684 $3
133
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-50. Capital costs for iron/steel COG PPS retrofit with 90 percent capture
Case: Iron/Steel COG PPS Section Estimate Type: Conceptual
Representative Plant Size: 2.54 M tonnes steel/year Cost Base: Dec 2018
Item Equipment Material Labor Bare Erected Eng'g CM Contingencies Total Plant Cost
Description
No. Cost Cost Direct Indirect Cost H.O. & Fee Process Project $/1,000 $/tonnes/yr (CO2)
3 Feedwater & Miscellaneous BOP Systems
3.1 Feedwater System $833 $1,428 $714 $0 $2,975 $521 $0 $699 $4,195 $2
3.2 Water Makeup & Pretreating $2,125 $212 $1,204 $0 $3,541 $620 $0 $832 $4,993 $3
3.3 Other Feedwater Subsystems $413 $136 $129 $0 $678 $119 $0 $159 $956 $1
3.4 Industrial Boiler Package w/Deaerator $5,510 $0 $1,602 $0 $7,112 $1,245 $0 $1,671 $10,028 $6
3.5 Other Boiler Plant Systems $100 $36 $91 $0 $227 $40 $0 $53 $321 $0
3.6 NG Pipeline and Start-Up System $774 $33 $25 $0 $832 $146 $0 $196 $1,173 $1
3.7 Waste Water Treatment Equipment $3,965 $0 $2,430 $0 $6,396 $1,119 $0 $1,503 $9,018 $5
3.9 Miscellaneous Plant Equipment $107 $14 $54 $0 $175 $31 $0 $41 $247 $0
Subtotal $13,827 $1,860 $6,249 $0 $21,937 $3,839 $0 $5,155 $30,931 $18
5 Flue Gas Cleanup
5.1 Cansolv CO2 Removal System $74,921 $32,406 $68,053 $0 $175,379 $30,691 $29,814 $47,177 $283,062 $168
5.4 CO2 Compression & Drying $21,146 $3,172 $7,070 $0 $31,389 $5,493 $0 $7,376 $44,258 $26
5.5 CO2 Compressor Aftercooler $182 $29 $78 $0 $289 $51 $0 $68 $408 $0
134
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
135
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
The initial and annual O&M costs for an iron/steel retrofit site were calculated and are shown in
Exhibit 6-51 and Exhibit 6-52 for 99 percent and 90 percent capture, respectively, while Exhibit
6-53 shows the retrofit COC of the representative iron/steel plants at both capture rates.
Exhibit 6-51. Initial and annual O&M costs for iron/steel site with 99 percent capture
Case: Iron/Steel Cost Base: Dec 2018
136
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-52. Initial and annual O&M costs for an iron/steel retrofit site with 90 percent capture
Case: Iron/Steel Cost Base: Dec 2018
Component 99% capture COC, $/tonne CO2 90% capture COC, $/tonne CO2
Capital 27.8 28.0
Fixed 9.3 9.5
Variable 5.6 5.7
Purchased Power and Fuel 22.6 22.6
Total COC 65.4 65.9
137
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
As the cost of capturing CO2 is a normalized cost (i.e., $/tonne CO2), higher capture rates appear
to cost less than lower capture rates. Comparing the true capital and O&M costs (i.e., not as
normalized costs) shows that capital and O&M expenditures increase at higher capture rates.
The cost of the capture system and associated consumables increases at a lesser rate than that
of the amount of CO2 captured (i.e., a 10 percent increase from 90 to 99 percent capture). The
margin of error associated with the financial assumptions and cost scaling methodology
employed in this study indicate that with increasing capture rate in the low purity cases, the
COC is effectively the same. The reported minor increase in capital cost with increased capture
rate (up to 99 percent for sources with CO2 purity greater than 12 percent) has been validated
by independent modeling performed by the CCSI team at NETL and has been reported
independently in literature. [4] Exhibit 6-55 shows the error in the calculated capture system
BEC associated with the vendor’s quoted uncertainty rate (-25/+40 percent) alongside the
amount of CO2 captured in the cement case from 90 to 99 percent capture rate.
