0% found this document useful (0 votes)
96 views58 pages

Sample Boq Villa

Uploaded by

wilbert palo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
96 views58 pages

Sample Boq Villa

Uploaded by

wilbert palo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 58

SAMPLE PROJECT BILL OF QUANTITIES

FIRST FLOOR BOQ B01-Prelims

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

#VALUE!

Tenderers are to insert their prices hereunder for items of a


general nature relating to the entire works and Contract, and not
necessarily allocable to individual measured works

Fit-Out ID Contractor is to allow for Contractual requreirements of a


general nature relating to entire Works and required to perform his job
satisfactory

Allow for samples and testing, site laboratory, approval of materials,


shop drawings, as built drawings, operation and maintenance manuals,
site progress reports, site security, photography, videography and all
incidental cost of periodic inspection visits and testing facility by
representative of the Employer, Project Manager and Conslutatnt etc.
complete as specified in the tender documents.

B Allow for full and comprehensive compliance of all the tender


documents including technical, contractual, financial safety, security,
protection and QA/ QC requirement and obligation etc., complete as
specified in the tender documents, from commencement of works until
issuance of final handling over certificate/ final completion.

C Allow for site survey, protection and safeguard, keeping site clear,
removal of debris and other rubbish outside the site approved by
authority, including protection of work during progress and upon
completion etc., complete as specified in the tender documents.

D Allow for submittal and approvals from various local authorities,


permits, fees/ charges, certificates pertinent to the successful
completion of the project etc. complete as specified in the tender
documents.

E Allow for full coordination and cooperation with all the parties/ suppliers/
sub-contractors/ designers/ consultants/ stakeholders involved in the
tender documents

F Allow for all necessary fences, scaffolding and access to allow for the
completion of the works.

B01-Prelims 1 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B01-Prelims

TOTAL FOR BILL NO. 01: PRELIMINARIES, EURO

B01-Prelims 2 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B02-Demolition

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

DEMOLITION WORKS

Demolished existing plastered blockworks and other


existing materials, disposal to approved area and all
necessary requirements as per Drawings, Specifications
and other Tender Documents

Rooms FF-04, FF-11, FF-12, FF-15, FF-16, FF-17, FF-18,


FF-20, FF-21, FF-22, FF-23, FF-24, FF-25, FF-26, FF-27, FF-
30, FF-33, FF-34, FF-36, FF-39 & FF-41
A Blockworks to be removed 201.09 m2

B Other materials Item

Sundries

Protect finished surfaces during subsequent construction


operations, repair damage and keep clean as per
specification section

C To adjacent areas of demolished blockworks Item

D To adjacent areas of other demolished materials Item

B02-Demolition 1 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B02-Demolition

Carried to Architechtural Screed Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

Important Note :

A Confirm that any and all items not mentioned in this Bill of
Quantities but indicated / required elsewhere in the Tender
Documents and with respect to the particular scope of works
and whatsoever necessary for the satisfactory completion and
handing over of the project. All such items shall be deemed to
be included within the lump sum unit rates of this Bill Division

B02-Demolition 2 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B02-Demolition

Carried to Architechtural Screed Summary

ARCHITECHTURAL SCREED SUMMARY AMOUNT (EURO)

Page 1

Page 2

Page 3

Page 4

B02-Demolition 3 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B02-Demolition

TOTAL FOR BILL NO. 02: ARCHITECTURAL SCREED, EURO

B02-Demolition 4 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B03-Concrete

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

DIVISION 3 - CONCRETE

ARCHITECTURAL SCREED

Supply, fixing, installation, proper protection up to


handing over, testing and commissioning (where
applicable) and maintenance. (all as per the Tender
Documents.)

Cement and sand lean concrete screed, including steel


reinforcement and all necessary requirements and works
complete all in accordance with drawings, specifications and
other Tender Documents, complete

To concrete surfaces, 70-85mm thick, to received High grade


machine carpet to the following rooms

A FF-11 13.84 m2

B FF-12 52.22 m2

C FF-14 55.46 m2

D FF-15 14.11 m2

E FF-17 43.27 m2

F FF-18 8.29 m2

G FF-19 40.71 m2

H FF-21 6.48 m2

J FF-23 27.06 m2

K FF-25 40.71 m2

L FF-26 5.99 m2

M FF-28 7.08 m2

N FF-33 30.29 m2

P FF-35 59.00 m2

Q FF-36 63.97 m2

R FF-38 59.00 m2

S FF-39 33.82 m2

B03-Concrete 1 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B03-Concrete

Carried to Architechtural Concrete Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

DIVISION 3 - CONCRETE

ARCHITECTURAL SCREED

Supply, fixing, installation, proper protection up to


handing over, testing and commissioning (where
applicable) and maintenance. (all as per the Tender
Documents.)

Cement and sand lean concrete screed, including steel


reinforcement and all necessary requirements and works
complete all in accordance with drawings, specifications and
other Tender Documents, complete

To concrete surfaces, 50-75mm thick, to receive the


following marble floor

Room FF-60
A Light Traventine 21.64 m2

Rooms FF-08
B Light Traventine, with border and design as shown on
drawing F006 57.33 m2

Rooms FF-04, FF-13 & FF-29


C Light Traventine, with border and design as shown on drawing 185.88 m2

Rooms FF-16, FF-20 & FF-27


D Black Marquina polished ref. ST13 31.88 m2

Room FF-51
E Marble Black Marquise 6.30 m2

Room FF-10
F Black Marquise, Ref. ST-21 with design as shown on drawing
FF-10.01 5.95 m2

Room FF-30
G Light Traventine with black jet border 165mm width as shown
on drawing FF-04.01 8.24 m2

Room FF-41
H Volakas Polished with 80mm width Rosso Levato as design
as shown on drawing FF-41.01 28.61 m2

Room FF-34
J Volakas Polished with black marquina polished border as
shown on drawing FF-34.01 13.90 m2

Room FF-22
K Omani white with Black Marquina polished ref. ST13 with
design as shown on Drawing FF-22.01 6.09 m2

Rooms FF-34 & FF-41


L Volakas Polished 5.16 m2

Rooms FF-22 & FF-24


M Omani white 7.20 m2

Room FF-24

B03-Concrete 2 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B03-Concrete

N Omani white with Black Marquina polished ref. ST13 with


design as shown on Drawing FF-24.01 6.09 m2

Carried to Architechtural Concrete Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

DIVISION 3 - CONCRETE

ARCHITECTURAL SCREED

Supply, fixing, installation, proper protection up to


handing over, testing and commissioning (where
applicable) and maintenance. (all as per the Tender
Documents.)

Cement and sand lean concrete screed, including steel


reinforcement and all necessary requirements and works
complete all in accordance with drawings, specifications and
other Tender Documents, complete

To concrete surfaces, 50-75mm thick, to receive the


following marble floor

Rooms FF-16, FF-20, FF-22, FF-24, FF-27, FF-34 & FF-41


A Volakas Polished (polished & sanded) as shown on Drawing
FF-41.01 for Shower marble floor detail 1.21 m2

B Ditto, as shown on Drawing FF-34.01 for Shower marble floor


detail 1.21 m2

C Ditto, as shown on Drawing FF-16.01 for Shower marble floor


detail 0.86 m2

D Ditto, as shown on Drawing FF-27.01 for Shower marble floor


detail 1.52 m2

E Ditto, as shown on Drawing FF-20.01 for Shower marble floor


detail 1.02 m2

F Ditto, as shown on Drawing FF-22.01 for Shower marble floor


detail 1.02 m2

G Ditto, as shown on Drawing FF-24.01 for Shower marble floor


detail 1.02 m2

Rooms FF-02, FF-05, FF-06, FF-06A, FF-07 & FF-08


H Flooring, light travertin 115.50 m2

Rooms FF-02, FF-07 & FF-07


J Flooring with pattern, light travertin & black jet marble, size
1590mmL x 1590mmW, pattern as shown on Dwg. FF-01.02
8.00 No.

