Assignment 2 1
Assignment 2 1
Group Assignment 2
GROUP
Calculate the expected profit for planting maize and for planting beans. Based on the expected values, advise the
farmer on which crop to plant.
Answer
MAIZE
Profit/lose Probability
= 60 000KSh
BEANS
Profit/loss Probability
=53 000KSh
Maize= 60,000KSh
Beans= 53,000KSh
According to the expected profit of planting beans and maize, it has been shown that the expected profit is higher
than beans by 7 000KSh, so it is more recommendable to plant maize to gain more profit. Other factors such as the
weather forecast should be considered before making the well-informed decision to ensure maximum profit.
Question 2 a)
What is the probability that a randomly selected container will have a weight between 0.95 liters and 1.05 liters?
Answer
Z = (X-u)/SD
Mean = 1
SD = 0.05
Z = (0.95-1)/0.05
= -1
Z = (1.05-1)/0.05
=1
Hence using Standard Deviation table we found out that X1 = 1 and our X2 = -1 as follows:
X1 = -1 = 0.15866
X2 = 1 = 0.84134
= 0.84134 – 0.15866
= 0.68268
0.6826
OR
68.26%
Question 2 b)
If the company wants to ensure that only 1% of containers weigh less than a certain amount, what is the cutoff
weight below which only 1% of the containers will fall?
Answer
1% = 0.01
X=U+Z*∅
X = 1 + (-2.33) * 0.05
1 + (-0.1165)
= 0.8835
Thus, the cut-off weight below which only 1% of the containers will fall is approximately
=0.8835 liters
Question 3
Formulate a linear programming model to determine how many units of each textile the company should produce to
maximize profit, subject to the resource constraints. Solve graphically to find the optimal solution.
Answer
Labor 2 4 <=100
Labor
2x+4y=100
Raw materials
3x+2y=80
Maximizing profit
200x+150y;
2x+4y=100 3x+2y=80
Y=(100+2x)/4 y=(80+3x)/2
X Y= (00+2x)/4
0 25
2 24
4 23
6 22
X Y = (80+3x)/2
0 40
2 37
4 34
6 31
60
50
50
40
40
textile B
30 26.7
25
20
10
0
1 2
Textile A
Where the two lines intersect (15,17.5) it is the optimal solution. It shows optimal units of x (textile A) and units of y
(textile B) that can produce maximum profit.
Question 4 a)
Calculate the expected monetary value (EMV) for both projects.
Answer
Project X Y
EMV Calculations
EMV = (200 x 0.7) + (-50 x 0.3) EMV = (100 x 0.7) + (20 x 0.3)
= 140-15 = 70 + 6
Question 4 b)
Based on the EMV criterion, advise the company on which project to invest in.
Answer
Because Project X’s EMV is higher than Project Y’s EMV, based on EMV criteria the company should invest in Project
X.