Compendium CEA July 2024
Compendium CEA July 2024
by
Central Electricity Authority
Disclaimer:
All efforts have been made to ensure that the contents of the Compendium
are free from editorial mistakes. However, the versions of the Regulations
in the Gazette Noti ications are authentic and binding and shall prevail in
the event of the discrepancies with the Regulations in the Compendium.
Central Electricity
Ministry of Power Govt.Authority
of India
SewaShakti
Shram Bhawan, R.K. Puram,
Bhawan, Ra i Marg,
Sector-1,
NewNew Delhi-110 066
Delhi-110001
Preface
As you explore this Compendium, we hope that this will be a valuable resource for
reference for the stakeholders.
Sr. Notification
Subject Page No.
No. Date
17.03.2006
[04.06.2010,
26.11.2014, Central Electricity Authority (Installation & Operation of Meters)
1 01-23
23.12.2019 Regulations, 2006 (Amended in 2010, 2014, 2019 and 2022)
and
28.02.2022]
21.02.2007
[15.10.2013 Central Electricity Authority (Technical Standards for Connectivity
3 29-45
and to the Grid) Regulations, 2007 (Amended in 2013 and 2019)
06.02.2019]
10.04.2007
[17.03.2022 Central Electricity Authority (Furnishing of Statistics, Returns &
4 46-166
and Information) Regulations, 2007 (Amended in 2022 and 2023)
25.07.2023]
NOTIFICATION
1 Inserted vide Amendment, 2014 w.e.f. 26.11.2014, and later omitted vide Amendment, 2019 w.e.f. 23.12.2019.
Page 01 of 510
Infrastructure or a part of the Advanced Metering Infrastructure, till its transfer to the
licensee;]2
(e) ‘Appropriate Load Despatch Centre’ means ‘National Load Despatch Centre’
(NLDC) or ‘Regional Load Despatch Centre’ (RLDC) or the ‘State Load Despatch
Centre’ (SLDC) as the case may be;
(f) ‘Appropriate Transmission Utility’ means the ‘Central Transmission Utility’ (CTU) or
the ‘State Transmission Utility’ (STU), as the case may be;
(g) [ ]3
(h) ‘Buyer’ means any generating company or licensee or consumer whose system receives
electricity from the system of generating company or licensee;
[(i) ‘Check Meter’ means a meter, which shall be connected to the same core of the
Instrument Transformer to which main meter is connected and shall be used for
accounting and billing of electricity in case of failure of main meter;]4
[(j) ‘Consumer Meter’ means a meter used for accounting and billing of electricity supplied
to or from the consumer but excluding those consumers covered under Interface
Meters;]5
[(k) ‘Correct Meter’ means a meter, complying the standards as specified in the Schedule to
these regulations;]6
(l) ‘Energy Accounting and Audit Meters’ means meters used for accounting of the
electricity to various segments of electrical system so as to carry out further analysis to
determine the consumption and loss of energy therein over a specified time period;
[(m) ‘Instrument Transformer’ means the ‘Current Transformer’ (CT) or ‘Current
Transformer’ (CT) and ‘Capacitor Voltage Transformer’ (CVT) or ‘Current
Transformer’ (CT) and ‘Inductive Voltage Transformer’ (IVT);]7
[(n) ‘Interface Meter’ means a meter used for accounting and billing of electricity,
connected at the point of interconnection between electrical systems of generating
company, licensee and consumers, directly connected to the Inter-State Transmission
System or Intra-State Transmission System or Distribution System and who have been
permitted open access by the Appropriate Commission;]8
(o) ‘Main Meter’ means a meter, which would primarily be used for accounting and billing
of electricity;
Page 02 of 510
[(p) ‘Meter’ means a device suitable for measuring, indicating and recording the
conveyance of electricity or any other quantity related with electrical system and shall
include, wherever applicable, other equipment such as Instrument Transformer
necessary for the purpose of measurement and also mean ‘Correct Meter’, if it
complies with the standards as specified in the Schedule to these regulations;]9
(q) ‘Power Factor’ means the cosine of the electrical angle between the voltage and current
vectors in an AC electrical circuit;
(r) [ ]10
(s) ‘Reactive Energy’ means, the integral of Reactive Power with respect to time and
measured in the units of ‘Volt-Ampere hours reactive (VARh) or in standard multiples
thereof;
(t) ‘Reactive Power’ means the product of root mean square (rms) voltage, root mean
square (rms) current and the sine of the electrical phase angle between the voltage
complex or and current complex or, measured in ‘Volt – ampere reactive’ (VAr) and in
standard multiples thereof;
(ta) ‘Smart Meter’ means a meter as specified in IS 16444 and as amended from time to
time;]11
(u) ‘Standards’ means ‘Standards on Installation and Operation of Meters’ given in the
Schedule of these Regulations unless otherwise any other standard specifically
referred;
[(v) ‘Standby Meter’ means a meter connected to Instrument Transformer, other than those
used for main meter and check meter and shall be used for accounting and billing of
electricity in case of failure of both main meter and check meter;]12
(w) ‘Supplier’ means any generating company or licensee from whose system electricity
flows into the system of another generating company or licensee or consumer;
(x) [ ]13
[(y) ]14
(2) The words and expressions used and not defined in these Regulations but defined in the
Act shall have the meaning assigned to them in the Act.
3. Applicability of regulations. -
(1) These Regulations shall be applicable to meters installed and to be installed by all the
generating companies and licensees who are engaged in the business of generation,
9 Substituted vide Amendment, 2019 w.e.f. 23.12.2019.
10 Omitted vide Amendment, 2019 w.e.f. 23.12.2019.
11 Inserted vide Amendment, 2019 w.e.f. 23.12.2019.
12 Substituted vide Amendment, 2019 w.e.f. 23.12.2019.
13 Omitted vide Amendment, 2019 w.e.f. 23.12.2019.
14 Initially Inserted vide Amendment, 2014 w.e.f. 26.11.2014 and later Omitted vide Amendment, 2019 w.e.f. 23.12.2019.
Page 03 of 510
transmission, trading, distribution, supply of electricity and to all categories of
consumers.
(2) After coming into force of these regulations, the provisions of the Indian Electricity
Rules, 1956 relating to installation and operation of meters in this regard shall not be
applicable.
(3) These regulations provide for type, standards, ownership, location, accuracy class,
installation, operation, testing and maintenance, access, sealing, safety, meter reading
and recording, meter failure or discrepancies, anti tampering features, quality
assurance, calibration and periodical testing of meters, additional meters and adoption
of new technologies in respect of following meters for correct accounting, billing and
audit of electricity:
(i) Interface meter
(ii) Consumer meter
(iii) Energy accounting and audit Meter
4. Type of meters. -
(1) [(a) all new Interface Meters and Energy Accounting and Audit Meters shall be of
static type and shall have automatic remote meter reading facility;
(b) [All consumers in areas with communication network, shall be supplied electricity
with Smart Meters working in prepayment mode, conforming to relevant IS, within the
timelines as specified by the Central Government:
Provided that all consumer connections having current carrying capacity beyond
that specified in relevant IS, shall be provided with meters having automatic remote
meter reading facility or Smart Meters as per relevant IS.
Provided further that in areas which do not have communication network,
installation of prepayment meters, conforming to relevant IS, shall be allowed by the
respective State Electricity Regulatory Commission.]15]16
(2) The meters not complying with these regulations shall be replaced by the licensee on
his own or on request of the consumer. The meters may also be replaced as per the
regulations or directions of the Appropriate Commission or pursuant to the reforms
programme of the Appropriate Government.
5. Standards. -
All interface meters, consumer meters and energy accounting and audit meters shall –
(a) [comply with the relevant standards of Bureau of Indian Standards (BIS). If BIS
Page 04 of 510
Standards are not available for a particular equipment or material, the relevant
International Electro-technical Commission (IEC) Standards, or any other equivalent
Standard shall be followed:
Page 05 of 510
(b) [If any consumer opts to purchase a meter, the same may be purchased by him as per
the technical specifications laid down by the licensee in compliance with these
regulations and meter purchased by the consumer shall be tested, installed and sealed by
the licensee:
Provided that the consumer shall claim the meter purchased by him as his asset
only after it is permanently removed from the system of the licensee.]19
(c) All consumer meters shall bear BIS mark, meet the requirements of these regulations
and have additional features as approved by the Appropriate Commission or pursuant
to the reforms programme of the Appropriate Government. To facilitate this, the
licensee shall provide a list of makes and models of the meters.
(3) Energy accounting and audit meters
Energy accounting and audit meters shall be owned by the generating company or licensee,
as the case may be.
[7. Locations of meters.- (1) Interface meter.- (a) The location of interface meters shall be
as specified in Table -1
Provided that the location of main, check and standby meters installed at the existing
generating stations shall not be changed unless permitted by the Authority:
Provided further that the generating companies or licensees may install meters at
additional locations in their systems depending upon the requirement
[[Table -1
Page 06 of 510
ownership or or different
both ownership or
both
2. Transmission and (i) At one end (i) There shall be
Distribution of the no separate
System line between the standby meter.
substations - (ii)Meter installed
of the same at other end of the
licensee; line in case of two
(ii) At both ends different licensees
of the line shall work as
between standby meter.
substations of two
different
licensees:
Provided that
meters at both
ends shall be
considered as
main meters for
respective
licensees.
3. Inter-Connecting High Voltage - Low Voltage
Transformer (HV) side of ICT. (LV) side of ICT.
(ICT)
4. Consumer
directly
connected to the
Inter- State
Transmissi As decided by the Appropriate Commission.”.
on System or
Intra-State
Transmission
System or
Distribution
Page 07 of 510
System who has
been permitted
open access by
the Appropriate
commission
or
any other system
not covered
above
]20
(b) The scheme for location of interface meters shall be submitted to the Central
Transmission Utility or the State Transmission Utility or the licensee by owner of the
meter in advance, before the installation of the scheme.
2. Consumer meter.- (a) The consumer meter shall be installed by the licensee either at
the consumer premises or outside the consumer premises:
Provided that where the licensee installs the consumer meter outside the premises of
the consumer then the licensee on a request from consumer shall provide [in home display
unit]21 at the premises of the consumer for his information to indicate the electricity
consumed by the consumer:
Provided further that for the purpose of billing, the reading of consumer meter shall
be taken into account.
(b) [The location of meter and height of meter display from the floor shall be as specified
in IS 15707 and as amended from time to time.]22
(c) [For outdoor installations, the meters shall be protected by appropriate enclosure of
level of protection as specified in the IS 15707 and as amended from time to time.]23
[(d) ]24
3. Energy accounting and audit meter.- The Energy accounting and audit meters shall
be installed at following locations to facilitate the accounting of the energy generated,
transmitted, distributed and consumed in various segments of the power system and the
energy loss, namely:-
(i) Generating Stations.- (a) at a point after the generator stator terminals and before
the tap-off to the unit auxiliary transformer(s),
Page 08 of 510
[Provided that in case of Renewable energy generating station, the meter shall
be installed at the inverter Alternating Current (AC) output terminals.]25
(b) on each incoming feeder of 3.3 kV and above.
(c) low voltage side of each incoming transformer feeder of low voltage (415 V)
buses, and
(d) on all high tension motor feeders.
Provided that in case, numerical relays having built-in feature of energy
measurement of requisite accuracy are provided in high voltage or low voltage
switchgear, separate energy meter is not necessary.
(ii) Transmission system.- all incoming and outgoing feeders (if the interface meters
do not exist)
(iii) [Distribution system.-
(a) all incoming feeders (3.3 kV and above);
(b) all outgoing feeders (3.3 kV and above);
(c) sub-station transformer including distribution transformer – Licensee may
provide the meter on primary or secondary side or both sides depending upon
the requirement for energy accounting and audit:
Provided that all feeders and distribution transformers shall be provided
with meters having automatic remote meter reading facility or Smart Meters as
per relevant IS, as per the timelines specified by the Central Government:
Provided further that distribution transformer level energy accounting
data shall be uploaded by the distribution licensees on quarterly basis on
National Power Portal as per the format prescribed in Bureau of Energy
Efficiency (Manner and Intervals for Conduct of Energy Audit in electricity
distribution companies) Regulations, 2021.]26]27
8. Accuracy Class of meters. -
Every meter shall meet the requirement of accuracy class as specified in the standards
given in the Schedule.
9. Installation of meters. -
(1) Generating company or licensee, as the case may be, shall examine, test and regulate
all meters before installation and only correct meters shall be installed.
(2) The meter shall be installed at locations, which are easily accessible for installation,
testing, commissioning, reading, recording and maintenance. The place of installation
Page 09 of 510
of meter shall be such that minimum inconvenience and disruptions are caused to the
site owners and the concerned organizations.
(3) [In case of single phase meters, the consumer shall ensure that there is no common
neutral or phase or looping of neutral or phase of two or more consumers on
consumers’ side wiring:
Provided that, if such common neutral or phase or looping of neutral or phase
comes to the notice of licensee, it shall suitably inform the consumer through
installation report or regular electricity bills or meter test report or SMS as applicable,
as soon as it comes to it’s notice and the same shall be rectified by the consumer within
15 days from such notice by the licensee.]28
(4) Consumer shall install the Earth Leakage Protective Device (ELPD) in accordance with
the provisions of the rules or regulations in this regard.
(5) [If the earth leakage indication is displayed in the meter, the licensee shall suitably
inform the consumer through installation report or regular electricity bills or meter test
report or SMS as applicable, as soon as it comes to it’s notice and the same shall be
rectified by the consumer within 15 days from such notice by the licensee.]29
(6) [In case Instrument Transformer form part of the meters, the meter shall be installed as
near as possible to the Instrument Transformer to reduce the potential drop in the
secondary leads.]30
10. Operation, Testing and Maintenance of meters. -
The operation, testing and maintenance of all types of meters shall be carried out by the
generating company or the licensee, as the case may be.
11. Access to meter. -
The owner of the premises where, the meter is installed shall provide access to the
authorized representative(s) of the licensee for installation, testing, commissioning, reading
and recording and maintenance of meters.
12. Sealing of meters. -
(1) Sealing Arrangements
(a) All meters shall be sealed by the manufacturer at its works. In addition to the seal
provided by the manufacturer at its works, the sealing of all meters shall be done
as follows at various sealing points as per the standards given in the Schedule:
(i) Sealing of interface meters, shall also be done by both the supplier and the
buyer.
Page 10 of 510
(ii) Sealing of consumer meters shall be done by the licensee.
(iii) Sealing of energy accounting and audit meters shall be done by the licensee
or generating company as the case may be.
(b) [A tracking and recording mechanism for all seals shall be maintained by the
licensee so as to track total movement of seals starting from procurement (with
manufacturer’s details), storage, record keeping, installation, series of inspections
and removal.]31
(c) Seal shall be unique for each utility and name or logo of the utility shall be clearly
visible on the seals.
(d) Only the patented seals (seal from the manufacturer who has official right to
manufacture the seal) shall be used.
(e) Polycarbonate or acrylic seals or plastic seals or holographic seals or any other
superior seal shall be used.
(f) Lead seals shall not be used in the new meters. Old lead seals shall be replaced by
new seals in a phased manner and the time frame of the same shall be submitted by
the licensee to the Appropriate Commission for approval.
(2) Removal of seals from meters
(a) Interface meters
Whenever seals of the interface meters have to be removed for any reason, advance
notice shall be given to other party for witnessing the removal of seals and resealing of
the interface meter. The breaking and re-sealing of the meters shall be recorded by the
party, who carried out the work, in the meter register, mentioning the date of removal
and resealing, serial numbers of the broken and new seals and the reason for removal of
seals.
(b) Consumer meters
Seal of the consumer meter shall be removed only by the licensee. No consumer shall
tamper with, break or remove the seal under any circumstances. Any tampering,
breaking or removing the seal from the meter shall be dealt with as per relevant
provisions of the Act.
(c) Energy accounting and audit meters
Seal of the energy accounting and audit meter shall be removed only by the generating
company or the licensee who owns the meter.
13. Safety of meters. -
(1) The supplier or buyer in whose premises the interface meters are installed shall be
Page 11 of 510
responsible for their safety.
(2) The consumer shall, as far as circumstances permit, take precautions for the safety of
the consumer meter installed in his premises belonging to the licensee.
(3) Licensee shall be responsible for the safety of the [Consumer Meter]32 located outside
the premises of the consumer and the consumer shall be responsible for the safety of the
[in home display]33 unit installed by the licensee in consumer premises.
(4) The generating company or the licensee who owns the energy accounting and audit
meters shall be responsible for its safety.
14. Meter reading and recording. –
(1) [Interface Meters:
(a) It shall be the responsibility of the Generating Company or the licensee, in whose
premises the meter has been installed, to download the meter data, record the
metered data and furnish such data to various agencies as per the procedure laid
down by the Appropriate Commission:
Provided that the responsibility of maintaining database of all the information
associated with the Interface Meters and verifying the correctness of the metered
data shall be in accordance with the procedure laid down by the Appropriate
Commission.
(b) The metered data shall be communicated to the respective Load Despatch Centre
by using a secured and dedicated communication system.
(2) Consumer Meters:
(a) It shall be the responsibility of the licensee to download the Meter data either
locally or remotely, record the metered data, maintain database of all the
information associated with the Consumer Meters and verify the correctness of the
metered data:
Provided that the Appropriate Regulatory Commission shall specify suitable
time frame for ensuring electronic meter reading of all consumer meters by the
licensees.
(b) The licensee shall maintain accounts for the electricity consumption and other
electrical quantities of its consumers:
Provided that the licensee shall provide information to the consumer related
to his energy consumption through Mobile App or Web application or in home
display or any other suitable means.
(c) Brief history, date of installation and details of testing, calibration and replacement
Page 12 of 510
of meters shall be maintained by the licensee.
(3) Energy Accounting and Audit Meters.-
(a) It shall be the responsibility of the generating company or licensee to download
the meter data locally or remotely, record the metered data, maintain database of
all the information associated with the energy accounting and audit meters and
verify the correctness of the metered data.
(b) Each generating company or licensee shall prepare quarterly, half-yearly and
yearly energy account for its system for taking appropriate action for efficient
operation and system development.]34
15. Meter failure or discrepancies. -
(1) Interface meters
(a) [Whenever difference between the readings of the Main Meter and the Check
Meter for any month is more than 0.5%, the following steps shall be taken:
(i) checking of Instrument Transformers connections;
(ii) testing of accuracy of Interface Meter at site with a reference standard meter
of accuracy class higher than the meter under test;
(iii) based on the test results as specified in items (i) and (ii), corrective action
shall be taken to replace the defective meter.
(b) In case of conspicuous failures like burning of meter and erratic display of
metered parameters and when the error found in testing of meter is beyond the
permissible limit of error provided in the relevant standard, the meter shall be
replaced immediately:
Provided that whenever an Interface Meter is replaced, it shall be ensured that
Interface Meter at the other end, if any, of the transmission or distribution system,
shall have same accuracy class.]35
(c) In case where both the Main meter and Check meter fail, at least one of the meters
shall be immediately replaced by a correct meter.
(d) Billing for the Failure period:
(i) The billing for the failure period of the meter shall be done as per the procedure
laid down by the Appropriate Commission.
(ii) Readings recorded by Main, Check and Standby meters for every time slot
shall be analysed, crosschecked and validated by the Appropriate Load
Despatch Centre (LDC). The discrepancies, if any, noticed in the readings shall
be informed by the LDC in writing to the energy accounting agency for proper
Page 13 of 510
accounting of energy. LDC shall also intimate the discrepancies to the
Appropriate Transmission Utility or the licensee, who shall take further
necessary action regarding testing, calibration or replacement of the faulty
meters in accordance with the provisions laid down.
(e) The defective meter shall be immediately tested and calibrated
(2) Consumer meters
In case the consumer reports to the licensee about consumer meter readings not
commensurate with his consumption of electricity, stoppage of meter, damage to the
seal, burning or damage of the meter, the licensee shall take necessary steps as per the
procedures given in the Electricity Supply Code of the Appropriate Commission read
with the notified conditions of supply of electricity.
(3) Energy accounting and audit meters
Energy accounting and audit meters shall be rectified or replaced by the generating
company or licensee immediately after notice of any of the following abnormalities:
(a) the errors in the meter readings are outside the limits prescribed for the specified
Accuracy Class;
(b) meter readings are not in accordance with the normal pattern of the load demand;
(c) meter tampering, or erratic display or damage.
[(d) readings not in conformity with the readings of Interface Meters.]36
16. Anti-tampering features of meters. -
The meters shall be provided with such anti-tampering features as per the
Standards on Installation and Operation of Meters given in the Schedule.
17. Quality assurance of meters. -
(1) The distribution licensee shall put in place a system of quality assurance and testing of
meters with the approval of Appropriate Commission.
(2) [(a) The licensee shall set up accredited testing laboratories or utilise the services of
other accredited testing laboratories.
(b) The licensee shall take immediate action to get the accreditations for their existing
meter testing laboratories from NABL, if not already done.
(3) The generating company or licensee shall ensure that all type, routine and acceptance
tests are carried out by the manufacturer complying with the requirement of the
relevant Indian Standards.]37
18. Calibration and periodical testing of meters. –
Page 14 of 510
(1) Interface meter
(a) At the time of commissioning, each interface meter shall be tested by the owner at site
for accuracy using standard reference meter of better accuracy class than the meter
under test.
(b) [All Interface Meters shall be tested on-site using accredited test laboratory for routine
accuracy testing at least once in five years and recalibrated if required.
Provided that these meters shall also be tested whenever the energy and other
quantities recorded by the meter are abnormal or inconsistent with electrically adjacent
meters.
(c) Testing and calibration of Interface Meters shall be carried out in the presence of the
representatives of the supplier and buyer by giving the advance notice to the other party
regarding the date of testing.]38
(2) [Consumer Meters:
The testing of Consumer Meters shall be done at site through accredited test laboratory at
least once in five years and recalibrated, if required:
Provided that the licensee instead of testing the meter at site can remove the meter
and replace the same by a meter duly tested in an accredited test laboratory:
Provided further that meter shall be tested if the consumption pattern changes
drastically from the similar months or seasons of the previous years or if there is consumer’s
complaint pertaining to a meter:
Provided also that the meter used for testing shall be of better accuracy class than the
meter under test.
(3) Energy Accounting and Audit Meters:
Energy Accounting and Audit Meters shall be tested at site through accredited test
laboratory at least once in five years or whenever the accuracy is suspected or whenever the
readings are inconsistent with the readings of other meters, e.g., Check Meters, Standby
Meters and defective meters shall be recalibrated, if required:
Provided that the testing shall be carried out without removing the Instrument
Transformers connection.]39
19. Additional meters. -
In addition to any meter which may be placed for recording the electricity consumed by the
consumer, the licensee may connect additional meters, maximum demand indicator or other
apparatus as he may think fit for the purposes of ascertaining or regulating either the
Page 15 of 510
quantity of electricity supplied to the consumer, or the number of hours during which the
supply is given, or the rate per unit of time at which energy is supplied to the consumer, or
any other quantity or time connected with the supply to consumer:
Provided that the meter, indicator or apparatus shall not, in the absence of an agreement
to the contrary, be placed otherwise than between the distributing mains of the licensee and
any meter:
Provided further that, where the charges for the supply of energy depend wholly or
partly upon the reading or indication of any such meter, indicator or apparatus as aforesaid,
the licensee shall, in the absence of an agreement to the contrary, keep the meter, indicator
or apparatus correct.
20. [ ]40
[21. Cyber Security. –
Generating Company and licensee shall comply with cyber security guidelines issued by the
Central Government, from time to time, and the technical standards for communication
system in Power Sector laid down by the Authority.