Rooms FF-02, FF-06 & FF-07


K Ditto, size 1590mmL x 4190mmW, pattern as shown on Dwg.
FF-01.02 4.00 No.

Room FF-05
L Ditto, size 2660mmL x 2660mmW, pattern as shown on Dwg.
FF-01.02 4.00 No.

To Stairs

Room FF-01

B03-Concrete 3 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B03-Concrete

M Ditto, to Landing 16.30 m2

N Light Traventine toTread, size 362mmW 100.60 m

Carried to Architechtural Concrete Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

BLOCKWORKS

Supply and installtion of blockworks including mortar,


accessories and all requirements as shown on Drawings,
Specifications and other Tender Documents

BLockworks to be build to

A Room FF-04 118.32 m2


B Room FF-06 73.44 m2
C Room FF-08 3.89 m2
D Room FF-11 1.00 m2
E Room FF-12 61.20 m2
F Room FF-13 5.61 m2
G Room FF-15 11.56 m2
H Room FF-16 21.72 m2
J Room FF-17 82.62 m2
K Room FF-19 45.90 m2
L Room FF-20 32.52 m2
M Room FF-21 1.02 m2
N Room FF-22 23.36 m2
P Room FF-23 54.06 m2
Q Room FF-24 23.36 m2
R Room FF-25 46.41 m2
S Room FF-26 4.23 m2
T Room FF-27 14.76 m2
U Room FF-29 37.03 m2
V Room FF-33 44.47 m2
W Room FF-34 21.28 m2
X Room FF-35 12.24 m2
Y Room FF-36 187.07 m2
Z Room FF-38 9.52 m2
AA Room FF-39 18.36 m2
AB Room FF-41 38.37 m2

B03-Concrete 4 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B03-Concrete

Carried to Architechtural Concrete Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

Important Note :

A Confirm that any and all items not mentioned in this Bill of
Quantities but indicated / required elsewhere in the Tender
Documents and with respect to the particular scope of works
and whatsoever necessary for the satisfactory completion and
handing over of the project. All such items shall be deemed to
be included within the lump sum unit rates of this Bill Division

B03-Concrete 5 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B03-Concrete

Carried to Architechtural Concrete Summary

ARCHITECHTURAL CONCRETE SUMMARY AMOUNT (EURO)

Page 1

Page 2

Page 3

Page 4

Page 5

B03-Concrete 6 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B03-Concrete

TOTAL FOR BILL NO. 03: ARCHITECTURAL CONCRETE, EURO

B03-Concrete 7 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B04-TMP

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

DIVISION 7 - THERMAL AND MOISTURE PROTECTION

Supply, fixing, installation, proper protection up to


handing over, testing and commissioning (where
applicable) and maintenance. (all as per Drawings,
Specifications and other Tender Documents.)

Waterproofing system to wet areas (floor)

A Cementitious waterproofing to wet areas floor 152.55 m2

B Ditto, to Terrace 34.22 m2

C Cementitious waterproofing to wet areas walls 580.31 m2

Sundries

Protect finished surfaces during subsequent construction


operations, repair damage and keep clean as per
specification section

D To waterproofing system to floor Item

E To waterproofing system to walls Item

B04-TMP 1 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B04-TMP

Carried to Thermal & Moisture Protection Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

Important Note :

A Confirm that any and all items not mentioned in this Bill of
Quantities but indicated / required elsewhere in the Tender
Documents and with respect to the particular scope of works
and whatsoever necessary for the satisfactory completion and
handing over of the project. All such items shall be deemed to
be included within the lump sum unit rates of this Bill Division

B04-TMP 2 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B04-TMP

Carried to Thermal & Moisture Protection Summary 0.00

Thermal and Moisture Protection SUMMARY AMOUNT (EURO)

Page 1

Page 2

B04-TMP 3 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B04-TMP

TOTAL FOR BILL NO. 04: THERMAL AND MOISTURE PROTECTION, EURO

B04-TMP 4 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B05-Acoustic Underlay

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

ACOUSTIC UNDERLAYMENT

Supply, fixing, installation, proper protection up to


handing over, testing and commissioning (where
applicable) and maintenance. (all as per the Tender
Documents.)

Rebonded recycled rubber Impact Sound Insulation including


adhesives, including all necessary requirements and works as
per Drawings, Specifications and other Tender Documents

To concrete to received High grade machine carpet to the


following rooms

A FF-11 13.84 m2

B FF-12 52.22 m2

C FF-14 55.46 m2

D FF-15 14.11 m2

E FF-17 43.27 m2

F FF-18 8.29 m2

G FF-19 40.71 m2

H FF-21 6.48 m2

J FF-23 27.06 m2

K FF-25 40.71 m2

L FF-26 5.99 m2

M FF-28 7.08 m2

N FF-33 30.29 m2

P FF-35 59.00 m2

Q FF-36 63.97 m2

R FF-38 59.00 m2

S FF-39 33.82 m2

B05-Acoustic Underlay 1 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B05-Acoustic Underlay

Carried to Acoustic Underlay Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

Important Note :

A Confirm that any and all items not mentioned in this Bill of
Quantities but indicated / required elsewhere in the Tender
Documents and with respect to the particular scope of works
and whatsoever necessary for the satisfactory completion and
handing over of the project. All such items shall be deemed to
be included within the lump sum unit rates of this Bill Division

B05-Acoustic Underlay 2 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B05-Acoustic Underlay

Carried to Acoustic Underlay Summary

ACOUSTIC UNDERLAY SUMMARY AMOUNT (EURO)

B05-Acoustic Underlay 3 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B05-Acoustic Underlay

TOTAL FOR BILL NO. 05: ACOUSTIC UNDERLAY, EURO

B05-Acoustic Underlay 4 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B06-Doors & Hardware

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

DIVISION 8 - OPENINGS

ACOUSTIC WOOD DOORS

Supply, fixing, installation, proper protection up to


handing over, testing and commissioning (where
applicable) and maintenance. (all as per the Tender
Documents.)

The rates for all acoustic wood doors shall include for all
frames, sub-frames, architraves, transoms, glazing, flashing,
protective and decorative coatings, acoustical insulation,
including all necessary requirements and works as per
Drawings, Specifications and other Tender Documents,
complete

Wooden doors complete all in accordance with drawings and


specification

Room FF-36
A Doble leaf door with jamb including architrave (one side
considered, other side measured somewhere as molding) as
shown on Drawing FF-36.10 Section AA, Ref. 01F, door
opening size 1660 x 2300mm high 1.00 No.

Room FF-35
B Ditto, including architrave bothsides Ref. 02F, door opening
size 1660 x 2300mm high 1.00 No.

Room FF-38
C Ditto, including architrave bothsides Ref. 05F, door opening
size 925 x 2300mm high 1.00 No.

Room FF-35
D Single leaf door with jamb including architrave bothsides Ref.
03F, door opening size 900 x 2300mm high 1.00 No.

Room FF-33
E Ditto, including architrave (one side considered, other side
measured somewhere), Ref. 04F, door opening size 830 x
2300mm high 1.00 No.

Room FF-38
F Ditto, including architrave bothsides Ref. 06F, door opening
size 900 x 2300mm high 1.00 No.

