Detail Engg and Design Phase
Detail Engg and Design Phase
Detail Engg and Design Phase
Introduction
Introduction
Detailed Design Engineering Design Integrity Workflow (EDIW )
Situations will arise when work will need to be done out of sequence,
typically to meet demanding project schedule. Use of the EDIW allows the
risks of out-of-sequence working to be identified and the necessary
mitigation strategies to be put in place.
Phase 1
Scope Definition and Engineering Execution
Strategy
Preparation for commencement of detail design. To evaluate FEED
deliverables to ensure engineering is sufficiently mature for detail design to
progress in a controlled and minimal change environment. To confirm
Engineering Execution Plan.
Phase 2
Commencement of Detail Design
To formally kick off the Engineering Design Process in accordance with the
project execution plan
and to ensure that key engineering strategies / philosophies are in place.
Phase 3
Initial Design Development and Hazard
Identification
To develop initial design deliverables to Inter Discipline Review (IDC) stage
and identify key hazards..
Phase 5
Design Approval
To ‘Freeze’ the Process design, and develop dependent design &
procurement activities.
Phase 6
Activities / Deliver
Activities / Key Supporting
Description
Deliverable Discipline Documentation
1 SHE Audit AFC Conduct SHE Audit at AFC stage in Technical SHE Audit Procedure OAG-
accordance with Harmonized Procedure Safety X160-190-PRO-023
2 IEC 61511 Final report to formally demonstrate that the Instruments Management of Functional
Compliance Report Safety Instrumented Systems comply with Safety, OAG-X160-
the requirements of IEC 61511. 190-GDL-004
3 PFD’s AFC Issue Approved For Construction (AFC) Process
Process Flow Diagrams
4 Operational Safety Commence operational Safety Case Technical
Case Development development. Safety
5 P&ID’s AFC Issue Approved For Construction (AFC) Process
Process and Instrumentation Diagrams.
6 Quantitative Risk Complete QRA activities to confirm that the Technical
Assessment (QRA) design is robust and complies with Safety
legislative requirements
7 C&E AFC Issue Approved For Construction (AFC) Instruments
Cause & Effects
8 Operating Ensure operating procedures are verified Process, Formal HAZOP, OAG-X160-
Procedures Review line by line against the facilities provided on Technical 190-PRO-017
/ Operational HAZOP the P&ID’s. Safety (previously AOD-92-022);
Engineering & Design
Reviews, OAG-X160-190-
PRO-013
9 Fabrication Issue Approved For Construction (AFC) Affected
Drawings AFC Piping Isometrics, Structural Steelwork drgs, Disciplines
etc.
10 Verification of Verify, primarily through review of vendor Affected
Vendor Information documentation, that their design & Disciplines
& Certification - manufacture of fabricated packages, etc is
Installation, robust and contains sufficient information to
Operation & facilitate safe installation, operation &
Maintenance maintenance.
11 EC Design Where AMEC are deemed to be the PER Focal Project Compliance with the
Examination manufacturer of the piping systems, then point Pressure
Certificates under the PED/PER, AMEC have to apply to Equipment Directive,
the Notified Body (NoBo) for an EC Design Document
Examination Certificate (Cat IV assemblies No. OAG-X160-190-GDL-
only). 007.
12 Declaration of Where AMEC are deemed to be the Project Project Compliance with the
Conformity manufacturer of the piping Manager Pressure
systems, then under the PED/PER, AMEC Equipment Directive,
have to create a Document
Declaration of Conformity, signed by the No. OAG-X160-190-GDL-
Project Manage 007.
Phase 7
Design Close-Out
To ensure all final design deliverables are completed and that client and
statutory obligations are satisfactorily resolved