22. Relaxation of Regulations. -
The Authority, by order in writing and the reasons to be recorded, may relax any provision
of these regulations in respect of any matters referred to the Authority on case to case
basis.]41
Page 16 of 510
SCHEDULE
(see regulations 2,5,8,12 and 16)
Standards on Installation and Operation of Meters Part I Standards Common
To All Type of Meters
(1) [These standards provide for specification of meters, immunity to external factors,
sealing points and functional requirements that are required from regulatory perspective:
Provided that, detailed technical specifications shall be prepared by the Generating
Company or licensee, as the case may be.]42
[(2) Specifications of meters
1 Standard Reference Voltage, As per relevant Indian Standards (IS).
. Voltage Range, Standard
Frequency, Starting Current
and Maximum Current,
Power Factor Range, Power
Frequency withstand voltage,
Impulse voltage withstand
test for 1.2/50 micro
sec, Power
Consumption
2 Standard Basic Current As per relevant IS. Current range of
. consumer meters shall be so chosen as to
record the load current corresponding to
the sanctioned load.
3 Accuracy class Meters shall meet the following
. requirements of Accuracy
Class:
(a) Interface 0.2S
Meters
(b) Consumer Meters
(i) Upto 650 1.0
Volts Direct
Connected
Page 17 of 510
(ii) Upto 650 Class 0.5S as per
volts CT relevant IS
Connected where separate
CTs are used
Or
Class 1.0 as per
relevant IS for
terminal less
direct connected
long current
range meters.
(iii) Above 650 0.5S
volts and
up to 33 kilo volts
(iv) Above 33 kilo 0.2S
volts
(c) Energy Accounting and Audit Meters
(i) In generating stations, the accuracy
class of meter(s) at a point after the
generator stator terminals, before the tap
off to the unit auxiliary transformer(s) and
at the inverter AC output terminals in case
of Renewable Energy generating station,
shall not be inferior to that of 0.2S
accuracy class:
Provided that, the accuracy class of
other meters shall not be inferior to that of
1.0S accuracy class.
(ii) The accuracy class of meters in
transmission system shall not be inferior to
that of 0.2S accuracy class.
(iii) The accuracy class of meters in
distribution system shall not be inferior to
that of 0.5S accuracy class where separate
CTs are used with meter:
Page 18 of 510
Provided that in case of terminal less
direct connected long current range meters
accuracy class shall not be inferior to class
1.0.
(iv) The accuracy class of Energy
accounting and Audit Meters for
renewable energy generating station
located
at consumer premises shall be same as that
of consumer meter.
4 Ambient Temperature and Temperature range:
. Humidity (in case an Limit range of operation: -10 °C to +70
International Standard or an °C
IEC Standard is followed) Limit range for storage and transport: -10
°C to +70 °C Relative Humidity: up to
100%
Note: (1) For Special applications other
temperature values can be used according
to agreement between manufacturer and
purchaser.
(2) Operation, storage and transport of the
meter at the extremes of the temperature
range should be for a maximum period of
six hours.
5 Only fundamental frequency quantities shall be measured and computed while
. measuring Wh and VArh.”;
]43
(3) [Meter shall have one port for downloading facilities of metered data through Common
Meter Reading Instrument (CMRI) and another port/system for remote
communication.] 44
43 Initially substituted vide Amendment, 2010 w.e.f. 04.06.2010 and later Omitted vide Amendment, 2019 w.e.f. 23.12.2019.
44 Substituted vide Amendment, 2019 w.e.f. 23.12.2019.
Page 19 of 510
suspension and harmonics and necessary tests shall be carried out in accordance with
relevant standard.
(6) [(a) The accuracy class of Instrument Transformer shall not be inferior to that of
associated meters.
(b) The Instrument Transformer shall comply with relevant Indian Standards.
(c) The existing Instrument Transformer not complying with these regulations shall be
replaced by new Instrument Transformer, if found defective or non-functional.]46
(7) [ ]47
Page 20 of 510
(iii) cumulative Wh transmittal at each midnight, in eight digits including one decimal;
(iv) cumulative VArh transmittal for voltage high condition, at each midnight, in eight
digits including one decimal;
(v) cumulative VArh transmittal for voltage low condition, at each midnight, in eight
digits including one decimal;
(vi) date and time blocks of failure of VT supply on any phase, as a star(*) mark and
(Z) mark in case of complete voltage failure;
(vii) net VArh transmittal during each successive time block upto two decimal with
plus sign for reactive power sent out from station busbars and minus sign for
reactive power received into the busbars;
(viii) average voltage upto 2 decimal truncation:
Provided that the time block for recording of meter data by the meter shall be 15
minutes or as specified by the Central Commission.]48
(c) [ ]49
(d) [ ]50
(e) [There shall be two reactive energy registers, one for the period when average RMS
voltage is above 103% and the other for the period when the voltage is below 97%
(f) The Wh recording shall have a +ve sign when there is a net Wh export from substation
busbars, and a –ve sign when there is a net Wh import:
Provided that the integrating (cumulative) registers for Wh and VArh shall move
forward when there is Wh or VArh export from substation busbars, and backward when
there is an import.
(g) The meters shall also display (on demand), by turn, the following parameters :
(i) Unique identification number of the meter,
(ii) Date,
(iii) Time,
(iv) Cumulative Wh register reading,
(v) Average frequency of the previous time block,
(vi) Net Wh transmittal in the previous time block, with +/-sign,
(vii) Average percentage voltage,
(viii) Reactive power with +/- sign,
(ix) Voltage-high VArh register reading,
(x) Voltage-low VArh register reading,
Page 21 of 510
(xi) Net VArh transmittal in the previous time block, with +/-sign.
(h) (i) the three line-to-neutral voltages shall be continuously monitored, and in case any of
these falls below 80%, the same shall be suitably indicated and recorded in the meter
memory.
(ii) the meters shall normally operate with the power drawn from the VT secondary
circuits:
Provided that there shall be provision to operate the meters from AC and DC
auxiliary power supply.
(iii) each meter shall have a built-in calendar and clock and shall have facility of
automatic time synchronisation.
(iv) the meters shall be properly sealed and tamper evident with no possibility of any
adjustment at site.]51
(i) [ ]52
(j) [The Main Meter and the Check Meter shall be connected to same core of Instrument
Transformer.]53
[(k) All new meters shall have capability of recording frequency in steps of 0.01 Hz.
(l) All new meters shall be re-configurable at site for change of time block as specified by
the Central Commission.]54
(b) The meter shall register energy even when the return path of the load current is not
terminated back at the meter and in such a case the circuit shall be completed through the
Page 22 of 510
earth. In case of metallic bodies, the earth terminal shall be brought out and provided on
the outside of the case.
(c) The meter shall work correctly irrespective of the phase sequence of supply (only for
poly phase).
(d) In the case of 3 phase, 3 wire meter even if reference Y phase is removed, the meter shall
continue to work. In the case of 3 phase, 4 wire system, the meter shall keep working
even in the presence of any two wires i.e., even in the absence of neutral and any one
phase or any two phases.
(e) In case of whole current meters and LV CT operated meter, the meter shall be capable of
recording energy correctly even if input and output terminals are interchanged.
(f) The registration must occur whether input phase or neutral wires are connected properly
or they are interchanged at the input terminals.
(g) The meter shall be factory calibrated and shall be sealed suitably before dispatch.
(h) The meter shall be capable of recording occurrences of a missing potential (only for VT
operated meters) and its restoration with date and time of first such occurrence and last
restoration along with total number and duration of such occurrences during the above
period for all phases.
(i) [Additional anti-tampering features including logging of tampers such as current circuit
reversal, current circuit short or open and presence of abnormal magnetic field may be
provided as per the regulations or directions of the Appropriate Commission.
NOTE.- Smart Meter is bi-directional and therefore anti tamper feature stipulated at (3)
(e) above shall not be applicable.]56
Page 23 of 510
Central Electricity Authority
NOTIFICATION
New Delhi, the 18th August, 2006
Page 24 of 510
(3) In particular and without prejudice to the generality of the above provisions, the
Secretary shall perform the following duties, namely:-
(a) he shall have custody of the records of proceedings of meetings of the Authority;
(b) he shall receive or cause to receive all correspondence related to the Authority;
(c) he shall prepare or cause to be prepared briefs and summaries of proceedings of
all meetings of the Authority;
(d) he shall assist the Authority in the proceedings relating to the power exercisable
by the Authority;
(e) he shall authenticate the orders and resolutions passed by the Authority;
(f) he shall ensure compliance of the orders and resolution passed by the Authority;
and
(g) he shall collect from the Central or the State Governments or other offices,
companies and firms or any other party as may be directed by the Authority, such
information as may be considered useful for the purpose of efficient discharge
of the functions of the Authority under the Act and place the information before
the Authority.
4. Power to designate officers .-
In the absence of the Secretary, the Chairperson, or in the absence of Chairperson, the
senior most Member present in office may designate such other officer of the Authority,
who may exercise any or all of the functions of the Secretary.
5. Power to review, revoke, etc., orders made or action taken .-
The Authority shall have the power either on an application made by any interested or
affected party or suo motu , to review, revoke, revise, modify, amend, alter or otherwise
change any order made or action taken by the Secretary or any officer of the Authority,
if the Authority considers the same to be appropriate.
CHAPTER II
Meetings
6. Place and time of Meetings .-
All meetings of the Authority shall ordinarily be held at the office of the Authority in
New Delhi or any other place at such time as the Chairperson may direct. The Authority
shall ordinarily meet once in a month.
7. Notice for Ordinary Meetings .-
The Secretary, for every ordinary meeting of the Authority shall send a notice in writing
of at least seven days in advance to all Members, including the Chairperson.
8. Agenda and notes for the meeting .-
The Secretary shall invariably send the agenda for the meeting together with notes,
statements and reports, if any, along with notice of the meeting.
Page 25 of 510
9. Special Meeting .-
(1) The Chairperson may, at his discretion, call for a special meeting either on his own
or on receipt of a requisition in writing from any Member, specifying the subject for
consideration at the said meeting.
(2) In case a special meeting is called by the Chairperson under sub-section (1) above,
the notice period of seven days, stipulated under regulation 7, shall not apply.
10. Presiding of meetings in the absence of Chairperson .-
The Chairperson shall preside over the meetings and the conduct of business of the
Authority. If for any reason the Chairperson is unable to be present at the meeting, any
other Member nominated by the Chairperson in this behalf and in the absence of such
nomination or when there is no Chairperson, any Member present at the meeting shall be
elected by the Members present, to preside over the meeting and perform the duties of
the Chairperson.
11. Effect of Non-receipt of notice of Meeting by a Member .-
The non-receipt of a notice of meeting by any Member shall not invalidate the
proceedings of the meetings or any resolution passed or decision taken at such meetings.
12. Quorum .-
(1) The quorum for the meeting shall be four full-time Members, including the
Chairperson. If the Chairperson is unable to attend the meeting for any reason, the
quorum shall be four full-time Members.
(2) In the absence of a quorum, the meeting of the Authority shall stand adjourned.
(3) In case of adjournment, the Chairperson shall decide the date, time and place of
meeting for transacting the business of the Authority which could not take place due
to adjournment and notice for such meeting shall be sent by the Secretary to all the
Members including the Chairperson, in writing. In such cases, the notice period of
seven days stipulated under regulation 7 shall not apply.
13. Decisions of the Authority .-
All decisions of the Authority shall be taken on the basis of the majority of Members
present and voting and in the event of an equality of votes, the Chairperson or a Member
presiding over the meeting shall have the right to exercise a second or casting vote.
14. Discussion on matters not included in the Agenda .-
Any Member of the Authority may propose for discussion of any matter which is not
included in the agenda, with the permission of the Chairperson, and the decision taken at
the meeting on such item shall be deemed to be a decision of the Authority.
15. Decision of Authority by circulation .-
The Chairperson or any Member with the permission of the Chairperson, may propose
any matter of importance to be circulated for a decision to all the Members of the
Page 26 of 510
Authority and in case the majority of the Members are agreed on a matter, it shall be
construed as a decision of the Authority.
16. Ratification of decisions taken by circulation .-
All matters, on which decision has been taken by circulation by majority of the Members
including the Chairperson, shall be placed in the succeeding meeting of the Authority, for
ratification by the Authority.
CHAPTER III
RECORDING OF MINUTES OF MEETINGS AND COMMUNICATION
17. Recording of Minutes .-
(1) The Secretary or any other person authorised by the Chairperson shall be responsible
for recording the minutes of the meeting which shall contain a fair, concise and correct
summary of the proceedings at the meeting and which shall mention the following,
among other:-
(a) the name and designation of Members and invitees present in the meeting, and
(b) notes of dissent, if any.
(2) The draft minutes shall, as soon as possible after conclusion of the meeting, be sent
to the Chairperson and the Members who have attended the meeting for approval.
(3) The approved minutes shall be communicated to the Chairperson and Members and
only the relevant portion of the minutes shall be communicated to other concerned
officers for implementation.
18. Confirmation of Minutes of Meeting of Authority .-
The minutes of the previous meeting of the Authority shall be placed in its next meeting
for confirmation.
19. Register of Minutes of Meetings of the Authority .-
The Secretary or any person authorised in this behalf shall maintain a register for
recording the minutes of the meetings of the Authority and shall record therein the
minutes of each meeting and shall be responsible for getting the minutes of each meeting
authenticated by the person who presided over the meeting.
20. Minutes in the form of resolutions .-
All the minutes of the decisions taken at the meeting of the Authority shall be recorded
in the form of resolutions in clear and concise manner to facilitate implementation.
21. Compilation of Resolutions .-
The Secretary shall codify and compile subject-wise all resolutions and decisions taken
in the meetings of the Authority and shall, at the end of the calendar year, make it
available to all Members of the Authority.
Page 27 of 510
CHAPTER IV
MISCELLANEOUS
22. Power to relax .-
(i) Nothing in these regulations shall bar the Authority from adopting in conformity with
the provisions of the Act, a procedure, which is at variance with any of the provisions
of these regulations, if the Authority, in view of the special circumstances of a matter
or class of matters and for reasons to be recorded in writing, deems it necessary or
expedient for dealing with such a matter or class of matters.
(ii) Nothing of these regulations shall, expressly or impliedly, bar the Authority to deal
with any matter or exercise any power under sub-section (9) of section 70 the Act for
which no regulations have been framed, and the Authority may deal with such
matters, powers and functions in accordance with the provisions of the Act.
Page 28 of 510
CENTRAL ELECTRICITY AUHORITY
NOTIFICATION
New Delhi, the 21st February, 2007
Now, therefore, in exercise of powers conferred by Section 7 and clause (b) of Section
73 read with Sub-section (2) of Section 177 of Electricity Act, 2003, the Central Electricity Authority
hereby makes the following Regulations for regulating the technical standards for connectivity to the
grid, namely :—
1. Short title and commencement:-
(1) These Regulations may be called the Central Electricity Authority (Technical Standards for
Connectivity to the Grid), Regulations, 2007
(2) These Regulations shall come into force on the date or their publication in the Official
Gazette.
2. Definitions:-
In these regulations, unless the context otherwise requires:-
(1) “Act" means The Electricity Act, 2003 (No. 36 of 2003);
(2) "Appropriate Load Despatch Centre" means the National Load Despatch Centre (NLDC),
Regional Load Despatch Centre (RLDC) or State Load Despatch Centre (SLDC) or Area
Load Despatch Centre as the case may be;
(3) "Area Load Despatch Centre" means the centre as established by the state for load
despatch and control in a particular area of the state;
(4) "Appropriate Transmission Utility” means the Central Transmission Utility or State
Transmission Utility as the case may be;
(5) "Automatic Generation Control" (AGC) means capability to regulate the power output of
selectable units in response to total power plant output, tie-line power flow, and power
system frequency;
(6) “Automatic Voltage Regulator” (AVR) means a continuously acting automatic excitation
control system to regulate a generating unit terminal voltage;
(7) "British Standards” (BS) means those standards and specifications approved by the British
Standards Institution;
(8) "Bulk consumer" means a consumer who avails supply at voltage of 33 kV or above;
(9) "Earth Fault Factor" at a location in a three-phase system means the ratio of 'the highest
root mean square(r.m.s.)phase-to-earth power frequency voltage on a sound phase during a
Page 29 of 510
fault to earth (affecting one or more phases)' to 'the r.m.s. phase-to-earth power frequency
voltage which would be obtained at the selected location without the fault‟;
(10) ["Earthing" means electrical connection between non-energized conducting parts and the
general mass of earth by an earthing device;]1
(11) "Energy Management System” (EMS) means a complete system comprising software for
facilitating operation of a power system, maintaining safety, reliability and economy;
(12) “Event Logging Facilities" means a device provided to record the chronological sequence
of operations of the relays and other equipment;
(13) "Frequency" means the number of alternating cycles per second [expressed in Hertz (Hz)];
(14) "Generating Unit" means an electrical Generator coupled to a prime mover within a Power
Station together with all Plant and Apparatus at that Power Station (up to the Connection
Point) which relates exclusively to the operation of that generator;
[In case of Solar Photo voltaic generating station, each inverter along with
associated modules will be reckoned as a separate generating unit;]2
(15) “IEC Standard " means a standard approved by the International Electrotechnical
Commission;
(16) "Indian Standards" (IS) means standards specified by Bureau of Indian Standards;
[(16A) “installed capacity”,-
(i) in case of coal, lignite, gas engines and hydro stations, means the summation of the
name plate capacities of all the units of the generating station or Maximum
Continuous Rating of the generating station; and
(ii) in case of wind generating stations and generating stations using inverters, means
the summation of the name plate capacities of wind turbines or solar generating
units, as the case may be;]3
(17) ["Interconnection point" means a point on the grid, including a sub-station or a
switchyard, where the interconnection is established between the facility of the requester
and the grid and where electricity injected into -or drawn from the grid can be measured
unambiguously for the requester;]4
[(17A) "Inverter" means a device that changes direct current power into alternating current
power;]5
(18) "Isolator” means a device for achieving isolation of one part of an electrical system from
the rest of the system:
(19) [“Maximum Continuous Rating" (MCR) will carry same meaning as defined in the Central
Electricity Authority (Technical Standards for Construction of Electrical Plants and
Electric Lines) Regulations, 2010;]6
Page 30 of 510
(20) [ ]7
(21) ''Power Factor" means the cosine of the electrical angle between the voltage and current
complexors in an AC electrical circuit;
(22) "Power System Stabilizer" (PSS) means controlling equipment which receives input
signals of speed, frequency and power to control the excitation via the voltage regulator for
damping power oscillations of a synchronous machine;
(23) "Protection System" means the equipment by which abnormal conditions in the grid are
detected and fault clearance, actuating signals or indications are initiated without the
intervention by the operator;
(24) "Reactive Power" means in relation to an AC electrical system, the product of root mean
square (r.m.s.)voltage, root mean square (r.m.s.) current and the sine of the electrical phase
angle between the voltage complexor and current complexor, measured in volt-amperes
reactive (VAr);
(25) [“requester” includes a generating company, captive generating plant, energy storage
system, transmission licensee (other than Central Transmission Utility and State
Transmission Utility), distribution licensee, solar park developer, wind park developer,
wind-solar photo voltaic hybrid system, or bulk consumer seeking connection for its new
or expanded electrical plant to the Grid at voltage level 33 kV and above;]8
(26) "SCADA" means Supervisory Control and Data Acquisition System that acquires data
from remote locations over communication links and processes it at centralised control
location for monitoring, supervision, control as well as decision support;
(27) "Site Common Drawing" means a drawing prepared for a connection site, which depicts
layout of connection site, electrical layout, common protection and control drawings and
common services;
(28) "Site Responsibility Schedule" (SRS) means a Schedule for demarcating the ownership,
responsibility for control, operation and maintenance of the equipment at the
interconnection point;
[(28A) "Standard Protection" means electrical protection functions specified in Central
Electricity Authority (Technical Standards for Construction of Electrical Plants and
Electric Lines) Regulations, 2010;]9
(29) "System Protection Scheme" means a scheme designed to detect abnormal system
conditions and take predetermined, corrective action to preserve system integrity and
provide acceptable system performance;
(30) "Thermal Generating Unit" means a generating unit using fossil fuels such as coal, lignite,
gaseous and liquid fuel;
(31) "Total Harmonic Distortion" (THD) means a measure of distortion of the voltage or
current wave form (which shall ideally be sinusoidal) and is the square root of the sum of
squares of all voltage or current harmonics expressed as a percentage of the magnitude of
Page 31 of 510
the fundamental;
(32) "Transmission System" means a network of transmission lines and sub-stations;
(33) "Under Frequency Relay" means a relay which operates when the system frequency falls
below a preset value;
(34) [“user” includes a generating company, captive generating plant, energy storage system,
transmission licensee (other than the Central Transmission Utility and State Transmission
Utility), distribution licensee, solar park developer, wind park developer, wind-solar photo
voltaic hybrid system, or bulk consumer whose electrical plant is connected to the Grid at
voltage level 33 kV and above;]10
(35) "Voltage Unbalance" means the deviation between highest and lowest line voltage divided
by Average Line Voltage of the three phases,
[(36) “wind farm developer” means a person who has developed or proposes to develop the
wind generating station or wind generating farm comprising more than one wind
generating unit owned by the developer or any other person;’;
(37) “solar park developer” means a person who has developed or proposes to develop the
solar park or solar generating station comprising more than one solar generating unit
owned by the developer or any other person;’;
(38) “wind - solar photo voltaic hybrid system” means a system of electricity generation,
which has combination of wind and solar photo voltaic resources, with or without storage
system;]11
The words and expressions used and not defined in these regulations but defined in the
Act shall have the meanings assigned to them in the Act.
3. Applicability of the Regulations
These regulations shall be applicable to all the users, requesters, Central Transmission
Utility and State Transmission Utility.
4. Objectives
(1) The aim of these regulations is to ensure the safe operation, integrity and reliability of the
grid.
(2) The new connection shall not cause any adverse effect on the grid. The grid shall continue
to perform with specified reliability, security and quality as per the [Central Electricity
Authority (Grid Standards) Regulations, 2010]12. However, these regulations are not to be
relied upon to protect the plant and equipment of the requester or user.
(3) A requester is required to be aware, in advance, of the standards and conditions his system
has to meet for being integrated into the grid.
5. Standards
The equipment shall meet the requirements in accordance with the provisions of Technical
Standards for Connectivity to the Grid as given in the Schedule of these regulations and [Central
10
Substituted vide Second amendment, 2019 w.e.f. 06.02.2019
11
Inserted vide Second amendment, 2019 w.e.f. 06.02.2019
12 Substituted vide First amendment, 2013 w.e.f. 15.10.2013
Page 32 of 510
Electricity Authority (Grid Standards) Regulations, 2010 ] 13 and Grid Code and the State Grid
Code(s) as specified by the appropriate Commission.
6. General Connectivity Conditions
(1) The requester shall be responsible for the planning, design, construction, reliability,
protection and safe operation of its own equipment subject to the regulations for
construction operation and maintenance and connectivity and other statutory
provisions,
(2) The requester and user shall furnish data as required by the Appropriate
Transmission Utility or by the licensee or generating station with whose system the
inner-connection is proposed, for permitting inter connection with the grid,
(3) The requester and user shall provide necessary facilities for voice and data
communication and transfer of on-line operational data, such as voltage, frequency,
line flows, and status of breaker and isolator position and other parameters as
prescribed by the Appropriate Load Despatch Centre.