Room FF-39
G Single leaf door with jamb including architrave Ref. 08F
(TBD), door opening size 1410 x 2195mm high 1.00 No.

Room FF-35
H Single leaf door with jamb including clear beveled mirror and
architrave on one side (other side architrave measured
somewhere) Ref. 09F, door opening size 900 x 2300mm high
1.00 No.

Room FF-05
J Single leaf door with jamb including architrave on one side
(other side architrave measured somewhere) Ref. 10F, door
opening size 900 x 2300mm high 1.00 No.

B06-Doors & Hardware 1 of 58


SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B06-Doors & Hardware

Carried to Doors and Hardware Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

DIVISION 8 - OPENINGS

ACOUSTIC WOOD DOORS (Continued)

Supply, fixing, installation, proper protection up to


handing over, testing and commissioning (where
applicable) and maintenance. (all as per the Tender
Documents.)

The rates for all acoustic wood doors shall include for all
frames, sub-frames, architraves, transoms, glazing, flashing,
protective and decorative coatings, acoustical insulation,
including all necessary requirements and works as per
Drawings, Specifications and other Tender Documents,
complete

Wooden doors complete all in accordance with drawings and


specification

Room FF-15
A Single leaf door with jamb including architrave bothsides Ref.
13F, door opening size 900 x 2300mm high 1.00 No.

B Ditto, Ref. 15F, door opening size 830 x 2300mm high 1.00 No.

Room FF-14
C Single leaf door with jamb including architrave Ref. 14F, door
opening size 900 x 2300mm high 1.00 No.

Rooms FF-18, FF-21, FF-26 & FF-28


D Single leaf door with jamb including architrave (one side
considered, other side measured somewhere as molding),
Ref. 16F, door opening size 900 x 2300mm high 1.00 No.

E Ditto, Ref. 18F, door opening size 830 x 2300mm high 1.00 No.

F Ditto, Ref. 19F, door opening size 900 x 2300mm high 1.00 No.

G Ditto, Ref. 20F, door opening size 900 x 2300mm high 1.00 No.

H Ditto, Ref. 21F, door opening size 830 x 2300mm high 1.00 No.

J Ditto, Ref. 24F, door opening size 900 x 2300mm high 1.00 No.

K Ditto, Ref. 25F, door opening size 830 x 2300mm high 1.00 No.

Room FF-18
L Single leaf door with jamb and clear mirror with border
including architrave bothsides Ref. 17F, door opening size
830 x 2300mm high 1.00 No.

Rooms FF-19 & FF-25


M Single leaf door with jamb including architrave Ref. 22F, door
opening size 900 x 2300mm high 1.00 No.

N Ditto, Ref. 23F, door opening size 900 x 2300mm high 1.00 No.

B06-Doors & Hardware 2 of 58


SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B06-Doors & Hardware

Carried to Doors and Hardware Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

DIVISION 8 - OPENINGS

ACOUSTIC WOOD DOORS (Continued)

Supply, fixing, installation, proper protection up to


handing over, testing and commissioning (where
applicable) and maintenance. (all as per the Tender
Documents.)

The rates for all acoustic wood doors shall include for all
frames, sub-frames, architraves, transoms, glazing, flashing,
protective and decorative coatings, acoustical insulation,
including all necessary requirements and works as per
Drawings, Specifications and other Tender Documents,
complete

Moisture Resistant Wooden doors complete all in


accordance with drawings and specification

Room FF-41
A Single leaf door with jamb including architrave and mirror
(measured separately), Ref. 07F, door opening size 841 x
2330mm high 1.00 No.

Room FF-10
B Ditto, including architrave on one side (other side considered
in Hallway FF-10) as shown on Drawing FF-10.01 Ref. 11F,
door opening size 850 x 2310mm high 1.00 No.

Room FF-11
C Ditto, Ref. 12F, door opening size 935 x 2315mm high 1.00 No.

Room FF-51
D Single leaf door with jamb including architrave (one side
considered, other side measured somewhere as molding),
Ref. 26F, door opening size 805 x 2300mm high 1.00 No.

Room FF-11
E Double leaf door (concealed) to match Pantry wall finish for
Electrical room as shown on Drawing FF-11.01 Section CC,
size 1300 x 2295mm high 1.00 No.

B06-Doors & Hardware 3 of 58


SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B06-Doors & Hardware

Carried to Doors and Hardware Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

DOOR HARDWARE

Supply, fixing, installation, proper protection up to handing


over, testing and commissioning (where applicable) and
maintenance. (all as per Drawings, Specifications and other
Tender Documents.), complete

Door Hardware to

Room FF-36
A Doble leaf door with jamb including architrave (one side
considered, other side measured somewhere as molding) as
shown on Drawing FF-36.10 Section AA, Ref. 01F, door
opening size 1660 x 2300mm high 1.00 No.

Room FF-35
B Ditto, including architrave bothsides Ref. 02F, door opening
size 1660 x 2300mm high 1.00 No.

Room FF-38
C Ditto, including architrave bothsides Ref. 05F, door opening
size 925 x 2300mm high 1.00 No.

Room FF-35
D Single leaf door with jamb including architrave bothsides Ref.
03F, door opening size 900 x 2300mm high 1.00 No.

Room FF-33
E Ditto, including architrave (one side considered, other side
measured somewhere), Ref. 04F, door opening size 830 x
2300mm high 1.00 No.

Room FF-38
F Ditto, including architrave bothsides Ref. 06F, door opening
size 900 x 2300mm high 1.00 No.

Room FF-39
G Single leaf door with jamb including architrave Ref. 08F
(TBD), door opening size 1410 x 2195mm high 1.00 No.

Room FF-35
H Single leaf door with jamb including clear beveled mirror and
architrave on one side (other side architrave measured
somewhere) Ref. 09F, door opening size 900 x 2300mm high
1.00 No.

Room FF-05
J Single leaf door with jamb including architrave on one side
(other side architrave measured somewhere) Ref. 10F, door
opening size 900 x 2300mm high 1.00 No.

Room FF-15
J Single leaf door with jamb including architrave bothsides Ref.
13F, door opening size 900 x 2300mm high 1.00 No.

B06-Doors & Hardware 4 of 58


SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B06-Doors & Hardware

K Ditto, Ref. 15F, door opening size 830 x 2300mm high 1.00 No.

Room FF-14
L Single leaf door with jamb including architrave Ref. 14F, door
opening size 900 x 2300mm high 1.00 No.

Carried to Doors and Hardware Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

DOOR HARDWARE

Supply, fixing, installation, proper protection up to handing


over, testing and commissioning (where applicable) and
maintenance. (all as per Drawings, Specifications and other
Tender Documents.), complete

Door Hardware to

Rooms FF-18, FF-21, FF-26 & FF-28


A Single leaf door with jamb including architrave (one side
considered, other side measured somewhere as molding),
Ref. 16F, door opening size 900 x 2300mm high 1.00 No.

B Ditto, Ref. 18F, door opening size 830 x 2300mm high 1.00 No.

C Ditto, Ref. 19F, door opening size 900 x 2300mm high 1.00 No.

E Ditto, Ref. 20F, door opening size 900 x 2300mm high 1.00 No.

F Ditto, Ref. 21F, door opening size 830 x 2300mm high 1.00 No.

G Ditto, Ref. 24F, door opening size 900 x 2300mm high 1.00 No.

H Ditto, Ref. 25F, door opening size 830 x 2300mm high 1.00 No.

