Inspection Manual For Piping
Inspection Manual For Piping
Inspection Manual For Piping
Page 2 of 187
Page 3 of 187
PIPING MANUAL
INDEX
Page 4 of 187
Sl. No. Topics Page No.
10.1 Onstream Inspection (Pipelines under 59
Operation)
10.2 Inspection During Shutdown 66
10.3 Statutory Inspection 68
11.0 Quality Assurance Plan for New 71
Constructions
11.1 Quality Assurance during Design Stage 71
11.2 Quality Assurance during Construction Stage 74
12.0 Inspection of Piping during Fabrication 78
12.1 Inspection of Pipes before use 78
12.2 Injurious Defects 78
12.3 Forming of Pipes 79
12.4 Welding 80
12.5 Inspection after Welding 80
12.6 Supports 81
12.7 Pressure Tests 81
12.8 Painting 86
12.9 External Corrosion Control for Buried or 87
Submerged Pipelines
12.10 Insulation 88
13.0 Retiring Limits 90
14.0 Pipeline Repairs and Inspection 91
14.1 Inspection of Valves in Service 91
15.0 Documentation 93
16.0 Annexures 95
Annexure –I Extracts from ANSI/ ASME B 31.4.1979 – On 95
Liquid Petroleum Transportation Piping Systems
Annexure –II Preservation of New Pipes in Ware House 99
Annexure-II(a) Sample Preservation Scheme for Sulfur 100
Recovery Unit
Annexure-II(b) Idle Time Preservation Scheme for Amine 106
Treating Unit
Annexure-II(c) Procedure for Passivation of Austenitic Stainless 110
Steel Equipment
Annexure-II(d) NACE RP-0170 - On Protection of Austenitic 114
Stainless Steel Equipment
Annexure-II(e) Idle Time Preservation of Static & Rotary 120
Equipment – OISD-171
Annexure –III Dimensions of Seamless and Welded Steel Pipe 150
Annexure –IV Equivalents Specifications of ASTM to British, 153
French, German, Italian and Swedish Standards
Annexure-V Common Paint Colour Code for Refineries 156
Annexure-VI Standard Specification for Corrosion Protection 170
of Wrapping Coating & Tape Coating of Under
Ground Steel Pipelines
Annexure-VII A Sample of Isometric of Pipeline Circuit & Data 181
Record Cards
17.0 References 183
Page 5 of 187
1.0 SCOPE
Page 6 of 187
2.0 DEFINITION
2.1 PIPE
2.2 TUBING
Page 7 of 187
3.0 TYPE OF PIPES ACCORDING TO THE METHOD OF
MANUFACTURE
The submerged arc welded pipes are made from hot rolled coils or
sheets. The welding can be longitudinal or spiral. The pipe is welded
internally and externally using submerged arc-welding process.
Page 8 of 187
3.5 DOUBLE SUBMERGED ARC WELDED PIPE
Pipe having a helical seam with either a butt, lap or lock seam-joint
which is welded using either a electrical resistance, electric fusion or
double submerged arc weld.
Internal and external cement lined pipes are used in cooling water and
fresh water lines to combat microbial induced corrosion in the internal
surface and soil corrosion in the external surface. The cement lining is
normally 25mm thick on inside and outside with wire mesh as
reinforcement.
Cement lined pipes are fabricated at shop on need base and can be
manufactured for higher diameter pipes only. However, precautions
should be taken for handling/ fabrication of these pipes to avoid local
damage or cracks on the cement lining and the lining provided at the
insitu joints. While doing the welding for field joints asbestos-backing
ring should be suitably provided at the internal face to avoid direct
contact of water to the metal surface. For external insitu lining,
normally, shuttering is made alongwith holes at top and bottom. The
cement concrete mixture is injected through the bottom hole and
oozing out of concrete from the top hole is observed to ensure
complete filling of the annular space with concrete.
Page 9 of 187
3.11 CONCRETE EMBEDDED PIPE
The concrete embedded pipes are also used in cooling water service,
which can take care soil side corrosion. In this system, the carbon steel
pipe is encased by concrete of minimum 6” thickness to avoid soil
corrosion. However, in this system the porosity of concrete cannot be
avoided and may result in localized corrosion. Although, the system
provides a perfect casing and can operate even with corroded pipes,
but any local repair is difficult and cumbersome.
Page 10 of 187
Page 11 of 187
4.0 SELECTION OF MATERIAL
4.1 SCOPE
4.2 GENERAL
i) Design Life
Page 12 of 187
regenerating etc. the design metal temperature of the piping shall
conform to ANSI – B 31.3.
The design pressure of the piping system shall be not less than the
pressure at the most severe condition of coincident internal /
external pressure and temperature expected during the service life.
For further details refer ANSI – B 31.3.
vi) Economics
Page 13 of 187
Decarburization
Corrosion and general oxidation
Intergranular oxidation
High temperature
Sensitization to Intergranular corrosion
Carburization
Deterioration during shutdowns or in shutting down and starting
up.
Embrittlement attributable to high temperature exposure.
c) For the other modes of metal deterioration given in para, 4.3.1 the
temperatures and pressures to be considered are design
temperatures and pressures, except that for decarburization and
hydrogen attack due to hydrogen in the process stream design
hydrogen partial pressure shall also be considered.
Page 14 of 187
4.3.2 Exposure at Ambient & Intermediate Temperatures (from 0 0C to
232 0C)
Hydrogen blistering
Intergranular corrosion
Stress corrosion cracking
Hydrogen sulfide embrittlement
Fatigue
Corrosion fatigue
Caustic embrittlement
Deterioration at shutdown or in shutting down and starting up.
Chemical attack
Crevice corrosion
Galvanic corrosion
Page 15 of 187
g) Brass materials shall be specified only when pH of the environment
due to ammonia will be 7.2 or less. Above pH 7.2, 70-30 Cu-Ni or
other similar alloy shall be used.
Page 16 of 187
4.4 SPECIFIC REQUIREMENT FOR SPECIAL SERVICES SOUR GAS,
HYDROGEN, SULPHUR, AMMONIA, AMINES, CAUSTIC SERVICES
ETC.
4.4.1Resistance to Hydrogen
A brief study of the Nelson curve on the following reveals that the
principle alloying elements which impart resistance to elevated
temperature hydrogen attack the chromium and molybdenum. (Refer
Drawing No –2 attached).
a) 1-¼ Cr – ½ Mo - (P-11)
b) 5 Cr – ½ Mo - (P-5)
c) 9 Cr-1 Mo - (P-9)
d) 16 Cr, 12 Ni, 2 Mo - (S. S 316 H)
4.4.2Resistance to Sulphur
Page 17 of 187
Carbon steel generally is specified for most equipment to the 500-550 0F
(260-288 0C) temperature range, and the corrosion allowance used is
3mm. When the piping in this service are carbon steel and improved
corrosion resistance is necessary, TP 410S stainless steel cladding is
specified. Depending on the anticipated corrosion rates, heater tubes are
usually 5 Cr – ½ Mo or 9 Cr – 1 Mo. Piping systems are usually carbon
steel and 5 Cr – ½ Mo with varying corrosion allowances. Refer
corrosion allowance Table – 5 for large diameter piping 18” dia, usually
heater transfer lines, an alternative of carbon steel clad with TP 410S
stainless steel is specified.
Page 18 of 187
DEA (Diethanol amine) – For design temperature > 82 0C.
Page 19 of 187
Killed steels are defined as those, which are thoroughly deoxidized
during melting process. Deoxidation is accomplished by use of silicon,
manganese and aluminium additions to combine with dissolved gases,
usually oxygen, during steel making. This results in cleaner, better
quality steel which has fewer gas pockets and inclusions. Killed carbon
steel is specified for major equipment in the following services to
minimize the possibility or extent of hydrogen blistering and hydrogen
embrittlement:
a) Carbon ½ Moly. These low alloy steels are used for moderate
temperature services, moderate corrosive service and most
frequently for intermediate temperatures for its resistance to
hydrogen attack. They have the same maximum temperature
limitation as killed steel (ASME Code – 1000 0F) but the strength
above 700 0F is substantially greater. However, while selecting this
material care should be taken as the creep/ high temperature
strength properties of such material deteriorates with time.
b) 1% chrome ½ Moly and 1-¼ Chrome ½ Moly. These alloys are used
for higher resistance to hydrogen attack and sulphur corrosion.
They are also used for services where temperatures are above the
rated temperature for C ½ Mo steel.
Page 20 of 187
5.4 Ferritic and Martensitic Stainless Steel
a) Type 304 – This is the lowest cost type of 18-8 stainless steel for
protection against hydrogen and hydrogen sulphide attack at
elevated temperatures. It is susceptible stress corrosion.
b) Types 309 and 310 – These are special heat resistant austenitic
stainless steels which have oxidation resistance upto about 2000 0F.
Their composition are 25% Cr – 12% Ni and 25% Cr – 20 Ni
respectively, and are used in high temperature services and tube
supports in heaters.
Page 21 of 187
Table – 1
ASTM DESIGNATION OF MATERIALS
ELECTRIC
WROUGHT
MATERIAL PLATE PIPE FUSION WELDED TUBES CASTINGS FORGINGS CLADDING
FITTINGS
PIPE
Carbon Steel A-285-GR, A, B A-53 GR, A-671 GR, CA-55 A-214 (WELDED) A-216 GR, A-105 A-181 CL. A-234 GR,
&C A&B A-677 GR, A45- A-179 WCA,WCB & 60 OR 70 A-266 WPB
A55 (SEAMLESS) WCC CL I, II, OR III
Killed Steel A-515 GR, 55- A-106 GR, A-672 GR B55- A-179 A-216 GR, A-105 A-181 CL A-234 GR,
70 A-516 GR, A&B B70 A-672 GR, WCA, WCB 60 OR 70 A-266 WPB
55-70 C55-C70 & WCC CL I, II, OR III
C-1/2 Mo A-204 GR, A, B A-335 GR, A-691 GR, CM 65- A-209 GR, T1 A-217 GR A-182 GR, F1 A- A-234 GR,
&C P1 CM75 WC1 336 CL, F1 WP1
1 Cr-1/2Mo A-387 GR, 12 A-335 GR, A-691 GR, 1Cr A-213 GR, T12 A-182 GR, F12 A-234 GR
P12 A-336 CL F12 WP11
1-1/4 Cr-1/2 A-387 GR, 11 A-335 GR, A-691 GR, 1-1/4Cr A-199 GR, T11 A- A-217 GR, A-182 GR, F11 A-234 GR,
Mo P11 213 GR, T11 WC6 A-336 CL F11 WP11
2-1/4 Cr-1Mo A-387 GR, 22 A-335 GR, A-691 GR, 2-1/4 A-199 GR, T22 A- A-217 GR, A-182 GR, F22 A-234 GR,
P22 Cr 219 GR, T22 WC9 A-336 CL F22 WP22
3Cr-1Mo A-387 GR, 21 A-335 GR, - A-199 T21 A-213 - A-182 GR, F21 -
P21 GR, T21 A-336 CL, F21
5 Cr-1/2 Mo A-387 GR, 5 A-335 GR, A-691 GR, 5Cr A-199 GR, T5 A- A-217 GR, A-182 GR, F5 A- A-234 GR,
(Formerly A- P5 213 GR, T5 C5 336 CL, F5 WP5
357)
9Cr-1Mo A-387 GR, 9 A-335 GR, A-691 GR, 9CR. A-199 GR, T9 A- A-217 GR, A-182 GR, F9 A- A-234 GR,
P9 213 GR, T9 C12 336 CL F9 WP9
12Cr-TP405 A-240 TP405 A-268 GR, - A-268 GR, TP405 - - - A-263
TP405
13 Cr-TP410 A-240 TP410 A-268 GR, - A-268 GR, TP410 A-217 GR, A-182 GR, F6 A- - A-263
TP410 CA15 336 CL, F6
13 Cr- A-240 TP410S - A-263
TP410S
17 Cr- TP430 A-240 TP430 A-268 GR, - A-268 GR, TP 430 - A-263
Page 22 of 187
ELECTRIC
WROUGHT
MATERIAL PLATE PIPE FUSION WELDED TUBES CASTINGS FORGINGS CLADDING
FITTINGS
PIPE
TP 430
18 Cr-8 Ni- A-240 TP304 A-312 GR, A-358 GR, 304 A-213 GR, TP304 A-351 GR, A-182 GR, F304 A-403 GR, A-264
TP304 TP304 A- A-249 GR, TP304 CF8 A-744 A-336 CL, F304 WP304
376 GR, CF8
TP304
18 Cr-8Ni- A-240 TP304L A-312 GR, A-358 GR, 304L A-213 GR, A-351 GR, A-182 GR, A-403 GR, A-264
TP304L TP304L TP304L A-249 CF3 A-744 F304L A-336 CL, WP304L
GR, TP304L CF3 F304L
Page 23 of 187
Table – 2
ASTM DESIGNATION OF MATERIALS
ELECTRIC
WROUGHT
MATERIAL PLATE PIPE FUSION TUBES CASTINGS FORGINGS CLADDING
FITTINGS
WELDED PIPE
18Cr-8 Ni- A-240 A-312 GR, A-358 GR, A-213 GR, TP304H - A-182 GR, A403 GR, A-264
TP304H TP304H TP304H A-376 304H A-249 GR, TP304H F304H A-336 WP304H
GR, TP304H CL F304H
16Cr-12 Ni-2 A-240 A-312 GR, A-358 GR, 316 A-213 GR, TP316 A-351 GR, CF8M A-182 GR, A-403 GR, A264
Mo TP316 TP316 TP316 A-376 A-249 GR, TP316 A-744 CF8M F316 A-336 CL WP316
GR, TP316 F316
16Cr-12 Ni- A-240 A-312 GR, A-358 GR, A-213 GR, TP316L A-351 GR, CF8M A-182 GR, A-403 GR, A-264
2Mo TP316L TP316L TP316L 316L A-249 GR, TP316L A-744 GR CF8M F316L A-336 WP316L
CL F316L
16Cr-12 Ni- A-240 A-312 GR, A-358 GR, A-213 GR, TP316H - A-182 GR, A-403 GR, A-264
2Mo TP316H TP316H TP316H A-376 316H A-249 GR, TP316H F316H A-336 WP316H
GR, TP316H CL F316H
18Cr- 13 Ni- A-240 A-312 GR, A-249 GR, TP317 A-351 GR, CG-8M A-182 GR, A-403 GR, A-264
3Mo TP317 TP317 TP317 A-744 GR, CG-8M F317 (Bar WP317
Stock)
18Cr- 13 Ni- A-240 A-312 GR, - - - - A-403 GR, A-264
3Mo TP317L TP317L TP317L WP317L
18Cr- 10 Ni- A-240 A-312 GR, A-358 GR, 321 A-213 GR, TP321 A-182 GR, A-403 GR, A-264
Ti TP321 TP321 TP321 A-376 A-246 GR, TP321 F321 A-336 CL WP321
GR, TP321 F321
18Cr- 10 Ni- A-240 A-312 GR, - A-213 GR, TP321H A-182 GR, A-403 GR, A-264
Ti TP321H TP321H TP321H A-376 A-249GR, TP321H F321H A-336 WP321H
GR, TP321H CL F321H
18Cr- 10 Ni- A-240 A-312 GR, A-358 GR, 347 A-213 GR, TP347 A-351 GR, CF8C A-182 GR, A-403 GR, A-264
Cb TP347 TP347 TP347 A-376 A-249 GR, TP347 A-744 GR, CF8C F347 A-336 CL WP347
GR, TP347 F347
18Cr- 10 Ni- A-240 A-312 GR, - A-213 GR, TP347H A-182 GR, A-403 GR, A-264
Cb TP347H TP347H TP347H A-376 A-249 GR, TP347H F347H A-336 WP347H
Page 24 of 187
ELECTRIC
WROUGHT
MATERIAL PLATE PIPE FUSION TUBES CASTINGS FORGINGS CLADDING
FITTINGS
WELDED PIPE
GR, TP347H CL F347H
23 Cr-12 Ni A-240 A-312 GR, A-358 GR, A-213 GR, TP309 A-351 GR, CH-20 A-403 GR, A264
TP309 TP309S TP309S 309S WP309
25 Cr-20 Ni A-240 A-312 GR, A-358 GR, A-212 GR, TP310 A-351 GR, CK-20 A-182 GR, A-403 GR, A264
TP310 TP310S TP310S 310S A-249 GR F310 WP310
Inconal 600 B-168 B-167 B-517 B-163 Alloy Ni-Cr- B-564 Alloy Ni- B-366 GR / A-265
(Ni-Cr-Fe) Fe-B-516 Cr-Fe B-166 WPNCI
(Bar Stock)
Inconal 800 B-169 B-407 B-514 B-163 Alloy Ni-Cr- B-564 Alloy Ni- B-366 GR / A-265
(Ni-Cr-Fe) Fe-B-515 Cr-Fe B-408 WPNCI
(Bar Stock)
Alloy 20 (Cr- B-463 B464 B-474 B-468 A-351 GR, CN-7M B-462 B-366 GR, A-265
Ni-Fe-Mo- A-744 GR, CN-7M WP20CB
Cu-Cb)
Admiralty B-171 No. R-111 No. C44300
Brass. C44300 C44400 C44500
C44400
C44400
Page 25 of 187
Table – 3
ELECTRIC
WROUGHT
MATERIAL PLATE PIPE FUSION WELDED TUBES CASTINGS FORGINGS CLADDING
FITTINGS
PIPE
Naval Brass B-171 No.