138
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 6-55. Iron/steel capture system BEC and amount of CO 2 captured versus capture rate
139
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
7 ECONOMIC ANALYSIS
7.1 ECONOMIC RESULTS
Exhibit 7-1 shows the COC results of each industry considered in this study. When comparing
high purity to low purity industrial sources, the former show lower COCs, as they require less
equipment (i.e., no capture unit or boiler) and consumables (i.e., no solvents or NG fuel and less
purchased power) than the low purity industrial sources. The low purity sources higher COC is
notable not only in the additional capital costs, but in the O&M and purchased power and fuel
costs as well. These cases require an industrial boiler, which is fueled by purchased NG, and the
CO2 capture systems add consumables and additional electrical auxiliary loads that increase
purchased power costs over that of high purity sources.
Evaluating the capital portion of the COC for each source shows the effects of capital intensity.
The financial assumptions assumed in this report are industry specific. For instance, ethanol
financial factors suggest that ethanol facilities would incur higher capital intensity compared to
the cement, steel, and refining industries due to the return on equity and financing scenarios
prevalent within the ethanol production market. Another interesting observation regarding
capital intensity is the relationship between the EO and ethanol results. Although ethanol
presents a higher amount available CO2 for capture, its capital and power costs are higher than
EO. This is counter-intuitive to the notion of economies of scale but illustrates the role that
capture stream conditions (i.e., temperature, pressure, composition, and flow rate) plays on
capture costs. In the ethanol case, the pure CO2 stream must first be cooled, due to the high
temperature from the fermentation process, and then has a higher compression ratio
(compared to the EO case) to reach the required pipeline pressure of 2,200 psig. The additional
140
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
stage of compression and the additional HX impact the auxiliary load as well as the capital
expenditure.
Lastly, the CO2 available for capture is both process and market dependent. The process
emissions detailed for each case throughout the report are average constants; however, as each
individual market dictates production capacities, the total CO2 available from a plant could, with
increasing market demand (e.g., plant expansions, increased CF, etc.), drive down the COC for
that representative case. This trend could be estimated from the results of the plant size
sensitivities for each case, but it should be noted that these estimates, and the sensitivities to
plant size for each case, are dependent upon the assumption that equipment is available at any
and every capacity or rating. However, equipment is often manufactured in discrete sizes, which
would possibly affect the advantages of economies of scale and skew the results of the
estimates provided herein. A general observation made under the assumptions of this report is
demonstrated in the normalized COC elements and the total normalized COCs calculated: more
CO2 available results in lower normalized costs and realizes economies of scale.
141
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 7-2. Cost and performance summary comparison – high purity cases
Industrial Source Facilities
Ammonia EO Ethanol NGP CTL GTL
PERFORMANCE
Capacity Factor 85% 85% 85% 85% 85% 85%
394,000 364,500 50 M gallons 330 MMSCFD 50,000 barrels 50,000 barrels
Representative Plant Size
tonnes EO/year tonnes EO/year ethanol/year natural gas F-T liquids/day F-T liquids/day
CO₂ Captured (at 85% CF), tonnes/yearA 413,163 103,275 121,588 551,815 7,431,825 1,579,952
CO₂ Captured (at 85% CF), tonnes/hour 47 12 14 63 848 180
CO₂ Compressor Load, kW 5,770 1,180 1,810 6,010 43,480 6,700
Cooling Water Flowrate, gpm 2,994 673 1,098 3,479 25,172 3,823
Cooling Tower Duty, MMBtu/hour 30 7 11 35 252 38
COST
TPC, $/1,000 37,347 16,636 20,187 46,690 162,840 49,170
BEC 26,487 11,799 14,317 33,114 115,490 34,872
Home Office Expenses 4,635 2,065 2,505 5,795 20,211 6,103
Project Contingency 6,225 2,773 3,364 7,782 27,140 8,195
Process Contingency 0 0 0 0 0 0
TOC, $M 46 20 25 57 197 60
TOC, $/1,000 45,587 20,385 24,672 56,764 196,924 59,661
Owner's Costs 8,240 3,749 4,485 10,074 34,084 10,491
TASC, $/1,000 47,162 20,892 25,840 58,977 207,583 62,890
Capital Costs, $/tonne CO2 6.1 9.4 14.1 6.2 2.0 2.9
Fixed Costs, $/tonne CO2 3.9 9.8 9.2 3.4 0.7 1.2
Variable Costs, $/tonne CO2 2.7 1.7 1.7 1.5 0.3 0.3
Purchased Power and/or Fuel, $/tonne CO2 6.3 5.2 6.8 5.0 2.6 1.9
COC (ex. T&S), $/tonne CO2 19.0 26.0 31.8 16.1 5.6 6.4
ADue to simplification of BFDs and stream tables throughout the body of the report where minor process streams are omitted, actual CO2 captured as calculated in summary
tables may be slightly less than that calculated at the capture rates applied in each case. This is due primarily to trace amounts of CO2 entrained in water vapor generated during
dehydration. Such differences, where they appear, are not expected to have any meaningful impact on the key results of this study, as they account for less than 1 percent of the
CO2 generated by the emitter.