Room FF-18
J Single leaf door with jamb and clear mirror with border
including architrave bothsides Ref. 17F, door opening size
830 x 2300mm high 1.00 No.

Rooms FF-19 & FF-25


K Single leaf door with jamb including architrave Ref. 22F, door
opening size 900 x 2300mm high 1.00 No.
Ditto, Ref. 23F, door opening size 900 x 2300mm high 1.00 No.

B06-Doors & Hardware 5 of 58


SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B06-Doors & Hardware

Carried to Doors and Hardware Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

DOOR HARDWARE

Supply, fixing, installation, proper protection up to handing


over, testing and commissioning (where applicable) and
maintenance. (all as per Drawings, Specifications and other
Tender Documents.), complete

Door Hardware to

Moisture Resistant Wooden doors complete all in


accordance with drawings and specification

Room FF-41
A Single leaf door with jamb including architrave and mirror
(measured separately), Ref. 07F, door opening size 841 x
2330mm high 1.00 No.

Room FF-10
B Ditto, including architrave on one side (other side considered
in Hallway FF-10) as shown on Drawing FF-10.01 Ref. 11F,
door opening size 850 x 2310mm high 1.00 No.

Room FF-11
C Ditto, Ref. 12F, door opening size 935 x 2315mm high 1.00 No.

Room FF-51
D Single leaf door with jamb including architrave (one side
considered, other side measured somewhere as molding),
Ref. 26F, door opening size 805 x 2300mm high 1.00 No.

Room FF-11
E Double leaf door (concealed) to match Pantry wall finish for
Electrical room as shown on Drawing FF-11.01 Section CC,
size 1300 x 2295mm high 1.00 No.

Sundries

Protect finished surfaces during subsequent construction


operations, repair damage and keep clean as per
specification section

F To wood doors Item

B06-Doors & Hardware 6 of 58


SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B06-Doors & Hardware

Carried to Doors and Hardware Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

Important Note :

A Confirm that any and all items not mentioned in this Bill of
Quantities but indicated / required elsewhere in the Tender
Documents and with respect to the particular scope of works
and whatsoever necessary for the satisfactory completion and
handing over of the project. All such items shall be deemed to
be included within the lump sum unit rates of this Bill Division

B06-Doors & Hardware 7 of 58


SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B06-Doors & Hardware

Carried to Doors and Hardware Summary 0.00

DOORS AND HARDWARESUMMARY AMOUNT (EURO)

Page 1

Page 2

Page 3

Page 4

Page 5

Page 6

Page 7

B06-Doors & Hardware 8 of 58


SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B06-Doors & Hardware

TOTAL FOR BILL NO. 06: DOORS AND HARDWARE, EURO

B06-Doors & Hardware 9 of 58


SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B11-Carpet

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

DIVISION 9 - FINISHES

CARPETING

Carpet flooring, including glue, adhesive, fixing, acoustic


underlayment and accessories with all necessary
requirements and works complete all in accordance with
Drawings, Specification and other Tender Documents,
complete

High grade machine carpet to the following rooms

A FF-11 13.84 m2

B FF-12 52.22 m2

C FF-14 55.46 m2

D FF-15 14.11 m2

E FF-17 43.27 m2

F FF-18 8.29 m2

G FF-19 40.71 m2

H FF-21 6.48 m2

J FF-23 27.06 m2

K FF-25 40.71 m2

L FF-26 5.99 m2

M FF-28 7.08 m2

N FF-33 30.29 m2

P FF-35 59.00 m2

Q FF-36 63.97 m2

R FF-38 59.00 m2

S FF-39 33.82 m2

B11-Carpet 1 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B11-Carpet

Carried to Carpet Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

DIVISION 9 - FINISHES

CARPETING (Continued)

Carpet flooring, including glue, adhesive, fixing, acoustic


underlayment and accessories with all necessary
requirements and works complete all in accordance with
Drawings, Specification and other Tender Documents,
complete

Sundries

Protect finished surfaces during subsequent construction


operations, repair damage and keep clean as per
specification section

High grade machine carpet to the following rooms

A FF-11 Item

B FF-12 Item

C FF-14 Item

D FF-15 Item

E FF-17 Item

F FF-18 Item

G FF-19 Item

H FF-21 Item

J FF-23 Item

K FF-25 Item

L FF-26 Item

M FF-28 Item

N FF-33 Item

P FF-35 Item

Q FF-36 Item

R FF-38 Item

S FF-39 Item

B11-Carpet 2 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B11-Carpet

Carried to Carpet Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

Important Note :

A Confirm that any and all items not mentioned in this Bill of
Quantities but indicated / required elsewhere in the Tender
Documents and with respect to the particular scope of works
and whatsoever necessary for the satisfactory completion and
handing over of the project. All such items shall be deemed to
be included within the lump sum unit rates of this Bill Division

B11-Carpet 3 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B11-Carpet

Carried to Carpet Summary 0.00

CARPET SUMMARY AMOUNT (EURO)

Page 1

Page 2

Page 3

B11-Carpet 4 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B11-Carpet

TOTAL FOR BILL NO. 11: CARPET, EURO

B11-Carpet 5 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B12-Marble

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

STONE FLOORING

Supply, fixing, installation, proper protection up to


handing over, testing and commissioning (where
applicable) and maintenance. (all as per the Tender
Documents.)

Marble flooring, planned, cutting stone to required sizes and


shapes and including cement mortar bed, fixing, joint sealants
and accessories with all necessary requirements and works
complete all in accordance with Drawings, Specification and
Tender Documents, complete.

Room FF-60
A Light Traventine 21.64 m2

Rooms FF-08
B Light Traventine, with border and design as shown on
57.33
drawing F006 m2

Rooms FF-04, FF-13 & FF-29


C Light Traventine, with border and design as shown on
185.88
drawing FF-04.01, FF-13.01 & FF-29.01 m2

Rooms FF-16, FF-20 & FF-27


D Black Marquina polished ref. ST13 31.88 m2

Room FF-51
E Marble Black Marquise 6.30 m2

Room FF-10
F Black Marquise, Ref. ST-21 with design as shown on drawing
5.95
FF-10.01 m2

Room FF-30
G Light Traventine with black jet border 165mm width as shown
8.24
on drawing FF-04.01 m2

Room FF-41
H Volakas Polished with 80mm width Rosso Levato as design
28.61
as shown on drawing FF-41.01 m2

Room FF-34
J Volakas Polished with black marquina polished border as
13.90
shown on drawing FF-34.01 m2

Room FF-22
K Omani white with Black Marquina polished ref. ST13 with
6.09
design as shown on Drawing FF-22.01 m2

Rooms FF-22 & FF-24


L Omani white 7.20 m2

Room FF-24
M Omani white with Black Marquina polished ref. ST13 with
6.09
design as shown on Drawing FF-24.01 m2

Rooms FF-34 & FF-41


N Volakas Polished 5.16 m2

B12-Marble 1 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B12-Marble

Carried to Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

STONE FLOORING

Supply, fixing, installation, proper protection up to


handing over, testing and commissioning (where
applicable) and maintenance. (all as per the Tender
Documents.)

Marble flooring, planned, cutting stone to required sizes and


shapes and including cement mortar bed, fixing, joint sealants
and accessories with all necessary requirements and works
complete all in accordance with Drawings, Specification and
Tender Documents, complete.