C46400
Al. Brass B B-111 No.
C68700
Al. Bronze D B-171 No. B-111 No. B-432
C61400 C61400
90-10-Cu-Ni B-171 No. B-466 No. B-111 No. C70600 B-432
C70600 C70600
80-20-Cu-Ni B-466 No. B-111 No. C71000
C71000
70-30-Cu-Ni B-171 No. B-466 No. B-111 No. C71000 B-432
C71500 C71500
Monel (Ni- B-127 B-165 B-163 Alloy A-494A-GR, M- B-564 Alloy Ni- P-366 Gr. A-265
Cu) Ni-Cu 31-1 Cu B-164 (Bar WPNC
Stock)
Hastelloy-B B-333 B-622 Alloy Ni- R-619 Alloy Ni-Mo A-494 N-12MV R335 (Alloy Rod) R-366 Gr, A-265
(Ni-MO) Mo WPHB.
Hastelloy-C B-575 R-622 Alloy B-619 Alloy LowC A-494 CR, CW- B-574 (Alloy B-366 GR, A-265
(Ni-Mo-Cr.) Low C Ni-Mo- Ni-Mo-Cr 12MW Rod) WPHC
Cr
AI. 3003 B-209 Alloy B-241 Alloy B-324 Alloy 3003 B-247 Alloy 3003 R-361 Alloy WP
3003 3003 B-210 3003
Alloy 3003
Titanium. B-265 B-337 B-338 B-367 B-381 B-363
* ASTM A53 Gr. A&B CAN BE REPLACED BY API 5L Gr. A & B ALSO
Page 26 of 187
Table – 4
ALLOY STEEL
TEMP. CARBON INTER
SERVICE
RANGE 0C STEEL LOW MEDIATE HIGH ALLOY NON METALLIC
ALLOY
Hydrocarbon
Low temp. 0-250 A
Med Temperature 250-400 A D
High Temp. 400-550 D F
Very High Temp. 550-700 F, G K, M
Steam & BFW 0-400 A
400450 B, D E
AIR 0-250 A, J
Gas -80 to –45 H
-45 to –250 K, M, N
Flue Gas 0-650 A K
Acids 0-60 A, Y K, P S, Z, V
Chemical
Low Temp. 0-250 A K, N S
Water
Cooling 0-120 A
Acidic 0-120 A Z
Sour 0-120 A
Sea A W
Page 27 of 187
Legend:
A – CARBON
B – CARBON MOLY
C – 1% CR – ½ MOLY
D – 1-1/4% CR. – ½ MOLY.
E – 2-1/4% CR. – 1 MOLY.
F – 5% CR. – ½% MOLY.
G – 9% CR. 1% MOLY
H – 3-1/2% NI
I, J, K – S. S. TYPE 304, 304H, 304L
M – STABILIZED S. S. 316, 316H, 321, 347
N – 316 L
P – MONEL / INCONEL / INCOLOY
Q – HASTALLOY
R – LEAD
S – PVC
T – C. I. / SILICON IRON
V – FRP
W – CUPRO – NICKEL
Y – LINED STEEL
Z – HDPE
The above alphabets are also the last alphabets in piping class.
Page 28 of 187
Table – 5
Page 29 of 187
SL. CORR. PIPING
SERVICE FLANGE APPLICATION MATERIAL
NO. ALL. mm CLASS
RATING FACING
“ 300# RF MED. PRESSURE & HIGH 3.0 B4F A335 Gr. P5
TEMPERATURE
“ 150# RF LOW PRESSURE & HIGH 3.0 A4F A335 Gr. P5
TEMPERATURE
7. LVGO 150# RF LOW PRESSURE & MED. 1.5 A1A API 5L Gr. B/ A106 Gr. B
TEMPERATURE
“ 300# RF “ 1.5 B1A “
8. HVGO 300# RF MED. PRESSURE & MED. 1.5/3.0 B1A/B9A API 5L Gr. B/ A106 Gr. B
TEMPERATURE
“ 300# RF “ 3.0 B4F A335 Gr. P5
“ 150# RF LOW PRESSURE & HIGH 3.0 A4F “
TEMPERATURE
9. RCO 150# RF LOW PRESSURE & HIGH 3.0 A4F A335 Gr. P5
TEMPERATURE
“ 300# RF MED. PRESSURE & HIGH 3.0 B4F “
TEMPERATURE
10. VAC. RESIDUE 150# RF LOW PRESSURE & MED. 3.0 A9A API 5L Gr.B/ A 106 Gr. B
TEMPERATURE
“ 300# RF MED. PRESSURE & MED. 3.0 B9A “
TEMPERATURE
“ 150# RF LOW PRESSURE & HIGH 3.0 A4F A335 Gr. P5
TEMPERATURE
“ 300# RF MED. PRESSURE & HIGH 3.0 B4F “
TEMPERATURE
10A. VB TAR 150# RF LOW PRESSURE & MED. 3.0 A9A API 5L Gr. B/ A106 Gr. B
TEMPERATURE
“ 300# RF MED. PRESSURE & MED. 3.0 B9A “
TEMPERATURE
“ 150# RF LOW PRESSURE & HIGH 3.0 A4F A335 Gr. P5
TEMPERATURE
“ 300# RF MED. PRESSURE & HIGH 3.0 B4F “
TEMPERATURE
Page 30 of 187
SL. CORR. PIPING
SERVICE FLANGE APPLICATION MATERIAL
NO. ALL. mm CLASS
RATING FACING
11. SLOP DISTILLATE 150# RF LOW PRESSURE & HIGH 3.0 A4F A335 Gr. P5
TEMPERATURE
“ 300# RF MED. PRESSURE & HIGH 3.0 B4F “
TEMPERATURE
12. SLOP OIL 150# RF FROM HOT WELL LOW PRESSURE 4.5 A6A API 5L Gr. B/ A106 Gr. B
13. TC TAR 150# RF LOW PRESSURE 1.5/3.0 A1A/A9A “
“ 300# RF MED. PRESSURE 3.0 B9A “
14. CBD 150# RF LOW PRESSURE 1.5 A1A “
15. FLUSHING OIL 150# RF LOW PRESSURE 1.5 A1A “
16. CATALYST 150# RF LOW PRESSURE & HIGH 3.0 A14A API 5L Gr.B
TEMPERATURE
“ 300# RF MED. PRESSURE & HIGH 1.5 B4K A312 Gr. TP304H
TEMPERATURE
17. REACTOR OVHD 300# RF MED. PRESSURE & HIGH 3.0 B4D A335 Gr. P11
TEMPERATURE
REACTOR BYPAS 300# RF “ 6.0 B3F A335 Gr. P5
18. CYCLE OIL 300# RF “ 3.0 B4F A335 Gr. P5
HY. CYCLE OIL 300# RF MED. PRESSURE & MED. 3.0 B9A AP1 5L Gr.B/ A106 Gr. B
TEMPERATURE
HY. CYCLE OIL 150# RF LOW PRESSURE & MED. 3.0 A9A API5L Gr. B/ A106 Gr. B
TEMPERATURE
LT. CYCLE OIL 150# RF “ 1.5 A1A “
19. FRACTIONATOR 300# RF MED. PRESSURE & HIGH 6.0 B3F A335 Gr. P5
BOTTOM TEMPERATURE
MAIN CIRCULATION 300# RF “ 6.0 B11A API 5L Gr.B/ A106 Gr.B
OIL
20. MAIN COLUMN O / 150# RF LOW PRESSURE 3.0 A9A “
21. MAIN COLUMN RE 150# RF “ 1.5 A1A “
22. TORCH OIL (RAW OIL) 300# RF MED. PRESSURE & HIGH 3.0 B4F A335 Gr.P5/ API 5L Gr.B
TEMPERATURE
“ 300# RF MED. PRESSURE & MED. 3.0 B9A A106 Gr. B
TEMPERATURE
Page 31 of 187
SL. CORR. PIPING
SERVICE FLANGE APPLICATION MATERIAL
NO. ALL. mm CLASS
RATING FACING
23. SLURRY OIL 300# RF MED. PRESSURE & HIGH 6.0 B3F A 335 Gr. P5
TEMPERATURE
24. CLARIFIED OIL 300# RF “ 6.0 B3F “
“ 300# RF MED. PRESSURE & MED. 3.0 B9A API 5L Gr. B/ A106 Gr. B
TEMPERATURE
25. BLOW DOWN 150# RF LOW PRESSURE & LOW 1.5 A3A IS: 1239/
TEMPERATURE IS: 3589
“ 300# RF MED. PRESSURE & LOW 1.5 B1A API 5L Gr.B/ A 106 Gr. B
TEMPERATURE
26. GASOLINE 150# RF FCCU LOW PRESSURE & LOW 1.5 / 3.0 A1A / A9A “
TEMPERATURE
“ 300# RF FCCU MED. PRESSURE & LOW 1.5 B1A “
TEMPERATURE
27. DISULFIDE OIL 150# RF LOW PRESSURE & LOW 1.5 A1A/ A9A “
TEMPERATURE 3.0
“ 300# RF LOW/ MED. PRESSURE & LOW 3.0 B9A “
TEMPERATURE
28. SUPERIOR KEROS 150# RF LOW PRESSURE & LOW 1.5 A10A “
TEMPERATURE
29. PROPYLENE 300# RF MED. PRESSURE & LOW 1.5/ 3.0 B1A/ B7A “
TEMPERATURE
30. C4 &C5 150# RF LOW PRESSURE & LOW 1.5 A1A “
TEMPERATURE
“ 300# RF MED. PRESSURE & LOW 1.5 B1A “
TEMPERATURE
31. HEXANE 150# RF “ 1.5 A1A “
32. REFFINATE & 150# RF LOW PRESSURE & MED. 1.5 A1A “
EXTRACT TEMPERATURE
33. WAX PLANT FEED 150# RF LOW PRESSURE & LOW 3.0 A9A API 5L Gr.B/ A 106 Gr. B
TEMPERATURE
34. OIL + MIBK 150# RF LOW PRESSURE & LOW 3.0 A9A API 5L Gr.B/ A 106 Gr. B
TEMPERATURE
Page 32 of 187
SL. CORR. PIPING
SERVICE FLANGE APPLICATION MATERIAL
NO. ALL. mm CLASS
RATING FACING
“ 300# RF MED. PRESSURE & LOW 3.0 B9A “
TEMPERATURE
35. WAX + MIBK 150# RF LOW PRESSURE & LOW 3.0 A9A “
TEMPERATURE
36. INERT GAS + MIB 150# RF “ 3.0 A9A “
“ 300# RF MED. PRESSURE & LOW 3.0 B9A “
TEMPERATURE
37. WAX + CLAY 150# RF LOW PRESSURE & MED. 3.0 A9A “
TEMPERATURE
38. AIR + CLAY 150# RF “ 3.0 A9A “
39. WAX 150# RF “ 3.0 A9A “
40. WAX + SLURRY 150# RF “ 3.0 A9A “
41. SPENT CLAY 150# RF “ 3.0 A9A “
42. OIL 150# RF “ 3.0 A9A “
43. LPG VAPOUR 150# RF LOW PRESSURE & LOW 1.5 A.10A “
TEMPERATURE
SATURATED LPG 150# RF “ 1.5 A10A “
“ 300# RF MED. PRESSURE & LOW 1.5 B1A “
TEMPERATURE
CRACKED LPG 150# RF LOW PRESSURE & LOW 1.5 A1A “
TEMPERATURE
“ 300# RF MED. PRESSURE & LOW 1.5 B1A “
TEMPERATURE
44. FUEL OIL 300# RF BURNERS 1.5/3.0 B1A/ B9A “
FUEL OIL (OFFSIT) 150# RF OFFSITES 1.5 A10A “
45. REF. FUEL OIL 150# RF OFFSITES 3.0 A9A “
46. HYDROGEN BEAR 150# RF - 1.5 A5A “
HYDROCARBON
“ 300# RF - 1.5 B5A “
“ 600# RF - 1.5 D5A “
Page 33 of 187
SL. CORR. PIPING
SERVICE FLANGE APPLICATION MATERIAL
NO. ALL. mm CLASS
RATING FACING
II. ACID & CHEMICALS
1. DEMULSIFIER 300# RF MED. PRESSURE & LOW 1.5/ 3.0 B1A/ B9A API 5L Gr. B/ A106 Gr. B
TEMPERATURE
2. AMMONIA 150# RF LOW TEMPERATURE & LOW 3.0 A9A “
PRESSURE
“ 300# RF MED. PRESSURE & LOW 3.0 B9A “
TEMPERATURE
3. CAUSTIC (10-30 Be) 150# RF LOW PRESSURE & LOW 3.0 A19A “
MAX/100 TEMPERATURE
“ 300# RF MED. PRESSURE & LOW 3.0 B19A “
TEMPERATURE
CAUSTIC + AMMC 300# RF “ 3.0 B19A “
MIXTURE
4. CORROSION 150# RF LOW PRESSURE & LOW 1.5/ 3.0 A1A/ A9A “