(4) The requester and user shall cooperate with the Regional Power Committee, and
Appropriate Load Despatch Centres in respect of the matters listed below, but not
limited to :—
(a) protection coordination and settings of its protective relays accordingly;
(b) agree to maintain meters and communication system in its jurisdiction in
good condition;
(c) participate in contingency operations such as load shedding, increasing or
reducing generation, islanding, black start, providing start-up power and
restoration as per the procedure decided by the Appropriate Load Despatch
Centre;
(d) furnish data as required by Appropriate Transmission Utility or Transmission
Licensee, Appropriate Load Despatch Centre, Appropriate Regional Power
Committee, and any committee constituted by the Authority at appropriate
Government for system studies or for facilitating analysis of tripping or
disturbance in power system;
(e) carryout modifications in his equipment with respect to short circuit level,
protection coordination and other technical reasons considered necessary due
to operational requirements;
(f) abide by the coordinated outage plan of the state and region in respect of
generating units and transmission lines as approved by the Regional Power
Committee; and
(g) cooperate with the Regional Power Committee for tuning of Power System
Stabilizer provided in the excitation system of the generating unit.
(5) The requester and user shall make arrangements for integration of the controls and
tele-metering features of his system into the Automatic Generation Control,
Page 33 of 510
Automatic Load Shedding, Special Protection System, Energy Management
Systems and Supervisory Control and Data Acquisition System of the respective
state or region.
(6) For inter-connection studies the requester shall make a request for connection in the
planning stage to the Appropriate Transmission Utility. In case a requester is
seeking inter-connection to a distribution system such a request will be made to the
distribution licensee. The Appropriate Transmission Utility or distribution licensee
shall carry out the inter-connection study to determine the point of inter-connection,
required inter-connection facilities and modifications required on the existing grids,
if any, to accommodate the interconnection. The study may also address the
transmission system capability, transient stability, voltage stability, losses, voltage
regulation, harmonics, voltage flicker, electromagnetic transients, machine
dynamics, ferro resonance, metering requirements, protective relaying, sub-station
grounding and fault duties, as the case may be.
[Provided that in order to carry out the said study, the requester shall present the
mathematical model of the equipment in accordance with the requirements as
stipulated by the Appropriate Transmission Utility or distribution licensee, as the
case may be.]14
(7) (1) Every connection of a requester's system to the grid shall be covered by a
connection agreement between the requester and
(a) Appropriate Transmission Utility in case of connection to Inter-state
transmission system or intra state transmission system as the case may be,
(b) Distribution licensee in case of inter-connection to distribution licensee's
system; and
(c) Transmission licensee and Appropriate Transmission Utility, in case of
inter-connection to a transmission licensee (Tri-partite agreement).
(2) The connection agreement shall contain general and specific technical
conditions, applicable to that connection.
[(8) The State Transmission Utility shall inform the Central Transmission Utility and the
Authority, within thirty days of acceptance of application for connectivity of a
generating station to electricity system operating at 110 kV and above.] 15
7. Site Responsibility Schedule
(1) A Site Responsibility Schedule (SRS) for every connection point shall be prepared
by the [generating company or licensee operating the electricity system to which]16
connection is taking place.
(2) Following information shall be included in the Site Responsibility Schedule,
namely,—
(a) Schedule of electrical apparatus services and supplies;
Page 34 of 510
(b) Schedule of telecommunications and measurement apparatus; and
(c) Safety rules applicable to each plant and apparatus.
(3) Following information shall also be furnished in the Site Responsibility Schedule
for each item of equipment installed at the connection site, namely :—
(a) the ownership of equipment;
(b) the responsibility for control of equipment;
(c) the responsibility for maintenance of equipment;
(d) the responsibility for operation of equipment;
(e) the manager of the site;
(f) the responsibility for all matters relating to safety of persons at site; and
(g) the responsibility for all matters relating to safety of equipment at site.
8. Access at Connection Site
The requester or user, as the case may be owning the electrical plant shall provide
reasonable access and other required facilities to the licensee or Appropriate Transmission Utility or
Appropriate Load Despatch Centre, whose equipment is installed or proposed to be installed at the
Connection Site for installation, operation and maintenance, etc. of the equipment.
9. Site Common Drawings
Site Common Drawings shall be prepared for each connection point by the owner of the
Sub-station where connection is taking place.
[10. Cyber security.-
The requester and the user shall comply with cyber security guidelines issued by the
Central Government, from time to time, and the technical standards for communication system in Power
Sector laid down by the Authority.
11. Registration in the Registry maintained by the Authority.-
The user or the requester, as the case may be, shall get its generating unit or station, of
such capacity and with effect from such date as specified by the Authority, registered and get an
online generated Unique Registration Number from the Authority:
Provided that no generating unit or generating station shall be granted connectivity with
the grid without the unique registration number with effect from the date specified by the Authority.
12. Compliance of regulations.-
(1) The licensee shall ensure that before connectivity to the grid, all the provisions with
regard to the connectivity specified under these regulations are complied with by the
requester.
(2) Before allowing connectivity to the requester, the compliance of the provisions laid
down under sub-regulations (2), (3) and (5) of regulation 6 shall be verified by the
licensee and the verification of compliance of provisions of other regulations shall be
in the form of self-declaration in the proforma of connection agreement which shall be
checked and verified by the concerned licensee on sample basis.
Page 35 of 510
(3) The user may be disconnected from the Grid by the licensee for non-compliance of
any provision of these regulations and any non-compliance of the provisions of these
regulations shall be reported by the licensee or the State Load Dispatch Centre or the
Regional Load Dispatch Centre, as the case may be, to the appropriate
Commission.]17
SCHEDULE
(See Regulation No. 5)
Standards for Connectivity to the Grid
Part I General
Page 36 of 510
ground wells may be used to reduce the ground grid resistance to acceptable levels. Sub-station
grounding shall be done in accordance with the norms of the Institute of Electrical and Electronics
Engineers (IEEE)- 80.
4. Metering
Meters shall be provided as specified in the Central Electricity Authority (Installation and
Operation of Meters) Regulations, 2006.
5. Basic Insulation Level and Insulation Co-ordination
(1) Basic Insulation Level (BIL) of various items of equipment and ratings of surge
arresters for generating stations, lines and sub-stations shall be decided on the
following order of priority, namely :—
(a) ensure safety to public and operating personnel;
(b) avoid permanent damage to plant;
(c) prevent failure of costly equipment;
(d) minimise circuit interruptions; and
(e) minimise interruptions of power supply to consumers.
(2) Insulation co-ordination of equipment and lines on both sides of a connection point
belonging to the requester and the grid shall be accomplished and the co-ordination
shall be done by the AppropriateTransmission Utility.
6. Protection System and Co-ordination
(1) Protection system shall be designed to reliably detect faults on various abnormal
conditions and provide an appropriate means and location to isolate the equipment
or system automatically. The protection system must be able to detect power system
faults within the protection zone. The protection system should also detect abnormal
operating conditions such as equipment failures or open phase conditions.
(2) Every element of the power system shall be protected by a standard protection
system having the required reliability, selectivity, speed, discrimination and
sensitivity. Where failure of a protective relay in the requester’s system has
substantial impact on the grid, it shall connect an additional protection as back up
protection besides the main protection.
(3) Notwithstanding the protection systems provided in the grid, the requester and user
shall provide requisite protections for safeguarding his system from the faults
originating in the Grid.
(4) Bus Bar Protection and Breaker Fail Protection or LocaI Breaker Back Up
Protection shall be provided wherever stipulated in the regulations.
(5) Special Protection Scheme such as under frequency relay for load shedding, voltage
instability, angular instability, generation backing down or Islanding Schemes may
also be required to be provided to avert system disturbances.
(6) Protection co-ordination issues shall be finalized by the Regional Power
Committee.
Page 37 of 510
(7) The requester and user shall develop protection manuals conforming to various
standards for the reference and use of its personnel.
7. Disturbance Recording and Event Logging Facilities
Every generating station and sub-station connected to the grid at 220 kV or above shall be
provided with disturbance recording and event logging facilities. All such equipment shall be
provided with time synchronization facility for global common time reference.
8. Schematic Diagrams
The requester and user shall prepare single line schematic diagrams in respect of its system
facility and make the same available to the Appropriate Transmission Utility or licensee through
which his system is connected and the Appropriate Load Despatch Centre.
9. Inspection, Test, Calibration and Maintenance prior to connection
Before connecting, the requester shall complete all inspections and tests finalised in
consultation with the Appropriate Transmission Utility or licensee or generating station to which his
equipment is connected. The requester shall make available all drawings, specifications and test
records of the project equipment pertaining to integrated operation to the Appropriate Transmission
Utility or licensee or generating station as the case may be.
[Part II
Connectivity Standard applicable to the generating stations
A. Connectivity Standards applicable to the Generating Stations other than wind
and generating stations using inverters
These generating stations shall comply with the following requirements besides the
general connectivity conditions given in the said regulations and Part I of the schedule:-
A1. For Generating stations which are connected on or after the date on which Central
Electricity Authority (Technical Standards for Connectivity of the Grid) Regulation, 2007
became effective
(1) The excitation system for every generating unit:--
(a) shall have state of the art excitation system;
(b) shall; have Automatic Voltage Regulator (AVR). Generators of 100 MW
rating and above shall have Automatic Voltage Regulator with digital control
and two separate channels having independent inputs and automatic
changeover;
and
(c) The Automatic Voltage Regulator of generator of 100 MW and above shall
include Power System Stabilizer (PSS).
(2) The Short-Circuit Ratio (SCR) for generators shall be as per IEC-34.
(3) The generator transformer windings shall have delta connection on low voltage side
and star connection on high voltage side. Star point of high voltage side shall be
effectively (solidly) earthed so as to achieve the Earth Fault Factor of 1.4 or less.
Page 38 of 510
(4) All generating machines irrespective of capacity shall have electronically controlled
governing system with appropriate speed/load characteristics to regulate frequency.
The governors of thermal generating units shall have a droop of 3 to 6% and those
of hydro generating units 0 to 10%.
(5) Generating Units located near load centre, shall be capable of operating at rated
output for power factor varying between 0.85 lagging (over-excited) to 0.95 leading
(under-excited) and Generating Units located far from load centres shall be capable
of operating at rated output for power factor varying between 0.9 lagging (over-
excited) to 0.95 leading (under-excited).
Provided that all generating units commissioned on or after 01.01.2014, [Provided
also that all hydro-electric generating units, where Techno-Economic Concurrence
has been accorded by the Authority under section 8 of the Act, shall be capable of
operating at the rated output at the power factor as specified in such techno-
economic concurrence.]18 shall be capable of operating at rated output for power
factor varying between 0.85 lagging (over-excited) to 0.95 leading (under-excited).
Provided further that the above performance shall also be achieved with voltage
variation of± 5% of nominal, frequency variation of+ 3% and -5% and combined
voltage and frequency variation of ±5%. However, for gas turbines, the above
performance shall be achieved for voltage variation of ±5%.
(6) The coal and lignite based thermal generating units shall be capable of generating
up to 105% of Maximum Continuous Rating (subject to maximum load capability
under Valve Wide Open Condition) for short duration to provide the frequency
response.
(7) The hydro generating units shall be capable of generating up to 110% of rated
capacity (subject to rated head being available) on continuous basis.
(8) Every generating unit shall have standard protections to protect the units not only
from faults within the units and within the station, but also from faults in
transmission lines. For generating units having rated capacity greater than 100
MW, two independent sets of protections acting on two independent sets of trip
coils fed from independent Direct Current (DC) supplies shall be provided. The
protections shall include but not be limited to the Local Breaker Back-up (LBB)
protection.
(9) Hydro generating units having rated capacity of 50 MW and above shall be capable
of operation in synchronous condenser mode, wherever feasible.
Provided that hydro generating units commissioned on or after 01.01.2014 and
having rated capacity of 50 MW and above shall be equipped with facility to operate
in synchronous condenser mode, if necessity for the same is established by the
interconnection studies.
(10) Bus bar protection shall be provided at the switchyard of all generating station.
Page 39 of 510
(11) Automatic synchronisation facilities shall be provided in the requester's Project.
(12) The station auxiliary power requirement, including voltage and reactive
requirements, shall not impose operating restrictions on the grid beyond those
specified in the Grid Code or state Grid Code as the case may be.
(13) In case of hydro generating units, self-starting facility may be provided. The hydro
generating station may also have a small diesel generator for meeting the station
auxiliary requirements for black start.
Provided that hydro generating units shall have black start facilities in accordance
with provisions of Central Electricity Authority (Technical Standards for
Construction of Electrical Plants and Electric Lines) Regulations, 2010 from the
date of publication of these Regulations.
(14) The standards in respect of the switchyard associated with the generating stations
shall be in accordance with the provisions specified in respect of 'Sub-stations'
under Part III of these Standards.
A2. Generating stations which were already connected to the grid on the date on which Central
Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007
became effective
For thermal generating units having rated capacity of 200 MW and above and hydro units
having rated capacity of 100 MW and above, the following facilities would be provided at the time of
renovation and modernization.
(1) Every generating unit shall have Automatic Voltage Regulator. Generators having
rated capacity of 100 MW and above shall have Automatic Voltage Regulator with
two separate channels having independent inputs and automatic changeover.
(2) Every generating unit of capacity having rated capacity higher than 100 MW shall
have Power System Stabilizer.
(3) All generating units shall have standard protections to protect the units not only
from faults within the units and within the station but also from faults in
transmission lines. The protections shall include but not limited to the Local
Breaker Back-up (LBB) protection.
B. [Connectivity standards applicable to the wind generating stations, generating stations
using inverters, wind - solar photo voltaic hybrid systems and energy storage systems.
The generating stations shall comply with the following requirements in addition to the
general connectivity conditions specified under Part 1:
Provided that the energy storage systems shall comply, only with the requirements
specified under clause B1 in addition to the general connectivity conditions specified under Part 1.;]19
B1. Requirements with respect to Harmonics, Direct Current (DC) Injection and Flicker
(1) Harmonic current injections from a generating station shall not exceed the limits
specified in Institute of Electrical and Electronics Engineers (IEEE) Standard 519.
(2) The Generating station shall not inject DC current greater than 0.5 % of the full
Page 40 of 510
rated output at the interconnection point.
(3) The generating station shall not introduce flicker beyond the limits specified in IEC
61000.
Provided that the standards for flicker will come into effect from 1st April 2014.
(4) Measurement of harmonic content, DC injection and flicker shall be done at least
once in a year in presence of the parties concerned and the indicative date for the
same shall be mentioned in the connection agreement;
Provided that in addition to annual measurement, if distribution licensee or
transmission licensee or the generating company, as the case may be, desires to
measure harmonic content or DC-injection or flicker, it shall inform the other party
in writing and the measurement shall be carried out within 5 working days.
B2. For generating station getting connected on or after completion of 6 months from date of
publication of these Regulations in the Official Gazette.
(1) The generating station shall be capable of supplying dynamically varying reactive
power support so as to maintain power factor within the limits of 0.95 lagging
to 0.95 leading.
[(2) The generating unit shall be capable of operating in the frequency range 47.5 to 52 Hz
and be able to deliver rated output in the frequency range of 49.5 Hz to 50.5 Hz:
Provided that in the frequency range below 49.90 Hz and above 50.05 Hz, or, as
prescribed by the Central Commission, from time to time, it shall be possible to
activate the control system to regulate the output of the generating unit as per
frequency response requirement as provided in sub-clause (4):
Provided further that the generating unit shall be able to maintain its performance
contained in this subclause even with voltage variation of up to + 5% subject to
availability of commensurate wind speed in case of wind generating stations and
solar insolation in case of solar generating stations.
(3) The generating station connected to the grid, shall remain connected to the grid
when voltage at the interconnection point on any or all phases dips up to the level
depicted by the thick lines in the following curve, namely: —
VT : Actual Voltage; Vn: Nominal Voltage—
Page 41 of 510
Provided that during the voltage dip, the supply of reactive power has first priority,
while the supply of active power has second priority and the active power preferably
be maintained during voltage drops, provided, a reduction in active power within
the plant’s design specifications is acceptable and active power be restored to at
least 90% of the pre-fault level within 1 sec of restoration of voltage.
(4) The generating stations with installed capacity of more than 10 MW connected at
voltage level of 33 kV and above –
(i) shall be equipped with the facility to control active power injection in accordance
with a set point, capable of being revised based on directions of the State Load
Dispatch Centre or Regional Load Dispatch Centre, as the case may be;
(ii) shall have governors or frequency controllers of the units at a droop of 3 to 6% and
a dead band not exceeding ±0.03 Hz:
Provided that for frequency deviations in excess of 0.3 Hz, the Generating Station shall
have the facility to provide an immediate (within 1 second) real power primary
frequency response of at least 10% of the maximum Alternating Current active power
capacity;
(iii) shall have the operating range of the frequency response and regulation system
from 10% to 100% of the maximum Alternating Current active power capacity,
corresponding to solar insolation or wind speed, as the case may be;
(iv) shall be equipped with the facility for controlling the rate of change of power
output at a rate not more than ± 10% per minute.
(5) The generating stations of aggregate capacity of 500 MW and above shall have the
provision to receive the signal from the State Load Dispatch Centre or Regional Load
Dispatch Centre, as the case may be, for varying active and reactive power output.
(6) The standards in respect of the switchyard associated with the generating stations shall
be in accordance with the provisions specified in respect of ‘Sub-stations’ under Part III
of these Standards.
(7) The generating station connected to the grid, shall remain connected to the grid when
voltage at the interconnection point, on any or all phases (symmetrical or asymmetrical
overvoltage conditions) rises above the specified values given below for specified
time—
Over voltage (pu) Minimum time to remain connected (Seconds)
1.30 < V 0 Sec (Instantaneous trip)
1.30 ≥ V > 1.20 0.2 Sec
1.20 ≥ V > 1.10 2 Sec
V ≤ 1.10 Continuous
(8) Short Circuit Ratio at the interconnection point where the generating resource is
proposed to be connected shall not be less than 5.]20
Page 42 of 510
B3. [Special provision for certain Generating stations :
The generating stations commissioned before the commencement of the Central Electricity
Authority (Technical Standards for Connectivity to the Grid) (Amendment) Regulations, 2018 or
commissioned within six months of such commencement shall comply with the provisions of these
regulations as if they were not amended.]21]22
Part III
Grid Connectivity Standards applicable to the Transmission Line and Sub-Station
The transmission lines and sub-stations connected to the grid shall comply with the
following additional requirements besides the general connectivity conditions under these regulations
and General Standards for Connectivity to the Grid as specified in Part I of the Schedule.
(1) Bus bar protection shall be provided on all sub-stations at and above 220 kV levels
for all new sub-stations. For existing sub-stations, this shall be implemented in a
reasonable time frame.
(2) Local Breaker Back-up (LBB) protection shall be provided for all sub-stations of
220kV and above.
(3) Two main numerical Distance Protection Schemes shall be provided on all the
transmission lines of 220 kV and above for all new sub-stations. For existing sub-
stations, this shall be implemented in a reasonable time frame.
(4) Circuit breakers, isolators and all other current carrying equipment shall be capable
of carrying normal and emergency load currents without damage. The equipment
shall not become a limiting factor on the ability of transfer of power on the inter-
state and intra-state transmission system.
(5) All circuit breakers and other fault interrupting devices shall be capable of safely
interrupting fault currents for any fault that they are required to interrupt. The
Circuit Breaker shall have this capability without the use of intentional time delay in
clearing the fault. Minimum fault interrupting requirement need be specified by the
Appropriate Transmission Utility. The Circuit Breaker shall be capable of
performing all other required switching duties such as, but not limited to, capacitive
current switching, load current switching and out-of-step switching. The Circuit
Breaker shall perform all required duties without creating transient over-voltages
that could damage the equipment provided elsewhere in the grid. The short circuit
capacity of the circuit breaker shall be based on short-term and perspective
transmission plans as finalized by the Authority.
(6) Power Supply to Sub-Station Auxiliaries, shall:
(a) for alternating current (AC) supply (Applicable to new sub-stations):
220 kV and above: Two high tension (HT) supplies shall be arranged from
Page 43 of 510
independent sources. One of the two high tension supplies shall be standby to
the other. In addition, an emergency supply from diesel generating (DG)
source of suitable capacity shall also be provided.
66 kV and below 220 kV: There shall be one HT supply and one diesel
generating source.
33 kV and below 66 kV: There shall be one HT supply.
(b) for direct current (DC) Supply (Applicable to new sub-stations): Sub-stations
of transmission system for 132 kV and above and sub-stations of all
generating stations: There shall be two sets of batteries, each equipped with
its own charger.
For sub-stations below 132 kV: there shall be one set of battery and charger.
(7) Earth Fault Factor for an effectively earthed system shall be not more than 1.4.
Part IV
Grid Connectivity Standards applicable to the Distribution Systems and Bulk Consumers
The following additional requirements shall be complied with, besides the connectivity
conditions in these regulations and general Standards for Connectivity to the Grid given in Part-I and
those applicable to transmission lines and sub-stations in Part -III.
1. Under Frequency/df/dt Relays
Under frequency and df/dt (rate of change of frequency with time) relays shall be
employed for automatic load control in a contingency to ensure grid security under conditions of
falling grid frequency in accordance with the decision taken in the Regional Power Committee.
2. [(i) The distribution licensee and bulk consumer shall provide adequate reactive compensation
to compensate reactive power requirement in their system so that they do not depend upon
the grid for reactive power support.
(ii) The power factor for distribution system and bulk consumer shall be within ± 0.95;
3. Voltage and Current Harmonics. –
(i) The limits of voltage harmonics by the distribution licensee in its electricity system, the
limits of injection of current harmonics by bulk consumers, point of harmonic
measurement, i.e., point of common coupling, method of harmonic measurement and
other related matters, shall be in accordance with the IEEE 519-2014 standards, as
amended from time to time;
(ii) Measuring and metering of harmonics shall be a continuous process with meters
complying with provisions of IEC 61000-4-30 Class A.
(iii) The data measured and metered as mentioned in sub-paragraph (ii) with regard to the
harmonics, shall be available with distribution licensee and it shall also be shared with
the consumer periodically.
(iv) The bulk consumer shall install power quality meter and share the recorded data thereof
with the distribution licensee with such periodicity as may be specified by the
appropriate Electricity Regulatory Commission:
Page 44 of 510
Provided that the existing bulk consumer shall comply with this provision
within twelve months from the date of commencement of the Central Electricity
Authority (Technical Standards for Connectivity to the Grid) (Amendment)
Regulations, 2018.
(v) In addition to harmonics, periodic measurement of other power quality parameters such
as voltage sag, swell, flicker, disruptions shall be done as per relevant International
Electrotechnical Commission Standards by the distribution licensee and the reports
thereof shall be shared with the consumer.
(vi) The distribution licensee shall install power quality meters in a phased manner within
three years from the date of commencement of the Central Electricity Authority
(Technical Standards for Connectivity to the Grid) (Amendment) Regulations, 2018
covering at least 33% of the 33 kV substations each year.]23
4. Voltage Unbalance
The Voltage Unbalance at 33 kV and above shall not exceed 3.0%.
5. Voltage Fluctuations
(1) The permissible limit of voltage fluctuation for step changes which may occur
repetitively is 1.5%
(2) For occasional fluctuations other than step changes the maximum permissible limit
is 3%.
(3) The limits prescribed in (1) and (2) above shall come into force not later than five
years from the date of publication of these regulations in the Official Gazette.
6. Back-energization
[The bulk consumer shall not energize transmission or distribution system by injecting
supply from his generators or any other source either by automatic controls or manually unless
specifically provided for in the connection agreement with the Transmission or Distribution
Licensee.]24
Page 45 of 510
CENTRAL ELECTRICITY AUTHORITY
NOTIFICATION
New Delhi, the10th April, 2007
F.No. CEA/PLG/LF/9/40/07. – Whereas the draft of the Central Electricity Authority
(Furnishing of Statistics, Returns and Information) Regulations, 2006 were published, as required
by Sub-section (3) of Section 177 of the Electricity Act, 2003 (36 of 2003), read with rule
3 of the Electricity (Procedure for Previous Publication) Rules, 2005;
Now, therefore, in exercise of the powers conferred by Section177, read with Section 74 and
clause (i) of Section 73 of the Electricity Act, 2003, the Central Electricity Authority hereby
Makes the following regulations, namely:-
1. Short title and commencement - (1) These regulations may be called the Central Electricity
Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007.
