FIELD TRAINING REPORT
• Presented by - Mr. Utkarsh Uttam Jadhav.
• Course - Civil Engineering INTRODUCTION OF COMPANY
• Name of company: Unity Infrastructure
• Name of company owner: Sandeep Kakade. • Adress of company: Adityavardhan Heights,Urse Road,Vadgoan Phata,Talegoav Dhabhade Tal. Maval, Dist : Pune.410507 Material USED FOR CONSTRUCTION
CONCRETING. • The type of CONCRETE is M20,M35 GRADE. • Rate of CONCRETE is M20-5000/M3 • M35-5800/M3 STEEL
• The 25 Ton steel used for this
construction of diameter 8mm. • Rate of bar is 65/kg. • STEEL USE- 8,10,12,16 MM Gio Grid
• Gio Grid used for this Anchoring
RE Wall. • The is Mesh Type. • Rate of Gio Grid is 100/M2. Gio Strap
• This use For RE wall.
• Use of anchoring wall. • The rate is 150/m2. Gio Composite sheet
• This use For RE wall.
• Use of Water Drain Work. • The rate is 135/m2. WEEKLY REPORT WEEK DATE ACTIVITIES
1 03/06/2024 to 08/06/2024 In first week lineout is done with chalk pit
for 200 mtr length with width 15 mtr. And excavation is done with Pocklan machine 05 nos & Dumper -15 nos Width: 15 m Depth: 8 -10 m Panel Reinforcement & casting work in progress - M35 2 10/06/2024 to 15/06/2024 In second week Levelling Pad Exavation & Compaction work. soil testing work -SBC (40 MT load) Level Pad PCC shuttering & Casting -M20
3 17/06/2024 to 22/06/2024 In third week Panel Erection work started
Panel Line alignment work. Backfilling work started-200 mm layer with compaction 12 ton load vibro rollar. next 200 mm layer complete ,compaction , watering ,rolling & 400 mm layer Soil testing (FDT)-next 400 mm layer Gio Grid /Gio strap laying work after backfilling ,Watering ,Rolling, Soil Testing WEEK DATE ACTIVITIES 4 24/06/2024 to 29/07/2024 In Fourth Week Next layer panel erection,Gio composite Drain sheet fixing, Backfilling , Gio grid laying , backfilling ,line alignment & testing work panel casting work in progress
5 01/072024 to 06/07/2024 In Fifth Week Next layer panel erection,
Backfilling , Gio grid laying , backfilling ,line alignment & testing work panel casting work in progress 6 08/07/2024 to 13/07/2024 In Sixth Week Next layer panel erection, Backfilling , Gio grid laying , backfilling ,line alignment & testing work panel casting work in progress Panel steel Binding & Panel Board Fixing Work PANEL CASTING WORK IN PROGRESS- M35 RCC LEVELPAD PCC WORK & CURING WORK PANEL ERECTION & LINEOUT GIO GRID LAYING WORK ROLLING WORK -12 TON VIBRO ROLLAR WATERING WORK... MURUM BACKFILLING WORK PANEL SIDE COMPACTION & LEVELLING WORK PANEL ERECTION WORK SOIL TESTING -FDT , MDD,PLT LOAD