142
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit 7-3. Cost and performance summary comparison – low purity cases
Industrial Source Facilities
Iron/Steel Iron/Steel
Refinery H2 99% Refinery H2 90% Cement 99% Cement 90%
(Retrofit) 99% (Retrofit) 90%
PERFORMANCE
Capacity Factor 85% 85% 85% 85% 85% 85%
87,000 tonnes 87,000 tonnes 1.29 M tonnes 1.29 M tonnes 2.54 M tonnes 2.54 M tonnes
Representative Plant Size
H2/year H2/year cement/year cement/year steel/year steel/year
CO₂ Captured (at 85% CF), tonnes/yearA 340,550 309,548 1,017,920 925,793 3,145,352 2,860,681
CO₂ Captured (at 85% CF), tonnes/hour 39 35 116 106 359 327
CO₂ Compressor Load, kW 3,470 3,160 10,460 9,570 32,330 29,410
Cooling Water Flowrate, gpm 11,367 9,757 50,096 46,356 154,873 143,309
Cooling Tower Duty, MMBtu/hour 11 10 20 18 61 56
COST
TPC, $/1,000 130,630 127,184 338,949 322,871 958,530 878,803
BEC 85,303 82,950 220,519 210,137 621,718 571,122
Home Office Expenses 14,928 14,516 38,591 36,774 108,801 99,946
Project Contingency 21,772 21,197 56,491 53,812 159,755 146,467
Process Contingency 8,627 8,520 23,348 22,148 68,257 61,268
TOC, $M 159 155 414 394 1,160 1,064
TOC, $/1,000 159,244 154,978 413,960 394,192 1,160,313 1,063,524
Owner's Costs 28,614 27,794 75,011 71,320 201,783 184,720
TASC, $/1,000 164,929 160,510 436,252 415,418 1,266,188 1,160,567
Capital Costs, $/tonne CO2 21.3 22.8 21.8 22.8 27.8 28.0
Fixed Costs, $/tonne CO2 14.4 15.6 10.6 11.1 9.3 9.5
Variable Costs, $/tonne CO2 5.1 5.3 5.9 6.1 5.6 5.7
Purchased Power and/or Fuel, $/tonne CO2 16.5 16.2 22.6 22.6 22.6 22.6
COC (ex. T&S), $/tonne CO2 57.3 59.9 60.8 62.7 65.4 65.9
ADue to simplification of BFDs and stream tables throughout the body of the report where minor process streams are omitted, actual CO2 captured as calculated in summary
tables may be slightly less than that calculated at the capture rates applied in each case. This is due primarily to trace amounts of CO2 entrained in water vapor generated during
dehydration. Such differences, where they appear, are not expected to have any meaningful impact on the key results of this study, as they account for less than 1 percent of the
CO2 generated by the emitter.
143
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
144
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
The results show that changing financial assumptions can have a very large effect on the COC. In
the high purity cases, the largest change when varying the CCF over a range of 5–35 percent is
observed in the ethanol case, where an increase of $60.9/tonne CO2 is noted. In the low purity
cases, the effect is larger, as the low purity cases require more capital investment due to the
need for AGR equipment. The largest COC increase in the low purity cases when varying the CCF
occurs in the refinery hydrogen cases, where a $140.3/tonne CO2 change in the COC is observed
for the 99 percent capture case and a $150.2/tonne CO2 increase is noted in the 90 percent
capture case.
The CCFs used for the high purity and low purity cases, details of which have been given
previously in Section 3.2, are representative of a project-specific CCF in each individual
industrial sector. In addition to the industrial sectors’ market influences on CCF, the maturity of
a technology, specifically a capture technology like the AGR units employed in this study, may
also affect the CCF. As capture systems are becoming more prevalent, and the project learning
curve has improved, the low end of the CCF sensitivity curve demonstrated in this analysis may
be a more reasonable representation.