(2) These regulations shall come into force on the date of their publication in the official Gazette.
2. Definitions - unless the context otherwise requires, in these regulations,-
(1) “Act” means the Electricity Act, 2003 (36 of 2003);
(2) “Voltage” means the difference of electric potential measured in volts, between any two
conductors or between any part of either conductor and the earth as measured by a suitable
voltmeter and is said to be –
(a) “high voltage” where the voltage exceeds 650 volts but does not exceed 33000 volts
under normal condition; and
(b) “extra high voltage” where the voltage exceeds 33000 volts under normal condition;
(3) [All other words and expressions used and not defined in these regulations but defined in
the Act, Rules made by the Government of India, other Regulations of CEA and Regulations
of CERC assigned to them, shall have the meanings respectively assigned to them in the
Act, Rules and Regulations.]1
3. Applicability of the regulations - These regulations shall be applicable to all the licensees,
generating companies, person(s) generating electricity for its or his own use and person(s)
engaged in generation, transmission, distribution, trading and utilization of electricity.
1Substituted vide addition/ revision of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 25.07.2023.
Page 46 of 510
4. Sources of statistics, returns and information - All licensees, generating companies and
person(s) mentioned below, but not limited to, shall furnish to the Authority such statistics,
returns or other information relating to generation, transmission, distribution, trading and
utilization of electricity at such times and in such form and manner as specified under these
regulations-
(1) Licensees
(i) Transmission Licensees;
(ii) Distribution Licensees;
(iii) Trading Licensees;
(iv) Central Transmission Utility;
(v) State Transmission Utilities;
(vi) Appropriate Governments who are responsible for transmitting, distributing or trading
of electricity;
(vii) Damodar Valley Corporation established under sub-section (1) of section 3 of the
Damodar Valley Corporation Act, 1948 (14 of 1948);
(viii) Any person engaged in the business of transmission or supply of electricity under the
provisions of the repealed laws or any act specified in the Schedule;
(ix) Any person who intends to generate and distribute electricity in a rural area as notified
by the State Government;
(x) State Electricity Boards;
(xi) Local authorities including Cantonment Boards;
(xii) Deemed licensees and entities exempted from licence.
(xiii) Bhakra Beas Management Board.
(2) Generating companies
(i) Generating companies established by appropriate Governments;
(ii) Independent Power Producers;
(iii) Appropriate Governments responsible for generating electricity;
(iv) Bhakra Beas Management Board;
(v) Any person engaged in the business of generating electricity under the provisions of
the repealed laws or any act specified in the Schedule;
(vi) Damodar Valley Corporation.
(3) Person(s) generating electricity for own use:
(i) All captive power producers;
(ii) Any other person including Co-operative Society, Association of persons, body of
Page 47 of 510
individuals, etc. engaged in generating electricity for its or his own use.
(4) Other entities
(i) National Load Despatch Centre;
(ii) Regional Load Despatch Centre(s);
(iii) State Load Despatch Centre(s);
(iv) Regional Power Committee(s);
(v) High voltage or extra high voltage consumers of electricity.
[(vi) Electricity Regulatory Commissions (i.e. CERC, SERCs, JERCs);
(vii) Power Exchanges;
(viii) State Nodal Agency; recognized agency for renewable energy projects.]2
5. Formats for furnishing of statistics, returns or information - The entities shall furnish the
statistics, returns and information as per the formats annexed to these regulations and the list
of format is as per Annexure-I titled “List of formats, frequency (ies) and target date(s)”.
These formats can also be obtained from the website of the Central Electricity Authority.
The formats may be sent by mail or media, to the source (s) of the statistics, returns or
information, as and when required.
6. Time schedule for furnishing of statistics, returns or information -The time schedule or
targets for furnishing of statistics, returns or information shall be as specified by the
Authority on its prescribed formats. A consolidated list of time Schedule format-wise is
given at Annexure-I titled “List of formats, frequency (ies) and target date (s)”.
7. Frequency of submission of statistics, returns or information - The frequency of submission
i.e. daily, weekly, monthly, quarterly or annually shall be as specified by the Authority in
its prescribed formats. A consolidated list of frequency of submission format-wise is given
in Annexure-I titled “List of formats, frequency (ies) and target date(s)”.
8. Manner of furnishing the statistics, returns or information – (1) The statistics, returns or
information in the prescribed formats shall be furnished to the Authority preferably
electronically or by post or courier or fax.
(2) The entities shall supply complete and correct statistics, returns and information to the
Authority.
(3) Any provisional data supplied by the entities shall be finalized and furnished within
the period communicated by the Authority.
9. Addition and deletion in formats, time schedule, periodicity or furnishing method - (1) The
2Added vide addition/ revision of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 25.07.2023.
Page 48 of 510
Authority may revise format(s), time schedule(s), frequency (ies) or manner of furnishing
the data or may add or delete format(s) as and when necessary to carry out its functions
under clause (i) of section 73 of the Electricity Act, 2003.
(2) The Authority shall, before making change(s) in the format(s), time schedule(s), frequency
(ies), data furnishing manner or addition or deletion of format(s) prescribed by the Authority
under regulation 5 shall place a draft of changes in format(s) in the website of the Central
Electricity Authority for the information of persons likely to be affected thereby. A notice
in this regard inviting objections or suggestions shall be published in the widely circulated
daily news papers specifying the date of expiry of the notice period which shall not be less
than thirty days, on or after which the proposed changes will be taken into consideration by
the Authority. The Authority shall consider the objections or suggestions received on or
before the date so specified, from any person in respect of the proposed addition or deletion
or changes in the format (s). After revision (s) / change (s) and completion of above
procedure, the format (s) shall be notified by the Authority.
10. Right of access to records or documents - The Authority or any person authorized by it in
writing on its behalf shall, for the purposes of the collection of any statistics under these
regulations, have access to any relevant record or document in the possession of any person
required to furnish any information or return under these regulations and may enter at any
reasonable time any premises where he believes such record or documents to be available
and may inspect or take copies of relevant records or documents or ask any question
necessary for obtaining any information required to be furnished under these regulations.
11. Restriction on publication of information and returns - (1) No information, no individual
return and no part thereof with respect to any particular industrial or commercial concern,
given for the purposes of these regulations shall, without the previous consent in writing of
the owner for the time being of the industrial or commercial concern in relation to which the
information revealing the commercial and technical confidentiality, be published in such
manner as would enable any particulars to be identified as referring to a particular concern.
(2) Except for the purposes of these regulations, no person who is not engaged in the collection
of statistics under these regulations shall be permitted to see any information or individual
return referred to in sub-section (1).
12. Non-compliance and penalty – (1) If any person, -
(a) required to furnish any information or return-
(i) Willfully refuses or without lawful excuse neglects to furnish such information or
return as may be required under these regulations; or
Page 49 of 510
(ii) Willfully furnishes or causes to be furnished any information or return which he
knows to be false; or
(iii) refuses to answer or willfully gives a false answer to any question necessary for
obtaining any information required to be furnished under these regulations;
OR
(b) impedes the right of access to relevant records or documents or the right of entry
conferred by these regulations,
shall attract the relevant provisions under section 142 and 146 of the Act.
(2) No proceeding for an offence under these regulations shall be initiated except by or with the
approval of the Authority.
Page 50 of 510
ANNEXURE-I
Page 51 of 510
Title of Format Frequency Format Target Date
(By )
of data
furnishing No.
Annual data of HV/EHV industry having electricity Annual 21 30-Jun
demand of 1 MW or above
Daily Operational Data of Thermal Power Stations Daily 22 1030 hrs
and Nuclear Power Stations
Daily Operational Data of Hydro Power Stations Daily 23 1030 hrs
[ ]3
3Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 17.03.2022.
Page 52 of 510
]4
Proposed Coal Allocation for Short Term Linkages Quarterly 41 40 days before
for Thermal Power Stations the
commencement
of the
quarter
Monthly Fuel Supply Data of Gas Based Thermal Monthly 42 15th day
Power Stations
Monthly Fuel Supply Data of Liquid Fuel Based Monthly 43 15th day
Thermal Power Stations
Monthly Fuel Supply Data of DG Power Stations Monthly 44 15th day
]5
[ ]8
[Reliability Indices (SAFI, SAIDI, CAIDI & MAIFI) - Quarterly 53 30th day after the
Consumer Affected/ Load Interrupted basis on the end of quarter
feeder
Reliability Indices (SAIFI, SAIDI, CAIDI & MAIFI) Quarterly 54 30th day after the
for Urban/ Rural areas - Load Affected/ Load end of quarter]9
Interrupted basis on the feeder
[ ]10
4 Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 17.03.2022.
5 Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 17.03.2022.
6 Substituted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 17.03.2022.
7
Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 17.03.2022.
8
Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 17.03.2022.
9
Substituted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 17.03.2022.
10
Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 17.03.2022.
Page 53 of 510
Aggregate Technical & Commercial (A T & C) Annual 56 30th April
Losses for the Financial Year------------
[ ]11
]12
11
Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 17.03.2022.
12
Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 17.03.2022.
Page 54 of 510
(On Delivery date basis)
13Added vide addition/ revision of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 25.07.2023.
Page 55 of 510
Annexure-II
Statement of Specific Applicability of formats
Format Genco Transco Discom Traders/ SEBs/ NLDC/ SLDCs RPCs CPPs/ [CERC/
[Title of format No. PXs Licensees/ ED RLDCs Industries JERC/
/SNAs SERCs
Generation of Electricity 1 Y Y
Transmission of Electricity 2 Y Y
Distribution of Electricity 3 Y Y
Trading of Electricity 4 Y
Details of actual sale and purchase of Gross
Electrical Energy 5 Y Y Y Y
Installed Electricity Generating Capacity 6 Y Y
Details of electricity generating capacity added 7 Y Y
Details of electricity generating sets retired from
service 8 Y Y
Details of derations of electricity generating sets 9 Y Y
Details of fuel consumption 10 Y Y
Details of step-up transformers in service at the
power stations and various sub-stations as on 11 Y Y Y Y
31.03.20..
Details of step-down transformers in service as on
31.03.20.. 12 Y Y Y Y
Details of distribution transformers in service as on
31.03.20.. 13 Y Y Y
Details of transmission and distribution lines as on
31.03.20.. 14 Y Y Y Y
Details of electricity consumers, connected load and
consumption 15 Y Y
Details of manpower 16 Y Y Y Y
Training Facilities/Training Capacity in the Power
Sector (Man-days of year) 17 Y Y Y Y
Details of theft of electricity 18 Y Y
Statistics on electrical accidents 19 Y Y Y Y Y Y
Reasons for electrical accidents 20 Y Y Y Y Y Y
Annual data of HV/EHV industry having electricity
demand of 1 MW or above 21 Y
Daily Operational Data of Thermal Power
22 Y Y Y Y
Stations and Nuclear Power Stations
Page 56 of 510
Format Genco Transco Discom Traders/ SEBs/ NLDC/ SLDCs RPCs CPPs/ CERC/
Title of format No. PXs Licensees/ RLDCs Industries JERC/
ED /SNAs SERCs
Daily Operational Data of Hydro Power
23 Y Y Y Y
Stations
Monthly Operational Data of Thermal Power
Stations and Nuclear Power Stations 24 Y Y Y Y
Monthly Operational Data of Hydro Power
Y Y Y
Stations 25 Y
Data for fixation of annual targets of
electricity generation for year 20---20….. 26 Y Y Y
]15
Proposed Coal Allocation for Short Term
41 Y Y
Linkages for Thermal Power Stations
14
Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f. 17.03.2022.
15
Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f. 17.03.2022. Page 57 of 510
Format Genco Transco Discom Traders/ SEBs/ NLDC/ SLDCs RPCs CPPs/ CERC/
Title of format No. PXs Licensees/ ED / RLDCs Industries JERC/
SNAs SERCs
Monthly Fuel Supply Data of Gas Based Thermal
Power Stations 42 Y Y
Monthly Fuel Supply Data of Liquid Fuel Based
Thermal Power Stations 43 Y Y
Monthly Fuel Supply Data of DG Power Stations 44 Y Y
[
]16
District wise Monthly Progress of Inhabited Village 48 Y Y Y
Electrification
District-Wise Monthly Progress of Energisation of 49 Y Y
Irrigation Pump sets
[ ]17
16
Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f. 17.03.2022.
17
Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f. 17.03.2022.
18
Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f. 17.03.2022.
19
Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f. 17.03.2022.
20
Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f. 17.03.2022. Page 58 of 510
Title of Format Format Genco Transco Discom Traders SEBs / RLDCs SLDCs RPCs CPPs/ CERC/
No. Licensees/Elecy. Industries JERC/
Deptts. SERCs
[
]21
21
Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f. 17.03.2022.
Page 59 of 510
Title of Format Format Genco Transco Discom Traders SEBs / RLDCs SLDCs RPCs CPPs/ CERC/
No. Licensees/Elecy. Industries JERC/
Deptts. SERCs]22
Cross Border Trade Details 76 Y
Details of entities purchasing and selling on 77 Y
Power Exchanges in DAM/TAM/GTAM/
RTM/GDAM markets.
Details of tariff order and truing up order by the Y
Electricity Regulatory Commission 78
Details of Deviation Settlement Mechanism 79 Y
(DSM) volume.
Details of despatch under Reserve Regulations 80 Y
Ancillary Services (RRAS)
Details of Un-Requisitioned Surplus (URS) 81 Y
from the generations being scheduled by the
RLDCs
Monthly Renewable Energy Generation 82 Y Y Y Y Y
Note: If certain items of a format are not applicable to an Entity, then 'Not Applicable' may be marked at appropriate places.
Y= Yes Applicable
22 Added vide addition/ revision of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f. 25.07.2023.
23 Added vide addition/ revision of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f. 25.07.2023.
24 Substituted vide addition/ revision of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f. 25.07.2023.
Page 60 of 510
FORMAT-1
PERIODICITY-ANNUAL
DATA OF YEAR 20……20….
GENERATION OF ELECTRICITY Submission by 30th June
1 Station-1
2 Station-2
*Hydro turbine, Steam turbine (Coal), Steam turbine (Lignite), Steam turbine (Multifuel), Gas
turbine, Diesel engine, Wind turbine, etc.
Page 61 of 510
FORMAT-2
PERIODICITY- ANNUAL
DATA OF YEAR: 20…20….
SUBMISSION-BY 30th JUNE
TRANSMISSION OF ELECTRICITY
Figs. in
MkWh
Name & Address of State Transmission Utility/SEB/ED:
Page 62 of 510
FORMAT-3
PERIODICITY- ANNUAL
DATA OF YEAR : 20…20…
SUBMISSION-BY 30TH JUNE
DISTRIBUTION OF ELECTRICITY
Figs. in MkWh
(c) Any other entity within the State/UT/System-furnish break-up entity wise
Page 63 of 510
FORMAT-4
PERIODICITY- ANNUAL
DATA OF YEAR 20…. 20….
SUBMISSION-BY 30TH JUNE
TRADING OF ELECTRICITY
Figs. in MkWh
Name & Address of the TRADING COMPANY Category of Licence:
Note: Please furnish break-up of each of above for round the clock, off peak, peak and as & when required
trading.
Page 64 of 510
FORMAT-5
Periodicity-Annual
Data of year 20-- 20---
Submission by -30thJune
Figures in MkWh
Name of Utility/Licensee:
Note:- (i) Gross energy sale/purchase may be indicated utility/non-utility name-wise clearly & separately in this table.
(ii) Purchase of energy from captive power plant if any, may also be indicated.
(iii) Details of energy sold to licensees may be indicated Licensee-name wise.
(iv) Wheeling of energy should not be included in the above data.
(v) Energy imported/exported from /to Central Generating Stations may be given separately for each Power House.
Page 65 of 510
FORMAT-6
Periodicity-Annual
Data of year 20--- 20---
Submission by—30th June
INSTALLED ELECTRICITY GENERATING CAPACITY
Figs. in MW
Name and address of the Utility:
1. Hydro Turbine
2. Steam Turbine
Coal -
Lignite –
Gas/ Multifuel
3. Diesel Engine
4. Gas Turbine
5. Nuclear
6. Wind Turbine
7. Solar
8. Others, if any
Page 66 of 510
FORMAT-7
Periodicity-Annual
Data of year 20---- 20---
Submission by -30th June
Note: - The details of each unit are to be furnished in this format. Indicate primary fuel within brackets along with type of prime-mover.
Page 67 of 510
FORMAT-8
Periodicity-Annual
Data of year 20--- 20---
Submission by- 30th June
Sl. Name of the Unit size Type of Date of Date of Reason(s) for
No. Power House in MW Prime mover Commissioning Retirement Retirement
Page 68 of 510
FORMAT-9
Periodicity-Annual
Data of year 20--- 20---
Submission by 30th June
Sl. . Name of the Unit No. Date Type of Rated Derated Date Reason(s)
No. Power House of Prime mover Capacity (I.C) capacity of for
Commissioning (MW) (MW) Deration Deration
Page 69 of 510
FORMAT-10
Periodicity-Annual
Data of year 20--- 20---
Submission by -30th June
DETAILS OF FUEL CONSUMPTION
Note :- - Fuel consumption details regarding Gas/Diesel stations are to be shown separately.
- Give details of all primary & secondary fuels consumed during the year.
- mt = Metric Tonne
- kl = Kilo Litre
- MMSCM = Million Metric Standard Cubic Metre
Page 70 of 510
FORMAT-11
Periodicity-Annual
Data of year 20--- 20---
Submission by -30th June
DETAILS OF STEP-UP TRANSFORMERS IN SERVICE AT THE POWER STATIONS AND VARIOUS SUB-
STATIONS AS ON 31-03-20..
TOTAL
Page 71 of 510
FORMAT-12
Periodicity-Annual
Data of year 20--- 20---
Submission by 30th June
1. 400 kV
2. 220 kV
3. 132/110 kV
4. 78/66 kV
5. 44/33 kV
6. 22 kV
7. 13.2 kV
8. 11 kV
9. 6.6 kV
10. 4.4 kV
11. 3.3 kV
12. Any other (specify)
TOTAL
Page 72 of 510
FORMAT-13
Periodicity-Annual
Data of year 20--- 20---
Submission by -30th June
Sl. . Voltage Class Voltage Ratio Total No. Different capacities No. in each Aggregate
No. of transformers in use (kVA) capacity size capacity (kVA)
Total :
Page 73 of 510
FORMAT-14
Periodicity-Annual
Data of year 20--- 20---
Submission by -30th June
DETAILS OF TRANSMISSION AND DISTRIBUTION LINES AS ON 31-03-20---
Name and address of the Utility/Non-Utility/Entity:
Sl. Nominal Length of line in km at the Length of line added during the year Total Length of line in Ckt km Remarks
No Voltage beginning of the year in km at the beginning at the end of the year
Single Double Ckt Multi Ckt* Single Ckt Double Multi Ckt* Single Ckt Double Multi Ckt*
Ckt Ckt Ckt
1. EHV Lines:
above
500kV
2. 500 kV DC
lines
3. 400 kV
4. 230 kV
5. 220kV
6. 132 kV
7. 110 kV
8. 78 kV
9. 66 kV
10. 33 kV
11. 22 kV
12. 11 kV
13. 6.6 kV
14. 4.4 kV
15. 3.3 kV
16. 2.2 kV
17. 440/230 V, 3
phase, single phase
if available
18 * Direct current
lines (volts)
19 Any other (specify)
Page 74 of 510
FORMAT-15
Periodicity-Annual
Data of year 20--- 20---
Submission by -30th June
Page 75 of 510
FORMAT-16 (page 1 of 2)
DETAILS OF MANPOWER Periodicity-Annual
Data of year 20--- 20---
Name of Utility: Submission by -30th June
Class of employment
(A) Regular (i.e. monthly paid) N U M B E R OF EMPLOYEES Training provided Type of Training
As on As on No. of Personnel/Tech/Adm/Others Induction/Refresher/
1. Managerial and higher executives 31-03-20.(Yr.Start) 31-03-20.(Yr.end) Management/Others
(Rank of Chief Engineer and above)
2. Technical & Scientific Officers
3. Non-technical: Executive, clerical, accounting, revenue collection, meter reading staff & officers, etc.
4. Technical Supervisory staff in
(a) Generation
(b) Transmission
(c) Distribution
(d) Trading
(e) Others
5. Technicians and Operating Staff in
(a) Generation
(b) Transmission
(c) Distribution
(d) Trading
(e) Others
TOTAL REGULAR (1) to (5) = (A)
(B) Non-Regular
(a) Technical : Trainees & Apprentices
(b) Work Charged Staff
(Monthly paid basis)
i. Skilled
ii. Unskilled
Total ( b ) = (i)+(ii)
(c) Casual (daily paid basis)
i. Skilled
ii. Unskilled
Total ( c ) = (i)+(ii) (i.e.=c)
Page 76 of 510
FORMAT-16 (Contd.)
Page 2 of 2
General Guidelines for filling form for manpower in the electricity supply industry.
1. Managerial and higher executives: All engineering posts of the rank of Chief Engineer and above is to be included.
2. Technical and scientific officers: All engineering posts above the rank of supervisor/Junior Engineer/ Scientific Officer may be included.
3. Non-Technical : All regular non-technical employees i.e. Executive, clerical, accounting, revenue collection, meter reading staff and officers may be
included.
a) Generation: All technical staff of the rank of supervisor/Section officer/Junior engineer/ Assistant Controller engaged at generating stations and those
associated with planning of generation may be included.
b) & c) Similar staff mentioned above engaged in transmission & distribution system.
d) & e) Similar staff mentioned above engaged in trading & other activities.
5. a) Technicians and operation staff : All the technical staff below the rank of supervisor/Junior engineer engaged at generating stations.
b) & c)Similar staff mentioned above engaged in Transmission and Distribution system.
Page 77 of 510
Training Facilities / Training Capacity in the Power Sector (Man- Format-17
Days of Year) Periodicity-Annual
Submission by -30th June.
Name of Utility/Organisation Data of the Financial year
20--- 20---
1 2 3 4 5 6 7 8 9 10 11 12
Technical Non-
Technical
Page 78 of 510
FORMAT-18
Periodicity-Annual
Data of year 20--- 20---
Submission by -30th June
iii) Estimated quantity of electrical energy considered as theft in above cases for the period:
Page 79 of 510
FORMAT-19
Periodicity Annual
Data of year 20--- 20---
Submission by - 30th June …..
Name of Utility/Non-Utility/Entity:
Sl. . INSTALLATIONS H U M A N A N I M A L S
No. ------------------------------------------ ------------------------------------
FATAL NON-FATAL FATAL NON-FATAL
3. Installations of consumers other than industrial consumers e.g. domestic/agriculture/commercial consumers, etc.:
N.B. :- Indicate the number of human/animal affected. Also show the corresponding number of accidents within brackets.
Page 80 of 510
FORMAT-20
Periodicity-Annual
Data of year 20--- 20---
Submission by -30th June
R E A S O N S F O R E L E C T R I C A L A C C I D E N T S
Name of Undertaking:
Sl. R EAS O N S H U M A N A N I M A L S TOTAL
No. --------------------------------------- -------------------------------------------
FATAL NON-FATAL FATAL NON-FATAL
N.B. : Main reasons for accidents mentioned at Sl.No.(vii) are :- (Please specify)
Page 81 of 510
[FORMAT-21
Periodicity-Annual
Data of previous year: ------
Submission by – 30th June
(Applicable to the entities having electricity demand/CPP capacity of 0.5 MW & above)
25Substituted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 17.03.2022.
Page 82 of 510
Format No - 22 Page1 /2
Periodicity-Daily
Submission by 1030 hrs.
