2024:BHC-OS:18356: Diksha Rane
2024:BHC-OS:18356: Diksha Rane
2024:BHC-OS:18356: Diksha Rane
JUDGMENT :
and Conciliation Act, 1996 (for short ‘the Arbitration Act’), by the
original claimant seeking to quash and set aside the arbitral award
FACTS
1
Diksha Rane 24. ARBP 43-23-FINAL.doc
contract work of the said tender was awarded to the petitioner, for an
Order (for short ‘JPO’) dated 20 th December 2017, wherein all the
condition that the contractors would continue the ongoing work till
paid to the labourer till the foreclosure of the contract and no dues
withdraw from the contracted work as per the terms of the JPO. The
2
Diksha Rane 24. ARBP 43-23-FINAL.doc
the balance work and foreclosed the contract with the petitioner.
Arbitrator”.
Statement of Claim along with all the relevant annexures with the
sole Arbitrator. The Railways being the respondents filed their reply
3
Diksha Rane 24. ARBP 43-23-FINAL.doc
amounting to Rs.1,29,74,966/-.
Arbitrator went ahead and after hearing both the sides the Sole
SUBMISSIONS
Schedule VII of the Arbitration Act, the award passed by the Sole
4
Diksha Rane 24. ARBP 43-23-FINAL.doc
party waiving the right of raising objection is left with no choice but
12(5) of the Arbitration Act, was sought by the Railways, as per their
with the arbitration. On this issue, he relied upon the judgment of the
Madhya Pradesh2.
laid down in the JPO dated 20th December 2017 by the Railway
5
Diksha Rane 24. ARBP 43-23-FINAL.doc
sum of Rs.523/- to each worker per day, instead of Rs.374/- per day.
petitioner.
6
Diksha Rane 24. ARBP 43-23-FINAL.doc
proceedings.
quashed and set aside. He also relied upon the judgment of the
Development Authority4.
Arbitration Act makes it clear that the grounds for raising a challenge
out any case to set aside the award on any of the grounds under
(ii) The grounds raised by the petitioner are not grounds which can
7
Diksha Rane 24. ARBP 43-23-FINAL.doc
settled position in law that the Arbitrator is the final arbiter of facts.
and the objections to the impugned award are beyond the grounds
which can be urged under Section 34 of the said Act and hence
12(5) of the said Act. Under the said proviso, a party can waive the
8
Diksha Rane 24. ARBP 43-23-FINAL.doc
(vi) The documents of waiver are in writing and the same are
(vii) As regards the case of (a) Bharat Broadband Network Ltd. vs.
United Telecoms Ltd.5 and (b) JMC Projects (India) Ltd. vs. Indure
the learned Arbitrator's appointment does not suffer from any de jure
agreed to waive the applicability of Section 12(5) of the said Act the
9
Diksha Rane 24. ARBP 43-23-FINAL.doc
and (ii) the conscious intention to waive the applicability of the said
rejected.
Mills Limited vs. State of Madhya Pradesh 7 does not apply to the facts
of the present case. In the case of Ellora Paper Mills Limited vs. State
7 (2022) 3 SCC 1
10
Diksha Rane 24. ARBP 43-23-FINAL.doc
Respondent submits that this has not been done by the Petitioner,
which only shows that the Petitioner had never doubted the
filed any form of application raising any objections with regard to the
advanced by both sides. The Ld. Arbitrator has considered each of the
11
Diksha Rane 24. ARBP 43-23-FINAL.doc
claims raised the Petitioner and given detailed reasons for rejecting
the same.
the expected rise in the minimum wages. Thus the Petitioner cannot
be heard to say that the increase in the minimum wages rendered the
12
Diksha Rane 24. ARBP 43-23-FINAL.doc
labour. As per the said JPO, the contractor was required to issue an
unambiguous undertaking.
vide its letter dated 24th January 2018 had expressed its intent to
21.02.2018 had clearly stated that payment of wages, PF, ESIC, etc.