145
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Because the retrofit factors in this study are applied as a multiplier to TPC, the effect of varying
those factors across a range of values is an increasing COC with increasing retrofit factor for all
cases. An interesting observation from this sensitivity analysis is the differing slopes of the lines
between the low purity and high purity cases, meaning that the retrofit factors applied do not
have equal magnitude of effect on all cases. For instance, the change in COC for the high purity
cases ranged $3.3–7.1/tonne CO2 with increasing retrofit factor, whereas that of the low purity
cases ranged $11.9–13.3/tonne CO2. This is due to the higher capital costs required for purifying
the CO2 prior to compression creating a larger TPC, which is the figure that is affected by the
addition of the retrofit difficulty factor.
146
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
147
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
148
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
149
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
8 CONCLUSION
Nine different industrial sources were examined in this study: ammonia, EO, ethanol, NGP, CTL,
GTL, refinery hydrogen, cement, and iron/steel. Plant sizes were chosen based on different
factors, including representative plant sizes expected to be built or already built in the industry
(ammonia, refinery hydrogen), plant sizes representative of most of the production for the
industry (ethanol, steel/iron, EO, cement), or plant sizes that would justify the addition of
capture equipment (NGP). Plant sizes for CTL and GTL were determined based on those
presented in previous NETL studies. Both greenfield and retrofit application costs were
determined. The retrofit costs were derived by application of a retrofit factor to calculated total
greenfield plant cost.
The results of this study show that CTL gives the lowest greenfield COC for the CO 2 product, a
value of $5.6/tonne. This result is driven by the highly pure CO2 sources produced from the CTL
plant, as well as the largest amount of CO2 available for capture across the cases considered.
This combination of high availability coupled with high purity results in the lowest COC. The
costliest option for capturing CO2 in the group of industrial plants evaluated is iron/steel
production, with a retrofit cost of $65.4/tonne CO2 and $65.9/tonne CO2 at 99 and 90 percent
capture rates, respectively. The low purity CO2 emission streams from iron and steel mills
require purification equipment to attain EOR pipeline standards.
The greenfield COCs for the remaining cases fall in between the maximum and minimum cases
as follows: GTL at $6.4/tonne, NGP at $16.1/tonne, ammonia at $19.0/tonne, EO at 26.0/tonne,
ethanol at $31.8/tonne, refinery hydrogen with 99 percent capture at $57.3/tonne and with 90
percent capture at $59.9/tonne, and finally, cement at $60.8/tonne and $62.7/tonne for 99 and
90 percent capture, respectively. The assumed CO2 concentrations for GTL, NGP, EO, ammonia,
and ethanol were relatively high purity, either equivalent to or nearly the same purity as the
lowest-COC CTL case. The reason for the increasing COC given similar purity is related to the
amount of CO2 available for capture, or economies of scale.
Economies of scale have a notable impact when comparing 99 and 90 percent capture rates in
the low purity cases. On a normalized (i.e., $/tonne CO2) basis, COC appears lower for higher
capture rates in the refinery hydrogen, cement, and iron/steel analyses. This is also indicated in
the plant size sensitivity analyses for each low purity case. As discussed in Section 6.1.8, Section
6.2.8, and Section 6.3.8, capital and O&M costs rise with increasing capture rates, but as there is
more CO2 captured, those costs result in a lower normalized costs at higher capture rates as
presented. It is important to note that given the margin of error associate with the AACE Class 4
estimates applied in this study, and the margin of error assigned to the quotation from the
capture system vendor (-25/+40 percent), the change in normalized cost from 90 to 99 percent
is insignificant.
Sensitivity analyses of retrofit factor and purchased power price show minimal change in the
COC for all cases. The most noticeable sensitivity effect is observed with plant size (economy of
scale). For all cases, as the plant size is increased and, therefore, the amount of CO2 available for
capture increased, the COC decreased. The largest effect is observed with the iron/steel plant
size sensitivity, where the COC increased by $36.9/tonne CO2 and $37.6/tonne CO2, for 99 and
150
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
90 percent capture cases, respectively, was observed when plant size was varied over the range
of 0.5–6.8 M tonnes of steel per year. The base case production was 2.54 M tonnes of steel per
year. All sensitivity analyses were evaluated in isolation, and it is possible that if individual
design assumption changes were considered in combination, impacts on the COCs would
potentially differ from the additive values of each change in design assumption.