INHIBITOR TEMPERATURE
“ 150# RF LOW PRESSURE & AMINE 1.5 A6K A312 Gr. TP 304L
TREATING UNIT
5. PHOSPHATE 300# RF MED. PRESSURE & LOW 3.0 B9A API 5L Gr.B/ A 106 Gr. B
TEMPERATURE
6. RICH DEA 150# RF LOW PRESSURE & LOW 3.0 A19A “
TEMPERATURE
“ 300# RF MED. PRESSURE & LOW 3.0 B19A “
TEMPERATURE
7. LEAN DEA 150# RF LOW PRESSURE & LOW 3.0 A19A “
TEMPERATURE
“ 300# RF MED. PRESSURE & LOW 3.0 B19A “
TEMPERATURE
8. MEA 150# RF LOW/MED. PRESSURE & LOW 1.5/ 3.0 A1A/A19A “
TEMPERATURE
9. ANTI FOAMING AGENT 150# RF LOW PRESSURE & LOW 1.5 A1A “
TEMPERATURE
10. SULPHURIC ACID 150# RF LOW PRESSURE & LOW 1.5 A8A API 5L Gr. B
Page 34 of 187
SL. CORR. PIPING
SERVICE FLANGE APPLICATION MATERIAL
NO. ALL. mm CLASS
RATING FACING
TEMPERATURE & CORROSIVE
11. CHLORINE & DIL. 150# FF - NIL A1Z HDPE/ASTM D3035 Gr.
H2SO4 PE 3406 CLC
12. WET SOLVENT 150# RF LOW PRESSURE & LOW 1.5 A1A API 5L Gr.B/ A 106 Gr. B
TEMPERATURE
13. LEAN SOLVENT 150# RF LOW PRESSURE & MED. 1.5 A1A “
TEMPERATURE
“ 300# RF MED. PRESSURE & MED. 1.5 B1A “
TEMPERATURE
14. SODIUM CARBON 150# RF LOW PRESSURE & LOW 1.5 A3A IS: 1239/ IS: 3589
SOLUTION TEMPERATURE
15. ODORANT 300# RF LPG STORAGE 1.5 B1A “
16. MEROX WASTE 150# RF W.W.T.P. 3.0 A9A “
17. POLYELECTROLY 150# RF W.W.T.P. / ETP/ TTP NIL A1Z HDPE / ASTM D3035 Gr.
SOLUTION P 3406 CLC
“ 150# RF “ NIL A1K A312 Gr. TP 304L
18. FERROUS SULPH / 150# RF “ NIL A1Z HDPE / ASTM D3035 Gr.
SOLUTION P 3406 CLC
“ 150# RF “ NIL A1K A312 Gr. TP 304L
19. DILUTE ACID 150# RF “ NIL A1Z HDPE / ASTM D3035 Gr.
P 3406 CLC
“ 150# RF “ NIL A1K A312 Gr. TP 304L
20. ALUM. SOLUTION 150# RF “ NIL A1Z HDPE / ASTM D3035 Gr.
P 3406 CLC
“ 150# RF “ NIL A1K A312 Gr. TP 304L
21. UREA SOLUTION 150# RF “ NIL A1Z HDPE / ASTM D3035 Gr.
P 3406 CLC
“ 150# RF “ NIL A1K A312 Gr. TP 304L
22. D. A. P. SOLUTION 150# RF “ NIL A1Z HDPE / ASTM D3035 Gr.
P 3406 CLC
“ 150# RF “ NIL A1K A312 Gr. TP 304L
23. OIL EFFLUENT 150# RF “ NIL “ CAST IRON
Page 35 of 187
SL. CORR. PIPING
SERVICE FLANGE APPLICATION MATERIAL
NO. ALL. mm CLASS
RATING FACING
24. HCL 150# RF DM WATER PLANT NIL “ FRP
HCL 150# RF “ NIL A1Z HDPE / ASTM D3035 Gr.
P 3406 CLC 7 OF 10
IV. STEAM
1. LP STEAM 150# RF LOW PRESSURE & LOW 1.0 A2A A106 Gr. B
Page 36 of 187
SL. CORR. PIPING
SERVICE FLANGE APPLICATION MATERIAL
NO. ALL. mm CLASS
RATING FACING
TEMPERATURE
2. LP CONDENSATE 150# RF “ 1.0 A2A “
3. MP STEAM 300# RF MED. PRESSURE & MED. 1.0 B2A “
TEMPERATURE
4. MP CONDENSATE 300# RF “ 1.0 B2A “
5. HP STEAM 600# RF HIGH PRESSURE & MED. 1.0 D2A “
TEMPERATURE
6. HP CONDENSATE 600# RF “ 1.0 D2A “
7. STRIPPING STEAM 300# RF REACTOR MED. PRESSURE 1.0 B2A/ B2D A 106 Gr. B/ A335 Gr. P11
STRIPPER
V. TRANSFERLINES
1. CRUDE TRANSFER 150# RF LOW PRESSURE & HIGH 3.0 A4F A335 Gr. P5
TEMPERATURE
2. PLATFORMATE 300# RF HIGH PRESSURE & HIGH 3.0 B4D A335 Gr. P11
TRANSFER TEMPERATURE
3. KEROSENE 300# RF MED. PRESSURE & HIGH 3.0 B4D “
TRANSFER TEMPERATURE
4. DIESEL TRANSFER 600# RF HIGH PRESSURE & HIGH 3.0 D4F A 335 Gr. P5
TEMPERATURE
5. CRACKED GAS OIL 300# RF MED. PRESSURE & HIGH 3.0 B4F “
TEMPERATURE
6. MIDDLE DISTILLATE 150# RF LOW PRESSURE & MED. 1.5 A1A API 5L Gr. B/ A106 Gr. B
TRANSFER TEMPERATURE
7. LUBE TRANSFER 600# RF HIGH PRESSURE & HIGH 3.0 D4F A335 Gr. P5
TEMPERATURE
8. SULPHUR TRANSF. 150# RF LOW PRESSURE & MED. 1.5 A1A API 5L Gr. B/ A106 Gr. B
TEMPERATURE
9. VAC. TOWER BOTT. 900# RTJ HIGH PRESSURE & HIGH 3.0 E4F A335 Gr. P5
TRANSFER TEMPERATURE
10. FOOTS OIL TRANSFER 300# RF LOW PRESSURE & HIGH 3.0 B9A API 5L Gr.B/ A 106 Gr. B
TEMPERATURE
Page 37 of 187
SL. CORR. PIPING
SERVICE FLANGE APPLICATION MATERIAL
NO. ALL. mm CLASS
RATING FACING
11. CRUBE TRANSFER 300# RF MED. PRESSURE & HIGH 3.0 B4F A 335 Gr. P5
TEMPERATURE
12. VGO TRANSFER 300# RF “ 3.0 B4F “
13. HYDROGEN 300# RF MED. PRESSURE & HIGH 3.0 B4B A335 Gr. P1
TRANSFER TEMPERATURE
VI. WATERLINES
1. DESALTER WATER 150# RF LOW PRESSURE & LOW 3.0 A9A API 5L Gr.B/ A 106 Gr. B
TEMPERATURE
“ 3.00# RF MED. PRESSURE & LOW 3.0 B9A “
TEMPERATURE
2. SOUR WATER 150# RF LOW PRESSURE & LOW 3.0 A9A API 5L Gr.B/ A 106 Gr. B
TEMPERATURE
“ 300# RF MED. PRESSURE & LOW 3.0 B9A “
TEMPERATURE
3. COOLING WATER 150# RF LOW PRESSURE & LOW 1.5 A3A API 5L Gr. B/ A 106 Gr. B
TEMPERATURE As detailed in Sl. No. 4.5
4. COOLING SEA < 50 mm 150# RF PUMP GLAND COOLING - J5A API 5L Gr. B
WATER
“ 150# RF COOLING WATER / FIRE WATER - J5A IS 1239/ IS 3589
80 mm N/B TO 600 mm MAINS (CEMENT LINED)
N/b
5. SERVICE WATER 150# RF LOW PRESSURE & LOW 1.5 A3A IS: 1239/ IS : 3589
TEMPERATURE
6. BOILER FEED WATER 300# RF MED. PRESSURE & LOW 1.0 B2A A 106 Gr. B
(IBR) TEMPERATURE
“ 600# RF HIGH PRESSURE & LOW 1.0 D2A “
TEMPERATURE
“ 150# RF LOW PRESSURE & LOW 1.0 A2A “
TEMPERATURE
7. DM WATER 150# RF LOW PRESSURE & LOW 1.5 A3A IS: 1239/ IS: 3589
TEMPERATURE
Page 38 of 187
SL. CORR. PIPING
SERVICE FLANGE APPLICATION MATERIAL
NO. ALL. mm CLASS
RATING FACING
8. TEMPERED WATER 150# RF “ 1.5 A3A IS: 1239/ IS: 3589
9. RAW WATER 150# RF “ 1.5 A3A “
10. DRINKING WATER 150# RF - NIL J4A IS: 123(Galv.)
11. FIRE WATER 150# RF - 1.5 A3A API 5L Gr. B/ A 106 Gr. B
As detailed in Sl. No. 4.5
12. CHROMATE WATER 150# RF - 1.5 A3A “
13. OILY SEWER WASTE 150# RF O.W.S SYSTEM 1.5 A3A “
14. ACID WATER 150# RF D.M. WATER PLANT 1.5 A3A “
Page 39 of 187
Table – 6
Page 40 of 187
Sl. No. MATERIAL ASTM DIN GERMAN MAT. NO. BS GRADE
29. Nickel – Chrom – Iron B 161 N 08825 NiCr21Mo 2.4858 3074 NA 16
30. B 468 N 08020
31. Nickel – Chrom – Iron B 163 N 08820 X10NiCrAITi 3220 1.4876 3074 NA 15
32. Copper Alloy B 75 / B 111 No. 122 Si – Cu 2.0090 2871 C 106
33. Copper Alloy B 75 / B 111 No. 142 Cu As P 2.1491 2871 C107
34. Copper Alloy B 111 Ca. No. 443 CuZn28Sn 2.0470 2871 CZ 111
35. Copper Alloy B 111 Ca. No. 687 CuZn20AI 2.0460 2871 CZ 110
36. Copper Alloy B 111 Ca. No. 608 CuA15AS 2.0918 2871
37. Copper Alloy B 111 Ca. No. 706 CuNi10Fe 2.0872 2871 CN 102
38. Copper Alloy B 111 Ca. No. 715 CuNi30Fe 2.0882 2871 CN 107
39. Aluminium Alloys Alloy 1050 / 1050A A1 99.5 3.0255 1050A (1B)
40. Aluminium Alloys Alloy 5754 A1Mg3 3.3535 (N5)
41. Aluminium Alloys Alloy 3003 A1MnCu 3.0517
42. Aluminium Alloys Alloy 5083 A1Mg4.5Mn 3.3547 5083 (N8)
Page 41 of 187
Drawing No-1
Temperature Vs. concentration limits for caustic Service
Page 42 of 187
1500
800
1400
1300
700
1200
M
R
A
U
R
R
A
E
P
E
P
E
T
T
0
500
300
0 500 1000 1500 2000 2500
Hydrogen Partial pressure
Drawing No –2:
Nelson Curve
Drawing No-3
Curve showing material properties for high temperature sulfur corrosion
Page 45 of 187
5.0 SIGNIFICANCE OF PIPING CLASS NOMENCLATURE
USED BY DESIGNERS AND PMCs
150#
A – 150#
B – 300#
C – 400#
D – 600#
E – 900#
F – 1500#
G – 2500#
J – 125/ 150#
CA
No. Details
1. CA = 1.5
2. CA = 1.0 (IBR)
3. CA = 1.5 (CAT ‘D’ FLUIDS)
4. CA = 1.5 (LTCS)
5. CA = 1.5 (H2 SERVICE)
6. CA = 4.5
7. CA = 3.0
8. CA = 1.5 (CONC. H2SO4)
9. CA = 3.0
10. CA = 1.5 (OFFSITE)
11. CA = 6.0
12. NOT ALLOTTED
13. NOT ALLOTTED
14. CA = 3.0 (SPECIAL FOR FCC CATALYST)
15. NOT ALLOTTED
16. CA = 4.5 (NACE)
17. NOT ALLOTTED
Page 46 of 187
18. NOT ALLOTTED
19. CA = 3.0 (STRESS RELIEVED)
20. NOT ALLOTTED
Page 47 of 187
5.3 SIGNIFICANCE OF THIRD ALPHABET OF PIPING CLASS
Material grade
Material List
A – CARBON
B – CARBON MOLY
C – 1% CR – ½ MOLY
D – 1-1/4% CR. – ½ MOLY.