Daily Operational Data of Thermal Power Stations and Nuclear Power Stations
(Generation and Outage data)
Generation data for the date:
Station 2
Details of Units remained out of bars & Units tripped/ taken out of the bar during the day
(i)
Outage Reason(s) of
Name Unit Date & Expected date Outage extended
Of No. Time of return Reason(s) outage, if any Remarks
Station
Planned outage
Forced outage
Forced outage
Page 83 of 510
Format No - 22 Page2 /2
Station 1
Station 2
Partial loss in MkWh = (Cr1 x Hr1 +Cr2 xHr2…+ Crn x Hrn) /1000
Where Cr1............ Crn are "the reduction in the output of the operating units in MW due to constraints in
Auxiliaries/equipments or
any other causes." and Hr1……Hrn are the duration in hours of operation of the units at reduced output during the period
considered (day or month).
Page 84 of 510
Format 23 Page1/2
Periodicity-Daily
Submission by- 1030 hrs
Daily Operational Data of Hydro Power Stations
(Generation, outage and reservoir level data)
Generation Data for the date:
Name of the organisation:
Unit Gross
Name Of Unit No. Capacity Energy Peak Load Remarks, if any
Station in MW Generated during the day
during the (MW)
day in
MkWh
Station 1
Station 2
(i) Details of Units remained out of bars & Units tripped/ taken out of the bars during the day
Forced outage
Forced outage
Page 85 of 510
Format 23 Page2/2
(C) ENERGY LOSS DUE TO REASONS OTHER THAN FORCED OUTAGE AND PLANNED
MAINTENANCE (DAY WISE IN MkWh)
Energy
Unit Energy Energy Energy Energy Energy Energy Loss
Name Of Unit Capacity Loss due Loss due Loss due Loss due Loss due Loss due due to Remar
Station No. in MW to flood to to silt to high to reduced to system Equipm ks, if
weeding flushing silt inflows constraint ent any
content Proble
ms
Station 1
Station 2
(II) Wherever actual auxiliary consumption is not being metered, proportionate auxiliary consumption may be
furnished.
(III) *From the date of synchronisation to the date of commercial operation
** data to be furnished in case of new units/stations and any changes in the existing units
Signature
Page 86 of 510
Format : 24 Page 1/2
Periodicity-Monthly
Submission by-7th day
Monthly Operational Data of Thermal Power Stations and Nuclear Power Stations
(Generation and Outage data)
Data for the Month:
Name of the organization:
(A) UNIT WISE GENERATION, UNIT AUX . & STATION AUX. POWER CONSUMPTION
Unit Gross Energy Unit Aux. Station Aux. Unit Peak Load Station Peak
Name Of Unit Capacit generated Consumption Consumption during the month Load during
Station No. y in during the in MkWh in MkWh ( MW ) the month (
MW Month in MW )
MkWh
Station 1
Station 2
Details of Units remained out of bars & Units tripped/ taken out of the bars during the Month
(i)
Tripping Reason (s) of
Name Of Unit Date & Expected date of Outage extended
Station No. Time return Reason (s) outage, if any Remarks
Planned outage
Forced outage
Forced outage
Page 87 of 510
Format : 24 Page 2/2
(C) UNIT WISE PARTIAL ENERGY LOSS DATA (DAY WISE IN MkWh)
Station 1
Station 2
Partial loss in MkWh = (Cr1 x Hr1 +Cr2 xHr2…+ Crn x Hrn) /1000
Where Cr1 ........... Crn are "the reduction in the output of the operating units in MW due to constraints in
Auxiliaries/equipments
or any other causes." and Hr1……Hrn are the duration in hours of operation of the units at reduced output during the
period considered (day or month).
Page 88 of 510
Format no-25 Page 1/2
Periodicity- Monthly
Submission by- 7th day
Station 1
Station 2
Details of Units remained out of bars & Units tripped/ taken out of the bars during the Month
(i)
Name Of Unit Outage Expected date Reason(s) of
Station No. Date & of return extended
Time Outage outage, if any Remarks
Reason(s)
Planned outage
Forced outage
Forced outage
(C) ENERGY LOSS DUE TO REASONS OTHER THAN FORCED OUTAGES & PLANNED MAINTENANCE
Station 1
Station 2
Page 89 of 510
Format no-25 Page2/2
(E) Hydro Reservoir Inflow data
Reservoir inflow data for the month- year (mm-yy):
Page 90 of 510
FORMAT-26
Periodicity-Annual
Data for year 20--- 20---
Submission by -30th Nov.
DATA FOR FIXATION OF ANNUAL TARGETS OF ELECTRICITY GENERATION FOR YEAR 20----- 20---
Name of Company:
Name of Unit Capacity Station wise & Unit wise Schedule of Planned Maintenance (Unit wise)
Station No. (MW) monthly and yearly targets
for next year
(MkWh)
Start Date End Date
Page 91 of 510
FORMAT-27 Page 1/4
PERIODICITY- DAILY
SUBMISSION BY- 0900 HRS
Regional Power Supply Position (Daily Operation Report) in Region for (Date)
Date of Reporting at (Time)
Total
Region
Page 92 of 510
FORMAT-27 Page 2/4
3. Inter-Regional Exchanges - Physical Flows [Import(+)/ Export(-)]
Peak Hrs Off-Peak Hrs Maximum Inter-Change
(___Hrs) ( Hrs) Import Time Export Time Net Energy
Elements (MW) (MW) (MW) (Hrs) (MW) (Hrs) (MkWh)
A. Northern Region Links
1.
2.
Sub Total NR Links
B. Western Region Links
1.
2.
Sub Total WR Links
C. Southern Region Links
1.
2.
Sub Total SR Links
D. Eastern Region Links
1.
2.
Sub Total ER Links
Total (All Links)
5. Frequency Profile
% of Time
Frequency Range < 48.5 Hz < 49.0 Hz < 49.5 Hz 49.0 - 50.5 Hz > 50.0 Hz > 50.5 Hz > 51.0 Hz
%
Frequency
Day Variation Index
Instantaneous Maximum Instantaneous Minimum 15-Minutes Block Maximum 15-Minutes Block Minimum Average (FVI#)
Hz Time Hz Time Hz Time Hz Time Hz
Page 93 of 510
FORMAT-27 Page3/4
7. Major Reservoir Particulars
Designed Present Last Year Last Day Month
Progra
m me
MDDL FRL Energy Level Energy Level Energy Inflows Uses Usage
Reservoirs (metre) (metre) (MkWh) (metre) (MkWh) (metre) (MkWh) (MkWh) (MkWh (MkW
) h)
10. Weather Conditions Prevailed on the Day of Report & for the Following Day:
11A. Generating Units Revived During Last 24 Hrs. ( 06:00 Hrs of (Date) to 06:00 Hrs (Date))
Outage Revival Reasons
S.No. Stations Unit No. Capacity (MW) Date Time Date Time of outage
Central Sector
1.
2.
3.
4.
State Sector
1.
2.
3.
4.
Page 94 of 510
FORMAT-27 Page4/4
12. Transmission Lines Outage Status in Southern Region
As on Date Time 6:00 Hours
12 A. Transmission Lines Revived During Last 24 Hrs. ( 06:00 Hrs of (Date) to 06:00 Hrs (Date))
Page 95 of 510
FORMAT-28 Page 1/3
PERIODICITY- MONTHLY
SUBMISSION BY- 5TH DAY
Provisional Power Supply Position in Region for the Month of
A Generation Details
S.No. Constituents 1 2 3 ------ N REGION
(I) Gross Generation (MkWh)
Thermal
(i) Coal
(ii) Liquid
(iii) Gas Open Cycle
(iv) Gas Combined Cycle
(v) Nuclear
Hydro
IPPs
CPPs
Wind Mills
Total (MkWh) (I)
(II) Dedicated Power Stations#
(i)
(ii)
Total (MkWh) (I)+(II)
(II) Actual Demand Met (Gross MW)
Page 96 of 510
C Details of Calculations FORMAT-28 Page 2/3
1 Availability
2 Frequency Correction
3 Load Shedding
4 Power Cuts
5 Unrestricted Requirement (1+2+3+4)
Between Between
Between 48.5 Hz Between 48.8Hz Between 49.0 Between Between Between 50.5 Hz 51.0 Hz Above
Frequency Range Below 48.5 Hz & 48.8 Hz & Hz & 49.5 Hz & 49.8 Hz & 50.2 Hz & & & 51.5
49.0 Hz 49.5 Hz 49.8 Hz 50.2 Hz 50.5 Hz 51.0 Hz 51.5 Hz Hz
( % of time)
MONTH FREQUENCY
INSTANTANEOUS MAXIMUM INSTANTANEOUS MINIMUM 15-MINUTES BLOCK 15-MINUTES BLOCK LY VARIATION
MAXIMUM MINIMUM AVERA INDEX
GE
Hz Time Hz Time Hz Time Hz Time Hz
# Dedicated Power Stations: Power Stations whose generation is solely meant for the concerned State(s).
FORMAT-26 RPCs
Page 97 of 510
FORMAT-28 Page3/3
Power Cuts on Industries, Load Shedding & Power Supply to Agricultural Sector in
Region During (Month/Year)
Power Cuts28.3
Page 98 of 510
FORMAT-29 Page 1/4
PERIODICITY- MONTHLY
SUBMISSION BY- 18TH
DAY
Revised Power Supply Position in Region for the Month Of
A Generation Details
S.No. Constituents 1 2 3 ------ N REGION
(I) Gross Generation (MkWh)
Thermal
(i) Coal
(ii) Liquid
(iii) Gas Open Cycle
(iv) Gas Combined Cycle
(v) Nuclear
Hydro
IPPs
CPPs
Wind Mills
Total (I)
(II) Dedicated Power Stations#
(i)
(ii)
Total (MkWh) (I)+(II)
(II) Actual Demand Met (Gross MW)
Page 99 of 510
D Details of Calculations FORMAT-29 Page 2/4
S.No. Constituents 1 2 3 ------ N REGION
1 Net Actual Energy Supplied
2 Frequency Correction
3 Unscheduled Load Shedding
4 Scheduled Load Shedding/Power Cuts
5 Unrestricted Requirement (1+2+3+4)
E Peak Demand/ Unrestricted Peak Demand (Ex-Bus) (MW)
S.No. Constituents 1 2 3 ------ N REGION
1 Peak Unrestricted Demand (from Table F)
2 Peak Demand Met
3 Shortfall
4 % Shortfall
F Details of Calculations for Unrestricted Peak Demand (MW)
S.No. Constituents 1 2 3 ------ N REGION
1 Peak Demand Met
2 Frequency Correction
3 Unscheduled Load Shedding
4 Scheduled Load Shedding
5 Peak Unrestricted Demand (1+2+3+4)
G Details of Gross Generation, Declared Capacity, Scheduled Generation and Injection from CGSs
(MkWh)
Declared Scheduled Gross
Capacity Capacity Generation Injection
(Ex-Bus) (Ex-Bus)
S.No. CGSs (MkWh) (MkWh) (MkWh) (MkWh)
(i)
(ii)
(iii)
.
.
Total
1.1
1.2
1.3
Total (1)
2 Dedicated CG Stations :
2.1
2.2
Total (2)
3 Supply from Jointly owned Projects:
3. 1
3. 2
Total (3)
Total (1 + 2 + 3 )
Note : Central Generating Station (CGSs) within the region and outside the region
Total
Total
[ ]26
26 Page 103
Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) of 510
Regulations,
2007 w.e.f. 17.03.2022.
FORMAT-31
PERIODICITY- MONTHLY
SUBMISSION BY- 10TH DAY
Monthly Data regarding Loss of Generation on account of Shortage of Coal, Gas, Unreqisitioned Liquid
Fired Capacity & Backing Down due to System Constraints in
Region for the Month
CENTRAL SECTOR
1.
2.
3.
4.
Total
Summary
1. Loss of Generation due to
Shortage of Coal MkWh
2.
Loss of Generation due to
Shortage of Gas MkWh
3. Loss of Generation due to Unrequisitioned
Liquid Fired Capacity
MkWh
(Sub-Total) MkWh
4.
Loss of Generation due to System Constraints (Low System
Demand,
Transmission Constraints, etc.) MkWh
Total MkWh
FORMAT- RPCs
DATA FOR LOAD GENERATION BALANCE REPORT (LGBR) FOR THE YEAR 20…. TO 20……
1. Effective Capacity for the Year 20
-20
Generating Station Unit No. Plant
*Thermal/ Date of BLR Effective Aux. Forced outage
Nuclear/ Gas/ (for Thermal/ Capacity as on Consumption rate (%) Planned Outage
S. No Name Hydro/ Other Gas Stations) 31/3/20…. (%) (%) Target PLF % Remarks
4. Monthly Generation Ex-bus Targets (MW) (max.) and Average Energy (MkWh/day) for the Year 20 -20
5. Monthly Estimated Peak Demand (MW) (max.) and Average Energy Requirement (MkWh/day) of Constituents for the Year 20 -20
April…………. May………….. ……….. February……….. March………….
MW MkWh/Day MW MkWh/Day ……… …….. MW MkWh/Day MW MkWh/Day Remarks
% Growth Rate considered for calculating Energy Requirement and Estimated Peak Demand %
11. State wise Anticipated Energy Requirement Vs Energy Availability (MkWh) for the Year 20 -20
April 20 May 20_ June 20_ -------------- January 20_ February 20_ March 20_ Total
Region/ State/ System
Requirement
Availability
Surplus/ Deficit (-)
%
12. State wise Anticipated Peak Demand Vs Peak Availability for the Year 20 -20
April 20 May 20 June 20 ------------------ January 20 February 20_ March 20 Maximum
Region/ State/ System
Peak Demand
Peak Availability
Surplus/ Deficit (-)
%
* Thermal Generating Stations include Coal, Liquid, Gas Open Cycle, Gas Combined Cycle & Nuclear
FORMAT-48 GENCO/ State Utilities/ RPCs
FORMAT- RPCs
1
2
3
4
Progress of Capacitor Installation Programme in …………………... Region for the month of ……………
Constituent's Faulty
programme Capacitors
Total installed as Requirement during ……….. Actual addition removed during
on during (current year) during the the current
Name of the ………. current month month Total addition
Constituents …….. (previous (current year) ……… during the current
year) ……… year
1
2
3
4
5
6
.
.
.
.
.
Total Region
FORMAT-25 RPCs
Name of TPS Date Receipt Cumulative receipt Consumption Cumulative Stock Available
during the month Consumption during
the month
Name of TPS Date Total pro rata Name of Coal Company Total Receipt Receipt as (%) of
linkage Source-I Source-II So on linkage
(4) Wagons
Name of TPS Date Opening Balance Wagons Received Wagons Released Closing Balance
1. Name of TPS :
3. Capacity in MW :
4. Coal Data :
A. Link Source
1.
2.
B. Diverted if any
1.
2.
C. Imported if any
a) Indigenous Coal :
b) Imported Coal :
a) Indigenous Coal :
b) Imported Coal :
mt = metric tone
Date Unit No. Capacity in MW Total Energy Loss in MkWh due to Remarks
shortage of fuel
1 2 3 4 5
[ ]27
27 Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f.
17.03.2022.
Page 113 of 510
FORMAT-40
[ ]28
28 Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f.
17.03.2022.
Page 114 of 510
FORMAT-41
Periodicity-Quarterly
Submission 40 days before the
commencement of the quarter
PROPOSED COAL ALLOCATION FOR SHORT TERM LINKAGES FOR THERMAL POWER
STATIONS
1. Name of the Power Station
4. Planned Outage:
8. Average Stock Building per month in metric tonnes subject to stocking capacity of the station’s stock yard.
9. Average monthly coal requirement during the quarter in metric tonnes (details below)
Total
MONTHLY FUEL SUPPLY DATA OF GAS BASED THERMAL POWER STATIONS (UTILITY) FOR THE
MONTH ……. YEAR 20--
2 Owner's name:
3 Mailing address:
Telephone No.
Fax No.
4 Installed capacity ( Installed capacity & Unit rating in MW and No.
of Units)
10 Average gross calorific value of the fuel for the month kcal/SCM kcal/ kl kcal/ kg
15 Landed cost (Average for month) of fuel at power station in Rs./SCM Rs./kl Rs./mt
Rs./SCM
16 Remarks, if any.
MMSCM-Million Metric Standard Cubic Metre
mt = metric tonne
kl = kilo litre
MONTHLY FUEL SUPPLY DATA OF LIQUID FUEL BASED THERMAL POWER STATIONS (UTILITY)
FOR THE MONTH ……. YEAR 20--
2 Owner's name:
3 Mailing address:
Telephone No.
Fax No.
4 Installed capacity (Installed capacity & Unit rating in MW and No. GT ST
of Units)
16 Remarks, if any.
MONTHLY FUEL SUPPLY DATA OF DG POWER STATIONS (UTILITY) FOR THE MONTH
……. YEAR 20--
2 Owner's name:
3 Mailing address:
Telephone No.
Fax No.
4 Installed capacity (Installed capacity & Unit rating in MW and No.
of Units)
[ ]29
29 Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f. 17.03.2022.
[ ]30
30 Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f. 17.03.2022.
Page 120 of 510
FORMAT- 47
[ ]31
31 Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f. 17.03.2022.
State/U.T …………………..
Sl No Name of the District Nos. of inhabited No. of inhabited villages Achievement from No. of villages electrified during Cumulative villages electrified as
villages as per electrified up to 31.03.20 1.4.20… to ……… (during the …… (month under report) on …….. (end of month under
… ................ Census ---------------------- (end of current year upto the end of report ) (4+5+6)
previous year) month previous to the
month under report)
1 2 3 4 5 6 7
State/UT:………………………………………………………………………………
Name of Reporting Discom/utility: ……………………………………………………………
Electrical Circle/Division :………………………………………………
For the Month of ………………………………………………Year………………………………….
Sl. No. Name of the District Total Pumpsets Pumpsets Pumpsets Total Remarks
Existing /Effective at Energized De- Pumpsets
the end of the during the energized Existing
previous Month Month during the /Effective at
(Nos) Month the end of the
(Nos)
Month (Nos)
(Nos)
(=b+c-d)
a b c d e f
Total-A
B Irrigation Pumpsets Energization (Off grid supply)
Total-B
Total - A+B
]32
32Substituted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 17.03.2022.
[ ]33
33 Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f. 17.03.2022.
Area-Urban
Feeder Metering Power Sub Station (PSS) level (6.6 kV, 11 kV, 22 kV, 33 kV and higher, if any) (Please select the Voltage category
applicable and provide details accordingly)
Sl. Name of Name of 66, Capaci ty Name of Type of Feeder Feeder If Metered, If Metered with Remarks (Status of
No. Urban 33, 22/11 kV of 66, 33, Feeders feeders- Rural, Voltage metering Type of Meter AMR, Whether defective meters,
area/ PSS 22/ 11 originati ng Urban or (6.6 kV, 11 Status provided communica communication
Town, feeding the kV PSS, from the Mixed @ kV, 22 kV, (Yes/ No) (AMR / ting to National status, etc.)
Census feeders (with MVA PSS (with 33 kV, etc.) Normal Power Portal
code Code) codes) Electronic (Yes/ No)
meter)
1 2 3 4 5 6 7 8 9 10
1
2
3
Total-
Urban
Area-Rural
Feeder Metering PSS level (6.6 kV, 11 kV, 22 kV, 33 kV and higher, if any ) (Please select the Voltage category applicable and provide
details accordingly)
Sl. Name of Capacity of Name of Type of Feeder Voltage Feeder If Metered, Type of Meter If Metered with Remarks (Status of
No. 66, 66, 33, Feeder s feeders- (6.6 kV, 11kV, metering provided (AMR/ Normal AMR. Whether defective meters,
33, 22/ 11 kV origin Rural, 22 kV, Status (Yes/ Electronic meter) communica communication
22/11 kV PSS , MVA ating Urban or 33 kV, etc.) No) ting to NPP status, etc.)
PSS from the Mixed (Yes/ No)
feeding the PSS
feeders (with
(with codes)
Code)
1 2 3 4 5 6 7 8 9
1
2
3
Total-
Rural
Total -
Rural
+ Urban
@ Rural (domestic and commercial) Agriculture , or Mixed of Rural, Agriculture and Industrial, etc.
1 2 3 4 5 6 7 8 9 10
1
2
3
Total -
Urban
Area-Rural
Distribution Transformer (DT) (with 33kV, 22kV, 11 kV, 6.6 kV/ 0.4 kV or 0.215 kV) Metering (Please select the Voltage category applicable and
provide details voltage wise)
Sl. No. Name of Type of Feeder Voltage (6.6 Number Aggregate Tota l DTs If Metered Remarks
Feeders feeders- kV, 11kV, 22 of DTs in Capacity of Num Metered with AMR, (Status of
originati ng Rural, kV, or 33 kV, etc.) Service DTs (MVA) ber of with Whether defective
from the Urban or DTs AMR / communic meters,
PSS (with Mixed mete Normal ating to DC communi
codes) $ red Electroni c (Yes/ No) cation
meter status, etc.)
1 2 3 4 5 6 7 8 9
1
2
3
Total -
Rural
Total -
Urban +
Rural
$ Name / Type of feeders and their code must match with Feeders from PSS of Format-51(1/3).
Area-Urban
Sl. Name of Name Name of Total Type of Meters (Electronic / Smart / Prepaid) Total Number Percentage Remarks
No. Urban of PSS Number Number of Number of Number Number of of Consumers of Consumer (Status of
Areas $ Circle with of Electro- of metered metered defective
Smart/ Prepaid
Codes, Consumer Mechanical (= sum of (= column 9 meters,
AMI Prepaid (Standalone
supplying s Meters columns 5, x 100/ communi-
meters (Smart/A meters)
to 6, Column 4) cation
MI)
consumers 7 & 8) status,
meters
$ etc.)
1 2 3 4 5 6 7 8 9 10 11
1
2
3
Total -
Urban
Area-Rural
Sl. Name of Name of PSS with Total Type of Meters (Electronic / Smart / Prepaid) Total Number Percentage Remarks
No. Circle Codes, supplying Number of Consumers of Consumer (Status of
to consumers $ of metered metered defective
Number of Number of Number Number of
Consumer (= sum of (= column 8 meters,
Electro- Smart/ of Prepaid
s columns 4, x 100 / communi
Mechanical AMI Prepaid (Standalo ne
5, Column 3) cation
Meters meters (Smart/A meters)
6 & 7) status,
MI) etc.)
meters
1 2 3 4 5 6 7 8 9 10
1
2
3
Total -
Rural
Total -
Urban +
Rural
$ Name of PSS /feeder s and code must match with Format-51(1/3)
]34
34 Substituted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f.
17.03.2022.
Page 127 of 510
FORMAT- 52
[ ]35
35 Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f. 17.03.2022.
RELIABILITY INDICES (SAFI, SAIDI, CAIDI & MAIFI) -CONSUMER AFFECTED/ LOAD INTERRUPTED BASIS
ON THE FEEDER
State/UT: …………………………………………………………………………………………… Name of Reporting
Discom/utility: …………………………………………………………… Electrical Circle/Division
…………………………………………………………
For the Month of ………………………………………………Year………………………………….
Targets as per Standard SAIFI SAIDI CAIDI MAIFI Targets as per SAIFI SAIDI CAID MAIF
of Performance (Urban) Standard of I I
Performance
(Rural)
Calculation for SAIFI, SAIDI, CAIDI# Calculation for MAIFI#
Name of Type of Total Total Nos Nos of Duration of Nos of SAI SAIDI CAID Nos of Nos of MAIFI #
Circle/Area Circle/Ar No of of Interrupti Interruption consum FI I momentary consum
eas feeders consumers ons considered ers in Interruptio ers in
(Urban – (U/R) (U/R) in (>3min/ (>3min the ns(<3min/5 the
U Rural- in the the 5min /5min affecte min/10min) interrup
R) circle/ar feeders in /10min) /10min) d @ ted
ea $ the @ feeders feeders
Area - Urban circle/area
1
2
3
Total-Urban
Area - Rural
1
2
3
Total –Rural
Overall Discom
SAIDI – System Average Interruption Duration Index
SAIFI – System Average Interruption Frequency Index
CAIDI – Consumer Average Interruption Duration Index
CAIFI – Consumer Average Interruption Frequency Index
MAIFI – Momentary Average Interruption Frequency Index
@Strikeout whichever is not applicable.