CO2 purity, as expected, plays a large role in the normalized COC; however, the amount of CO2
and, therefore, the varying economies of scale from one industrial process to another, also has a
dramatic effect on the cost of capturing CO2. This analysis evaluated potential decarbonization
opportunities in representative industrial plant applications, and the results show that capturing
CO2 can be cost-effective in the industrial sector, especially when a facility has two specific
emissions stream characteristics: 1) high CO2 purity so that further purification is not required,
and (2) large amounts of CO2 available.
151
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
9 FUTURE WORK
Future work in this area should look to plants with the characteristics of relatively high CO2
purity and large CO2 supply to expand upon the findings in the report. Potential
recommendations include plants where CO2 removal is inherent to the base plant process. A
perfect example of this is ammonia and urea production, where not only is CO2 removal crucial
for maximizing ammonia synthesis loop efficiency and, therefore, production, but also reuse of
the CO2 for producing urea justifies this removal and recycle. The following items are potential
future work that could expand on the analysis presented in this study.
152
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
153
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
10 REFERENCES
[1] NETL, "Quality Guidelines for Energy System Studies: CO2 Impurity Design
Parameters," U.S. DOE/NETL, Pittsburgh, 2019.
[2] Shell, Proprietary Quote: CO2 Capture System, 2021.
[3] NETL, "Quality Guidelines for Energy System Studies: Capital Cost Scaling
Methodology: Revision 4 Report," U.S. DOE/NETL, Pittsburgh, 2019.
[4] Y. Du, T. Gao, G. T. Rochelle and A. S. Bhown, "Zero- and negative-
emissions fossil-fired power plants using CO2 capture by conventional
aqueous amines," International Journal of Greenhouse Gas Control, vol.
111, October 2021.
[5] NETL, "Cost and Performance Baseline for Fossil Energy Plants Volume 1:
Bituminous Coal and Natural Gas to Electricity," U.S. DOE/NETL, Pittsburgh,
2022.
[6] EPA, "Facility Level Information on Greenhouse Gases Tool (FLIGHT)," EPA,
2020. [Online]. Available:
https://ghgdata.epa.gov/ghgp/main.do#/facility/?q=Find%20a%20Facilit
y%20or%20Location&st=&bs=&et=&fid=&sf=11001100&lowE=-
20000&highE=23000000&g1=1&g2=0&g3=0&g4=0&g5=0&g6=0&g7=0&g8=
0&g9=0&g10=0&g11=0&g12=0&s1=0&s2=0&s3=1&s4=0&s5=0&s6=0&s7=0&s
8=0&s9=0&s10=0. [Accessed 3 September 2021].
[7] NETL, "Quality Guidelines for Energy System Studies: Carbon Dioxide
Transport and Storage Costs in NETL Studies," U.S. DOE/NETL, Pittsburgh,
2019.
[8] NETL, "Quality Guidelines for Energy System Studies: Process Modeling
Design Parameters," U.S. DOE/NETL, Pittsburgh, 2019.
[9] NETL, "Quality Guidelines for Energy System Studies: Cost Estimation
Methodology for NETL Assessments of Power Plant Performance," U.S.
DOE/NETL, Pittsburgh, 2019.
[10] AACE International, Cost Estimate Classification System – As Applied in
Engineering, Procurement, and Construction for the Process Industries;
TCM Framework 7.3 – Cost Estimating and Budgeting, AACE International,
2005.
[11] Chemical Engineering, Chemical Engineering Plant Cost Index, Access
Intelligence, LLC, Ed., 2021.
154
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
155
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
156
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
157
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
158
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
The carbon balance for the ammonia case is shown in Exhibit A-2.
The carbon balance for the natural gas processing (NGP) case is shown in Exhibit A-3.
The carbon balance for the ethylene oxide (EO) case is shown in Exhibit A-4.
iCarbon balances may show carbon content of minor process streams, including the CO2 entrained in the water vapor
vent from the TEG dehydration system and CO2 entrained in process water knockouts, that are not represented in the
block flow diagrams throughout the report body. These process streams were omitted from the report body for simplicity
and brevity. Cases where this simplification applies include ammonia, NGP, refinery H 2, iron/steel, and cement.