Rooms FF-16, FF-20, FF-22, FF-24, FF-27, FF-34 & FF-41


A Volakas Polished (polished & sanded) as shown on Drawing
1.21
FF-41.01 for Shower marble floor detail m2

B Ditto, as shown on Drawing FF-34.01 for Shower marble floor


1.21
detail m2

C Ditto, as shown on Drawing FF-16.01 for Shower marble floor


0.86
detail m2

D Ditto, as shown on Drawing FF-27.01 for Shower marble floor


1.52
detail m2

E Ditto, as shown on Drawing FF-20.01 for Shower marble floor


1.02
detail m2

F Ditto, as shown on Drawing FF-22.01 for Shower marble floor


1.02
detail m2

G Ditto, as shown on Drawing FF-24.01 for Shower marble floor


1.02
detail m2

Rooms FF-02, FF-05, FF-06, FF-06A, FF-07 & FF-08


H Flooring, light travertin 115.50 m2

Rooms FF-02, FF-07 & FF-07


J Flooring with pattern, light travertin & black jet marble, size
1590mmL x 1590mmW, pattern as shown on Dwg. FF-01.02 8.00
No.

Rooms FF-02, FF-06 & FF-07


K Ditto, size 1590mmL x 4190mmW, pattern as shown on Dwg.
4.00
FF-01.02 No.

Room FF-05
L Ditto, size 2660mmL x 2660mmW, pattern as shown on Dwg.
4.00
FF-01.02 No.

Room FF-08
Border, black jet marble, size 165mmW 16.60 m

To Stairs

Room FF-01
M Ditto, to Landing 16.30 m2

N Light Traventine toTread, size 362mmW 100.60 m

B12-Marble 2 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B12-Marble

P Ditto, Riser, size 133mmW 116.50 m

Carried to Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

STONE FLOORING

Supply, fixing, installation, proper protection up to


handing over, testing and commissioning (where
applicable) and maintenance. (all as per the Tender
Documents.)

MARBLE SKIRTING

Marble skirting fixed to wall including cutting stone to required


sizes and shapes, adhesives, background, support, backing,
etc including all necessary requirements and works as per
Drawings, Specifications and other Tender Documents,
complete.

Room FF-10
A 10mm thick Black marquise marble skirting, 105mm high 8.84 m

Room FF-51
B 25mm thick Black Marquise skirting as shown on Drawing FF-
7.73
51.10 Sections, 100mm high m

Room FF-30
C 25mm thick Black Marquise skirting as shown on Drawing FF-
8.26
51.10 Sections, 240mm high m

Room FF-14
D 20mm thick Light Traventine skirting, 140mm high 19.39 m

Room FF-36
E 23mm thick Light Traventine skirting, 140mm high 10.16 m

Room FF-13
F 25mm thick Light Traventine Skirting, 240mm high 40.96 m

Room FF-08
G Skirting, travertin, size 240mmH 10.90 m

Room FF-02, FF-05, FF-06, FF-06A, FF-07


H Skirting, travertin, size 240mmH, as shown on dwg. GF-26.21
77.20
Detail 11 m

B12-Marble 3 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B12-Marble

Carried to Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

STONE FLOORING

Supply, fixing, installation, proper protection up to


handing over, testing and commissioning (where
applicable) and maintenance. (all as per the Tender
Documents.)

DOOR SHOE

Marble door shoe fixed to wall including cutting stone to


required sizes and shapes, adhesives, background, required
supports, backing, etc including all necessary requirements
and works as per Drawings, Specifications and other Tender
Documents, complete.

Rooms FF-15, FF-18, FF-21, FF-26, FF-28 & FF-33


A 110mm high Light Traventine door shoe as shown on Drawing
FF-14.20 Sections, overall size 135 x 45mm width 4.00
No.

B Ditto, as shown on Drawing FF-18.20 Sections, overall size


2.00
125 x 45mm width No.

C Ditto, as shown on Drawing FF-21.01 Sections, overall size


6.00
135 x 45mm No.

D Ditto, as shown on Drawing FF-26.01 Sections, overall size


4.00
135 x 45mm No.

E Ditto, as shown on Drawing FF-28.10 Sections, overall size


4.00
140 x 35mm width No.

F Ditto, as shown on Drawing FF-33.10 Sections, overall size


4.00
140 x 35mm width No.

Room FF-33
G 140mm Light Traventine door shoe as shown on Drawing FF-
2.00
33.10 Sections, overall size 220 x 220mm width No.

Rooms FF-35, FF-38 & FF-39


H 145mm Light Traventine door shoe as shown on Drawing FF-
16.00
35.10 Sections, overall size 127 x 43mm width No.

J Ditto, as shown on Drawing FF-38.10 Sections, overall size


16.00
127 x 43mm width No.

K Ditto, as shown on Drawing FF-39.10 Sections, overall size


10.00
127 x 43mm width No.

Room FF-36
L 190mm Light Traventine door shoe as shown on Drawing FF-
6.00
12.20 Detail 01, overall size 135 x 145mm No.

M Ditto, as shown on Drawing FF-12.20 Detail 02, overall size


4.00
140 x 60mm width No.

B12-Marble 4 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B12-Marble

Rooms FF-13
N 250mm Light Traventine door shoe as shown on Drawing FF-
12.00
39.10 Sections, overall size 150 x 60mm width No.

P Ditto, overall size 265 x 95mm width 12.00 No.

Carried to Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

STONE FLOORING

Supply, fixing, installation, proper protection up to


handing over, testing and commissioning (where
applicable) and maintenance. (all as per the Tender
Documents.)

DOOR SHOE (Continued)

Marble door shoe fixed to wall including cutting stone to


required sizes and shapes, adhesives, background, required
supports, backing, etc including all necessary requirements
and works as per Drawings, Specifications and other Tender
Documents, complete.

Rooms FF-11, FF-12, FF-14, FF-17, FF-19, FF-23, FF-25,


FF-29 & FF-36
A 150mm Light Traventine door shoe as shown on Drawing FF-
16.00
04.10 Detail 01, overall size 92 x 32mm width No.

B Ditto, as shown on Drawing FF-04.10 Detail 01, overall size


2.00
129 x 92mm width No.

C Ditto, as shown on Drawing FF-14.20 Sections, overall size


10.00
135 x 45mm width No.

D Ditto, as shown on Drawing FF-17.20 Sections, overall size


2.00
135 x 45mm width No.

E Ditto, as shown on Drawing FF-12.20 Detail 01, overall size


4.00
140 x 45mm width No.

F Ditto, as shown on Drawing FF-19.10 Sections, overall size


8.00
140 x 35mm width No.

G Ditto, as shown on Drawing FF-23.10 Sections, overall size


8.00
140 x 35mm width No.

H Ditto, as shown on Drawing FF-25.10 Sections, overall size


8.00
140 x 35mm width No.

J Ditto, as shown on Drawing FF-29.10 Sections, overall size


12.00
140 x 35mm width No.

K Ditto, as shown on Drawing FF-11.10 Sections, overall size


2.00
140 x 60mm width No.

L Ditto, as shown on Drawing FF-14.20 Sections, overall size


13.00
150 x 35mm width No.

M Ditto, as shown on Drawing FF-17.20 Sections, overall size


17.00
150 x 35mm width No.

B12-Marble 5 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B12-Marble

N Ditto, as shown on Drawing FF-04.10 Detail 01, overall size


2.00
168 x 45mm thick No.

P Ditto, as shown on Drawing FF-04.10 Detail 01, overall size


2.00
230 x 89mm thick No.

Room FF-10
Q 360mm Light Traventine door shoe as shown on Drawing FF-
2.00
10.10 Sections, overall size 110 x 70mm width No.

Carried to Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

STONE FLOORING

Supply, fixing, installation, proper protection up to


handing over, testing and commissioning (where
applicable) and maintenance. (all as per the Tender
Documents.)