# calculation Formula as specified in Standard of Performance of SERCs/ JERCs
$-Nos of Feeders must match with Format – 51 (1/3)
Notes: Targets as fixed by respective SERCs/JERCs may be indicated. If not fixed/available, it may be clearly mentioned.
]36
36Substituted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 17.03.2022.
Overall
Discom
SAIFI – System Average Interruption Frequency Index
SAIDI – System Average Interruption Duration Index
CAIFI – Consumer Average Interruption Frequency Index
CAIDI – Consumer Average Interruption Duration Index
MAIFI – Momentary Average Interruption Frequency Index
@Strikeout whichever is not applicable.
# calculation Formula as specified in Standard of Performance of SERCs/ JERCs
$-Nos of Feeders must match with Format-51 (1/3)
Notes: Discoms to select the applicable Format (Format-1: consumer interruption basis) or
(Format-2: Load interruption basis) while submitting the data as specified in respective SOP order.
]37
37Substituted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 17.03.2022.
[ ]38
38Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations,
2007 w.e.f. 17.03.2022.
Page 131 of 510
FORMAT-56
Periodicity – Annual Submission
by 30th April
Name of Utility
[ ]39
39 Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007 w.e.f. 17.03.2022.
Page 133 of 510
FORMAT-58
Periodicity- `Monthly
Submission-by 20th day
HEAT RATE DATA OF COAL/LIGNITE BASED THERMAL POWER STATIONS FOR MONTH ………YEAR ………20…..20…...
1.0 General:
(i) Station Name:
(ii) Station Capacity: -(No. of units with size)
Unit No. Unit Capacity Date of Make Boiler Turbine Heat Unit Heat Rate Weighted Design Station Heat Rate
(MW) commissioning Boiler Turbine Efficiency (%) Rate (kcal/kWh) (Col.7x100)/ Col.6 w.r.t. Capacity (kcal/kWh)
(kcal/kWh)
1 2 3 4 5 6 7 8 9
U-1
:
:
:
:
Un
Station
3.0 Operational Performance Data For The Station (month-wise) For The Year : -------------------------
Month Coal / Lignite Coal / Lignite Coal / Lignite Total Coal / Lignite Generation Average Specific Coal / Oil Specific Oil Avg. Actual Station Heat
stocks at the stocks at the received during consumptio n during (MkWh) GCV of Lignite Consumpti Consumption GCV Rate Col.(7x8) +
beginning of the end of the the month the month Col.(2+4-3) during the Coal / Consumption on (kl) (ml/kWh) of Oil Col. (10x11)/1000
month month (Tonnes) (Tonnes) month Lignite (kg/kWh) Col.(9)/(6) (kcal/l) (kcal/kWh)
(Tonnes) (kcal/kg) Col.(5)/{(6)*1000}
1 2 3 4 5 6 7 8 9 11 12
April
May
:
:
:
:
March
Weighted/ Weighted Weighted
Total For The
Year (April - average average
March)
1.0 General:
i) Station Name: ----------------------------------------------------------
ii) Station Capacity: (No. of units with size)
No. of Modules Module Date of Make Module Heat Weighted Design Station.
Capacity commissioning Gas Turbine Steam Turbine Rate (kcal/kWh) Heat Rate w.r.t.Capacity
(MW) (if any) (kcal/kWh)
1 2 3 4 5 6 7
Module# 1
:
:
:
:
Module# n
2.0 Operational Performance Data For The Station For The Year : ---------------------------
Month Liquid fuel Liquid fuel Liquid fuel Total Liquid fuel Generatio Average Specific Gas Specific Gas Average GCV Actual Station
stock in the stock at the received consumption n GCV of Liquid fuel Consumption Consumption of Gas (at Heat Rate
beginning of end of the during the during the month (MkWh) Liquid Fuel Consumption (at S.T.P.) (Cu.m/kWh) S.T.P.) Col.(7x8+10x11)
the month month (kl) month (kl) Col. (kcal/l) (l/Kwh)) (million (9)/(6) (kcal/Cu. m) kcal/kWh)
(kl) (2+4-3) (kl) (5)/(6)*1000) Cu.m)
1 2 3 4 5 6 7 8 9 10 11 12
April
May
:
:
:
:
March
Weighted/AV.
Total (March
to March)
(mg/litre)
Copper (mg/litre)
Iron (mg/litre)
Total Suspended
Solids
(mg/litre)
pH
Oil & grease
(mg/litre)
Total suspended
solids
(mg/litre)
[ ]40
40Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 17.03.2022.
Page 138 of 510
Format 62
[ ]41
41Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 17.03.2022.
[ ]42
42Deleted vide Revision /deletion of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 17.03.2022.
1 Energy Purchased
Sl. Sources Units Purchased Cost
No. kWh Rs Cr.
a
Total
4 Distribution Losses
a Domestic days
b Commercial days
c Industrial days
7 Length of EHT lines……………. CktKm.
8 Availability of distribution Net work (%) =(Nos. of hours for which network was available/Total no. of hours) x 100
Foot Note: 4(b) Commercial losses = (Energy purchased- Energy billed)/Energy purchased =[Total(1)-(2)]/Total(1)
1 Revenue Income
4 Sources of Fund
a) Equity
b) Loans
5 Application of Funds
Technical Nos.
YEAR…………………….. LTPM-- [LAKH TONNES PER MONTH] ASH UTILIZATION IN THE MAIN AREAS [LTPM]
S. Ash Ash %age Hydro Agriculture/
No. Month Coal content Generation Ash Utilized utilization Bricks Cement Concrete Roads & Sector Ash dyke Mine fill Others/
Wasteland
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1 APRIL
2 MAY
3 JUNE
4 JULY
5 AUGUST
6 SEPTEMBER
Half yearly Sub-total
7 OCTOBER
8 NOVEMBER
9 DECEMBER
10 JANUARY
11 FEBRUARY
12 MARCH
TOTAL
ANNUAL (MTPA)
NOTE:
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
Notes: (i) If Registration No. on E-Gen portal is being filled in column (2), the details in column (3) to (8) need
not be filled.
(ii) Column (8) and (9) to be filled only if PPA is based on specific unit.
RTC- Round The Clock.
Details of Area Clearing Prices (Rs/MWh) -Time block wise on daily basis for DAM/ RTM/ GDAM
Date Hour Time Block *A1 *A2 *E1 *E2 *N1 *N2 *N3
DD-MM-
1 00:00 - 00:15
YYYY
DD-MM- 1 00:15 - 00:30
YYYY
DD-MM-
1 00:30 - 00:45
YYYY
DD-MM-
1 00:45 - 01:00
YYYY
DD-MM-
2 01:00 - 01:15
YYYY
DD-MM-
2 01:15 - 01:30
YYYY
DD-MM-
2 01:30 - 01:45
YYYY
DD-MM-
2 01:45 - 02:00
YYYY
DD-MM-
YYYY
DD-MM-
YYYY
DD-MM-
YYYY
DD-MM-
YYYY
DD-MM-
YYYY
DD-MM-
YYYY
DD-MM-
YYYY
DD-MM-
23 22:00 - 22:15
YYYY
DD-MM-
23 22:15 - 22:30
YYYY
DD-MM-
23 22:30 - 22:45
YYYY
DD-MM-
23 22:45 - 23:00
YYYY
DD-MM-
24 23:00 - 23:15
YYYY
DD-MM-
24 23:15 - 23:30
YYYY
DD-MM-
24 23:30 - 23:45
YYYY
DD-MM-
24 23:45 - 24:00
YYYY
*S1 *S2 *S3 *W1 *W2 *W3 Any other bid area in Wt. Avg. Market Clearing
future Price
Details of electricity transacted in Power Exchanges for DAM/ RTM/ GDAM (or any other product/ contract as
introduced in future).
Date Purchase Bid (MWh) Sell Bid (MWh) MCV (MWh) Cleared Volume (MWh)
DD-MM-YYYY
DD-MM-YYYY
DD-MM-YYYY
DD-MM-YYYY
DD-MM-YYYY
Total
Minimum
Maximum
Average
Congestion Volume Loss - Real Time Final Scheduled Volume Wt. Avg. MCP (Rs/MWh)
(MWh) Curtailment (MWh) (MWh)
s Market Clearing Congestion for Cleared Volume Wt. Avg. Market Clearing
Volume for traded traded date for traded date Price (for the traded volume
date (MWh) (MWh) (MWh) of electricity) (Rs/MWh)
DD-MM-YYYY
DD-MM-YYYY
DD-MM-YYYY
DD-MM-YYYY
DD-MM-YYYY
Total
Minimum
Maximum
Average
Cleared Volume for Real Time Final Scheduled Volume Wt. Avg. Market Clearing Price (for
Date delivery date Curtailment for delivery the delivered volume of
(MWh) (MWh) date (MWh) electricity) (Rs/MWh)
DD-MM-YYYY
DD-MM-YYYY
DD-MM-YYYY
DD-MM-YYYY
DD-MM-YYYY
DD-MM-YYYY
DD-MM-YYYY
Total
Minimum
Maximum
Average
PERIODICITY- ANNUALLY
SUBMISSION-BY-15-MAY-YYYY
Name of Power Exchange: (in .xls / API file)
Details of electricity transacted in Power Exchanges in DAM/ RTM/ GDAM
Month Purchase Bid (MWh) Sell Bid (MWh) Market Clearing Cleared Volume
Volume (MWh) (MWh)
APR-YYYY
MAY- YYYY
JUN- YYYY
JUL- YYYY
AUG- YYYY
SEPT- YYYY
OCT- YYYY
NOV- YYYY
DEC- YYYY
JAN- YYYY
FEB- YYYY
MAR- YYYY
Total
Congestion (MWh) Volume Loss - Real Time Final Scheduled Volume Wt. Avg. Market
Curtailment (MWh) (MWh) Clearing Price (Rs/MWh)
* Banking energy quantum under bilateral transactions (MU) between the contracting parties to be shown here.
* MoU between Governments, any other instrumentalities, etc. through which the electricity transaction is taking
place.
Sl. No. Name of the Distribution Date of application of the Tariff Date of issue of
Licensees/ petition & Tariff year the Tariff Order &
Transmission Licensees/ Tariff year
generating companies,
etc.
Control Period of the Tariff Date of application of the Date of issue of the Truing up Truing ups period Truing up
Order & Tariff Truing up petition & Order & Tariff year Order & Tariff year
year Tariff year
PERIODICITY- DAILY
SUBMISSION BY- 10:00 hours of next day
(in .xls / API file)
Provider: National Load Despatch Centre (NLDC)
Details of Un-Requisitioned Surplus (URS) from the generations being scheduled by the RLDCs
Region Entity/ Beneficiary Quantum of URS (MW) Quantum of URS energy (MU)
Sl. Type of Renewable Installed Capacity (MW) as on last date of Generation (MUs) during the month
No. Energy Generation the month
Source
Central State Private Central State Private Total
Sector Sector Sector Total Sector Sector Sector
1 Wind
Grand
Total:
Note:- The Generation/ Installed capacity is to be reported for the plant located within the physical
boundary of the respective State/ UT.
Abbreviations:-
Hybrid: Generation Plant where more than one renewable primary source of energy, including, storage is used.
1. Name of RLDC/SLDC/Genco/SNA/ED/Discom:
2. Data for the Month/Year-
S. E-gen Registration No. *Name of the *Name of the*Location/ District/ State *Installed
No. Plant Gener-ating Capacit
Comp-any y (MW)
(1) (2) (3) (4) (5) (6)
1 Plant 1
2 Plant 2
3
4
Note: 1. The data in Column Nos. (3) to (8) are static data and need to be provided one time only for Existing/New
Projects, in case E-Gen Registration No. is not available.
2. In case of 'Other**', the source may be specified.
Abbreviations:-
Hybrid: Generation Plant where more than one renewable primary source of energy, including, storage is used.
Note: 1. The data in columns marked as (*) are static data and need to be provided one time only for Existing/ New
Projects, in case E-Gen Registration No.is not available.
2. In case of 'Others**', the source may be specified.
Abbreviations:-
Hybrid: Generation Plant where more than one renewable
primary source of energy, including, storage is used.]43
43Inserted vide addition/ revision of the formats in the Central Electricity Authority (Furnishing of Statistics, Returns and Information)
Regulations, 2007 w.e.f. 25.07.2023.
(2) Words and expressions used and not defined in these regulations but defined in the Act
shall have the meaning assigned to them in the Act.
3. Standards for Operation and Maintenance of Transmission Lines.- (1) All Entities,
Appropriate Load Despatch Centres and Regional Power Committees, for the purpose of
maintaining the Grid Standards for operation and maintenance of transmission lines, shall,-
(a) make all efforts to operate at a frequency close to 50 Hz and shall not allow it to go
beyond the range 49.2 to 50.3 Hz or a narrower frequency band specified in the Grid Code,
except during the transient period following tripping.
(b) maintain the steady state voltage within the limits specified below in Table 1:
5 110 121 99
6 66 72 60
7 33 36 30
(c) ensure that the temporary over voltage due to sudden load rejection remains within the
limits specified in Table 2,-
Table 2
S. No. Nominal System Voltage Phase to Neutral Voltage
3 220 283
4 132 170
Provided that for the voltage level below 132 kV, the temporary over voltage limits as
given in Table 2 shall be decided by the State Commission in the respective State Grid Code.
(d) ensure that the maximum permissible values of voltage unbalance shall be as specified in
Table 3 below:-
Table 3
S.No. Nominal System Voltage Voltage Unbalance
3 33 to132 3%
Provided that Bulk consumers shall avoid unbalanced load during operation:
Provided further that the distribution licensees shall ensure that their loads are not
unbalanced.
(e) provide standard protection systems having the reliability, selectivity, speed and sensitivity
to isolate the faulty equipment and protect all components from any type of faults, within the
specified fault clearance time and shall provide protection coordination as specified by the
Regional Power Committee.
Explanation.- For the purpose of this regulation “fault clearance time” means the maximum
fault clearance times are as specified in the Table 4 below,-
Table 4
S.No. Nominal System Voltage Maximum Time
(kV rms)
( in milliseconds)
1 765 and 400 100
Provided that in the event of non clearance of the fault by a circuit breaker within the
time limit specified in Table 4, the breaker fail protection shall initiate tripping of all other
breakers in the concerned bus-section to clear the fault in the next 200 milliseconds.
(f) operate the system in a such a way that the Grid System is capable of withstanding one of
the following contingencies without experiencing loss of stability:-
(1) outage of one single largest generating unit of the system or
(2) outage of a 132 kV Double circuit line or
(3) outage of a 220 kV Double circuit line or
(4) outage of a 400 kV Single circuit line or
(5) outage of a 400 kV Single circuit line with series compensation or
(6) outage of 765 kV Single circuit line without series compensation or
(g) operate the system in a such a way that under any one of the following contingencies, the
system remains stable and sustains integrity so that no generator loses synchronism and no part
gets isolated from the rest of the system:
(1) tripping of a single largest generating unit; or
(2) transient ground fault in one phase of a 765 kV Single Circuit Line close to the bus; or
(3) a permanent single phase to ground fault in 400 kV single circuit line followed by 3 pole
opening of the faulted line; or
(4) a permanent fault in one circuit of a 400 kV Double Circuit Line when both circuits were in
service in the pre-contingency period; or
(5) a transient single phase to ground fault in one circuit of a 400 kV Double Circuit Line
when the second circuit is already under outage; or
(6) a three-phase permanent fault in a 220 kV or 132 kV line; or
(7) a permanent fault in one pole of HVDC bipolar in a HVDC Converter Station.
(h) observe the following permissible limits of voltage fluctuation :-
(i) the permissible limit of voltage fluctuation for step changes which may occur
repetitively is 1.5 percent:
(ii) for occasional fluctuations other than step changes the maximum permissible
limit is 3 percent:
Provided that the standard on voltage fluctuations shall come into force
concurrently with clause 4 of Part IV of the Schedule to the Central Electricity
Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007.
(2) The transmission licensee shall ensure that the voltage wave-form quality is maintained at
all points in the Grid by observing the limits given in Table 5 below,-
Table 5
S.No. System Voltage Total Harmonic Individual Harmonic of
(kV rms) Distortion any particular Frequency
(%) (%)
1 765 1.5 1.0
2 400 2.0 1.5
Provided that the standard on Harmonic Distortion shall come into force concurrently
with clause 3 of Part IV of the Schedule to the Central Electricity Authority (Technical
Standards for Connectivity to the Grid) Regulations, 2007.
Explanation : For the purpose of this regulation, Total Harmonic Distortion (VTHD)
expressed as percentage, shall be calculated as under,-
Category GI-1 - Tripping of one or more power system elements of the grid like a
generator, transmission line, transformer, shunt reactor, series capacitor
and Static VAR Compensator, which requires re-scheduling of
generation or load, without total loss of supply at a sub-station or loss of
integrity of the grid at 220 kV (132 kV in the case of North-Eastern
Region);
Category GI-2 - Tripping of one or more power system elements of the grid like a
generator, transmission line, transformer, shunt reactor, series capacitor
and Static VAR Compensator, which requires re-scheduling of
generation or load, without total loss of supply at a sub-station or loss of
integrity of the grid at 400 kV and above (220 kV and above in the case
of North-Eastern Region).
(2) Categorisation of grid disturbance in increasing order of severity,-
Category GD-1 - When less than ten per cent. of the antecedent generation or load in a
regional grid is lost;
Category GD-2 - When ten per cent. to less than twenty percent of the antecedent
generation or load in a regional grid is lost.
Category GD-3 - When twenty per cent. to less than thirty per cent. of the antecedent
generation or load in a regional grid is lost;
Category GD-4 - When thirty per cent. to less than forty per cent. of the antecedent
generation or load in a regional grid is lost ;
Category GD-5 - When forty per cent. or more of the antecedent generation or load in a
regional grid is lost.
Explanation: For the purpose of categorisation of grid disturbances, percentage loss of
(3) All operational data, including disturbance recorder and event logger reports, for analysing
the grid incidents and grid disturbance and any other data which in its view can be of help for
analysing grid incident or grid disturbance shall be furnished by all the Entities within
twenty four hours to the Regional Load Despatch Centre and concerned Regional Power
Committee.
(4) All equipment such as disturbance recorders and event loggers shall be kept in healthy
condition, so that under no condition such important data is lost.
(5) A real time operation display of the grid position shall also be made available to the
Regional Power Committee by Regional Load Dispatch Centre.
(6) Regional Load Dispatch Centre shall classify the grid incidents and grid disturbances
according to regulation 11, analyse them and furnish periodic reports of grid incidents and
grid disturbances to the Regional Power Committee which shall recommend remedial
measures to be taken on the Report of Regional Load Despatch Centre to prevent
recurrences of such grid incidents and grid disturbances.
16. Operational Data Records.- (1) Operational data including equipment and system
parameters logged manually and electronically shall be preserved for at least three years.
(2) Logbooks s h a l l be maintained by every manned switchyard and sub-station or at the
control centre responsible for operation of the unmanned switchyard and sub- station.
(3) All operations conducted shall be recorded in chronological order and the time of each
operation and occurrence of each event shall be recorded in such a manner that there shall
be no over-writing and any mistake shall be neatly cut by a line and new words written
thereafter.
(4) The observations made during inspection including important parameters and deviation of
parameters outside permissible tolerances shall also be recorded in the logbook and all entries
must be made in the logbooks immediately.
(5) A record shall be kept of the number of grid incidents and grid disturbances of various
categories by the respective Regional Power Committees for each financial year.
(6) A compendium of grid disturbances, indicating details such as the date and time of the
disturbance, the sequence of tripping, the cause, and the sequence of restoration, remedial
measures taken to avert recurrence of such incidents and disturbances shall be maintained by
the respective Regional Power Committee.
17. Communication facilities.- The communication facilities installed by the transmission
Secretary
(b) defining and documenting responsibilities for all levels of functionaries to carry
out safety related activities including responsibilities of the contractors;
(c) preparing detailed safety manual complying with the statutory requirements and
manufacturers' recommendations;
(d) [(i) establishing procedures to identify hazards that could give rise to the potential
of injury, health impairment or death and measures to control impact of such
hazards;
(ii) setting up an Early Warning System to deal with hazardous events such as
Glacial Lake and Landslide Outburst Floods, Earthquakes, Cloudburst, Flash
Floods, Avalanches, Dam Break event, etc. in case of all large hydro projects
under operation as well as under implementation; and
(iii) establishing Standard Operating Procedure to deal with these hazardous
events;]4
(e) providing adequate human, physical and financial resources to implement the
safety management system;
(f) providing safe working environment and evolving framework for occupational
safety and health;
(g) providing and maintaining medical facilities;
(h) providing adequate training to all employees to keep them aware of safety related
issues;
(i) establishing system for accident reporting, analysis, investigation and
implementation of recommendations;
(j) [establishing system for proper communication, documentation and record
management either in certified soft copy or hard copy form in relation to
occupational safety and health;]5
(k) formulating emergency management plan for quickly and effectively dealing with
(d) information regarding type of hazardous chemicals and fuels at plant site,-
(i) chemicals (quantities and toxicological data);
(ii) fuels (quantities and storage method);
(iii) material safety data sheets;
(e) internal and external communication plan in case of emergency;
(f) details of facilities available at site,-
(i) fire fighting equipment;
(ii) details of diesel generating sets and dewatering facilities available;
(iii) rescue equipment available;
(iv) medical resources available;
(v) type of vehicles, mobile cranes, dumpers etc.;
(vi) list of contractors and details of resources available with them;
(vii) list of private caterers providing canteen facility;
(viii) list of emergency material suppliers like tents, pumps, diesel generating
sets, tarpaulins etc.;
(ix) water resources available.
10. Medical facilities.- (1)The Owner shall provide medical facilities,-
(a) to prevent and control occupational diseases;
(b) to prevent and reduce disability;
(2) The Owner shall ensure that adequate safety training is provided by the
contractor to his employees.
[(4) Owner shall ensure availability of adequate infrastructure for imparting effective
audio-visual safety training at the plant or premises.
Schedule- II
[See regulation 5]
Minimum contents of safety manual for operation and maintenance of electrical
The following safety features shall be additionally covered in 'Safety Manual for
Operation and Maintenance' in addition to those covered in Schedule-I,-
(A) Common to all electrical plants and electric lines:
1. Procedure for obtaining permission to work for carrying out operations and
maintenance of equipment;
2. Safety in operation and maintenance of various electro-mechanical equipment
as per recommendations of manufacturers;
3. Safety of structures and buildings;
4. Safety in workshops and garages;
5. Safe handling, collection and disposal of hazarduous waste;
6. Safety in sub-station, switchyard and switchboards;
(a) Safe working clearance;
(b) Guarding of live apparatus;
(c) Operation on live apparatus;
(d) General provisions relating to maintenance;
(e) Working in areas containing exposed live high voltage and extra high voltage
conductors;
(f) Demarcation of work areas;
(g) Working on remotely controlled and automatically controlled equipment;
(h) Working on equipment operated by or containing compressed air;
(i) Working on circuit breakers, transformers, isolators, surge arresters,
instrument transformers, storage tanks etc.;
(j) Handling failed SF6 circuit breaker;
(k) Working on or near to low, medium, high voltage and extra high voltage
equipment;
(l) Procedure for adding or removing equipment to or from the extra high
voltage and high voltage system.