E – 2-1/4% CR. – 1 MOLY.
F – 5% CR. – ½% MOLY.
G – 9% CR. 1% MOLY
H – 3-1/2% NI
I, J, K – S. S. TYPE 304, 304H, 304L
M – STABILIZED S. S. 316, 316H, 321, 347
N – 316 L
P – MONEL / INCONEL / INCOLOY
Q – HASTALLOY
R – LEAD
S – PVC
T – C. I. / SILICON IRON
V – FRP
W – CUPRO – NICKEL
Y – LINED STEEL
Z – HDPE
The above alphabets are also the last alphabets in piping class.
Insulation details
Nomenclature Description
Ih Insulation for heat conservation
It Insulation for steam traced line
Is Insulation for personal safety
Ic Cold insulation for anti condensation
Ie Insulation for electrical traced line
Ij Insulation for jacketed line
Ik Insulation for dual insulation lines
Page 48 of 187
In general, SS foil of 0.1mm thickness is used below the insulation on
SS piping operating at higher temperature (approximately above 250
0
C) and aluminium foil of 0.25mm thickness is used for lower
temperatures to minimize chances of chloride leaching and aluminium
embrittlement in SS piping.
Page 49 of 187
6.0 NECESSITY OF INSPECTION
Page 50 of 187
7.0 INSPECTION TOOLS
Page 51 of 187
chalk). temperature during welding
23. Temperature indicating paint To monitor surface temperature
24. Intelligent pigging Health assessment of
underground cross-country
pipelines
Page 52 of 187
8.0 FREQUENCY OF INSPECTION
Page 53 of 187
8.2.2 Underground Pipelines
Piping in the installations which are in the coastal areas or near the
corrosive environment shall be inspected visually once in a year.
NB:
Page 54 of 187
9.0 LIKELY AREAS OF METAL LOSS AND CAUSES OF
DETERIORATION
3. External corrosion can take place at the pipe supports where gap
exists between piping and supports due to crevice corrosion.
4. Deterioration takes place on the pipe supports locations where
relative movement between pipe and pipe support takes place.
11. Austenitic stainless steel lines where chlorides can leach from
external thermal insulation due to rain/water are prone to stress
corrosion cracking.
Page 55 of 187
1. Points at which condensation of acid gases and/or water is likely
to occur.
2. Points at which acid-carryover from process operations is likely to
occur.
7. Valve bodies and trim, fittings, ring grooves and rings, flange
faces, and unexposed threads.
Page 56 of 187
17. Area of steam or electric tracing that contracts pipe handling
materials, such as caustic soda, where concentrated heat can
cause corrosion.
18. Area immediately downstream of chemical injection points where
localized corrosion might occur in the reaction zone.
20. Rubber lined and glass lined pipes may get damaged near the
flanges and due to cracks and deteriorations in the linings.
Page 57 of 187
Page 58 of 187
10.0 INSPECTION STAGES & PROCEDURES
i Leaks:
ii Misalignment:
a) Pipe dislodged from its support so that the weight of the pipe is
distributed unevenly on the hangers or the saddles.
iii Supports:
Page 59 of 187
b) Evidence of corrosion.
c) Distortion.
iv Vibrations:
Page 60 of 187
e) Intermittent wetting due to falling of liquid from leaky valves /
flanges or rainwater on bare hot piping (particularly alloy steel) have
resulted in cracks, leading to fire & unit interruption. Such cases
should be identified and corrective action taken.
v External Corrosion
b) The grass should not be allowed to touch the piping. If possible all
piping should be installed at an elevation above the grass growth
height. The minimum height of 0.5M should be maintained above
ground level to avoid corrosion of piping.
Page 61 of 187
Pipes should be inspected for Dents, Scratches etc. from external
sources
ix Cracks
x Inspection of Insulation
xi Concrete lining
Page 62 of 187
iv Minimum one ultrasonic scan (four readings) each on reducer /
expander and their downstream on the pipe.
vii One ultrasonic scan minimum on the straight pipe for every three
meters length at lower elevation portion where possibilities of
collection and stagnation of carryover water exists.
viii One ultrasonic scan on branch connections, dead ends etc. The
details of locations of thickness survey a piping circuit is given in the
attached sketch no.-1. The number of locations can increase
depending upon the thickness readings. The above methodology
can be used for insulated lines. Insulation on the lines may be
removed stage wise.
NOTE:
Corrosion Probes
Page 63 of 187
10.1.4 Corrosion Coupons
Page 64 of 187
Ultrasonic thickness survey should be carried out at these locations to
know the wall thickness. For straight portion one location for every 100
M should be exposed for thickness survey. If st. portion between two
bends is less than 100M, then one location in between these two
bends should be exposed for inspection. Internal metal loss and fouling
can also be determined by radiography. After inspection, number of
locations for digging and thickness survey may be increased or
decreased.
All lines should be inspected at and just below the point where these
enter the earth and concrete slab because serious corrosion occurs at
these locations due to differential aeration.
For cross country piping during each pigging, analysis of pig run
residue may be carried out to know the effectiveness of corrosion
inhibitor and to know whether internal corrosion is taking place or not.
Page 65 of 187
10.2 INSPECTION DURING SHUTDOWN
10.2.2 Cracks
10.2.3 Misalignment
Page 66 of 187
i Inadequate provision for expansion
ii Broken or defective anchors
iii Excessive friction on sliding saddles, indicating lack of lubrication or
necessity of rollers
iv Broken rollers or inability of rollers to turn because of corrosion or
lack of lubrication.
v Broken or improperly adjusted hangers
vi Hangers which are too short and thus limit movement of the piping
can cause lifting of the piping
The gasket faces of flange joints which have been opened should be
inspected visually for corrosion for defects (such as scratches, cut and
gouges) which might cause leakage. Grooves and rings of ring gasket
joints should be checked for defects like dents, cut, pitting and
grooving.
c. For RTJ flanges, ring material, hardness & ring face should be
checked.
Page 67 of 187
outside diameter of piping in high temperature service should be
measured to check for creep. Deformations.
i Hammer testing of pipe, valves and fittings of cast iron and stress
relieved lines in caustic and corrosive service should not be carried
out.
v Hammer testing should not be done on the charged lines and lines
under pressure.
Page 68 of 187
the above job shall also confirm to IBR requirements. For new Projects,
the approval for the steam piping drawings needs to be obtained from
IBR authorities at the beginning of the Project. Execution and
certification will be same as above.
Page 69 of 187
Page 70 of 187
QUALITY ASSURANCE PLAN FOR NEW
CONSTRUCTIONS
Quality assurance plan of new facilities needs attention right from the
design stage, P&ID review, checks during detail engineering,
construction quality control. Selection of the commissioning team and
the leader is also vital to ensure quality of the final facility. The major
areas to be looked into during these stages are suggested as under.
The PFD and P&ID reviews and layout checks are also need to be
reviewed critically. The Isometrics and General Arrangement Drawings
(GADs) developed by the detailed engineering contractor also needs
thorough review.
The QAP should clearly define the role and responsibility of the
Manufacturer, Third Party Inspector, PMC and Owner.
Page 71 of 187
Some specific points have been listed below based on the recent
experiences of commissioning of new facilities. These aspects should
Page 72 of 187
also be taken care of during the design stage to ensure reliability of the
new facilities.
(1) All small bore pipings and tracer lines, size ¾” and below should be
welded by TIG process for all types of joints, e.g. butt, socket, tee,
etc. to ensure proper quality of welding. Use of half coupling may
be considered to increase reliability of small-bore connections.
(2) Minimum thickness of pipe for sizes upto 1½” should be Sch.80 for
CS and AS.
(5) As far as possible long trunion types of supports more than 500mm
long are to be avoided. In case of long trunion supports are
unavoidable in straight length of pipe, it is to be provided with
reinforcement pad on the pipe.
(9) All the reinforcement pad telltale holes should be drilled and tapped
properly. Gas cut holes should not be accepted.
(11) In the Heaters having steam air decoking provision, the main lines
and decoking lines should be supported in such a fashion so that
either of the lines should not remain unsupported in the hanging
position when remaining disconnected.
Page 73 of 187
(13)Insulation windows for inspection and thickness survey are to be
provided in insulating piping of more than 6” diameter at all
approachable location with provision of caps to avoid ingress of
water.
(15)All the fittings like valves, flanges etc. in high temperature service
(> = 300 0C) should also be fully insulated if they are in open area
or the localized cooling can cause operational problems like coking
etc.
(16)All SS piping should have chloride free insulation or preferably
should have SS foil wrapped between pipe and insulation.
(25)Hard surfacing under the piping bay in offsite areas should be done
with proper slope & drainage facility.
Page 74 of 187
(26)Proper slope and gap should be provided in piping culverts to
avoid water logging.
(27)In fire water lines, the hydrant tapping should not be taken from the
bottom side of pipe. Tapping should be taken from the top or from
side.
In spite of best efforts in the design stage, the quality of new facilities
can’t be assured without proper involvement of Inspection & Project
team of the Owner. The selection of the Project team and
commissioning team is the most vital aspect for the successful
commissioning of the new facility and unfortunately is the most
neglected in our case.
(1) Spring type supports should be unlocked and cold set prior to
commissioning of the system by the contractor as per the
instructions of spring support manufacturer in presence of PMC/
Owner’s representative.
(2) The structural layout and erection should take care of adequate gap
for piping, considering insulation and expansion movement of
piping.
Page 75 of 187
(4) Piping passing through technology structure (RCC floors) or
passing near the concrete column etc. should have adequate
annular space to avoid restriction of line movement during thermal
expansion. The gap should be taken care for hot lines alongwith
insulation thickness.
(5) All the RTJ ring gaskets should have proper identification marking
with metallurgical certificate available.
(6) Positive Material Identification (PMI) should be carried out for all the
components of Alloy Steel, Stainless Steel and other higher
metallurgy piping and checked on three-tier basis to ensure correct
metallurgy. First at supplier’s shop, second at our stores and third
after fabrication & erection at site. The properly identified material
should be given a distinct colour by supplier before dispatch to
avoid any mixing with other material. Third Party Inspector should
also certify PMI.
Part of the weld joints should also be carried out for Alloy Steel/
Stainless Steel circuits in-situ. This should be incorporated in the
contract.
(7) Electrical resistance coils should be used for pre heating/ post
heating of all the alloy steel welding of dia. 2” and above. Pre
heating/ post heating should be made mandatory for all the alloy
steels irrespective of fillet/ butt weld sizes.
(9) Contractor, who is awarded the work involving use of low hydrogen
electrodes, must have a furnace suitable for baking of electrodes
at 300 0C.
(10)Welding of alloy steel butt weld joints should not be left incomplete
for long hours. Earlier in few cases, only root run was done on a
day and remaining welding was planned next day. Next day the
partially welded joints were found cracked.
(12)All critical service gate/ globe/ check valves should be site tested
prior to installation.
Page 76 of 187
(14)Flushing should be done properly after dropping the safety valves
and control valves etc. to avoid any ingress of foreign material.
Proper flushing to the satisfaction of Production Department should
be part of main contract.
(16)A list of all expansion bellows installed area wise alongwith spares
supplied should be handed over to XXX Inspection & Maintenance
Department by consultant/ contractor.
Page 77 of 187
Page 78 of 187
12.0 INSPECTION OF PIPING DURING FABRICATION
New Pipes
ii Check for pipe size (mainly diameter) and wall thickness. The
variations should be within the permissible limits as given in the
appropriate code & specification.
Old Pipes
iii There must not be any cracks, grooves, dents or other surface
defects that exceed the maximum permissible limits as per various
codes.
Page 79 of 187
resulting wall thickness is not less than that permitted by the
material specification.
6. All dents which affect the curvature of the pipe at the seem or at
any girth weld shall be removed. All dents which exceed a
maximum depth of ¼ inch (6 mm) in pipe NPS 12 and smaller or
two percent of the nominal pipe diameter in sizes greater than
NPS 12, shall not be permitted in pipelines intended to operate at
a hoop stress of more than 20 percent of the specified minimum
yield strength of the pipe. Insert-patching, overlay, or pounding out
of dents shall not be permitted in pipelines intended to operate a
hoop stress of more than 20 percent of the specified minimum
yield strength of the pipe.
