Project Master Schedule.1

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
58 views3 pages

Project Master Schedule.1

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

PROJECT MASTER SCHEDULE

PROVISION OF ENGINEERING PROCUREMENT CONSTRUCTION AND INSTALLATION (EPCI) FLOWLINE


KB-10 FOR KAMPUNG BARU DEVELOPMENT

PREPARED BY
KSO PT.Ramai Jaya Abadi - PT.Haryatek Elsindo Anugerah
JAKARTA - INDONESIA

DATE DESCRIPTION PRE'D CHK'D APP'D

17-Sep-24 Issued for Information DJ FUA TON


08-Oct-24 Issued for Information DJ FUA TON
PROVISION OF ENGINEERING PROCUREMENT CONSTRUCTION AND INSTALLATION (EPCI) FLOWLINE KB-10 FOR KAMPUNG BARU DEVELOPMENT
ID WBS Task Name Start Finish Duration Predecessors
Q4 Q1
Sep Oct Nov Dec Jan Feb Mar
1 1 PROVISION OF ENGINEERING PROCUREMENT Tue 10/09/24 Fri 28/02/25 172 days?
CONSTRUCTION AND INSTALLATION (EPCI)
FLOWLINE KB-10 FOR KAMPUNG BARU
2 1.1 DEVELOPMENT
Letter Of Award Tue 10/09/24 Tue 10/09/24 0 days 10/09
3 1.2 Kick of Meeting Fri 13/09/24 Fri 13/09/24 1 day 2FS+3 days
4 1.3 Preparation and General Wed 02/10/24 Thu 17/10/24 16 days
5 1.3.1 Perekrutan Pekerja Lokal Sat 05/10/24 Wed 09/10/245 days Perekrutan Pekerja Lokal
6 1.3.2 Medical check up Thu 10/10/24 Fri 11/10/24 2 days 5 Medical check up
7 1.3.3 Penyewaan TMC Dan Inspeksi Wed 02/10/24 Wed 02/10/241 day Penyewaan TMC Dan Inspeksi
8 1.3.4 Prepare Peralatan kerja Sat 05/10/24 Thu 10/10/24 6 days 7FS+2 days Prepare Peralatan kerja
9 1.3.5 Pembuatan Direksi kit Tue 15/10/24 Thu 17/10/24 3 days 8FS+2 days Pembuatan Direksi kit
10 1.3.6 Pengurusan izin kerja Mon 14/10/24 Tue 15/10/24 2 days 9SS
11
12 1.4 Engineering Document (Detail Design Fri 13/09/24 Sun 03/11/24 51 days
Engineering)
13 1.4.1 A. Engineering General Fri 13/09/24 Sun 22/09/24 10 days 3SS A. Engineering General
14 1.4.2 B. BASIC DESIGN REVIEW / VERIFY / Tue 17/09/24 Sun 03/11/24 47 days B. BASIC DESIGN REVIEW / VERIFY / REVISE / DEVELOP
REVISE / DEVELOP
51
52 1.5 Procurement - Material on Site Sun 29/09/24 Sat 11/01/25 105 days
53 1.5.1 Pipeline Accessories Materials Sun 29/09/24 Sat 26/10/24 28 days
58 1.5.2 Piping Materials Tue 01/10/24 Sat 26/10/24 26 days
74 1.5.3 Valve Tue 01/10/24 Sat 02/11/24 33 days Valve
75 1.5.4 Instrument Material Tue 15/10/24 Sat 11/01/25 89 days
83
84 1.6 Construction & Installation - Pekerjaan Thu 17/10/24 Fri 28/02/25 135 days?
Pemipaan
85 1.6.1 Civil Works Sun 20/10/24 Wed 20/11/2432 days 50
86 1.6.1.1 Foundation Pipe Header Sun 20/10/24 Sat 16/11/24 28 days 50FS-11 days Foundation Pipe Header
87 1.6.1.2 Foundation Pig Launcher Sun 20/10/24 Sat 16/11/24 28 days 50FS-11 days Foundation Pig Launcher
88 1.6.1.3 Foundation Pig Receiver Sun 27/10/24 Wed 20/11/2425 days 50FS-4 days Foundation Pig Receiver
89 1.6.1.4 Foundation Pipe Installation Sun 27/10/24 Wed 20/11/2425 days 50FS-4 days Foundation Pipe Installation
90 1.6.2 Pipeline Construction Thu 17/10/24 Sat 21/12/24 66 days
91 1.6.2.1 Ecer Pipa ( Stringing ) Thu 17/10/24 Sat 26/10/24 10 days Ecer Pipa ( Stringing )
92 1.6.2.2 Pipe Welding and Fitup Thu 17/10/24 Tue 05/11/24 20 days 91SS Pipe Welding and Fitup
93 1.6.2.3 PWHT & Hardness Test Tue 05/11/24 Sat 16/11/24 12 days 92FS-1 day PWHT & Hardness Test
94 1.6.2.4 NDT And Radiographi Tue 05/11/24 Sat 16/11/24 12 days 93SS NDT And Radiographi
95 1.6.2.5 Field Joint Coating + Holiday Test Sun 17/11/24 Thu 28/11/24 12 days 94 Field Joint Coating + Holiday Test
96 1.6.2.6 Pipe Bend 3LPE Wrapping Sun 17/11/24 Thu 28/11/24 12 days 95SS Pipe Bend 3LPE Wrapping

