P&MSP2010 06 MS-Project
P&MSP2010 06 MS-Project
Microsoft Project
Emanuele Della Valle
http://home.dei.polimi.it/dellavalle
Lecturer: Dario Cerizza
Credits 2
Session 5 Review
Microsoft Project Fundamentals
Activities Organization
R
Resources D
Definition
fi iti and
d All
Allocation
ti
Resource Leveling
Project Control
• Covered in Lesson 9 – Project Control
Scheduling Fundamentals
Scheduling Techniques
• Network Diagrams
• Bar Charts
Schedule Optimization Techniques
Mythical Man
Man-Month
Month
Session 5 Review
Microsoft Project Fundamentals
Activities Organization
R
Resources D
Definition
fi iti and
d All
Allocation
ti
Resource Leveling
Project Progress Update
Note: by default,
default the tables show only some columns.
columns To add
more columns: Right-click on a column and select insert column
1. View
2. Resource Sheet
Session 5 Review
Microsoft Project Fundamentals
Activities Organization
R
Resources D
Definition
fi iti and
d All
Allocation
ti
Resource Leveling
Project Progress Update
Dependency
p y
Relationships
A FS + lag
B
time
A FS - lead
B
time
Lags (positive)
Lead (negative)
Critical Path
Slack Times
Session 5 Review
Microsoft Project Fundamentals
Activities Organization
R
Resources D
Definition
fi iti and
d All
Allocation
ti
Resource Leveling
Project Progress Update
Unit
• Allocation is expressed by the time of the resource
d d
dedicatedd to the
h specific
f task
k
• i.e.: Mark is allocated the 30% of his time on Task1
W k
Work
• Allocation is expressed by total time that the resources
will dedicate to a task
• i.e.: Mark will work 40 hours on Task2
Costs
C t are calculated
l l t d automatically
t ti ll
based on the std cost defined
Work [t]
Work[t ]
Units[%] *100
Duration[t ]
Units [%] Duration [t]
1.
1 From Gantt Chart view
2. Right click on any column
3. Insert Column
4
4. C t
Cost
1. View
2. Table
3
3. Costs
Session 5 Review
Microsoft Project Fundamentals
Activities Organization
R
Resources D
Definition
fi iti and
d All
Allocation
ti
Resource Leveling
Project Progress Update
Two options:
1. Optimizing available resources
– Make under-allocated resources working to a task to
support over-allocated resources
– Pay
y attention to increased communication costs within that
task
Activity A Activity A
Delay
Activity B Activity B
To split a task
1. Select the blue task in the Gantt view
2. Right Click -> Split Task
3
3. Drag and Drop to split the task