Page 80 of 187
5. Flattening of the bends should be avoided and limits should be as
per the specifications of pipes.
12.4 WELDING
i After welding, all the weld joints and HAZ should be visually
checked preferably after removing the ripples for cracks and
defects. If required dye penetrant test may be carried out.
ii Radiography
Page 81 of 187
iii The welding may be checked ultrasonically in lieu of radiography.
The only limitation of ultrasonic examination is that no permanent
records are available. Acceptability of welds in radiographic and
ultrasonic examinations should be found out as per the relevant
codes.
12.6 SUPPORTS
iv The clear space around bends, loops and pipe terminal ends should
be sufficient to allow free movement of these portions on thermal
expansion.
vii The shoe on the pipelines should be fully welded to the pipe.
Otherwise corrosion may take place in space between pipe and the
shoe.
viii All the lines in the coastal refineries should be provided with fully
welded 1200 circumference pads at all the pipe supports locations
to protect the lines from external crevice corrosion.
The piping system should be pressure tested after all the welding jobs
on the line have completed. After pressure testing, if is not advisable to
do any welding jobs on the tested pipe. In the event of repairs or
additions are made following the tests, the affected piping shall be
retested.
Page 82 of 187
12.7.1 Test Fluid
The Test shall be hydrostatic using water, except for the following:
a) All joints including welds are to be left uninsulated and exposed for
examination during the test.
g) All pressure gages, flow meter etc. and other pressure parts of
connected instruments shall also be tested at the pressure at least
equal to that of line.
h) Pressure Gages
Page 83 of 187
iii Correctness of pressure gages should be ensured. Only
properly calibrated / tested pressure gauges should be used.
i) During liquid pressure testing all air should be expelled from the
piping through vents provided at all high points.
PT 1.5 P ST
=
S
Where
PT = Minimum hydrostatic test pressure (gage)
P = Internal design gage pressure
ST = Allowable stress of pipe material at test
temperature
S = Allowable stress of pipe material at temperature
When ST/S is greater than 6.5, 6.5 shall be used for
the value of ST/S for the calculation purposes.
Page 84 of 187
Hydrostatic Testing of Piping with Vessels as a System
ii Where the test pressure of the piping exceeds the vessel test
pressure and it is not considered practicable to isolate the piping
from the vessel, then the piping and the vessel may be tested
together at the test pressure of the vessel, and provided the vessel
test pressure is not less than 115% of the piping design pressure
adjusted for temperature.
iii In jacketed lines the jacket shall be pressure tested on the basis of
jacket design pressure unless other wise limited by the engineering
design.
Pneumatic Testing
Note:
i The pressure shall be maintained for a sufficient time not less than
10 minutes to determine if there are any leaks.
Page 85 of 187
iii Systems (such as underground lines) that cannot be inspected
visually for leaks should be tested by applying the desired pressure
and then removing the source of pressure. The pressure drop,
observed for an extended period, will be an indication of system
tightness. However, lengthy test periods may require temperature
corrections, when employing this method, pressure recorders are
used to furnish a permanent record of test.
b) API RP-1110 may be used for guidance for the hydrostatic test.
Page 86 of 187
a hoop stress of 50 per cent of the specific minimum yield
strength of the pipe.
Leak Testing
12.8 PAINTING
The surface should be free of moisture, dust, soil, rust, oil grease
etc. sand blasting/shot blasting method should be preferred
wherever practicable. After sand blasting, the surface should not
be left unprimed for more than 4 hrs.
iii The primer should be applied as soon as possible after the surface
preparation.
Page 87 of 187
v Each coat of paint must be thoroughly dry before the next is
applied unless a special wet-on-wet process is used. If the thumb
is pressed against the film with a slight twisting movement and no
damage to paint occurs, the film is hard enough for the next coat to
be applied. For curing time for each coat, manufacturer
recommendation may be followed.
A Common Paint Colour Code System for Piping & Equipment have
been developed and approved in line with ANSI Colour Code System
with minor changes to suit Refinery application. This will help in having
common colour identification for each service across all the Refineries,
easily identifiable colour for various groups of services. The new Colour
Code shall be followed in Refineries for all the new Projects and
additional facilities Projects. As regards, existing Plants the new Colour
Code System will be adopted in a manner, which coincides with the
repainting schedule of the Piping to optimize expenditure on this
account. The Common Paint Colour Code System for Refineries is
enclosed as Annexure –V for ready reference.
1. Mitigate corrosion
Page 88 of 187
5. Have properties compatible with any supplemental cathodic
protection.
c) Pipe to soil voltage of (–) 0.85 volts with respect to Cu-CuSO 4 half-
cell has been found to give adequate protection to the cathodically
protected pipelines. The excessive voltage may damage the
wrapping and coating of the pipe. A voltage (–) 1.2 volts may
adversely affect the wrapping and coating.
12.10 INSULATION
Page 89 of 187
insulating type coating must have low moisture absorption and provide
high electrical resistance. The insulating material for stainless steel
piping must contain low chlorides to prevent stress corrosion cracking.
For high temperature SS piping Al-shielding on the insulation should be
avoided. Check for clearance for piping with the ground. Piping should
not be in contact with grass, soil, water etc.
Page 90 of 187
RETIRING LIMITS
PD
T =
2 SE
Where t = The required thickness of the pipe wall in inches
P = Pressure within the pipe, in pounds per square inch
D = Outside diameter of the pipe, in inches
S = Allowable unit stress, in pounds per square inch, at the
maximum operating temperature
E = Longitudinal joint efficiency
Page 91 of 187
PIPELINE REPAIRS AND INSPECTION
The portion of piping, which has reached the retiring limit or will reach
retiring limit before the scheduled next inspection should be replaced.
While replacing the pipes the following points should be considered:
1. The metallurgy and dimensions of the new pipe should match with
the existing pipe. The new pipe should be inspected (Refer para
10.1 for details)
3. When ERW pipes are used, the weld seam should be kept
staggered and ERW or welded seams of the pipe should not
appear at 6 O’clock position.
5. Inspection of joint fit up, etc. should be done as per the inspection
requirements originally specified.
Page 92 of 187
Gate valves, which have been used for throttling, should be measured
for thickness at the bottom between the seats, as serious deterioration
may have occurred because of turbulence. This is a particularly weak
point because of the wedging action of the disc when the valve is
closed. The seating surface should be inspected visually for defect,
which might cause leaking. The wedging guides should be inspected
for corrosion and erosion. The connection between the stem and disc
should be inspected to assure that the disc will not become detached
from the stem during operation. Swing check valves can be inspected
by removing the cover or cap. The clapper or disc should be checked
for freedom of rotation and the nut holding it to the arm should be
checked for security and the presence of a locking pin, lock washer, or
tack weld. The arm should be free to swing and the anchor pin should
be inspected for wear. Also the seating surface on both the disc and
valve body can be checked for deterioration by feeling them with the
fingers. After the valves has been reassembled, it should be
hydrostatically and/or pneumatically tested for tightness. If tested
pneumatically a soap solution should be applied to the edges of the
seating surface and observed for any evidence of leakage.
Page 93 of 187
DOCUMENTATION
Page 94 of 187
Page 95 of 187
16.0 ANNEXURES
Annexure – I
i Dents which affect the pipe curvature at the pipe seam or at any
girth weld;
Page 98 of 187
7. Localized Corrosion Pitting
L = 1.12 B Dtn
B= c/tn
-( 1.1 c/tn – 0.15 )2 – 1
L = Maximum allowable longitudinal extent of the corroded area as
shown in Fig. 451.6.2 (a) (7) inch (mm)
B = A value not to exceed 4.0 which may be determined from the
above equation of Fig 451.6.2 (a) (7)
D = Nominal outside diameter of the pipe, inch (mm)
tn = Nominal wall thickness of the pipe, inch (mm)
C = Maximum depth of the corroded area, inch (mm)
Page 99 of 187
0.67 C
1– ( tn )
0.67 c
Pd = 1.1pi 1–
G2 + 1
tn
Where
G = 0.893 L
( Dtn )
G = A value not to exceed 4.0 in the above analysis and
which may be determined from the above equation
Pd = Derated internal design gage pressure, psi (bar)
Pi = Original internal design gage pressure, based on
specified nominal wall thickness of the pipe (see 404.1)
psi (bar).
L = Longitudinal extent of the corroded area as shown in fig.
451.6.2 (a) (7) in inches (mm).
For Tn, C and D, see 451.6.2 (a) (7)
For values of G greater than 4.0
Pd = 1.1Pi 1- C
tn
Moisture, oxygen and acidic environment are the main contributing factors
causing deterioration on the internal or external surface of pipes. These may
cause rusting, pitting of surfaces and other forms of deterioration. Hence new
pipe should be preserved properly in the pipe-stacking yard. Following points
should be considered while stacking new pipes in store yards.
i All the pipes (C. S. and low alloy steel pipes) should be stacked properly
in horizontal position over the steel racks or wooden rafters or sleepers.
ii All the tubes/pipes should be preferably stacked under the shed to protect
from rainwater.
iii All the pipes/tubes end should be plugged with suitable wooden plug or
plastic caps.
iv Before placing the plug/ caps the inside surface of pipes or tubes should
be flushed with dry air to ensure absence of any corrosive materials.
v For pipes with threaded connection extra care should be taken in
protecting the threads by putting plastic caps or wrapping with jute cloth
(Hessian cloth).
vi Pipes or tubes should not touch the ground or should not be allowed to
get submerged in ground or pool of water.
vii Pipes or tubes should be stacked away from acidic/corrosive environment
and also away from cooling tower as far as possible.
viii The pipes external surface should be cleaned manually and painted with
a coat of bituminous paint or any lubricating oil of viscosity of SAE 30
compounded with inhibitor and wetting agent (spent oil). Any used
lubricating oil can be used. It can be applied by brushing, splashing or
spraying. Anti corrosive compound, SERVO-RP-102 or equivalent can be
used as oil preservatives.
ix Water proof wrapping paper are also used for storing new pipes. Paper
coated with volatile corrosion inhibitor (V. C. I. paper) have long life and
easily available.
x A separate area should be earmarked for items covered under I. B. R.
pipes should have separate codification with same preservation
procedure.
xi Different types of pipes should be stacked separately.
xii In cases where it is decided to paint the entire piping, the colour and sizes
of legend letters stenciled on the piping for easy identification of materials
near the both ends of pipe.
Before taking shutdown for idle time preservation, liquid/solid materials from
all the lines, vessels, exchangers and any other metallic equipment shall be
drained, thereafter, all the lines, vessels and equipments shall be cleaned
thoroughly by steam flushing and water/solvent flushing. This is required to
avoid choking of lines and equipments by sulphur and sulphur compounds, as
any leftover sulphur and sulphur compounds, upon cooling from incrustation,
which cannot be removed easily.
STATIC EQUIPMENT
Acid Gas Knock Out (K.O) Drum (Carbon Steel), Hydrogen Rich Gas
K.O.Drum, Fuel Gas K.O.Drum: SWS Gas K.O.Drum, Ammonia Rich Gas
KOD. Acid Gas condensate collection drum, SWS / NH3 Rich Gas
condensate Drums. Atmospheric Flush Drum
Remove all water and liquids inside the Blow down drum. Clean the
inside drums manually. Wash with potable water if required and dry with
air.
Remove all the chemicals from the chemical injection pot and store separately
in plastic carboys. Wash inside surface of the pot and connected piping by
potable water and drain out after washing.
Blind all the inlet and outlet nozzles and ensure all the openings are
sealed and leak free excepting one inlet and outlet.
Purge with Nitrogen and maintain a positive pressure of 5-10 psig.
Shell side: Boiler feed water / Medium Pressure steam:
Flush with D.M. water and then fill with D.M. water containing 200ppm
of Hydrazine. The system shall be completely filled.
Blind all the inlet and outlet nozzles and ensure all the openings are
sealed and leak free excepting one inlet and outlet.
Purge with Nitrogen and maintain a positive pressure of 5-10 psig.
Flush with D.M. water and then fill with D.M. water containing 200ppm of
Hydrazine.
Blind all the inlet and outlet nozzles and ensure all the openings are
sealed and leak free excepting one inlet and outlet.
Purge with Nitrogen and maintain a positive pressure of 5-10 psig.
Flush with D.M. water and then fill with D.M. water containing 200ppm of
Hydrazine.
Clean inside of the pit manually and close the pit of all openings to
avoid any ingression of water and debris.
Heating coils (Low Pressure steam)
Flush with potable water and fill with D.M. water containing 200 ppm of
Hydrazine.
Service H2S, SO2, Sn, N2, CS2, H2O) Wash with potable water/solvent to
remove all chemicals completely and finally flush with D.M. water, dry with
instrument air and keep closed.
Remove all the nozzles and oil gun and keep it in safe custody.
Cover the burner from inside by a plastic sheet to avoid falling of
debris.
Grease and/or oil all moving parts associated with burners, Seal burner
openings.
Keep the yard clean and prevent accumulation of dirt and debris. Keep the
sulphur bags covered.
ROTATING EQUIPMENT
Apply Industrial grease and petroleum based oil in the exposed areas of shaft
and manually rotates the shaft once in a fortnight.
Drain all the vents and drains on both ends of the pump
Drain the casing and the bearings house
Flush with D.M. water to clean and dry with air.
Fill the pump casing with a petroleum based oil of approximately
SAE20 to 30 viscosity. Rotate the pump shaft to ensure complete
coverage.
Rotate the pump shaft manually once in a week
Spray the exposed portion of the pump shaft with petroleum based oil.
Repeat if necessary.
Fill the shaft couplings with rust preventive industrial grease with
corrosion inhibitor.
Spray the gland with the petroleum based oil of approximately SAE 20
to 30 viscosity.