Task Inactive Task Manual Summary Rollup External Milestone Baseline Milestone

Split Inactive Milestone Manual Summary Deadline Baseline Summary


Project: Pekerjaan Sipil Fasilitas
Milestone Inactive Summary Start-only Critical Progress
Date: Tue 08/10/24
Summary Manual Task Finish-only Critical Split Manual Progress

Project Summary Duration-only External Tasks Baseline

Page 1
PROVISION OF ENGINEERING PROCUREMENT CONSTRUCTION AND INSTALLATION (EPCI) FLOWLINE KB-10 FOR KAMPUNG BARU DEVELOPMENT
ID WBS Task Name Start Finish Duration Predecessors
Q4 Q1
Sep Oct Nov Dec Jan Feb Mar
97 1.6.2.7 Creek / River Crossing Sun 27/10/24 Sat 02/11/24 7 days Creek / River Crossing
98 1.6.2.8 Anhor Block Sun 24/11/24 Sat 30/11/24 7 days 95FS-5 days;92 Anhor Block
99 1.6.2.9 Trenching ( Penggalian ) Mon 25/11/24 Fri 20/12/24 26 days 98SS+1 day Trenching ( Penggalian )
100 1.6.2.10 Lowering and Backfill Tue 26/11/24 Sat 21/12/24 26 days 99SS+1 day Lowering and Backfill
101 1.6.2.11 Valve Fit Up Sun 03/11/24 Wed 20/11/2418 days Valve Fit Up
102 1.6.2.12 Warning Sign & Pipeline Marker Sun 24/11/24 Mon 02/12/249 days 100SS-2 days
103 1.6.3 CPP AREA Sun 27/10/24 Sat 30/11/24 35 days
104 1.6.3.1 Ecer Pipa ( Stringing ) Sun 27/10/24 Wed 30/10/244 days Ecer Pipa ( Stringing )
105 1.6.3.2 Pipe Welding and Fitup Mon 28/10/24 Sat 09/11/24 13 days 104SS+1 day Pipe Welding and Fitup
106 1.6.3.3 PWHT Sat 09/11/24 Tue 12/11/24 4 days 105FS-1 day PWHT
107 1.6.3.4 NDT And Radiographi Sat 09/11/24 Tue 12/11/24 4 days 106SS NDT And Radiographi
108 1.6.3.5 Piping Under Ground Installation ( Sun 17/11/24 Thu 21/11/24 5 days Piping Under Ground Installation ( including 3LPE Wrapping) + Holiday test
including 3LPE Wrapping) + Holiday
109 1.6.3.6 Trenching ( Penggalian ) Fri 22/11/24 Fri 29/11/24 8 days 108 Trenching ( Penggalian )
110 1.6.3.7 Lowering and Backfill Sat 23/11/24 Sat 30/11/24 8 days 109SS+1 day Lowering and Backfill
111 1.6.3.8 Hot Tap (Incl All accessories and Permit)
Sun 24/11/24 Sat 30/11/24 7 days 110SS+1 day Hot Tap (Incl All accessories and Permit)
112 1.6.3.9 Valve Fit Up Sun 03/11/24 Wed 20/11/2418 days 101SS Valve Fit Up
113 1.6.4 Chatodic Protection Sun 22/12/24 Sat 04/01/25 14 days
114 1.6.4.1 Installation Chatodic Protection Sun 22/12/24 Sat 04/01/25 14 days 100 Installation Chatodic Protection
115 1.6.5 Instrument Sun 12/01/25 Fri 28/02/25 48 days
116 1.6.5.1 Instrument Installation (Incl. Cable Sun 12/01/25 Sat 25/01/25 14 days Instrument Installation (Incl. Cable Control In
Control Installation, PLC/HMI
117 1.6.5.2 Instrument Fit Up Sun 12/01/25 Fri 28/02/25 48 days 116SS Instrument Fit Up
118 1.7 Testing & Commissioning Sun 02/02/25 Wed 12/02/2511 days
119 1.7.1 Pre-Commissioning (Pigging, Sun 02/02/25 Sat 08/02/25 7 days 90;84;111 Pre-Commissioning (Pigging, Hydrot
Hydrotest, Purging, Cleaning)
120 1.7.2 Commisioning / Gas-in Sun 09/02/25 Wed 12/02/254 days 119 Commisioning / Gas-in

Task Inactive Task Manual Summary Rollup External Milestone Baseline Milestone

Split Inactive Milestone Manual Summary Deadline Baseline Summary


Project: Pekerjaan Sipil Fasilitas
Milestone Inactive Summary Start-only Critical Progress
Date: Tue 08/10/24
Summary Manual Task Finish-only Critical Split Manual Progress

Project Summary Duration-only External Tasks Baseline

Page 2