[7. Safe storage, handling and Installation of various electro-mechanical equipment as
per recommendations of manufacturers.]17
(B) Additional requirements applicable for thermal generating stations:
1. Safety in conveyors, belts, cableways etc.;
2. Safety in storage and handling of materials.
(C) Additional requirements applicable for hydro-electric generating stations:
Schedule- III
[See regulation 9(2)]
(10) The coupling device shall be suitable for outdoor mounting and shall be fitted on the
steel structure and the temperature of metallic equipment mounted outdoor is expected
to rise up to 65 deg. C with ambient temperature of 50 deg. C.
(11) High frequency cable shall be provided to connect coupling unit installed in the sub-
station to the power line carrier communication terminals installed indoors, and values of
attenuation per km of the cable shall be as per the following Table, namely: -
TABLE
CHAPTER VI
CELLULAR COMMUNICATION
28. Requirements of cellular communication.-(1) Cellular communication may be
used for data acquisition system, where feasibility of access to wideband network is
not possible.
(2) Cellular communication shall be adopted after ensuring the available signal level
up to the required strength and dual or more Subscriber Identification Module (SIM)
with different service provider with automatic changeover to ensure 99.5 per cent. link
availability for interruption free operation of the communication system.
(3) Design shall be for satisfactory and continuous operation in open environment
with operating temperature range of -10 deg. C to 55 deg. C and humidity up to 95 per
cent. noncondensing.
(4) Field interface shall be optical port / RS232 / RS485 / RJ45 IP or any other
suitable port.
(5) Receiving device shall support International Electro-Technical Commission (IEC)
- 60870 -5- 101 and International Electro-Technical Commission (IEC) – 60870 -5- 104
protocol and Device Language Message Specification (DLMS) (IS15959/IEC 62056),
Modbus for interfacing.
(6) Receiving end shall have Multi Wide Area Network Virtual Private Network
(WAN VPN) concentrator with built-in facility to manage at least 250 remote nodes for
a fixed IP provided for control center.
(7) Receiving end shall have redundant Multi Wide Area Network Virtual Private
Network (WAN VPN) Concentrator with a fail over – fall back feature for uninterrupted
data communication.
(8) Router shall be capable of handling Virtual Private Network (VPN) based security
by assuming a fixed IP issued by the Multi Wide Area Network Virtual Private Network
(WAN VPN) concentrator at the supervisory control and data acquisition (SCADA)
end.
(9) Device shall have the capability of data encryption with Triple Data Encryption
Standard (3-DES) or Advanced Encryption Standard (AES) 128 or latest to ensure
secured communication network over broadband, 2G or 2.5G or 3G or 4G or 5G or
latest.
CHAPTER VII
VERY SMALL APERTURE TERMINAL COMMUNICATION
29. Requirement for very small aperture terminal. - (1) Very small aperture terminal
communication shall be used for supervisory control and data acquisition (SCADA)
control functions of power system operation and shall not be used for primary
protection function of power system as geo-stationery satellite hop delay is 240
milliseconds.
(2) Very small aperture terminal shall be able to work with all geostationary satellites
to the extent possible, visible from India and work efficiently from all parts of India.
(3) Very small aperture terminal shall work either on Ku-band or C-band or extended C
band or any other band for interruption free continuous operation in extremely rainy
(more than 10 millimeter/hour intensity) and cloudy conditions.
(4) Very small aperture terminal communication shall be adopted after ensuring link
availability of 99.5 per cent. and required level of signal strength.
(5) Very small aperture terminal communication shall not be part of national or State
wideband backbone network.
(6) All regulatory clearance from regulatory bodies shall be taken to operate the very
small aperture terminal communication.
(7) All regulatory guidelines including size of the antenna shall be followed.
(8) Pool band width feature shall be adopted for the very small aperture terminal
network.
CHAPTER VIII
RADIO FREQUENCY COMMUNICATION
30. Requirement of radio frequency communication. - (1) Radio frequency (RF)
communication shall be used below 132 kilovolt / 110 kilovolt system for low speed
data acquisition system and shall not be used for protection of power system equipment.
(2) Radio frequency (RF) communication shall be adopted after ensuring required level
of signal level with clear line of sight and link availability (99.5 per cent.) for
interruption free operation of the communication system.
(3) Radio frequency (RF) communication shall be designed for satisfactory and
continuous operation in open environment with operating temperature range of -10 deg.
C to 55 deg. C and humidity up to 95 per cent. non-condensing.
(4) Radio frequency (RF) communication shall not be part of national or State wideband
backbone network.
(5) Utilisation of radio spectrum in radio frequency (RF) communication shall be
subject to regulatory clearance and all regulatory guidelines shall be followed.
(6) Radio frequency (RF) communication shall be capable of delivering data, voice and
video conferencing, and latency shall be less than 5 milliseconds (ms).
(7) Radio frequency (RF) communication equipment shall comply with Ingress
Protection (IP) rating suitable for the installation condition as agreed between the user
and provider.
(8) Radio frequency (RF) communication system shall support concurrent use of
Internet Protocol (IP), voice over internet protocol (VoIP) and video.
(9) Radio frequency (RF) communication shall be capable of channel bandwidth
selection with 5 MHz steps.
(10) Radio frequency (RF) communication shall be capable to capture both side (local
and remote) spectrum view and the equipment shall have site and link management
facility for configuration.
(11) Radio frequency (RF) communication shall support Simple Network Management
Protocol (SNMP), Management Information Base (MIB) II and Bridge Management
Information Base (MIB).
(12) After terminating the radio frequency (RF) network at the gateway, the upstream
communication till the receiving end control centre shall comply to IPv4 and IPv6
Analog 4 5 6 4 5 7
Value
Phasor Analog/Sta 0.04 to 0.04 to
tus 0.01 0.01
Forecast/ Value 60 60
Video H.323
Cellular GPRS/3G/4G/ ETSI, 3GPP Compliant
NBIoT/MPLS
MPLS-TP: G.8110,8112,8113.1,8113.2,8121,8121.1,8121.2,8131,8151,81
52.
MPLS-IP: As per standard Industry practice.
(a) Generator star point : Through dry type distribution transformer with
secondary loaded with a resistor.
(b) Generator transformer, Station : Solidly earthed.
transformer – high voltage
winding star point
(c) 33kV,11kV, 6.6kV or 3.3 kV : Through a resistance in case of star connected
system windings;
or
Through artificial transformer with its
secondary loaded with resistor in case of delta
connected windings.
(d) 415 V system : Solidly earthed.
(e) DC system : Unearthed.
(9) Earthing system.─
(a) the earthing system shall be designed for a life expectancy of at least forty
years and for maximum system fault current or 40 kA for 1.0 sec, whichever
is higher;
(b) the minimum rate of corrosion of steel used for earthing conductor shall be
considered as 0.12 mm per year while determining the conductor size;
(c) grounding and lightning protection for the entire Station shall be provided in
accordance with relevant Indian Standard or Institute of Electrical and
Electronics Engineers Standards.
(10) Protection system.─
(a) fully graded protection system with requisite speed, sensitivity and selectivity
shall be provided for the entire station and shall be designed to avoid mal-
operation due to stray voltages:
Provided that the generator, generator transformer, unit auxiliary
transformer shall be provided with protection systems connected to two
Gas Turbine rating (ISO) Gross Heat Rate of CCGT module (on
HHV basis) in kcal/kWh at ISO conditions
with natural gas as fuel at 100% load
20 MW to 30 MW 2250
> 30 MW to 200 MW 1825
> 200 MW 1700
15. Gas Turbine and Auxiliaries.─ (1)The gas turbine and auxiliaries shall comply
with latest versions of applicable codes of International Organization for
Standardization or American Society of Mechanical Engineers.
(2) The gas turbine compressor shall have a stable aerodynamic characteristic
throughout its operating regime:
Provided that the operating point in the entire frequency range of 47.5 to 51.5
Hz shall be sufficiently away from surge line so that it is stable at all conditions of
load, ambient temperature and blade fouling.
(3) The compressor shall be provided with variable type inlet guide vanes to meet
start up and shutdown requirements, improved part load performance in combined
cycle mode of operation and exhaust gas temperature control over a wide range.
(4) Combustion chamber arrangement shall be such as to allow maintenance without
dismantling of compressor or turbine section and with minimum dismantling of
piping and electrical connections.
(5) NOx control shall be either through dry low NOx combustor or through steam or
water injection and shall be able to achieve the NOx level limits stipulated by
pollution control authorities.
(6) Combustion system shall be provided with flame detection system for monitoring
and protection.
(7) Gas turbine shall be provided with self contained lubrication oil system and
control oil system with adequate redundancy for pumps and coolers.
(8) Gas turbine shall be provided with an air intake filtration system along with on-
line cleaning system to deliver filtered air of acceptable quality to the gas turbine.
(9) Gas turbine generating unit shall be controlled by an electro-hydraulic governing
system with 100% back up:
(c) Gas Insulated Sub- station enclosure shall be non-magnetic type and for 400kV
and higher voltage levels, it shall be isolated phase type.
(d) The arrangement of gas sections or compartments shall be such as to facilitate
future extension on either end without any drilling, cutting or welding on
existing equipment from any manufacturer and without the necessity of
moving or dislocating the existing switchgear bays.
(e) The layout of Gas Insulated Bus Ducts shall be for easy accessibility &
maintenance and the length of bus bars, bus ducts, isolator sections shall be
optimized considering effects of fast transient voltage due to isolator
operations.
Windings Bushings
Rated power Rated Rated Rated Rated Rated
Highest frequency switching lightning power switching lightning
voltage for withstand impulse impulse frequency impulse impulse
equipment voltage withstand withstand withstand withstand withstand
(kVrms) voltage voltage voltage voltage voltage
(kVpeak ) (kVpeak) (kVms) (kVpeak ) (kVpeak )
(phase to (phase to
earth) earth)
1200 kV NA 1800 2250 1320 1950 2550
Parameter 66 110 132 220 +320 kV 400 765 +500 +800 1150
kV kV kV kV/ HVDC kV kV kV kV kV
Site Pollution Severity (SPS) class (As per IS Specific Creepage Distance (in
16683:Part-I:2018) mm/kV)
Very Light or Light or Medium 20
Heavy 25
Very Heavy 31
(b) The silicone content in composite silicone rubber insulator shall be minimum
30% by weight and RTV silicone coating, if used on any insulator, shall be in
accordance with IS 11310.
(c) Number of insulators, insulator profile, profile parameters and dimensions shall
be selected based on electrical system parameters and site specific factors like
Design RoW
Conductor Structure Type Spa String Type (in m)
n (in
m)
Commonly "I"
used Lattice type/ 250 String/Suspension 15 meter
ACSR Steel pole Tension
Bare 150 "I" 12 meter
conductor String/Suspension
Tension
Concrete 100 Pin Insulator 9 meter
Pole/Rail 60 Pin Insulator 8 meter
Pole/H Pole/
Single Steel
Pole
Covered Pole 100 6 meter
90. Electrical Design Parameters of the Electric Lines.─ (1) The electrical design
parameters of the electric lines for altitude upto 1000 m above MSL shall be as
indicated in Table 22 below:
Table 22
Parameter 33 kV 22 kV 11 kV 0. 415 kV
Nominal system voltage (kV) 33 22 11 0.415
SCHEDULE- I
[See sub-regulation (10) of regulation 10]
List of Electrical Protection Functions for Thermal
Generating Units
3. Ash handling system shall have the provision for following standby
arrangement:
(a) Bottom ash - 100% standby for drag link chain conveyor
system
(b) Fly ash - 100% standby for vacuum pumps, collector
system tanks, wetting heads;
- 100% standby blowers for intermediate
and storage silos;
- 50% standby for air compressors to be
used for transporting ash.
(c) Ash slurry One pump stream as operating standby and
disposal one pump stream as maintenance standby
for wet slurry system;
One standby stream for high
concentration slurry system.
SCHEDULE-IV
[See clause(f) of sub-regulation (12) of regulation 40]
Minimum Protections to be provided for Hydro- electric Generating Units
1. Generator
*For short line (less than 10 km) or cable or combination of overhead line and cable,
line differential protection shall be used with built-in backup distance protection.
# For cable or combination of overhead line and cable, autoreclosing shall not be
provided.
Note: (1) Y- Required; N- Not required; Y/N- Optional.
(2) Transmission lines with distance protection shall, in general, have carrier aided or
fibre optic based inter- tripping or blocking feature.
(3) Separate cores of current transformer and voltage transformer shall be used for
Main-I and Main-ll.
2. Transformer Protection
SCHEDULE-VI
(See regulation 49)
PART-A
Technical Details of Classical HVDC Terminals/ Stations
1. General: The conventional Thyristor (Gate Turn On device) based HVDC converter
(c) DC wall bushing- DC wall bushings, used for electrical connection between
the equipment inside the valve hall and the outdoor DC yard shall be of
polymer housing as per relevant standards. All bushings inside the valve hall
including HVDC wall bushing shall be dry type / SF6 gas filled or
combination of both.
(d) Smoothing Reactor- The smoothing reactor shall be of air core type. The
reactors shall comply with relevant standards and shall have successfully
passed DC tests as per their application. The smoothing reactor shall be
divided between pole and neutral for DC voltage above 500kV. Each
converter station shall be provided with one spare coil of smoothing reactor.
For the design of smoothing reactor, the Si factor has to be within the limits
(0.22 <Si< 1) where Si factor is defined as
Si= Udn/ Ld*Idn
Udn = Nominal HVDC Voltage level per pole
RoW width
Voltage Configuration Conductor type Terrain Design String Type in m (for
level Span compensation
purpose)
"I"
String 67
Normal 400 "V"
route without String
constraint Tension
Forest "V" 56
NOTIFICATION
New Delhi, the 8th June, 2023
No. CEA-PS-16/1/2021-CEI Division.—Whereas the draft of the Central
Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2022
was published in six newspaper dailies, as required by sub- section (3) of section 177 of the
Electricity Act, 2003 (36 of 2003) read with sub-rule (2) of rule 3 of the Electricity
(Procedure for Previous Publication) Rules, 2005 for inviting objections and suggestions
from all persons likely to be affected thereby, before the expiry of the period of forty-five
days, from the date on which the copies of the newspaper containing the said draft
regulations were made available to the public;
And whereas copies of the said newspapers containing the public notices and the
said draft regulations on the website of the Central Electricity Authority were made
available to the public on 14th June, 2022;
And whereas the objections and suggestions received from the public on the said
draft regulations were considered by the Central Electricity Authority;
Now, therefore, in exercise of the powers conferred by clause (b) of sub-section (2)
of section 177 and read with section 53 of the Electricity Act, 2003, and in suppression of
the Central Electricity Authority (Measures relating to Safety and Electric Supply)
Regulations, 2010, except as respects things done or omitted to be done before such
suppressions, the Central Electricity Authority hereby makes the following regulations,
namely: –
Chapter I
Preliminary
1. Short title and Commencement. – (1) These regulations may be called the Central
Electricity Authority (Measures relating to Safety and Electric Supply) Regulations,
2023.
(2) These regulations shall come into force on the date of publication in the Official
Gazette.
(3) Scope and extent of application. – These regulations shall be applicable to
electrical installation including electrical plant and electric line, and the person engaged
in the generation or transmission or distribution or trading or supply or use of
electricity.
2. Definitions. – (1) In these regulations, unless the context otherwise requires,
(a) “Act” means the Electricity Act, 2003 (36 of 2003);
(b) “accessible” means within physical reach without the use of any appliance or special
effort;
(c) “aerial bunched cable” means polyethylene or cross linked polyethylene insulated
cable having three or four cores with aluminium conductors twisted over a central
bare or insulated aluminium alloy or steel messenger wire;
(d) “apparatus” means electrical apparatus and includes all machines, fittings,
accessories and appliances in which conductors are used;
(e) “bare” means not covered with insulating materials;
(f) “bonding conductor” means the inter connecting conductors for the purpose of
(2) The following protection shall be provided in all systems and circuits to
automatically disconnect the supply under abnormal conditions, namely: –
(i) over current protection to disconnect the supply automatically if the rated
current of the equipment, cable or supply line is exceeded for a time which the
equipment, cable or supply line is not designed to withstand;
(ii) earth fault or earth leakage protection to disconnect the supply automatically, if
the earth fault current exceeds the limit of current for keeping the contact potential
within the reasonable values;
(iii) buchholz relay, pressure relief device and winding and oil temperature
protection with alarm and trip contacts shall be provided on all transformers of
ratings 1000 kVA and above;
(iv) transformers of capacity 10 MVA and above shall be protected against incipient
faults by differential protection;
(v) all generators with rating of 100 kVA and above shall be protected against earth
fault or leakage;
(vi) all generators of rating 1000 kVA and above shall be protected against faults
within the generator winding using restricted earth fault protection or differential
48. Testing, Operation and Maintenance. – (1) Before the approval is accorded by the
Electrical Inspector under regulation 45, the manufacturer’s test certificates shall, if
required, be produced for all the type, acceptance and routine tests as required under
the relevant standards.
(2) No new apparatus, cable or supply line of voltage exceeding 650 V shall be
commissioned unless such apparatus, cable or supply line are subjected to site tests as
per relevant standards.
(3) No apparatus, cable or supply line of voltage exceeding 650 V which has been kept
disconnected for a period of six months or more from the system for alterations or
repair, shall be connected to the system until such apparatus, cable or supply line are
subjected to the site tests as per relevant standards.
(4) Notwithstanding the provisions of this regulation, the Electrical Inspector may
require certain tests to be carried out before or after charging the installations.
(5) All apparatus, cables and supply lines shall be maintained in healthy conditions and
tests shall be carried out periodically as per the relevant standards.
(6) Records of all tests, trippings, maintenance works and repairs of all apparatus,
cables and supply lines shall be duly kept in such a way that these records can be
compared with the past records.
(7) It shall be the responsibility of the owner of all installations of voltage exceeding
650 V to maintain and operate the installations in a condition free from danger and as
recommended by the manufacturer or by the relevant standards.
(8) Failures of any 220 kV and above voltage level transformer, reactor and
transmission line towers shall be reported by the owner of electrical installation, within
forty eight hours of the occurrence of the failure, to the Authority and the reasons for
failure and measures to be taken to avoid recurrence of failure shall be sent to the
Authority within one month of the occurrence in the forms provided in Schedule VII:
Provided that in case of mines and oil-fields, the failure of 10 MVA or above
transformers shall be reported to Electrical Inspector of mines.
49. Precautions to be taken against excess leakage in case of metal sheathed electric
supply lines. – The following precautions shall be taken in case of electric supply lines
other than overhead lines, for use at voltage exceeding 650 V, namely: –
(i) the conductors of the cable except the cable with thermoplastic or cross linked
polyethylene, insulation without any metallic screen or armour shall be enclosed in
metal sheathing which shall be electrically continuous and connected with earth, and
the conductivity of the metal sheathing shall be maintained and reasonable
Explanation. – For the purposes of this regulation “shock proof”, as applied to X-ray
and high-frequency equipment, shall mean that such equipment is guarded with
(i) the overhead conductors of voltage exceeding 650 V but not exceeding
33 kV, unless suitably guarded against personal contact, shall be adequately
spaced and high voltage leads on tilting tables and fluoroscopes shall be
adequately insulated or so surrounded by barriers as to prevent inadvertent
contact;
(ii) the circuit of voltage not exceeding 250 V of the step up transformer shall
contain a manually operated control device having overload protection, in
addition to the over current device for circuit protection, and these devices shall
have no exposed live parts and for diagnostic work there shall be an additional
switch in the said circuit, which shall be of one of the following types:-
(a) a switch with a spring or other mechanism that will open
automatically except while held close by the operator; or
(b) a time switch which will open automatically after a definite period of
time for which it has been set;
(iii) if more than one piece of apparatus be operated from the same source of
voltage exceeding 650 V, each shall be provided with a switch of voltage
exceeding 650 V to give independent control;
(iv) low frequency current-carrying parts of a machine of the quenched-gap or
open gap type shall be so insulated or guarded that they cannot be touched
during operation but the high frequency circuit- proper which delivers high-
frequency current normally for the therapeutic purposes shall be exempt from
such insulation;
(v) all X-ray generators having capacitors shall have suitable means for
discharging the capacitors manually; and
(vi) except in the case of self-contained units, all 200 kV peak or higher X-ray
generators shall have a sphere gap installed in the system of voltage exceeding
650 V but not exceeding 33 kV adjusted so that it will break down on over
voltage surges.
(3) (i) all non-current carrying metal parts of tube stands, fluoroscopes and other
apparatus shall be properly earthed and insulating floors, mats or platforms shall
be provided for operators in proximity to parts of voltage exceeding 650 V unless
such parts have been rendered shock proof; and
(ii) where short wave therapy machines are used, the treatment tables and
examining chairs shall be wholly non-metallic.
(4) The owner of any X-ray installation or similar high frequency apparatus shall not
bring the same into use without giving to the Electrical Inspector not less than fourteen
days‟ notice in writing of his intention to do so:
Provided that the aforesaid notice shall not be necessary in the case of shock-
proof portable X-ray and high-frequency equipment which have been inspected before
the commencement of their use and periodically thereafter.
Chapter VII
Safety requirements for overhead lines and underground cables
57. Material and strength. – (1) All conductors of overhead lines other than those
(3) The minimum factor of safety shall be based on such load as may cause failure of
the support to perform its function, assuming that the foundation and other components
of the structure are intact.
(4) The load shall be equivalent to the yield point stress or the modulus of rupture, as
the case may be, for supports subject to bending and vertical loads and the crippling
load for supports used as strut.
(5) The strength of the supports of the overhead lines in the direction of the line shall
not be less than one-fourth of the strength required in the direction transverse to the line.
(6) The minimum factor of safety for stay-wires, guard-wires or bearer-wires shall be
2.5 based on the ultimate tensile strength of the wire.
(7) The tension limit for conductor and earth wire shall be as per relevant standards.
(8) For the purpose of calculating the factors of safety in sub-regulation (2), the
following conditions shall be observed, namely: –
(i) the maximum wind pressure shall be as specified in the relevant standards;
(ii) for cylindrical bodies the effective area shall be taken as full projected area
exposed to wind pressure; and
(iii) the maximum and minimum temperatures shall be as specified in the relevant
standards.
(9) Notwithstanding anything contained in sub-regulation (2) to (8), in localities where
overhead lines are likely to accumulate ice or snow, the load and permissible stresses on
the structural members, conductors and earth wire of self supporting steel lattice towers
(2) In any case of a crossing specified in sub-regulation (1), whoever lays his overhead
line later, shall provide the clearance between his own overhead line and the overhead
line which will be crossed in accordance with the provisions of the sub-regulation (1):
Provided that if the later entrant is the owner of the lower overhead line and is
not able to provide adequate clearance, he shall bear the cost for modification of the
upper line so as to comply with sub-regulation (1).
62. Clearance from buildings of lines of voltage and service lines not exceeding 650 V.
– (1) An overhead line shall not cross over an existing building as far as possible and
no building shall be constructed under an existing overhead line.
(2) Where an overhead line of voltage not exceeding 650 V passes above or adjacent to
or terminates on any building, the following minimum clearances from any accessible
point, on the basis of maximum sag, shall be observed, namely: –
(ii) for lines of voltages exceeding 33 kV - 3.7 metre plus 0.30 metre for
every additional 33 kV or part
thereof.
(3) The horizontal clearance between the nearest conductor and any part of such
building shall, on the basis of maximum deflection due to wind pressure, be not less
than, –
(v) for lines of voltages exceeding 33 kV - 2.0 metre plus 0.3 metre for
every additional 33 kV or part
thereof.