13
Diksha Rane 24. ARBP 43-23-FINAL.doc
conditions of the JPO as is evident from the fact that the submission
Petitioner was required to submit due compliances and the bills of the
Petitioner in the said letter dated 16 May, 2018 admits that it would
14
Diksha Rane 24. ARBP 43-23-FINAL.doc
certificate, the Petitioner has invoked the Arbitration Clause and filed
and therefore, the same cannot be interfered with, since the same
costs.
grounds. It is the case of the petitioner that they had no choice but to
15
Diksha Rane 24. ARBP 43-23-FINAL.doc
clause.
stated that it was in fact the duty of the Sole Arbitrator to disclose his
submitted that since the contract between the parties post the
2015, the learned Arbitrator should have disclosed his link with the
contract, the claimant could not have raised the issue before the
Arbitrator himself and the issue being that of law, the same can be
raised even under Section 34 of the Arbitration Act before this Court.
the issue between the claimant and the respondent. It is the case of
the claimant that after the amendment to the Arbitration Act, in the
16
Diksha Rane 24. ARBP 43-23-FINAL.doc
year 2015, there were major changes made in Section 12 of the said
Act. Section 12 of the Arbitration Act mentions about the grounds for
mentions that any person whose relationship with the parties or the
subject matter of the dispute which falls under the VII Schedule shall
appointed as an Arbitrator.
17
Diksha Rane 24. ARBP 43-23-FINAL.doc
chose to go ahead with the Arbitration. The claimant had invoked the
the claimant cannot now take a defence that they were not aware
about the legal implications while they issued the letter of invocation
of arbitration.
18
Diksha Rane 24. ARBP 43-23-FINAL.doc
dispute between the parties. Admittedly, the claimants have not taken
19
Diksha Rane 24. ARBP 43-23-FINAL.doc
(Emphasis supplied)
effect from 23rd October 2015. To canvas this point the learned
counsel appearing for railways also relied upon the judgment passed
18.1 In Bharat Broad Band (supra), the Supreme Court held that if
as per the Section 12(5) proviso, parties in writing agree to waive the
20
Diksha Rane 24. ARBP 43-23-FINAL.doc
there was no waiver between the parties, and hence the ratio laid
signed waiver form and on their signature they had sent it across to
Arbitration Act.
Vs. Delhi Metro Rail Corporation Ltd. - reported in (2017) 4 SCC 665
21
Diksha Rane 24. ARBP 43-23-FINAL.doc
has considered Section 12(5) and the VII Schedule to the Arbitration
Act, and has held that under Section 12(5) of the Act,
foul with the amended provisions i.e. Section 12(5), the appointment
22
Diksha Rane 24. ARBP 43-23-FINAL.doc
23
Diksha Rane 24. ARBP 43-23-FINAL.doc
Tribunal, the same can be made before the Arbitral Tribunal, and the
of India Ltd.), 2017 SCC OnLine SC 1024 has held that if the
on that ground.
24
Diksha Rane 24. ARBP 43-23-FINAL.doc
section 34.
21. For the first time in the present proceedings which is filed u/s.
any such steps. Again, I would like to mention here that the claimants
such an issue has been raised by the claimant. According to me, the
25
Diksha Rane 24. ARBP 43-23-FINAL.doc
has also raised an issue that if the claimant could have desired, they
almost one year on petitioner’s request after the balance work was
foreclosed. The claimant did not raise any issue about foreclosure
SCC 163, Supreme Court held that the Court does not sit in appeal
26
Diksha Rane 24. ARBP 43-23-FINAL.doc
set out in Section 34(2)(b)(ii) is met that the Court may interfere
with an arbitral award under the said provision but such interference
does not entail a review on the merits of the dispute and is limited to
illegality is not trivial but goes to the root of the matter. An arbitral
award may not be interfered with if the view taken by the arbitrator
is a possible view based on facts. The Court cannot travel beyond the
restrictions laid down under Section 34. The Court cannot undertake
reported in 2019 SCC OnLine SC 677 has held that under Section 34
27
Diksha Rane 24. ARBP 43-23-FINAL.doc
the award. A finding based on the documents taken behind the back
illegality.
goes to the root of the matter. It is held that once it is found that the
arbitral award. Patent illegality must go to the root of the matter and
cannot be of trivial nature. Apart from the grounds which are dealt
28
Diksha Rane 24. ARBP 43-23-FINAL.doc
23.4 Single Judge of Bombay High Court in the case of Star Track
Fasteners Private Limited Vs. Union of India, 2019 SCC OnLine Bom
1453 has held that the Court has no power to allow any claim which
made by the learned arbitrator. Court can either set aside the award
29
Signed by: Diksha Rane
Designation: PS To Honourable Judge
Date: 12/11/2024 14:01:10