Change of lubricants as per manufacturer’s instructions.
Motors
The cooling water system shall not be shutdown, Cooling water shall be
circulated through coolers, condensers and piping as per design flow rate.
Fill and keep pressurized with potable water containing 500mg/l of REMIDOL
4000, manufactured by chemtreat India Ltd. Navi Mumbai or VISCO 3900,
supplied by NALCO Chemicals, Calcutta.
Process side of Shell and Tube Heat Exchangers: Seal all openings purge
with nitrogen and keep under positive pressure of 5-10 psig.
INSTRUMENTATION
Valves
Lubricate and cover exposed valve stem with Industrial grease. Spray
petroleum oil in between flanges, if any, operate the valves once in a fortnight.
Place bags of silica Gel in the cabinet of switchgear and motor controls
located in the buildings and maintain heat in the buildings.
Ensure environment is dust free by keeping the door closed.
Before taking shutdown for idle time preservation, the Amine Treating Unit
shall be operated without feed process gas to remove acid gases from amine
solution as much as possible. Required level of corrosion inhibitor shall also
be maintained in the circulating amine before idle time shutdown. This is
required to avoid corrosion of carbon steel surfaces by the leftover amine
solution after the shutdown.
STATIC EQUIPMENT
Purge individual equipment with Nitrogen and ensure that all openings are
sealed and leak free. Maintain under a positive pressure of 5-10 psig.
Clean with potable water and dry by compressed air and keep closed.
1st stage and 2nd stage caustic wash vessel. Clean and flush with potable
water. Keep covered.
Gas side: Purge with Nitrogen and seal all the openings and maintain positive
pressure of 5-10 psig with Nitrogen.
Cooling watersides: Drain cooling water and purge with Nitrogen and keep
under positive of 5-10 psig N2.
b) Heat Exchanger
For plate Heat Exchanger:
Amine Regenerator Reboiler Steam Side Keep filled with D.M. water
containing 200ppm Hydrazine
Lean amine cooler Amine side: Purge with Nitrogen and seal all the
openings maintain positive pressure of 5-10 psig.
Cooling waterside: Drain, purge with nitrogen and keep under nitrogen
pressure of 5-10 psig.
ROTATING EQUIPMENT
Filters
Charcoal Filters
Cartridge Filters
Drain, backwash with potable water and keep filter media/cartridge under
Potable water
INSTRUMENTS
Pressure instrument
Temperature instruments
Level instruments
Flow instruments
All the above instruments shall be protected from weather by covering with
plastic sheet.
PIPING
Purge with Nitrogen and seal all the openings without any leaks and maintain
positive pressure of 5-10 psig.
Antifoam agent liquid piping. Flush with potable water and dry by air.
Valves
Lubricate and cover exposed valve stem with Industrial grease. Spray
petroleum oil in between flanges, if any operate the valves once in a fortnight.
MOTORS
INTRODUCTION
NEUTRALIZATION SOLUTION
Use neutralizing tank by adding low chloride 250 Kgs. Soda ash and 50
Kgs. Of Sodium nitrate for each batch. Alternative combination and
batches may also be used as may be suitable.
Scheme for 2 (two) circuits may be made. One for tube side of exchanger
alongwith other equipment that can easily be taken on line e.g. Reactor,
vessels etc.
Another circuit may be made for covering shell side of the exchanger and
some other equipment in this circuit.
Before taking the Reactor into the circuit for neutralization, approval of
licensor should be taken. If no work is involved in Reactor, the same may
be maintained under Nitrogen positive pressure with inlet and outlet
positively blinded.
COLUMN
FURNACE/ HEATER
External
External surface should be sprayed with suitable sprayer (long nose nozzle).
Swabbing may not give uniformity and will not be possible to cover the entire
lengths and breadths of tubes. Entire operation should be done at the earliest
possible time. Minimum number of manhole/pinholes should be opened.
Internal
Can either be kept under nitrogen positive pressure if feasible or filled with
neutralizing solution by pumping and ensuring that the heater is completely
filled with solution through suitable inlet and outlet joints.
Procedure
Fill the tube side and Reactor from the filling point No. 1 (see attached
drawing) with the solution backward to Exchangers E01 C/B/A tube side.
Take samples from points 2 and 4 and check the concentration of the solution,
prepare additional batches and continue re-filling if the solution concentration
is less than 1%.
Soaking Time
Soak the system for 8 hours minimum before dumping the catalyst, if Reactor
is involved.
OUT SOLUTION
2
E-1A
0
4
REACTOR
OUT
V-10-01
E-1B
4 1
E-1C
1
E-05
03
TO HEATER
3 02
TYPICAL PROCESS EQUIPMENT NEUTRALIZATION SCHEME
Annexure-II(d)
1.0 General
1.1.1 Polythionic acid SCC normally occurs with the standard (0.08% carbon
max.) and high carbon (0.10% max.) grades that have become
sensitized either by weld fabrication or by operation in the sensitizing
range of 3700 to 8150C (7000 to 15000F).
1.1.2 Low-carbon (0.03% max) and chemically stabilized grades (e.g., alloys
with titanium or columbium alloying additions) may also become
sensitized by prolonged exposure in the sensitizing temperature range.
Sensitization will be more rapid in the presence of carbon (coke).
1.2 The degree of sensitization and stress levels are generally not known.
Therefore, austenitic stainless steel and other austenitic alloy process
equipment on which sulfide corrosion products may be present should
be protected using one or more of the following methods.
1.2.1 Exclusion of oxygen (air) and water by using a dry nitrogen purge.
1.2.2 steels and other austenitic alloys are effectively protected with properly
applied alkaline solutions.)
1.2.3 Exclusion of water by using a dry air purge with a dew point lower
than–150C (50F).
1.4 The internal surface of austenitic stainless steel and other austenitic
alloy furnace tubes maybe susceptible to polythionic acid SCC whether
or not they have been thermally decoked and should be protected. If
thermally decoked, protection should be performed after decoking.
2.2 If reactors to be opened but furnaces are not, the furnaces may be
purged with nitrogen and blinded off. A small positive nitrogen pressure
should be maintained.
2.2.1 Nitrogen should be dry and free of oxygen. (The user is cautioned that
oxygen levels as high as 1000 ppm have been found in commercial
nitrogen).
2.3 At the user’s discretion, 5000 ppm ammonia may be added to the
nitrogen.
2.5 If steam is being used for purging or steam air decoking, steam
injection should be stopped before the metal temperature cools to 56 0C
3.1 Sodium carbonate (soda ash) solutions are used to protect austenitic
stainless steels and other austenitic alloys from polythionic acid SCC.
Solution pH should be greater than 9. These solutions may also
contain an alkaline surfactant and corrosion inhibitor.
3.2 The recommended wash solution is 2 wt% soda ash (industry practice
varies from 1 to 5 wt%, with a majority using 2 wt% solutions). A 1.4 to
2 wt% soda ash solution will provide a sufficient level of residual
alkalinity on metal surfaces after the solution drain from the equipment.
Additionally, this low concentration will facilitate solution preparation.
3.5 The addition of an alkaline surfactant to the wash solution at 0.2 wt%
concentration is recommended to promote penetration of coke, scale,
or oil films. Heating of the wash solution to 49 0C (1200F) may
accelerate the penetration of oily films and residues.
3.6.1 At the user’s option, 0.4 wt% sodium nitrate maybe added. (In
laboratory tests, low concentrations of sodium nitrate have been found
4.1.1 The equipment must be alkaline washed before any exposure to air. It
is very important to contact 100% of the equipment’s internal surfaces.
4.1.4 It is essential that the alkaline wash not be followed by a water wash.
4.2.1 After hydro jetting, equipment should be kept dry and out of the
weather. If this is not possible, the soda ash wash should be repeated
as required to maintain a residual film of soda ash. Equipment shall be
reinstalled with soda ash residual film left on surfaces.
4.4 If sodium chloride ions cannot be tolerated in the process system, the
equipment can be washed with ammoniated condensate after being
closed. If the unit is not started up immediately, the solution can be left
5.3.2 If the catalyst is to be discarded, the reactor can be filled with soda ash
solution to wet both catalyst and reactor parts. The solution strength
should be increased to 5 wt% to compensate for the acidity of deposits
held by the catalyst. Unloading can then be conducted in air while
keeping the catalyst wetted with soda ash solution to prevent
pyrophoric ignition. The reactor should then be washed down with soda
ash solution and dried prior to repairs or catalyst loading.
5.3.3 If the user wishes to eliminate the use of soda ash solutions and fresh
air breathing equipment while unloading the catalyst, the catalyst may
be dumped, following wetting with good quality fresh water (less than
50 ppm chloride), without nitrogen purging. This should be preceded by
a careful investigation to determine that:
S. No. CONTENTS
1.0 General
1.1. Introduction
1.2 Scope
1.3 Definition
1.4 Consideration for Selection of Protective System
1.0 GENERAL
1.1. INTRODUCTION
1.3 DEFINITIONS
a) Preservation:
Preservation is safeguarding of unattended and inactive equipment
from deterioration during their down period.
b) Coating :
Coating means an application of a coat of preservative media like
paint, Oil or grease etc.,
c) Surface Preparation:
Surface Preparation includes cleaning of the parent metal surface
for removing foreign particles like rust, scale, liquid etc., by
mechanical or chemical cleaning techniques.
a) Period of shutdown
c) Probability of reuse
a) Heat Exchangers
d) Cooling Towers
e) Storage Tanks
f) Boilers
g) Pipelines
d) Reassemble all components, blank off all nozzles and close all vents
and drains.
h) For finned air cooler, clean the tubes internally, circulate preservative
oil through the tubes and seal off all the header boxes.
b) Purge with nitrogen after ensuring that all the openings are sealed
and leak free. Maintain a positive pressure of 100 mm of water
column. Alternatively spraying oil on the inner surfaces or filling and
draining oil or placing desiccants like bags of lime or silica gel may
be considered.
c) Remove the safety valves (bolted only) and close all the openings.
Safety valves shall be stored indoors.
d) Coat all the exposed bolts anchor bolts, gaskets, flange faces with
grease/preservative oil.
In heaters when idle, corrosion may take place either due to condensation
or chemical reaction of atmospheric moisture with scale/deposits on the
tubes. Following procedures for preservation should be adopted.
b) All the hinges on access doors, peep holes, drains and dampers, etc.
should be coated with grease to ensure smooth operation after
shutdown.
d) Refractory should be kept dry at all the times to prevent any cracking
due to water ingress. The ingress of atmospheric moisture should be
avoided by proper capping of stack and duct opening and by sealing
all those locations from where water or moist air can seep in.
Supplementary heat or a desiccant can also be considered.
The cooling tower consists of concrete basin, main structure of red wood,
fan and fan motor. The conditions are more severe when the cooling
tower is in operation than it is idle. Following preservation procedures
should be adopted while cooling tower is idle.
b) Drain all water from the basin, remove all debris, muck, etc. and clean
the basin thoroughly.
d) Carryout repairs to the concrete walls and floors of the basin for cracks,
loose concrete, slope of the floor, etc.
g) Clean the fan with appropriate cleaner and apply suitable paint, if
required.
h) Cover the fan drive gear with a light grease and water proof paper.
The dry wood of an idle cooling tower is a serious fire hazard. Therefore,
for idle periods of about two months, a perforated hose should be laid
around the tower and spray water periodically to keep wood in wet
condition all the time. For extended shutdowns, the plenium and fill should
be sprayed with a fire retarding chemical and a biocide.
a) The tank shall be made free of gas and any residue. Extra precautions
shall be taken when pyrophoric iron sulfide or residue of leaded
gasoline are present.
b) All the loose scales on the internal surface of the tank should be
removed.
g) If the tank is with steam coils, the condensate should be drained off
and the steam coil should be positively blinded.
a) Dry Storage
After placing the quick lime or silica gel in the boiler as per
manufacturer’s recommendation, all openings should be tightly closed.
The unit should be checked at an interval of every two or three months,
as experience dictates, for renewal of the lime or regeneration of silica
gel.
b) Wet Storage
The boiler should be cleaned and inspected and then filled to the normal
water level. If deaerated water is not available, dissolved gases should
be expelled by boiling water for a short time with boiler vented to
atmosphere. The boiler water alkalinity should be adjusted with caustic
soda to a minimum of 400 PPM. Sufficient Sodium sulfite should also be
added to produce a minimum sulfite residual of 100 PPM. After the boiler
is cooled and before a vacuum is created, the unit should be filled
completely with water and all connections closed.
Nitrogen or other inert gas may also be used for storage purpose. A
slight positive pressure of the gas is maintained after the boiler has been
filled to operating level with deaerated feed water.
2.6.2Hot storage
c) Start FD fan
e) After about 5 minutes of venting of steam, open the main stop valve
and close the start up vent and SH drain valve
a) Close the accumulator steam 2” gate valve near the MUD DRUM
b) Open the flange joints and valves at low points to ensure complete
draining.
g) Spray all external surfaces of the valves with oil and cover valve
stem with grease. Relief valve should be rotated or separated from
their discharge piping. Their discharge side should be sprayed with
oil and covered with water proof paper or plastic.
h) Tighten all flanges. Spray mating flanges joints with oil, and wrap
them with suitable wrapper to prevent crevice corrosion between
mating flanges.
On idle units, process and utility lines (except fire water lines) should be
blinded off near the battery limit.
a) Pumps
b) Compressors
c) Steam Turbines
d) Gas Turbine
e) Diesel Engine
a) Close the suction and discharge valves and blind the same. Isolate
the pump from all other connected auxiliary lines. In case the pump
is to be removed and kept in storage, disconnect all pipe
connections and blind the suction and discharge flanges.
b) Open all vents and drains in the pump casing and bearing housing.