(vi) a person laying or proposing to lay a line which may cross or be in proximity
with an existing line, shall provide arrangements on his own line or require the
owner of the other overhead line to provide guarding arrangements as referred to in
clause (iii) and (iv);
(vii) in all cases referred to in this regulation the expenses of providing the guarding
arrangements or protective devices shall be borne by the person whose line was laid
later;
(viii) where two lines cross each other, the crossing shall be made as nearly at right
angles as the nature of the case admits and as near the support of the line as
practicable, and the support of the lower line shall not be placed in the right of way
of the upper line; and
(ix) the guarding arrangement shall be carried out by the owner of the support on
which it is made and he shall be responsible for its proper maintenance.
72. Guarding. – (1) Where guarding arrangement is required under these regulations,
the following shall be observed, namely: –
(i) every guard wire shall be connected with the earth at each point at which its
electrical continuity is broken;
(ii) every guard wire shall have an actual breaking strength of not less than 635 kgf
and if made of iron or steel, shall be galvanised; and
(iii) every guard wire or cross-connected system of guard wires shall have sufficient
current carrying capacity to ensure them rendering dead, without risk of fusing of the
guard wire, till the contact of any live wire has been removed.
(2) In the case of a line crossing over a trolley wire, the guarding arrangement shall be
subjected to the following conditions, namely: –
(i) where there is only one trolley-wire, two guard-wires shall be provided as
illustrated in DIAGRAM-A;
(ii) where there are two trolley wires and the distance between them does not exceed
forty centimetre, two guard-wires shall be provided as illustrated in DIAGRAM-B;
(iii) where there are two trolley wires and the distance between them exceeds forty
centimetre but does not exceed 1.2 metre, three guard-wires shall be provided as
illustrated in DIAGRAM-C;
(iv) where there are two trolley-wires and the distance between them exceeds 1.2
metre, each trolley-wire shall be separately guarded as illustrated in DIAGRAM-D;
MIN 60 cm
DIAGRAM-B DIAGRAM-C
20 cm 20 cm 20 cm 20 cm
O O
MIN MIN MIN MIN
60 cm 60 cm 60 cm 60 cm
O Upto O O Over O
40 cm 40 cm and upto 120 cm
DIAGRAM-D
20 cm 20 cm 20 Cms 20 cm
O O O O
60 cm 60 cm
O O
Over 120 cm
(v) the rise of trolley boom shall be limited such that the trolley wire shall not foul the guard
wires; and
(vi) where a telegraph-line is liable to fall or be blown down upon an arm, stay-wire or span-
wire and so slide-down upon a trolley-wire, guard hooks shall be provided to prevent such
sliding.
73. Service lines from overhead lines. – No service line or tapping shall be taken off an overhead
line except at a point of support:
Provided that the number of tappings per conductor shall not be more than six in case of
connections at voltage not exceeding 650 V.
74. Earthing. – (1) Earthing of support of overhead lines up to 33 kV shall be provided as under,
namely: –
(a) all metal supports and all reinforced and pre-stressed cement concrete supports of
overhead lines and metallic fittings attached thereto, shall be permanently and effectively
earthed by providing a continuous Page 439 of 510
earth wire and securely fastened to each pole and connected with the earth at each
support and the metallic fittings attached thereto shall also be permanently and
effectively earthed;
(b) metal cross arms and insulator pins for Plain Cement Concrete and Pre-Stressed
Cement Concrete poles shall be bonded together and normally earthed at every pole;
(c) for locations involving railways, electric line crossings and special structures,
pipe or rod type earthing shall be provided;
(d) all steel poles on which switches, transformers, fuses are mounted shall be
earthed;
(e) for poles of the electric lines below 650 V guarding arrangement with
continuous earth wire or messenger wire in case of aerial bunched cable shall be
provided and shall be connected to earth at three equidistant points in every km; and
(f) each stay-wire shall be similarly earthed unless insulator of same voltage class
as that of line has been placed in it at a height not less than three metre from the
ground and shall be provided with insulated tube up to three metre height from the
ground.
(2) For 66 kV and above voltage class overhead line, earthing and requirement of earth
wire shall be as per the regulations notified by the Authority under clause (e) of sub-
section (2) of section 177 of the Act.
75. Anti-climbing devices. – The owner of every overhead line of voltage exceeding 650
V shall make adequate arrangements as per relevant standards to prevent unauthorised
persons from climbing any of the supports of such overhead lines which can be easily
climbed upon without the help of a ladder or special appliances:
Provided that the barbed wires conforming to relavant standards for a vertical
distance of 30 to 40 cm, at a height of 3.5 metre to 4 metre from ground level or clamps
with protruding spikes at a height of 3 to 4 metre shall be provided on each pole or
tower of 11 kV line and above.
Explanation. – For the purposes of this regulation, rails, reinforced cement concrete
poles and pre-stressed cement concrete poles without steps, tubular poles, wooden
supports without steps, I-sections and channels shall be deemed as supports which
cannot be easily climbed upon.
76. Safety and protective devices. – (1) Every overhead line which is not being
suspended from a dead bearer wire, not being covered with insulating material and not
being a trolley-wire, is laid over any part of a street or other public place or in any
factory or mine or on any consumer’s premises shall be protected with earth guarding
for rendering the line electrically harmless in case its conductor breaks.
(2) An Electrical Inspector may, by notice in writing, require the owner of any such
overhead line, wherever it may be laid, to protect it in the manner specified in sub-
regulation (1) of this regulation.
(3) To prevent bird dropping on the suspension insulator strings, suitable bird guards as
per relevant standards, shall be provided on cross arms of suspension tower or
suspension pole structures, over the suspension insulator strings.
77. Protection against lightning. – (1) The owner of every overhead line, substation or
generating station which is exposed to lightning shall adopt means as per relevant
standards for diverting electrical surges to the earth due to lightning which may result
into injuries.
(2) The earthing lead for any lightning arrester shall be as short as possible and shall not
pass through any iron or steel pipe, but shall be taken as directly as possible from the
96. Application of chapter. – The regulation in this chapter shall apply only where
electricity is used in mines as defined in the Mines Act, 1952 (35 of 1952) and oil-
fields.
97. Responsibility for observance. – (1) It shall be the duty of every person in charge of
and responsible to the mine including the owner, agent, manager, engineer and
installation manager and Engineer of mine and oil-field to comply with and enforce the
regulations and it shall be the duty of all persons employed to conduct their work in
accordance with the regulations:
Provided that in case of power stations, transformer substations, converter
substations, rectifier substations and accumulator, storage stations for supplying
electricity to solely and mainly for the purpose of working of the mine or number of
mines and which do not fall in the precincts of a mine, Engineer holding a degree in
electrical engineering from university with adequate experience may be appointed as
manager of that installations.
Explanation. – For the purposes of this regulation, the word “Engineer” shall, –
(i) in the case of a coal mine, have the same meaning as assigned to it in the Coal
Mines Regulations, 2017;
(ii) in the case of a metalliferous mine, have the same meaning as assigned to it in
the Metalliferous Mines Regulations, 1961, as amended from time to time; and
(iii) in the case of an oil-field, means the Installation Manager‟ under the Oil Mines
Regulations, 2017.
98. Notices. – (1) On or before the first day of February in every year, in respect of every
mine or oil-field, returns giving the size and type of apparatus, together with such
particulars in regard to circumstances of its use as may be required, shall be sent to the
Electrical Inspector of mines by the persons specified in regulation 97 in the Form
provided in Schedule IX or, as the case may be, Schedule X, whichever is applicable.
(2) The persons specified in regulation 97, shall also give to the Electrical Inspector of
mines not less than seven days notice in writing of the intention to bring into use any
new installation in a mine or oil-field giving details of apparatus installed and its
location:
Provided that in case of any additions or alterations to an existing installation
of voltage not exceeding 650 V, immediate notice in writing shall be sent to the
Electrical Inspector of mines before such additions or alterations are brought into use:
Provided further that this regulation shall not apply to telecommunication or
signalling apparatus:
Provided also that in case of emergency which may lead to loss of life or
machinery and is detrimental to safety of mine, intimation shall be given within twenty
four hours to the Electrical Inspector of mines giving the healthiness of the apparatus
alongwith self-certification report of such additions or alterations undertaken.
99. Plans. – (1) A correct plan, on the same scale as the plan kept at the mine in fulfillment
of the requirements of the Mines Act, 1952 (35 of 1952), and Single Line Diagram of
the electrical installations from point of commencement of supply shall be available in
the office at the mine showing the position of all fixed apparatus and conductors
therein, other than lights, telecommunication or signalling apparatus, or cables for the
same.
Chapter X
Additional safety requirements for renewable generating stations
119. Additional safety requirements for renewable generating stations. – The
regulations under this chapter shall be applicable to renewable generating stations
which shall be in addition to the regulations provided from chapter I to VII.
120. Safety requirements for biomass and waste to energy installations. – All biomass
plants and waste to energy plants including Municipal solid waste or refuse derived
fuel shall comply with the safety standards as mentioned in Regulations notified by the
Authority under clause (e) of sub-section (2) of section 177 of the Act.
121. Safety requirements for solar installations. – (1) The following general safety
requirement for solar installations shall be ensured, namely: –
(i) clear pathways of minimum seventy five centimetre in width with hand rails for
roof access and emergency exit shall be provided for roof top system;
(ii) there shall be clear pathways, walkways between the rows or columns of solar
panels which is necessary for cleaning and maintenance;
(iii) cables shall be laid in trenches for ground based photovoltaic installation;
(iv) ground mounted solar installations shall be protected by fencing or other means
not less than 1.8 metre in height so as to prevent unauthorised entry;
(v) disconnection switches or circuit breakers provided in combiner boxes to
disconnect the photovoltaic system from all other conductors of the system shall be
located at a readily accessible location;
(vi) three phases on the alternating current side, and positive and negative conductor
on the direct current side shall be marked and identified with different colours;
(vii) inverter unit for solar photovoltaics shall be installed in the periphery of the
building and as near as the solar panel:
Provided that the direct current cable shall be ultraviolet protected or
routed through ultraviolet protected pipe;
(viii)there shall be a manual disconnection switch to isolate the system from grid
and shall be situated outside the alternating current combiner box; and
(ix) protection shall be deployed (for both input and output) on site for overload,
surge current, surge voltage, short circuit, high temperature, over voltage, under
voltage and over frequency, under frequency, reverse polarity and lightning.
136. Deviations. – (1) The Central Government or the State Government, as the case may
be, by an order in writing, allow deviations in respect of matters referred in these
regulations except regulation 32.
(2) The Electrical Inspector or the Electrical Inspector of mines may, by an order in
writing, and reasons to be recorded allow deviation in respect of matters referred in
regulations 14 to 19, regulation 30, sub-regulations (2), (3) and (5) of regulation 37,
sub-regulation (3) of regulation 38, clauses (i) to (iv) of regulation 39, clause (xii) of
regulation 43, regulation 45, sub-regulation (2) of regulation 46, regulations 48,
regulations 54 to 56, regulations 59 to 63, regulation 67, regulation 74, regulation 77,
regulations 81 to 94, regulation 104, sub-regulations (6), (8) and (10) of regulation 109,
regulation 116 and regulations 119 to 135 on case to case basis.
Explanation. – Every order allowing the deviations by the Electrical Inspector or the
Electrical Inspector of Mines under sub-regulation (2) shall be placed before the Central
or State Government which shall have the final decision.
Schedule I
Precautions to be observed: -
(1) Hotline maintenance trained personnel only shall be designated to do work on line.
(2) Work permit shall be taken from the terminal substations at each end of the line.
(3) Work shall be performed with proper planning and prior understanding and clarity.
(4) Favourable climatic condition for hotline operations is sunny weather. If the
weather forecasts rain or thunderstorms work will not begin.
(5) Organisation of work shall be discussed among the members and responsibility of each
team member fixed.
(6) Before going to the work site, all equipment and tools shall be inspected and checked
for correct operation.
(7) Auto re-closure shall be in `OFF‟ position for the line at both ends.
(8) The work procedure shall be discussed with the team member at the tower location and
the responsibility of each member shall be properly defined.
(9) The land in close vicinity to the tower/poles shall be cleared to provide a site area for
the required tools.
(10) All cleaned hot sticks, strain carrier and other assemblies shall be kept on the hotline
Handling high voltage direct current apparatus for carrying out shutdown work or
testing
[See sub-regulation (3) of regulation (21)]
Part-III
Precautions to be observed: -
(1) The Engineer or Supervisor in-charge of the work shall obtain proper Permit-To-Work
(PTW) from the concerned Operation In-charge(s) and ensure that the electric supply line or
apparatus or section is isolated from all sources of energy, de-energised and earthed.
(2) Before commencement of any shutdown work or testing of high voltage direct current
apparatus, the Engineer or Supervisor in-charge of the work or testing shall identify the
possible hazards, such as; electrocution, flash over, fall of person from height, fall of objects
from height, failure of tools and plants, fire, and the like, that may be encountered while
carrying out the work or testing near charged area and take necessary precaution to protect
the working personnel.
(3) The Engineer or Supervisor in-charge of the work shall, before commencement of any
work, brief the entire working group or gang of the hazards that may be encountered and the
necessary precautions to be taken by them.
(4) Attach warning labels to all neighboring installation parts (to be removed after the works
have been carried out).
(5) The Engineer or Supervisor in-charge of the work shall allow access to the valve hall,
DC Filter Area, AC Filter Area and DC hall (if any) only when the apparatus therein are
completely de-energised and effectively earthed.
(6) The work on AC/DC filter bank shall only begin after earthing the entire capacitor bank.
(7) There shall be at least ten minute time gap between earthing the entire capacitor bank
and starting the work on bank. There after unit must be short circuited.
(8) The de-energised bushing shall be checked for stored charge by touching all the surfaces
of both indoor and outdoor side composite insulators and all other parts of the bushing using
a proper test instrument.
(9) The gas pressure inside high voltage direct current through wall bushing shall be
reduced to a level prescribed by the manufacturer before starting any work or handling of
the bushing.
Handling Gas Insulated Switchgear (GIS) apparatus for carrying out shutdown work
Part-IV
Precautions to be observed: -
(1) The Engineer or Supervisor in-charge of the work shall obtain proper Permit-To-Work
from the concerned Operation In-charge(s) and ensure that the electric supply line or
apparatus or section is isolated from all sources of energy, de-energised and earthed.
(2) Operation, maintenance and repair must be carried out by trained and certified personnel
only.
(3) Before commencement of any shutdown work or testing of gas insulated switchgear
apparatus, the Engineer or Supervisor in-charge of the work or testing shall identify the
possible hazards, such as; electrocution, flash over, fall of person from height, fall of objects
from height, failure of Tools and Plants, fire, and the like, that may be encountered while
carrying out the work or testing near charged area and take necessary precaution to protect
the working personnel.
(4) The Engineer or Supervisor in-charge of the work shall, before commencement of any
work, brief the entire working group or gang of the hazards that may be encountered and the
necessary precautions to be taken by them.
(5) Wear hearing protection during operation.
(6) Take care while touching the enclosure at any time as enclosures may heat up to the
temperature of 70°C.
(7) Observe the procedures for storage, transportation, and the use of filling equipment.
(8) Wear the personal protective equipment: respirator mask (self-contained breathing
equipment if necessary), protective overall, protective gloves, safety shoes, safety glasses.
(9) Attach warning labels to all neighboring installation parts (to be removed after the works
have been carried out).
(10) Provide proper electrical clearance as required by interlocking rules. Mark e.g. main
circuits and control circuits with appropriate tags.
(11) Block off neighboring live parts with screens, insulating mats or spacer grids in order to
prevent unintended contacts.
(12) While working on any compartment in gas insulated switchgear, the immediate
adjacent compartment(s) must be also depressurised for safety of the working person.
(13) SF6 gas becomes contaminated and contains poisonous substances after events such as
arc faults. Hence, handling of SF6 in such cases must be done using proper PPEs and by a
trained personnel, preferably from the original equipment manufacturer.
(14) The switchgear installation shall not be operated if the density of SF6 gas indicated at
the density monitors is not in the operating range.
(15) Do not remove any protective covers if an assembly is energized.
(16) The Engineer or Supervisor in-charge of the work shall ensure that adequate and
appropriate local earths are fixed at the zone of working, and the earthing rods remain
connected to the isolated section of the electric supply line or apparatus or section till all
men and materials have been moved away to safe zone and Permit-To-Work is returned on
completion of the work.
Report
Date of inspection by Electrical Inspector or self-certification by
supplier/owner/consumer___________
Date of last inspection or self-certification
1. Consumer No.
2. Voltage and system of supply:
(i)
(ii)
8. General conditions of the installation:
Date:
Name
Designation
File No.
FORM II
[See Regulation (32) and (45)]
(Installations of voltage level more than 250 V up to and including 650 V)
Report / Application No.
(i)
(ii)
(b) Other equipment (complete details to be furnished):
(i)
(ii)
(c) Total connected load kW / kVA
_____________________________________________________
(d) Generators: (complete detail to be enclosed)
(iii)
(iv)
7. General condition of the installation:
Date:
(i)
(ii)
(b) Generators: (complete detail to be enclosed)
(v)
(vi)
(c) List of Motors with rating, protection, overload setting, size of earth conductor used to
be furnished Make S. No. kW/MW rating Voltage rating
Type
(iii)
(iv)
(d) List of equipment with complete details of HT /LT switchgears/ apparatus with their
rating to be furnished):
(iii)
(iv)
(e) Total connected load kW / kVA
In addition to above, following electrical equipment wise test details to be given, if applicable:
CERTIFICATE
[Under Regulation (32) and (45) of CEA (Measures relating to Safety & Electricity
Supply) Regulation, 2023]
This is to certify that the electrical installation is complete in all respects and the work
has been carried out conforming to the CEA (Measures relating to Safety & Electric Supply)
Regulation, 2023 and relevant standards. The site tests done are found to be in order and it is
electrically safe to operate the apparatus free from any danger.
File No.
To: Office of Electrical Inspector for ………………...
FORM IV
(Electrical Installations in Mine)
Report No.: Date of Inspection:
Date of last inspection: Name of the Inspecting Officer:
1. Name of the Mine:
2. Name of the Owner:
3. Name of the Agent:
4. Name of the Mine Manager:
5. Name of the Colliery Engineer:
Date:
Schedule III
Form for obtaining test results by supplier at each supply point to
consumer [See sub-regulation (4) of regulation (33)]
1. Name and address of the consumer
2. Details of installation
3. Short circuit fault level of the installation
4. Date of commissioning of installation (in case of additional supply or reconnection)
5. Results of tests conducted:
General Observations:
Date :
(Name, Signature, Designation and Seal of Authoity)
Place:
Time:
Schedule V
Minimum safety working clearances where electricity at voltage exceeding 650 V is
supplied, converted,
transformed or used
[See sub-regulation (2)(iii) of regulation (46)]
(1) The above values are valid for altitude not exceeding 1000 m. A correction factor of
1.25 per cent per 100 m is to be applied for increasing the clearance for altitude more than
1000 m and up to 3000 m;
(2) The above safety working clearances are based on an insulation height of 2.44 m
which is the height of lowest point on the insulator, where it meets the earthed metal, from
the ground;
(3) “Safety Working Clearance” is the minimum clearance to be maintained in air between
the live part of the equipment on one hand and earth or another piece of equipment or
conductor on which it is necessary to carry out the work, on the other;
(4) The “Highest System Voltage” is defined as the highest rms phase to phase voltage
which occurs under normal operating conditions at any time and at any point of the system.
It excludes voltage transients (such as those due to system switching) and temporary
Schedule VI
Minimum safety clearances to be maintained for bare conductors or live parts of any
apparatus in out- door HVDC substations, excluding overhead lines of HVDC
istallations
[See sub-regulation (3) of regulation (46)]
(1) The above ground clearances are not applicable to equipment that are housed within
fence or a building and where access is prevented under energised condition through a
suitable safety interlocking scheme;
(2) The above pole to earth clearances are for conductor-structure electrode configuration
using gap factor k equal to 1.35.
(4) Clearance shall be provided for electrical apparatus so that sufficient space is available
for easy operation and maintenance without any hazard to the operating and maintenance
personnel working near the equipment and for ensuring adequate ventilation.
Schedule VII
Part-A
Form for reporting failure of transformer & reactor of 220 kV and above voltage class
[See sub-regulation (8) of regulation (48)]
1. Name of Substation :
To,
The Secretary
Central Electricity Authority
Sewa Bhawan, R .K. Puram
New Delhi-110066
Part-B
Form for reporting failure of towers of 220 kV and above voltage class transmission
lines
[See sub-regulation (8) of regulation (48)]
Date:
New Delhi-110066
Schedule VIII A
Minimum clearance in air above ground and across road surface of Highways or
roads or railway corridors or navigational or non-navigational rivers for lowest
conductor of an alternating current overhead lines, including service lines of
nominal voltage system.
[See sub-regulation (1) of regulation (60)]
Nominal Clearance above ground Clearance Clearance between Clearance above HFL for
voltage of between conductor and rail level River crossing
system conductor across Railway Corridor
and road (m)
surface
Across Along Elsewhere across Normal High rise Navigational Non-
Street Street (m) Highway OHE OHE for river (m) navigatiional
(m) (m) (m) (where no running of river
double double stack (m)
stack containers on
containers railway
are to be tracks.
run on
railway
tracks.)
Up to 650 5.80 5.50 4.60 U/G U/G Cable U/G Cable 16.50 5.80
V Cable
11 kV 6.50 5.80 4.60 U/G U/G Cable U/G Cable 19.00 6.50
Cable
22 kV 6.50 5.80 5.20 U/G U/G Cable U/G Cable 19.00 6.50
Cable
33 kV 6.50 5.80 5.20 11.60 or U/G Cable U/G Cable 19.00 6.50
U/G
Cable
66 kV 6.50 6.10 5.50 11.60 or U/G Cable U/G Cable 19.00 6.50
U/G
Cable
110 kV 6.50 6.10 6.10 11.60 15.56 17.56 19.00 6.50
132 kV 6.50 6.10 6.10 11.60 15.56 17.56 19.22 6.50
220 kV 7.02 7.02 7.02 12.52 16.46 18.46 20.10 7.02
400 kV 8.84 8.84 8.84 14.00 18.26 20.26 21.90 8.84
765 kV 18.00* 18.00* 18.00* 18.80 21.86 23.86 25.55 18.00
1200 kV 24.00* 24.00* 24.00* 30.00 25.46 27.46 29.90 24.00
1. Highway clearances required 4.75 m higher then ground clearances (considering the
vehicle hight is 4.75, as mentioned in the Indian Road Congress documents, 1983).
2. # Railway clearances required 10% higher value than HVAC values (HVAC values are
mentioned in Indian Railway document: IRSOD, 2004).
3. Navigational River clearances as mentioned in the Regulation of Inland Waterways
Authority of India (Classification of Inland Waterways in India), Regulation, 2006.
Schedule IX
Lighting:
Power:
(3) Particulars of motor etc.: -
POWER
(a) On Surface
(b) In Mine
(c) Lighting
Year ending:
Name of Oil-field: State:
Situation of Oil-field: District:
Postal address of Oil-field:
Name of agent:
Name of manager:
Name of engineer:
Name of Electrical Supervisor:
Part B
(1) System of supply (whether direct current or alternating current): Voltage of supply:
Periodicity (if alternating current): Source of supply:
(2) Voltage at which electricity is used for: -
Lighting:
Power:
(3) Particulars of motor etc.: -
(a) On wells
Type and rating of motor Purpose for which used Identifying mark on map
1 2 3
(4) Other electrical appliances, not including in item 3, in use on the field: -
Appliances type and size in KW Purpose for which used Identifying mark on map
Signed
Examined by
Electrical Supervisor:
Engineer:
Manager.
*State which apparatus has been examined or tested and its result.
Note: - This log sheet should be filled in as completely as possible. If, for instance, there are no
defects of insulation to report, the word ‘none’ should be written in the vacant space.