RPMES FORM 1

REGIONAL PROJECT MONITORING AND EVALUATION SYSTEM (RPMES)


INITIAL PROJECT REPORT
Physical and Financial Targets for Ongoing Programs and Projects
FY

Implementing Agency:

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15)
(a) Name of Project
(b) Location
(c) Sector/Subsector
(d) Funding Source
(e) Mode of Implementation
(f) Project Schedule Total Project Target JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC TOTAL

(a) Construction of Multi-Purpose Building FS - ₱ 4,999,001.96


(b) Brgy. Caloocan, Balayan, Batangas % - Percent
(c) Infrastructure Accomplished%
(d) 20% DF (2022 Current) OI - Building
(e) By Contract (Name of Contractor )
(f) Start and Completiond Date
EG -

(a) Construction of 30 Units Solar Streetlights FS - ₱ 776,032.46


(b) Brgy. Carenahan, Balayan, Batangas % - Percent
(c) Infrastructure Accomplished%
(d) 20% DF (2022 Current) OI - Units of Streetlights
(e) By Contract (Name of Contractor)
(f) Start and Completiond Date
EG -

(a) Construction of 31 Units Solar Streetlights FS - ₱ 6,128,954.61


(b) Brgy. Dao, Balayan, Batangas % - Percent
(c) Infrastructure Accomplished%
(d) 20% DF (2022 Current) OI - Units of Streetlights
(e) By Contract (Name of Contractor)
(f) Start and Completiond Date
EG -

(a) Construction of Hog Pen for Slaughterhouse FS - ₱ 2,171,483.05


(b) Brgy. Santol, Balayan, Batangas % - Percent
(c) Infrastructure Accomplished%
(d) 20% DF OI - Building
(e) By Contract (LDV Construction)
(f) December 20, 2021 - April 21, 2022
EG -
FS - Financial Schedule % - Overall Physical Target in Percent OI - Output Indicator EG - Employment Generated

Submitted by: Noted by:


Designation/Office: Agency Head
Date:
IPR-001-00
RPMES FORM 2
REGIONAL PROJECT MONITORING AND EVALUATION SYSTEM (RPMES)
PHYSICAL AND FINANCIAL ACCOMPLISHMENT REPORT
As of Month Year (Quarterly)

Implementing Agency:

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15) (16)
(a) Name of Project & Financial Status (in PhP) Physical Status (%)
Description Allocation Releases Obligations Expenditures
(b) Date Started
(c) Target Completion Date Target Actual to Actual Employment Issues & Actions
(d) Location As of As of As of As of Output Indicator Target to for the for the Generated Taken/to be Taken
Reporting For the Reporting For the Reporting For the Reporting For the Date Date
(e) Funding Source Month Month Month Month Month Month
(f) Total Project Cost Period Period Period Period

Submitted by: Noted by:


Designation/Office: Agency Head
Date:

PFAR-001-00
RPMES FORM 3

REGIONAL PROJECT MONITORING AND EVALUATION SYSTEM (RPMES)


PROJECT EXCEPTION REPORT
As of Month Year (Quarterly)

Name of Project: Location:


Sector/Subsector: Implementing Agency:
Implementation Status: ( ) Ahead of Schedule ( ) On Schedule ( ) Behind Schedule

(1) (2) (3)


Findings Possible Reasons/Causes Recommendations

Submitted by:
Designation/Office:
Date:
PER-001-00
RPMES Form 4

REGIONAL PROJECT MONITORING AND EVALUATION SYSTEM (RPMES)


PROJECT RESULTS
As of December (Year)

Implementing Agency:

(1) (2) (3) (4)


Name of Project Project Objective/s Results Indicator/Target Observed Results
(Based on LogFrame) (Based on LogFrame)

Submitted by: Noted by:


Designation/Office: Agency Head
Date: