Design of Water Treatment Plant .. 100 M 3

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 10

DESIGN A WATER TREATMENT PLANT (100m3/hr

Design Assumptions
Pumping time 16 hr/day
Flow rate 100 m3/hr
Clear water (qav) 0.02777777777778 m3/s
Raw water (qav) 0.02777777777778 m3/s
surface loading rate ≤ 0.5m3/m2/hr ̶ 4.5m3/m2/hr
therefore assumed = 0.8m3/m2/hr

number of tanks = 2

Depth of tank = 2 m

total depth = 2 ⁺

= 2.5 m

Retention time = 3 hrs

SEDIMENTATION TANK

Capacity of 1 tank
= design flow X Retention time

= 150 m3/hr

Volume of 1 tank

= area X

150 = π/4D2 X

76.3943727033152 = D2

D = √76.3943727
Diameter = 8.740387445 m

surface area of 1 tank

= volume of 1 tank
height of tank

60 m2

Surface loading rate

= 0.833333333333333 m3/m2/hr

RAPID SAND FILTER

Assume filter loading rate ≤ 5m3/ m2/hr ̶ 7m3/m2/hr


= 6 m3/m2/hr

Depth of filter = 3.5 ⁺

= 4

Water losses during backwash

assumed 3% of filtered water used for backwash

Filtered water required per day

= flow rate x

= 100 x

= 1600 m3/day

= 1648 m3/day

Assume time required to do backwash per day


= 0.5 hrs

Assumed operating hours per day

= 16 hrs

Quantity of filtered water per hour


= filtered water required per day /(16- 0.5 )

106.322580645161 m3/hr

Filter area required


= quantity of filtered water per hour

= 17.7204301075269 m2

Assumed number of filters


= 2

Single filter area = filter area required /


8.86021505376344 m2

diameter of filter = √A/(π*0.25)

= 3.86021505 m

Area of rectangular tank


A = 3B2

therefore B = √A/3
= √8.860215054/3
= 1.71854735690383 m
L = 5.1556420707115 m
Depth of sand = 6.70233469192495 m
Total Area Req = 17.7204301075269 m2
= 0.00177204301075269 Ha
0.5

height

2.5
OK

0.5 freeboard

Operating time

16

x 1.03
÷ filter loading rate

assumed number of filters


UNDER-DRAINAGE SYSTEM
Given Data
Total Area of holes = 0.30%
0.3%of bed area = 0.3 X 17.72043
100
= 0.053161 m2

Area of lateral = 2(area of holes of laterals)

Area of manifold = 2(area of laterals)


= 4 X area of holes
= 0.212645 m2

Diameter of manifold = (4 X Area/π)1/2


= 0.520384 m
= 52.03838 cm 0.520384 m

Assume c/c of lateral = 25 cm 0.25 m


Assumed depth of sand = 55 cm 0.55 m

Total Numbers = 55 length of fliter = 5.2 = 20.8


0.25 spacing 0.25 21

= on either side

Length of lateral = 1.718547 - 0.520384


2 2
= 0.599082 m

Cross-sectional Area of lateral = 2(area of perforations per lateral. Take dia of holes (13mm)

= π D2
4
= 132.7857
= 0.013279
= 0.026557
range of dia holes
Number of holes = n.π(1,3) 2
0.053161 m2
4 531.6129 cm2

n = 4 x 531.6129
π x (1.3)2

= 400.354
= 405

Number of holes per lateral = number of holes


numer of laterals

= 405
42

= 9.642857

= 10

Area of perforations per lateral = 13 x π (1,3)2


4

17.26214 cm2

Spacing of holes = length of lateral


number of holes per lateral

= 0.599082
10

= 0.059908 m

C.S area of lateral = 2x area of perforations

2x 17.26214

34.52429 cm2

Diameter of lateral = (4 x area/π)1/2

= 6.629629 cm 0.066296 m

CHECK: length of lateral < 60d

0.599082 < 60 x 0.066296

0.599082 < 3.977778 Hence acceptable

Rising washwater velocity in bed = 80 cm/min

Washwater discharge/bed = (0.80/60) x 1.718547 x 5.155642


= 0.118136 m3/s

Velocity of flow through lateral = 0.118136


total lateral area

= 0.814721 m/s

Manifold velocity = washwater discharge/bed


C.S.A

= 0.118136
0.345243

= 0.342183 m/s

WASHWATER GUTTER

Dis
on either side

area

3.142857

1.69