DOOR SHOE (Continued)

Marble door shoe fixed to wall including cutting stone to


required sizes and shapes, adhesives, background, required
supports, backing, etc including all necessary requirements
and works as per Drawings, Specifications and other Tender
Documents, complete.

Room FF-30
A 250mm high Black Marquise door shoe as shown on Drawing
4.00
FF-51.10 Sections, size 240 x 90mm width No.

Room FF-51
B 360mm high Black Marquise door shoe as shown on Drawing
2.00
FF-51.10 Sections, size 110 x 70mm width No.

Marble Handrails

Marble Handrails fixed to floor including cutting stone to


required sizes and shapes, adhesives, background, required
supports, backing, etc including all necessary requirements
and works as per Drawings, Specifications and other Tender
Documents, complete.

Rooms FF-02, FF-06 & FF-07


C Handrails & balustrades in patinated bronze finish, posts in
marble ball black jet & travertin, size 900mmH at hallway 33.90
m

Room FF-01
D Handrails & balustrades in patinated bronze finish, posts in
marble ball black jet & travertin, size 900mmH at staircase 58.70
m

E PROVISIONAL SUM for marble thresholds Item

Sundries

Protect finished surfaces during subsequent construction


operations, repair damage and keep clean as per
specification section

B12-Marble 6 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B12-Marble

F To marble floors Item

G To marble skirting Item

H To door shoe Item

J To marble handrail Item

K To marble thresholds Item

Carried to Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

STONE FACING

Supply, fixing, installation, proper protection up to


handing over, testing and commissioning (where
applicable) and maintenance. (all as per the Tender
Documents.)

Marble panel fixed vertically on and including metal framing,


mdf backing, cutting stone to required sizes and shapes,
including fixing, grouting, joint sealants and accessories
including all necessary requirements and works as per
Drawings, Specifications and other Tender Documents,
complete.

Room FF-36
A Light Traventine 5.99 m2

Rooms FF-16, FF-20 & FF-27


B Thala Beige polished 44.61 m2

Room FF-27
C Thala Beige polished molding, size 55 x 30mm width 5.35 m

Room FF-41
D Roso levanto, 60mm width 200.71 m

Rooms FF-22 & FF-24


E Oman White 125.14 m2

Rooms FF-16, FF-20 & FF-27


Combined marble stripe pattern to concrete/ blockwork
including backing and support as required on site, 150mm
F wide Thala Beige polished & 150mm wide Black marquina 103.02
polished m2

Rooms FF-16 & FF-20


G Black Marquina polished ref. ST13 18.03 m2

Rooms FF-22, FF-24 & FF-27


H Black Marquina 8.94 m2

Rooms FF-22 & FF-34


J Black Marquina, 70mm width 7.20 m

K Ditto, 60mm width 89.58 m

B12-Marble 7 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B12-Marble

L Ditto, 190mm wide 39.76 m

M Ditto, 165mm width 5.27 m

N Ditto, 265mm width 4.64 m

Rooms FF-22 & FF-24


Black Marquina Molding as shown on Drawing FF-24.10
P 10.64
section EE, overall size 40 x 20mm width m

Ditto, as shown on Drawing FF-22.10 section EE, overall size


Q 10.64
40 x 20mm width m

Carried to Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

STONE FACING

Marble panel fixed vertically on and including metal framing,


mdf backing, cutting stone to required sizes and shapes,
including fixing, grouting, joint sealants and accessories
including all necessary requirements and works as per
Drawings, Specifications and other Tender Documents,
complete.

Rooms FF-22 & FF-24


Black Marquina Molding as shown on Drawing FF-22.10
A 5.41
section EE, overall size 65 x 40mm width m

Ditto, as shown on Drawing FF-24.10 section EE, overall size


B 5.41
65 x 40mm width m

Room FF-16
Black Marquina polished ref. ST13 Bathtub surround in
C marble top, as shown in Drawing FF-16.01 Floor Lay-out, 1.00
overall size 2000 x 995mm width No.

Room FF-20
Ditto, as shown on Drawing FF-20.01 Floor Lay-out, overall
D 1.00
size 2405 x 1048mm width No.

Room FF-22
Ditto, as shown on Drawing FF-22.01 Floor Lay-out, overall
E 1.00
size 2320 x 1050mm width No.

Room FF-24
Ditto, as shown on Drawing FF-24.01 Floor Lay-out, overall
F 1.00
size 2320 x 1050mm width No.

Room FF-27
Ditto, as shown on Drawing FF-27.01 Floor Lay-out, overall
G 1.00
size 2050 x 990mm width No.

Rooms FF-34 & FF-41


H Volakas Polished 46.72 m2

Room FF-41
Volakas polished, EO to removable plumbing access, size
J 1.00
1790 x 640mm high No.

B12-Marble 8 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B12-Marble

Room FF-34
K Volakas polished with 60mm black marquina polished 17.57 m2

Room FF-41
Volakas polished for bench a shown on Drawing FF-41.10
L 1.00
Section HH, 1506 x 413mm width No.

Sundries
Protect finished surfaces during subsequent construction
operations, repair damage and keep clean as per
specification section

N To marble walls Item

Access Panels

Allow for proprietary access panels to marble walls including


P
framework, fittings and fixtures, etc. Item

Carried to Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

STONE CEILING

Supply, fixing, installation, proper protection up to


handing over, testing and commissioning (where
applicable) and maintenance. (all as per the Tender
Documents.)

Marble panel fixed vertically on and including metal framing,


mdf backing, cutting stone to required sizes and shapes,
including fixing, grouting, joint sealants and accessories
including all necessary requirements and works as per
Drawings, Specifications and other Tender Documents,
complete.

Rooms FF-22 & FF-24


A Black marquina polished, size 700 x 230mm width 4.00 No.

Room FF-20
B Ditto, size 743 x 200mm width 2.00 No.

Room FF-27
C Ditto, size 710 x 190mm width 2.00 No.

Room FF-34
D Ditto, size 860 x 265mm width 1.00 No.

E Ditto, size 1580 x 100mm width 1.00 No.

F Black Marquina polished ref. ST13, size 1925 x 185mm width


1.00
No.

Room FF-16
G Black Marquina polished, size 1010 x 300mm width 1.00 No.

Rooms FF-22 & FF-24


H Black marquina polished, size 1890x 600mm width 2.00 No.

Rooms FF-22 & FF-24


J Ditto, size 1985 x 190mm width 2.00 No.

Room FF-34
K Ditto, 2575 x 165mm width 1.00 No.

B12-Marble 9 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B12-Marble

Room FF-41
L Rosso Levato, 271 x 942mm width 3.00 No.

M Ditto, 145 x 1641mm width 1.00 No.

Sundries

Protect finished surfaces during subsequent construction


operations, repair damage and keep clean as per
specification section

N To marble ceilings Item

Access Panels

Allow for proprietary access panels to marble walls including


P
framework, fittings and fixtures, etc. Item

Carried to Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

Important Note :

A Confirm that any and all items not mentioned in this Bill of
Quantities but indicated / required elsewhere in the Tender
Documents and with respect to the particular scope of works
and whatsoever necessary for the satisfactory completion and
handing over of the project. All such items shall be deemed to
be included within the lump sum unit rates of this Bill Division

B12-Marble 10 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B12-Marble

Carried to Summary 0.00

MARBLE WORKS SUMMARY AMOUNT (EURO)

Page 1

Page 2

Page 3

Page 4

Page 5

Page 6

Page 7

Page 8

Page 9

Page 10

B12-Marble 11 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B12-Marble

TOTAL FOR BILL NO. 12: MARBLE, EURO

B12-Marble 12 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B13-Painting

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

PAINTING AND SPECIAL FINISHES

Supply and application of paint including preparation and all


necessary requirements and works as per Drawings,
Specifications and other Tender Documents, complete.