159
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
The carbon balance for the coal-to-liquids (CTL) case is shown in Exhibit A-5.
The carbon balance for the gas-to-liquids (GTL) case is shown in Exhibit A-6.
The carbon balance for the refinery hydrogen case with 99 percent capture is shown in Exhibit
A-7.
Exhibit A-7. Refinery hydrogen case with 99 percent capture carbon balance
Carbon In Carbon Out
kg/hr (lb/hr) kg/hr (lb/hr)
SMR Off-Gas Stream 16,102 (35,499) CO2 Captured Stream 12,480 (27,513)
Amine Recycle 405 (893) TEG Vent 1 (2)
Gas to PSA 3,543 (7,812)
Recycle 378 (832)
Process Knockout Entrainment 106 (233)
Total 16,507 (36,392) Total 16,507 (36,392)
The carbon balance for the refinery hydrogen case with 90 percent capture is shown in Exhibit
A-8.
160
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit A-8. Refinery hydrogen case with 90 percent capture carbon balance
Carbon In Carbon Out
kg/hr (lb/hr) kg/hr (lb/hr)
SMR Off-Gas Stream 16,102 (35,499) CO2 Captured Stream 11,343 (25,008)
Amine Recycle 368 (811) TEG Vent 6 (14)
Gas to PSA 4,675 (10,307)
Recycle 378 (832)
Process Knockout Entrainment 67 (149)
Total 16,470 (36,310) Total 16,470 (36,310)
The carbon balance for the iron/steel case coke oven gas (COG)/blast furnace stove (BFS) stream
with 99 percent capture is shown in Exhibit A-9.
Exhibit A-9. Iron/steel case COG/BFS stream with 99 percent capture carbon balance
Carbon In Carbon Out
kg/hr (lb/hr) kg/hr (lb/hr)
COG Stream 27,380 (60,363) CO2 Captured Stream 57,475 (126,710)
BFS Stream 30,704 (67,690) TEG Vent 10 (23)
Clean Flue Gas 599 (1,320)
Total 58,084 (128,053) Total 58,084 (128,053)
The carbon balance for the iron/steel case COG/BFS stream with 90 percent capture is shown in
Exhibit A-10.
Exhibit A-10. Iron/steel case COG/BFS stream with 90 percent capture carbon balance
Carbon In Carbon Out
kg/hr (lb/hr) kg/hr (lb/hr)
COG Stream 27,380 (60,363) CO2 Captured Stream 52,273 (115,242)
BFS Stream 30,704 (67,690) TEG Vent 9 (21)
Clean Flue Gas 5,802 (12,790)
Total 58,084 (128,053) Total 58,084 (128,053)
The carbon balance for the steel case COG power plant stack (PPS) stream with 99 percent
capture is shown in Exhibit A-11.
161
COST OF CAPTURING CO2 FROM INDUSTRIAL SOURCES
Exhibit A-11. Steel case COG PPS stream with 99 percent capture carbon balance
Carbon In Carbon Out
kg/hr (lb/hr) kg/hr (lb/hr)
COG PPS Stream 58,400 (128,751) CO2 Captured Stream 57,788 (127,400)
TEG Vent 10 (23)
Clean Flue Gas 602 (1,328)
Total 58,400 (128,751) Total 58,400 (128,751)
The carbon balance for the steel case COG PPS stream with 90 percent capture is shown in
Exhibit A-12.
Exhibit A-12. Steel case COG PPS stream with 90 percent capture carbon balance
Carbon In Carbon Out
kg/hr (lb/hr) kg/hr (lb/hr)
COG PPS Stream 58,400 (128,751) CO2 Captured Stream 52,558 (115,870)
TEG Vent 9 (21)
Clean Flue Gas 5,833 (12,860)
Total 58,400 (128,751) Total 58,400 (128,751)
The carbon balance for the cement 99 percent capture case is shown in Exhibit A-13.
The carbon balance for the cement 90 percent capture case is shown in Exhibit A-14.
162
www.netl.doe.gov
Albany, OR • Anchorage, AK • Morgantown, WV • Pittsburgh, PA • Sugar Land, TX
(800) 553-7681