Flush the casing and housing with a suitable solvent or cleaning
agent.
c) For pumps with gland packing, remove the packing, coat the interior
of the stuffing box with light grease, repack with a few rings of
ordinary non-metallic packing to avoid ingress of water into the
stuffing box and then retighten the gland.
d) For pumps with single mechanical seal, loosen the seal gland, pack
the seal with a light grease and tighten the seal gland lightly.
e) For pumps with double mechanical seal, drain the stuffing box and
flush it with a cleaning agent, plug the lower stuffing box drain and
fill it with lightweight grease or lubricating oil.
f) Plug the bearing housing drains and fill the bearing housing
completely with lubricating oil.
g) Close all drains and fill the entire pump casing with a lubricating oil.
Rotate the pump shaft slowly to ensure complete coating of the
inner surfaces.
a) Open all vents and drains on both the liquid end and steam/air end
of the pump.
c) Remove the packing from the stuffing box and coat the stuffing box
and rods inside the box with light grease. Repack the stuffing box
with a non-metallic packing and re tighten the gland.
d) Remove the valve cover plate from liquid end of the pump and slide
valve cover from steam/air end. Remove a valve from each end of
each cylinder on the liquid end. Flush the cylinders with a cleaning
agent. Fill all cylinders with suitable preservative oil. Fill the steam/
air cylinders with a suitable preservative oil through slide valve
opening at the steam/air end. Slowly bar each piston back and
forth.
e) Apply a suitable rust preventive to all valves and valve covers and
install them back.
f) Drain the excess preservative oil from the cylinders and close all
vents and drains.
b) Remove the pump, clean, fill the liquid chamber with lubricating oil
and fix back the pump.
d) In case of diaphragm type pump drain the hydraulic oil from the
hydraulic chamber, flush and fill the hydraulic chamber with a
lubricating oil.
e) Drain the gear box oil; flush and fill the gear box with a lubricating
oil.
f) Close all vents and drains in the pump and gear box.
g) For pumps with gland packing, remove the packing, coat the interior
of the stuffing box with light grease, repack with a few rings of
ordinary non-metallic packing to avoid ingress of water into the
stuffing box and then retighten the gland.
b) The lube oil and seal systems should be operated for half an hour
once a week to protect the system against corrosion.
a) Blind off all process, oil supply and oil drain openings
b) Remove the rotor and associated parts, such as bearing and seals
and diaphragms.
While the crank mechanism lube oil pump in operation, rotate the shaft
by a few revolutions at least once in every two weeks. The shaft needs
not to be stopped at previous locations.
d) Apply suitable grease on the shaft end outside the crankcase and
all other exposed surfaces.
f) When lubricated compressors are kept idle for less than 6 months,
wet the cylinder and packing with sufficient quantity of lube oil and
also have 10-15 piston strokes at the same time. Repeat the
operation once in every two weeks.
g) When dry lubricated compressors are kept idle for less than 6
months, Seal all holes of the cylinder, purge with dry nitrogen and
maintain a pressure of about 100 mm WG. If nitrogen is not
available, keep sufficient quantity of dehydrating agent such as
silica gel and close tightly. Check periodically effectiveness of the
dehydrating agent.
j) Drain cooling water from cylinder jackets, inter coolers and after
coolers wherever applicable.
k) Purge the piping with dry nitrogen. Close all openings and
maintain a nitrogen pressure of 100 mm of WG. As an alternative,
close all openings tightly and keep inside the piping sufficient
quantity of dehydrating agent such as silica gel, in accordance with
their dimensions and shape. Check the dehydrating agent
periodically.
When the compressor kept idle for more than two months, the following
steps should be adopted
b) Remove the moisture trap flange of the inter cooler and place
sufficient quantity of moisture absorbing agent inside the moisture
trap.
c) Close the flange hole of moisture trap airtight. Keep the flange
separate in dry condition.
f) Drain off the lubricating oil and refill the oil sump with a suitable
preservative oil
g) Run the compressor on no load after first two months for at least
half an hour to ensure that the normal working temperatures have
been reached. Before running the compressor, remove and discard
the moisture absorbing agent and refit the moisture trap flange.
i) When the unit is standing idle for an extended period the above-
mentioned procedure should be repeated every six months.
j) Drain the cooling water, close the inlet and outlet valves and fill the
line with fresh water.
When the compressor is going to be idle fore more than six months
c) Flush and fill the casing of the screw elements with a suitable preservative
oil.
e) Drain the cooling water, close the inlet and outlet valves and fill the line
with fresh water dozed with anticorrosive chemical.
f) Rotate the compressor drive shaft a few turns by hand once a week.
g) Change the preservative oil every six months/one year as per schedule.
a) The lube oil system and governing oil system shall be either kept in
service on a weekly basis or filled with a low positive pressure of
dry nitrogen.
b) Dry nitrogen may be admitted into the turbine including all steam
spaces and gland sealing through one of the pressure tapping
points in the turbine exhaust hood of turbine case. This shall be
done during a period of minimum humidity and air inside the turbine
is to be purged out completely.
a) For a single shaft turbine, cranking has to be done for half an hour
once in a week keeping the lube oil system under operation. Apart
from cranking of HP shaft, Low pressure (LP) shaft of two-shaft
turbine has to be rotated manually for a few complete revolutions
every week with help of suitable fixtures fitted with coupling hub in
the direction of rotation keeping the lube oil under operation.
Machine already commissioned and the idle period is longer than one
month
When the engine is kept idle for a period more than six months the
following steps should be adopted.
b) Drain all lubricating oil from the oil sump and refill the oil sump with
suitable preservative oil.
c) Drain coolant from cooling system and thoroughly flush with clean
water and suitable radiator cleaner. Refill the cooling system with
mixture of water and suitable radiator protector in the ratio
recommended by the manufacturer.
d) Fill two portable containers one with diesel and other with the
preservative oil mentioned in (b) above
e) Start the engine with engine pulling fuel from the container with
diesel through the filter and the injector drain line flowing into the
container with diesel. Once the engine is running smooth at idle,
switch the fuel line to the container with preservative oil. Run the
engine 5-10 minutes on NO LOAD till it is observed that the
preservative oil is coming out from injector return line. Stop the
engine.
f) Drain the oil sump, fuel filter and fix back the drain plugs.
g) Turn fuel pump manual shut off valve to ‘OFF’ position so that the
engine will not start.
h) When the engine has become cool, disconnect the inlet and
exhaust manifolds, spray suitable preservative oil into air intake and
exhaust outlets, engine being turned by hand during spray
operation. Cover all intake manifold opening with tape to prevent
entry of dirt and moisture. Cover all engine openings of cylinder
block, oil breather and crank case including coolant inlets and
outlets. All vents, dynamo, starter motor, magneto if any and air
cleaners to be carefully sealed with water proof paper and water
proof adhesive tape.
i) Clean off all accumulated dirt and rust preventive using suitable
solvent from exterior of engine.
ii) Remove all paper cover, tape and wrappings and reinstall the
dismantled components. Carry out precommissioning checks.
v) Adjust the injectors, valve and belts and check cylinder head
cap screws, filters, air filter and screens.
vii) Run the engine with diesel on NO LOAD LOW IDLE for 5
minutes to flush the entire fuel system out of any preservative oil
When the diesel engine is kept in store as a spare complete set and
likely to be unused for more than six months
b) Just after six months from the date of dispatch, the preservative oil should
be drained off from the engine. After flushing the internal parts with a
suitable solvent, wipe and clean the parts with the solvents. Clean the
parts with dry felt cloth.
c) After drying suitable rust preventive should be again sprayed and dried on
the parts
d) The crank case should be filled with suitable rust preventive and should be
filled up to the high oil level mark of crank ease
f) All the openings to be covered or blinded to make the engine air tight
g) Run the lube oil pump once in week to achieve the operating pressure
inside the engine and then stop the pump. By this method all bearings,
pistons connecting rod, rocker arms, valves, etc. will be lubricated
h) After six months repeat the above procedure as per steps (b) to (g)
mentioned above
The following procedure should be adopted for preserving idle fans and
blowers
a) Coat the interior of the casing and the impeller of the fan/blower
with a suitable rust preventive.
f) In case of oil lubricated bearings drain the oil. Flush and fill the
housing fully with suitable grade of fresh lubricating oil. Close all
openings of the bearing housing
h) Drain the oil from gear box and refill it with a high grade mineral oil.
Clean the exterior surfaces of the gear box and paint them. Wrap all
exposed shaft with Plastic tape. Store the reducer in a warm and
dry. The gear box rotor shall be rotated by the following procedures:
Both CS and low alloy steel heater tubes can be stored outdoor on a
sloped concrete surface. These tubes shall be kept either on steel
racks or wooden rafter. Tubes shall not be allowed to get submerged
in the ground or in contact with water. Both the ends of tubes shall be
suitably capped or plugged. CS heater tubes shall be given a coat of
oil preservative externally before stacking the tubes. 300 mm length
at each end of tube shall be coated with grease and water proof
wrapping paper where rolling operation is performed. To avoid
chloride attack, it is preferable to store Stainless steel heater tubes
indoors on wooden rafter with both the ends plugged.
CS/ Low alloy steel cast plug type return bends should be stored in a
covered shed. Grease preservative shall be applied on all the
machined and threaded surfaces. However other type of return bend
can be stored outdoors after applying necessary protective coatings as
given to heater tubes in downward position to avoid any accumulation of
water inside the bend.
Fasteners shall be kept indoors. Carbon steel and alloy steel fasteners
shall be stored in separate bays after oil preservation spray. Stainless
steel fasteners do not require any protection.
End cover of all the valves shall be plugged by wooden/ rubber/ PVC
blanks.
4.3.1 Bundles:
Tube bundles of brass/ stainless steel and high alloy steel shall be
stored on wooden rafters with proper covers. Special care needs to be
taken for SS bundle to avoid chloride attack. No preservative is needed
for these bundles.
4.3.2 Tubes:
These shall be stored indoor. CS/AS fittings shall be kept after a spray
of oil preservatives. Stainless steel parts shall be kept as it is.
Castables shall be kept in dry storage and protected from rains and
moisture. The stacking of castables shall start approximately 15 cms
above the concrete floor which itself shall be sufficiently above ground
level. If the floor is not dry ensure storage of bags above the damp floor
by providing timber boards on bricks, planks or any other suitable
device.
4.11.1 Rotor: -
4.11.2 Casing:-
a) Inspect the Crank case cover to check the condition of crank shaft,
connecting rod and other components. After cleaning them thoroughly
flush and drain the Crankcase by filling suitable preservative oil and then
fill the same oil upto the Crank Case oil level.
b) Open the inspection cover to check the condition of piston rod, rod nut,
cross head, etc and after cleaning these are to be coated with rust
protective layers. Close the crank case cover to prevent the entry of dirt/
dust and moisture.
When the oil free screw air compressor is not commissioned and kept idle
for more than five months.
a) Renew the drying agent such as silica gel placed in the inter cooler
moisture trap immediately upon receipt of the compressor at site
b) Renew the drying agent such as silica gel kept in the inter cooler moisture
trap once in every 3 months
d) Ensure that there is absolutely no water in the crate, on any plastic cover,
or any where along the canopy or the base frame of the unit
e) Install a motor driven special lube oil pump of small capacity capable of
developing the maximum operating pressure of the main oil pump of the
compressor with suction of the pump connected to the oil sump drain point
and the discharge of the pump connected to the upstream of the lube oil
filter.
g) Run the special oil pump for 15 minutes. While the oil circulates, turn the
compressor coupling by hand. The silica gel kept in the inter cooler
moisture trap is to be removed before starting the lube oil pump. After
lubrication insert new silica gel.
5.0 REFERENCES
(iii) ASME Boiler & Pressure Vessel Code, Sec VII – Recommended
Rules for care of Power Boilers.
EQUIVALENTS SPECIFICATIONS OF ASTM TO BRITISH, FRENCH, GERMAN, ITALIAN AND SWEDISH STANDARDS
1 2 3 4 5 6 7 8
MATERIAL API 5L U.S. SPECIFICATIONS BRITISH FRENCH GERMAN ITALIAN SWEDISH NOTES
Seamless BS. 3601 GAPAVE 411 DIN 1629 Aq 35 UNI 663C SIS 1233-05 1,2
Grade A HFS 22 or CDS 22 A 37C St 35 Aq 45 UNI 663C Sis 1434-05 3,4
Grade B HFS 27 or CDS 27 A 42 C St 45
Carbon steel Electric resistance welded Bs 3601 …. DIN 1625
line pipe Grade A ERW 22 …. Blatt 3st 34-2/Electric …. SIS 1233-06 45
Grade B ERW 27 …. Blatt 4st 37-2/ resistance …. SIS 1434-06
welded
Electric fusion welded BS 3601 (Double …. DIN 1626 …. ….
welded)
Grade A EFW 22 …. Blatt 3st 34-2/ Fusion …. …. 2,4
Grade B EFW 27 …. Blatt 4 st 37-2/ welded …. …. 5
Furnace butt BS 3601 …. DIN 1626 ….
Welded BW 22 …. Blatt 3 st 34-2 Furnace butt …. ….
welded
ASTM A 53
Seamless BS, 3601 Gapave 411 Din 1629 Aq35 Uni 663C SIS 1233-05 1,2
Grade A HFS 22 or CDS 22 A 37 C St 35 Aq45 Uni 663C SIS 1434-05 3,4
Grade B HFS 22 or CDS 22 A 42 C St 45
Electric resistance welded BS 3601 …. Din 1626 Blatt 3 …. ….
Carbon steel Grade A ERW 22 …. St 34-2 Electric …. …. 4
pipe
Grade B ERW 27 …. St 37-2 Resistance …. ….
welded
Furnace butt BS 3601 …. Din 1626 Blatt 3 …. ….
