0% found this document useful (0 votes)
26 views22 pages

Presentation of TIIPPL Project

Uploaded by

adityakurade019
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views22 pages

Presentation of TIIPPL Project

Uploaded by

adityakurade019
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 22

FIELD TRAINING REPORT

• Presented by - Mr. Utkarsh Uttam Jadhav.


• Course - Civil Engineering
INTRODUCTION OF COMPANY

• Name of company: Unity Infrastructure


• Name of company owner: Sandeep Kakade.
• Adress of company: Adityavardhan Heights,Urse
Road,Vadgoan Phata,Talegoav Dhabhade
Tal. Maval,
Dist : Pune.410507
Material USED FOR CONSTRUCTION

• Cement
• Steel
• Giogrid
• Gio Strap
• Gio Composite sheet
• Concrete -RMC Plant
RMC PLANT

• RMC PLANT used for this construction of


CONCRETING.
• The type of CONCRETE is M20,M35
GRADE.
• Rate of CONCRETE is M20-5000/M3
• M35-5800/M3
STEEL

• The 25 Ton steel used for this


construction of diameter 8mm.
• Rate of bar is 65/kg.
• STEEL USE- 8,10,12,16 MM
Gio Grid

• Gio Grid used for this Anchoring


RE Wall.
• The is Mesh Type.
• Rate of Gio Grid is 100/M2.
Gio Strap

• This use For RE wall.


• Use of anchoring wall.
• The rate is 150/m2.
Gio Composite sheet

• This use For RE wall.


• Use of Water Drain Work.
• The rate is 135/m2.
WEEKLY REPORT
WEEK DATE ACTIVITIES

1 03/06/2024 to 08/06/2024 In first week lineout is done with chalk pit


for 200 mtr length with width 15 mtr. And
excavation is done with Pocklan machine
05 nos & Dumper -15 nos
Width: 15 m
Depth: 8 -10 m
Panel Reinforcement & casting work in
progress - M35
2 10/06/2024 to 15/06/2024 In second week Levelling Pad Exavation &
Compaction work.
soil testing work -SBC (40 MT load)
Level Pad PCC shuttering & Casting -M20

3 17/06/2024 to 22/06/2024 In third week Panel Erection work started


Panel Line alignment work.
Backfilling work started-200 mm layer with
compaction 12 ton load vibro rollar.
next 200 mm layer complete ,compaction ,
watering ,rolling & 400 mm layer Soil
testing (FDT)-next 400 mm layer Gio Grid
/Gio strap laying work after
backfilling ,Watering ,Rolling, Soil Testing
WEEK DATE ACTIVITIES
4 24/06/2024 to 29/07/2024 In Fourth Week Next layer panel
erection,Gio composite Drain sheet fixing,
Backfilling , Gio grid laying , backfilling ,line
alignment & testing work
panel casting work in progress

5 01/072024 to 06/07/2024 In Fifth Week Next layer panel erection,


Backfilling , Gio grid laying , backfilling ,line
alignment & testing work
panel casting work in progress
6 08/07/2024 to 13/07/2024 In Sixth Week Next layer panel erection,
Backfilling , Gio grid laying , backfilling ,line
alignment & testing work
panel casting work in progress
Panel steel Binding & Panel Board Fixing
Work
PANEL CASTING WORK IN PROGRESS-
M35 RCC
LEVELPAD PCC WORK & CURING WORK
PANEL ERECTION & LINEOUT
GIO GRID LAYING WORK
ROLLING WORK -12 TON VIBRO ROLLAR
WATERING WORK...
MURUM BACKFILLING WORK
PANEL SIDE COMPACTION & LEVELLING
WORK
PANEL ERECTION WORK
SOIL TESTING -FDT , MDD,PLT LOAD

You might also like