Painting to reinforced plastered concrete wall/


blockworks (plaster not part of scope)

Room FF-35 & 38


A Wall Paint 247.66 m2

Room FF-34
B Moisture resistant paint to wall 1.65 m2

Rooms FF-13, FF-15, FF-17, FF-18, FF-19, FF-21, FF-23,


FF-25, FF-26, FF-28, FF-29, FF-33, FF-35, FF-36, FF-38 &
C FF-39
Painting to reinforced plaster (white) behind cupboards and
other joinery 337.62 m2

Rooms FF-11, FF-34 & FF-41


D Ditto, but moisture resistant 25.42 m2

Rooms FF-12, FF-14, FF-15, FF-17, FF-18, FF-19, FF-21,


FF-23, FF-25, FF-26, FF-28, FF-29, FF-33, FF-36 & FF-39
E Decorative Paint 434.47 m2

Rooms FF-10, FF-11 & FF-51


F Ditto, but moisture resistant 51.02 m2

Room FF-14
G Decorative Painting (fake Perchamin) 24.61 m2

Room FF-01, FF-02, FF-05, FF-06, FF-06A, FF-07, FF-08,


FF-13
H Decorative Painting (fake stone) 711.38 m2

B13-Painting 1 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B13-Painting

Carried to Painting Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

PAINTING AND SPECIAL FINISHES

Supply and application of paint including preparation and all


necessary requirements and works as per Drawings,
Specifications and other Tender Documents, complete.

CEILING PAINTING

Rooms FF-02, FF-04, FF-05, FF-06, FF-06A, FF-07, FF-08,


FF-12, FF-13, FF-14, FF-15, FF-17, FF-18, FF-19, FF-21, FF-
23, FF-25, FF-26, FF-28, FF-29, FF-30, FF-33, FF-35, FF-36,
FF-38, FF-39
A Gypsum board to received paint (measured separately) 1,165.29 m2

Rooms FF-10, FF-11, FF-16, FF-20, FF-22, FF-24, FF-27,


FF-34, FF-41 & FF-51
B Ditto, but moisture resistant 125.22 m2

Rooms FF-02, FF-05, FF-06, FF-06A & FF-07


C Gypsum Board bulkhead to received paint (measured
separately), size 100mm 149.07 m

Room FF-01
D Bulkhead + P, size 100mm @ Dome 79.20 m

Rooms FF-17, FF-19, FF-23, FF-25 & FF-29


E Ditto, 120mm high 103.70 m

Room FF-13
F Ditto, 180mm high 11.26 m

Room FF-13
G Ditto 230mm high 2.50 m

Rooms FF-02, FF-06, FF-07, FF-17, FF-19, FF-25 & FF-29

H Ditto, 250mm high 55.92 m

Room FF-2
J Ditto, 280mm high 5.72 m

Rooms FF-35 & FF-38


K Ditto, 310mm high 11.00 m

Room FF-01
L Gypsum board including support & catway @ Dome 116.56 m2

Room FF-23
M Ditto but to received decorative paint (measured separately), m
280mm high 12.45

Room FF-08
N Gypsum board with painting false stone (measured m2
separately) 2.50

B13-Painting 2 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B13-Painting

Carried to Painting Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

PAINTING AND SPECIAL FINISHES

Supply and application of paint including preparation and all


necessary requirements and works as per Drawings,
Specifications and other Tender Documents, complete.

CEILING PAINTING

Protection

Protect finished surfaces during subsequent construction


operations, repair damage and keep clean as per
specification section

A To painted gypsum board ceilings of room FF-02


B Ditto, FF-04 1.00 Item
C Ditto, FF-05 1.00 Item
D Ditto, FF-06 1.00 Item
E Ditto, FF-07 1.00 Item
F Ditto, FF-08 1.00 Item
G Ditto, FF-12 1.00 Item
H Ditto, FF-13 1.00 Item
J Ditto, FF-14 1.00 Item
K Ditto, FF-15 1.00 Item
L Ditto, FF-17 1.00 Item
M Ditto, FF-18 1.00 Item
N Ditto, FF-19 1.00 Item
P Ditto, FF-21 1.00 Item
Q Ditto, FF-23 1.00 Item
R Ditto, FF-25 1.00 Item
S Ditto, FF-26 1.00 Item
T Ditto, FF-28 1.00 Item
U Ditto, FF-29 1.00 Item
V Ditto, FF-30 1.00 Item
W Ditto, FF-33 1.00 Item
X Ditto, FF-35 1.00 Item
Y Ditto, FF-36 1.00 Item
Z Ditto, FF-38 1.00 Item
AA Ditto, FF-39 1.00 Item

AB To painted moisture resistant gypsum board ceiling of Room


FF-10 1.00 Item
AC Ditto, FF-10 1.00 Item
AD Ditto, FF-11 1.00 Item
AE Ditto, FF-16 1.00 Item
AF Ditto, FF-20 1.00 Item
AG Ditto, FF-22 1.00 Item
AH Ditto, FF-24 1.00 Item
AJ Ditto, FF-27 1.00 Item
AK Ditto, FF-34 1.00 Item
AL Ditto, FF-41 1.00 Item
AM Ditto, FF-51 1.00 Item

B13-Painting 3 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B13-Painting

Carried to Painting Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

PAINTING AND SPECIAL FINISHES

Supply and application of paint including preparation and all


necessary requirements and works per Drawings,
Specifications and other Tender Documents, complete.

PAINTING TO FIBROUS PLASTER - CEILING

Room FF-18
A Fibrous Plaster Covelight to received paint as shown in
Drawing FF-18.20 Detail 04, overall size 210 x 420mm high
11.23 m

Rooms FF-17, FF-19, FF-23, FF-25 & FF-29


B Fibrous Plaster Covelight with paint, overall size 265 x
600mm high, as shown in Drawing FF-17.10 Sections 18.16 m
C Ditto, as shown in Drawing FF-19.10 Sections 18.56 m
D Ditto, as shown in Drawing FF-25.20 Detail 04 18.58 m
E Ditto, as shown in Drawing FF-23.20 Detail 01 21.45 m
F Ditto, as shown in Drawing FF-29.10 Sections 12.99 m

Room FF-13
G Fibrous Plaster Covelight with paint as shown in Drawing FF-
13.10 & FF-13-11 Sections, overall size 300 x 315mm high
55.25 m

Rooms FF-21, FF-26 & FF-58


H Fibrous Plaster Covelight with paint, overall size 340 x
420mm high,, as shown in Drawing FF-21.20 Detail 05 10.17 m

J Ditto, as shown in Drawing FF-26.20 Detail 04 9.05 m

K Ditto, as shown in Drawing FF-28.20 Detail 05 9.55 m

Room FF-15
L Fibrous Plaster Covelight with paint as shown in Drawing FF-
15.20 Detail 4, overall size 340 x 420mm high 14.44 m

Room FF-30
M Ditto, as shown in Drawing FF-30.01 Sections, overall size
320x 490mm high 9.09 m

Room FF-12
N Ditto, as shown in Drawing FF-12.01 Detail 03, overall size
450 x 620mm high 28.34 m

Room FF-39
P Ditto, as shown in Drawing FF-39.20 Sections, overall size
454 x 500mm high 31.64 m

B13-Painting 4 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B13-Painting

Carried to Painting Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

DIVISION 9 - FINISHES

PAINTING AND SPECIAL FINISHES

Supply and application of paint including preparation and all


necessary requirements and works per Drawings,
Specifications and other Tender Documents, complete.

