PROVISION OF ENGINEERING PROCUREMENT CONSTRUCTION AND INSTALLATION (EPCI) FLOWLINE KB-10 FOR KAMPUNG BARU DEVELOPMENT
ID WBS Task Name Start Finish Duration Predecessors
Q4 Q1
Sep Oct Nov Dec Jan Feb Mar
97 1.6.2.7 Creek / River Crossing Sun 27/10/24 Sat 02/11/24 7 days Creek / River Crossing
98 1.6.2.8 Anhor Block Sun 24/11/24 Sat 30/11/24 7 days 95FS-5 days;92 Anhor Block
99 1.6.2.9 Trenching ( Penggalian ) Mon 25/11/24 Fri 20/12/24 26 days 98SS+1 day Trenching ( Penggalian )
100 1.6.2.10 Lowering and Backfill Tue 26/11/24 Sat 21/12/24 26 days 99SS+1 day Lowering and Backfill
101 1.6.2.11 Valve Fit Up Sun 03/11/24 Wed 20/11/2418 days Valve Fit Up
102 1.6.2.12 Warning Sign & Pipeline Marker Sun 24/11/24 Mon 02/12/249 days 100SS-2 days
103 1.6.3 CPP AREA Sun 27/10/24 Sat 30/11/24 35 days
104 1.6.3.1 Ecer Pipa ( Stringing ) Sun 27/10/24 Wed 30/10/244 days Ecer Pipa ( Stringing )
105 1.6.3.2 Pipe Welding and Fitup Mon 28/10/24 Sat 09/11/24 13 days 104SS+1 day Pipe Welding and Fitup
106 1.6.3.3 PWHT Sat 09/11/24 Tue 12/11/24 4 days 105FS-1 day PWHT
107 1.6.3.4 NDT And Radiographi Sat 09/11/24 Tue 12/11/24 4 days 106SS NDT And Radiographi
108 1.6.3.5 Piping Under Ground Installation ( Sun 17/11/24 Thu 21/11/24 5 days Piping Under Ground Installation ( including 3LPE Wrapping) + Holiday test
including 3LPE Wrapping) + Holiday
109 1.6.3.6 Trenching ( Penggalian ) Fri 22/11/24 Fri 29/11/24 8 days 108 Trenching ( Penggalian )
110 1.6.3.7 Lowering and Backfill Sat 23/11/24 Sat 30/11/24 8 days 109SS+1 day Lowering and Backfill
111 1.6.3.8 Hot Tap (Incl All accessories and Permit)
Sun 24/11/24 Sat 30/11/24 7 days 110SS+1 day Hot Tap (Incl All accessories and Permit)
112 1.6.3.9 Valve Fit Up Sun 03/11/24 Wed 20/11/2418 days 101SS Valve Fit Up
113 1.6.4 Chatodic Protection Sun 22/12/24 Sat 04/01/25 14 days
114 1.6.4.1 Installation Chatodic Protection Sun 22/12/24 Sat 04/01/25 14 days 100 Installation Chatodic Protection
115 1.6.5 Instrument Sun 12/01/25 Fri 28/02/25 48 days
116 1.6.5.1 Instrument Installation (Incl. Cable Sun 12/01/25 Sat 25/01/25 14 days Instrument Installation (Incl. Cable Control In
Control Installation, PLC/HMI
117 1.6.5.2 Instrument Fit Up Sun 12/01/25 Fri 28/02/25 48 days 116SS Instrument Fit Up
118 1.7 Testing & Commissioning Sun 02/02/25 Wed 12/02/2511 days
119 1.7.1 Pre-Commissioning (Pigging, Sun 02/02/25 Sat 08/02/25 7 days 90;84;111 Pre-Commissioning (Pigging, Hydrot
Hydrotest, Purging, Cleaning)
120 1.7.2 Commisioning / Gas-in Sun 09/02/25 Wed 12/02/254 days 119 Commisioning / Gas-in