Welded BS 22 …. St 34-2 Furnace butt welded ---- ----
Carbon steel ASTM A83 BS 3059/1 or 2 Gapave 211 Din 1629 …. …. 4
boiler tube, A 37 C St 35 …. ….
seamless
Silicon-killed carbon ASTM A 106 BS 3602 Capave 421 Din 1717
steel pipe for high Grade A HFS 23 A 37 C St 35.8 Aq35 Uni 663C SIS 1234-05 2,3
temperature Service Grade B HFS 27 A 42 C St 45.8 Aq45 Uni 663C SIS 1435-05 4,6
Grade C HFS 35 A 48 C ………………………. …. …. Contd.
1 2 3 4 5 6 7 8
MATERIAL U.S. SPECIFICATIONS BRITISH FRENCH GERMAN ITALIAN SWEDISH NOTES
Electric fusion welded ASTM A 134 BS 3601 EFW …. Din 1626 Blatt 2 Electric …. …. 2,4
steel pipe furion welded
Electric resistance ASTM A 135 BS 3601 …. Din 1626 Blatt 3 ….
welded steel pipe Grade A ERW 22 …. Din 34- Electric resis- …. SIS 1233-06 4
2
Grade B ERW 27 …. St 37-2 tance welded …. SIS 1434-06
Electric fusion welded ASTM A 139 BS 3601 …. Din 1626 Blatt 2 …. ….
steel pipe Grade A EFW 22 …. St 37 …. …. 2,4
Grade B EFW 27 …. St 42 …. ….
Electric fusion welded ASTM A 155 …. …. Din 1626 Blatt 3mit
pipe for high Class 2 …. Abnahmezeugnis C …. ….
temperature service C 45 …. …. St 34-2 …. ….
C 50 …. …. St 37-2 …. ….
C 55 BS. 3602 EFW 28 …. St 42-2 …. ….
KC 55 …. …. St 42-2 Si-killed …. …. 2,4
KC 60 BS. 3602 EFW 28S …. St 42-2 Si-killed …. …. 7,8
KC 65 …. …. St 52-3 …. ….
KC 70 …. …. St 52-3 …. ….
WSN Designation
ASTM A 312 BS 3605 …. 4301 …. ….
TP 304 Grade 801 …. …. X5CrNi189 X 8CN1910 SIS 2333-02
TP 304H Grade 811 …. 4306 …. …. ….
TP 304L Grade 801L …. 4841 X2 CrNi189 X3CN1911 SIS 2352-02
TP 310 Grade 805 …. 4401.4436 X15CrNiSi2520 25CN 2520 SIS 2361-02
TP 316 Grade 845 …. …. X5CrNiMo1810 X8CND1712 SIS 2343-02
Austenitic stainless TP 316H Grade 855 …. 4404 …. …. ….
steel pipe TP 316L Grade 845L …. …. X2CrNiMo 1810 …. SIS 2353-02
TP 317 Grade 846 …. 4541 …. …. ….
TP 321 Grade 822 Ti …. …. X10CrNiTi189 X8CNT1810 SIS 2337-02
TP 321H Grade 832 Ti …. 4550 …. …. ….
TP 347 Grade 822 Nb …. …. X10CrNiNb18.9 X8CNNb1811 SIS 2338-02
TP 347H Grade 822 Nb …. …. …. …. ….
Pipe for low ASTM A333 BS 3603 …. WSN Designation
temperature service Grade 1 27 LT 50 …. 0437 SEW680TTSt41 …. …. 9
Grade 3 503 LT 100 …. 5637 …. 10Ni 14 …. …. Contd..
…. …. Gapave 222 …. …. ….
…. …. Afnor 1503 Din 17175 15Mo3 …. SIS 2912-05
1 2 3 4 5 6 7 8
MATERIAL U.S. SPECIFICATIONS BRITISH FRENCH GERMAN ITALIAN SWEDISH NOTES
ASTM A335
BS 3604
Samples ferritic alloy P1 …. …. WSN5423 16Mo5 …. ….
pipe for elevated P2 …. Afnor15CD2-05 …. …. ….
temperature tube P12 HF620 or CD 620 …. Din17175 13CrMo44 …. SIS 2216-05
service P11 HF621 or CD 621 Afnor 10CD5- …. …. ….
05
P22 HF622 or CD 622 Afnor 10CD9- DIN17175 13CrMo44 …. SIS2216-05
10
ASTM B241 P5 HF625 or CD 625 …. …. …. ….
P9 …. Afnor Z10CD9 …. …. SIS2203-05
Aluminium alloy pipe 303 h112 …. …. Din 1746 A1 MnF10 …. ….
5154 H112 BS 1471NT5 or …. Din 1746 A1 Mg3F18 …. ….
BS 1474NT5 ….
6061 T6 BS 1471 HT Din 1746 A1 MgSi 1F32 …. ….
20WP
Notes:
1. For pipe fabricated to ASA B 31.3 steel should be specified to be open hearth, electric furnace or basic oxygen. Alternatively,
Thomas steel is acceptable if fully killed or if it meets the following composition requirements:
S 0.05% max, P 0.05% max, N 0.009% max.
2. Ramming steel is not acceptable for seamless or fusion welded pipe.
3. Analysis and test certificates are required.
4. Above 6500F use mechanical properties quoted in the appropriate national standard as a basis for design in critical applications.
5. For British and Swedish standard welded pipe supplied as equivalent to API 5L Grade B specify: “Welded seams to be non-
destructively tested in accordance with para. 11.5 and 11.6 of API 5L. Din 1626 Blatt 4 already requires an equivalent degree of
testing.
6. Specify “Silicon-killed” for Gapave 421, Din 17175 and UNI 663.
7. Above 10000F use mechanical properties accepted be the national code-writing body as a basis for design in critical
applications.
8. Din 1626 Blatt 4 may be used as equivalent to ASTM A 155 Class 1.
9. SEW = Stahl – Eisen Werkstoffblatt.
Annexure –V
1.0 SCOPE
2.0 IDENTIFICATION
2.2 Secondary colours: The narrow bands presenting the secondary colour
which identifies the specific service, may be applied by painting or
preferably by use of adhesive plastic tapes of the specific colour.
3.2 Colour bands: The location and size of bands, as recommended, when
used, shall be applied to the pipe.
3.3 For piping, writing of name of service and direction of flow for all the
lines shall be done at following locations:
3.4 The letters will be in black on pipes painted with light shade colours
and white on pipes painted with dark shade colours to give good
contrast.
3.5 Only writing of service name shall be done on stainless steel lines.
Precautions should be taken while painting by using low chloride
content painting to avoid any damage to the stainless steel pipes. It is
preferable to use adhesive plastic tapes to protect stainless steel pipes.
4.0 For alloy steel/ stainless steel pipes and fittings in stores/ fabrication
yard, color band (Minimum ½” wide) should be applied along the
complete length of pipe, bends/ tees, side-curved surface (on
thickness) of flanges as well as valves as per the metallurgy.
29. BLOW DOWN, VAPOUR LINE Off White / Aluminium with 1-Brown band
62. ETP TREATED WATER Sky blue with 2 oxide red bands
80. CONDENSATE ABOVE 150 0F Sky blue with 3 oxide red bands
Note: For all insulated steam lines, the colour coding shall be followed as given for uninsulated lines with the specified
length of colour bands.
(i) The following items shall be painted for camouflaging, as per specific site requirement of Defence.
a) All columns
b) All tanks in offsites
c) Large vessels
d) Spheres
(ii) Two coats of selected finish paint as per defence requirement shall be applied in a particular pattern as per (iii) and as per
the instructions of the Engineer-in-Charge.
a) Disruptive painting for camouflaging shall be done in three colours in the ratio of 5:3:2 (all matt finish)
STANDARD SPECIFICATION FOR CORROSION PROTECTION OF WRAPPING COATING & TAPE COATING OF UNDER
GROUND STEEL PIPELINES
1. SCOPE
This specification covers the requirement for materials, surface preparation, application, inspection, repairs and handling for
external corrosion protection tape coating, in situ. of underground steel pipelines with service temperature upto 60 0C using.
Coaltar based tape coating materials conforming to AWWA C-203 (1991)
2. REFERENCE DOCUMENTS
The latest edition of the following standards and documents shall apply
2.1 AWWA C-203 (1991): Coal tar protective coatings and linings for steel water pipelines.
2.2 Doc:MTD 24 (3624) BIS: Draft Indian Standard specification for coaltar based Anticorrosion tape for protection of
underground mild steel pipeline.
2.3 SIS05-5900 “Pictorial surface preparation standard for painting steel surface”. Or ISO-8501-1988
2.4 SSPC-SP Steel structure painting council surface preparation specifications:
SSPC-SPI Solvent cleaning
SSPC-SP3 Power tool cleaning
SSPC-SP10 Near white metal blast cleaning
High voltage test conform to NACE standard RP-02-74
3. GENERAL REQUIREMENTS
3.1 Equipments and accessories required for tape coating shall be in good operating conditions at least for
completion of the coating job. Adequacy of equipments and accessories shall be approved by the Engineer-in-
charge.
3.2 Necessary arrangements for power supply and other utilities shall be made for the completion of the job.
3.3 Necessary testing and inspection facilities as required by this standard shall be developed at site and shall be approved
by the Engineer-in-charge.
4.1 A written quality plan with procedures for qualification trials and for the actual work.
The quality plan shall include a time table for the various activities with a description of coating materials to be used,
their application qualification of personnel involved in the work, responsibilities and lines of communications, details of
equipment and their calibration, proposed hold points for company’s inspection and endorsement and the detailed
procedures for the testing and inspection.
4.2 Daily progress reports with details on weather conditions, particulars of application, e.g. blast cleaning, number of wraps
and type of materials applied, anomalies and progress of work versus programme.
4.3 Documented evidence that the requirements of this specification have been met, during production trials as well as
during the work.
(a) Raw Coal Tar Pitch:The coal tar (hard pitch) component shall be produced from coal that has a minimum heating value
of 13000 BtU/Ib (7.223x106 cal/kg) on a moisture and mineral matter free basis (ASTM D 388) and that has been carbonized
in a slot-type coke even at a temperature of not less than 900 0C. The coal tar (hard pitch) shall have the following salient
properties:
Softening point 0C 65 Min. 121 ASTM D36-86
Max.
Specific gravity 1.30 0.05 ASTM D 71-94
Ash content 0.5% Max. ASTM D 2415-66(1991)
Physical state Solid at ambient temperature
(b) Fabric:
Type : The fabric shall be a thin, flexible, uniform mat or tissue composed of glass fibers in an open structure bonded with a
suitable resinous inert material compatible with coal tar.
Weight (min) g/m2 40
Thickness (min.) mm 0.3
Note (1) Manufacturer’s test data in the laboratory are required for the above properties on the materials supplied.
(c) Physical properties of coaltar tape:
Property Requirement Test Method
Min. Max.
Service - 60
temperature 0C
Tape thickness 2.0 2.5 Section 8.11.3 of AWWA C-203
mm
Weight average 1.25 ASTM D146
kg/sq.m/mm
6. Surface preparation:
- All oil, grease on the pipe metal surface shall be thoroughly removed by flushing with a suitable solvent (such as xylene
or 1.1.1 trichloroethylene) and wiping with clean rags. The solvent cleaning shall be as per SSPC-SP-1. If required
detergent cleaning shall be done before or after solvent cleaning.
- The degreased pipe metal surface shall be blast cleaned to Sa 2 ½ of SIS-05-5900 OR SSPC-SP-10. With a surface
profile of 30-50 microns depth. Blasted surface that rusts before priming shall be cleaned by wire brushing or shall be
reblasted. Priming shall be done within 4 hours of completion of blast cleaning. Otherwise total reblasting may be
necessary.
Surface preparation:
Blast cleaning equipment for nozzle type, size, safety gauges, working condition, pressure at the tip of the gun
Abrassive type, hardness to provide required profile size and cleanliness
Measurement of surface profile and comparing cleanliness with Visual standards of ISO 8501 – 1988
Measurement of pitting depth area of pitted portion. Inspection of weld filling and grinding and patch plate welding, welding of
replaced pipe, if any.
Checking of condition of concrete saddles. Rubber padding and end seals wherever required.
- The enamel pieces shall be heated in the kettle and brought to the application temperature conforming to. AWWAC
203/66/Manufacturer’s specification. Accurate thermometers shall be used on the dope kettle and positioned so as to
accurately determine the maximum temperature to which the enamel is heated. Kettles shall not be permitted to act as
continuous enamel supply source by adding unmelted enamel during the time such kettles are in use, but shall be
completely emptied of one charge before the next charge of enamel is added.
- Enamel shall be condemned and dumped as unfit for use when in the judgement of Site Engineer, it has become
damaged by overheating or by continuous heating.
- The application of coating materials on the pipe shall be at temperature recommended by the enamel manufacturer or
AWWA C 203/66 specification.
- The coated pipes including field joint coating shall be visually inspected for cracks, trapped air, uniformity, damage etc.
Any repair arising out of visual inspection will be decided by Engineer-in-charge.
- Adhesion between tape to tape can be tested following similar procedure as above. However, this should preferably be
done on a test panel.
MEASUREMENT OF COATING THICKNESS
- Coating thickness of the coated pipes shall be measured at the beginning of coating operation to ensure proper
thickness.
- Thickness has to be measured with a caliper with caliper surfaces of at least 20 mm diameter, on 5 tape pieces with an
edge length of at least 50 mm taken from 5 different coils. The measuring pressure should 0.5N/m2. The measuring
accuracy should be within 0.1 mm.
- All holidays, pinholes, torn wrap, abraded or mutilated spots in the coat and wrap operations shall be immediately
repaired. The original coating and wrapping shall be cleaned away and the good edges of the original coating shall be
beveled or clipped to ensure satisfactory application. The damaged area shall be thoroughly cleaned before recoating. All
the Holiday test should pass stipulations as per Section 8.9 of AWWA C-203 (1991) std. and contractor to furnish support
documents.
Form No. 2