PAINTING TO FIBROUS PLASTER - CEILING (Continued)

Room FF-35
A Fibrous Plaster Covelights, as shown in Drawing FF-35.20
Detail 05, overall size 494 x 492mm high 16.69 m

Room FF-38
B Ditto, as shown in Drawing FF-38.20 Sections, overall size
496 x 492mm high 16.69 m

C Ditto, as shown in Drawing FF-38.20 Sections, overall size


620 x 756mm high 23.30 m

Room FF-35
D Ditto, as shown in Drawing FF-35.20 Detail 04, overall size
620 x 776mm high 23.30 m

Room FF-04
E Ditto, shown in Drawing FF-04.10 Detail 09, overall size 727 x
520mm high 34.21 m

Room FF-01
F Ditto, size 880mmH x 300mmW @ Dome 37.25 m

DECORATIVE PAINTING

Rooms FF-14, FF-33 & FF-36


G Fibrous Plaster Covelight with decorative painting (fake wood)
as shown in Drawing FF-33.10 Sections, overall size 453 x
500mm high 38.29 m

H Ditto, as shown in Drawing FF-36.20 Sections, overall size


702 x 756mm high 31.77 m

J Ditto, as shown in Drawing FF-14.20 Detail 02, overall size


737 x 890mm high 27.20 m

Room FF-02, FF-05, FF-06, FF-06A & FF-07


K Ditto, size 300 x 470mm high 149.97 m

Room FF-08
L Ditto, cornice with Decorative Paint false stone, size
800mmH x 800mmW 26.70 m

B13-Painting 5 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B13-Painting

Carried to Painting Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

DIVISION 9 - FINISHES

PAINTING AND SPECIAL FINISHES

Supply and application of paint including preparation and all


necessary requirements and works per Drawings,
Specifications and other Tender Documents, complete.

PAINTING TO WATER RESISTANT FIBROUS PLASTER -


CEILING

Rooms FF-16, FF-20, FF-22, FF-24 & FF-27


A Moisture Resistanct Fibrous Plaster Covelight with paint,
overall size 130 x 220mm high, as shown in Drawing FF-
16.20 Detail 10 7.25 m

B Ditto, as shown in Drawing FF-20.20 Detail 10 16.45 m

C Ditto, as shown in Drawing FF-22.20 Detail 09 16.56 m

D Ditto, as shown in Drawing FF-24.10 Sections 16.56 m

E Ditto, as shown in Drawing FF-27.10 Detail 10 11.41 m

Room FF-34
F Fibrous Plaster Covelight with paint as shown in Drawing FF-
34.20 Detail 07, overall size 206 x 335mm high 13.87 m

Room FF-27
G Ditto, as shown in Drawing FF-27.20 Detail 06, overall size
257 x 320mm high 10.27 m

Room FF-22
H Ditto, as shown in Drawing FF-22.20 Detail 08, overall size
265 x 320mm high 8.10 m

Room FF-34
J Ditto, as shown in Drawing FF-34.20 Detail 05, overall size
282 x 448mm high 8.77 m

Room FF-24
K Ditto, as shown in Drawing FF-41.20 Detail 07, 08 & 09,
overall size 286 x 386mm high 17.67 m

Rooms FF-16, FF-20 & FF-24


L Fibrous Plaster Covelight with paint, overall size 300 x
320mm high, as shown in Drawing FF-16.20 Detail 6 11.00 m

M Ditto, as shown in Drawing FF-20.20 Detail 6 7.21 m

B13-Painting 6 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B13-Painting

N Ditto, as shown in Drawing FF-24.10 Sections 8.10 m

Carried to Painting Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

DIVISION 9 - FINISHES

PAINTING AND SPECIAL FINISHES

Supply and application of paint including preparation and all


necessary requirements and works per Drawings,
Specifications and other Tender Documents, complete.

PAINTING TO WATER RESISTANT FIBROUS PLASTER -


CEILING (Continued)

Room FF-51
A Fibrous Plaster Covelight with paint as shown in Drawing FF-
51.20 Detail 04, overall size 310 x 350mm high 10.30 m

Room FF-41
B Dito, as shown in Drawing FF-41.20 Detail 04, overall size
310 x 500mm high 15.72 m

Room FF-34
C Ditto, as shown in Drawing FF-34.20 Detail 05, overall size
326 x 500mm high 11.85 m

Room FF-10
D Ditto, as shown in Drawing FF-10.01 Detail 01, overall size
345 x 350mm high 9.38 m

Room FF-11
E Dito, as shown in Drawing FF-11.01 Sections, overall size 513
x 620mm high 13.14 m

Sundries

Protect finished surfaces during subsequent construction


operations, repair damage and keep clean as per
specification section

F To fibrous plaster ceilings Item

B13-Painting 7 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B13-Painting

Carried to Painting Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

DIVISION 9 - FINISHES

PAINTING AND SPECIAL FINISHES

Supply and application of paint including preparation and all


necessary requirements and works per Drawings,
Specifications and other Tender Documents, complete.

PAINTING TO FIBROUS PLASTER-WALLS

Room FF-30
A Fibrous plaster molding as shown on Drawing FF-30.01
Section CC, overall size 220 x 80mm width 13.12 m

Room FF-29
B Fibrous plaster + decorative paint (fake wood) as shown on
Drawing FF-29.10 Sections, overall size 100mm wide x 25mm
thick 11.08 m

Rooms FF-19 & FF-25


C Ditto, overall size 115mm wide x 25mm thick, as shown on
Drawing FF-19.10 Sections 21.84 m

D Ditto, as shown on Drawing FF-25.10 Sections 21.84 m

Room FF-17
E Ditto, as shown on Drawing FF-17.10 Detail 01, 02 & 03,
overall size 120mm wide x 30mm thick 130.06 m

Room FF-14
F Ditto, as shown on Drawing FF-14.20 Detail 01, overall size
120mm wide x 40mm thick 57.45 m

Room FF-13
G Reinforced plaster with false stone finish as shown on
Drawing FF-13.10 Section AA, size 140 x 55mm thick 24.57 m
Ditto, but size 220 x 80mm thick 46.51 m

Sundries

Protection

Protect finished surfaces during subsequent construction


operations, repair damage and keep clean as per
specification section

G To fibrous plaster walls Item

B13-Painting 8 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B13-Painting

Access Panels

J Allow for proprietary access panels to fibrous plaster walls


including framework, fittings and fixtures, etc. Item

Carried to Painting Summary

AMOUNT
ITEM DESCRIPTION QTY UNIT RATE
EURO

Important Note :

A Confirm that any and all items not mentioned in this Bill of
Quantities but indicated / required elsewhere in the Tender
Documents and with respect to the particular scope of works
and whatsoever necessary for the satisfactory completion and
handing over of the project. All such items shall be deemed to
be included within the lump sum unit rates of this Bill Division

B13-Painting 9 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B13-Painting

Carried to Painting Summary 0.00

PAINTING SUMMARY AMOUNT (EURO)

Page 1

Page 2

Page 3

Page 4

Page 5

Page 6

Page 7

Page 8

Page 9

B13-Painting 10 of 58
SAMPLE PROJECT BILL OF QUANTITIES
FIRST FLOOR BOQ B13-Painting

TOTAL FOR BILL NO. 13: PAINTING, EURO

B13-Painting 11 of 58