Microsoft Project 2010 Manual EDGESCOM
Microsoft Project 2010 Manual EDGESCOM
Microsoft Project 2010 Manual EDGESCOM
Course Material
This page is blank for printing purposes
Table of Contents
THEORY OF PROJECT MANAGEMENT ............................................................................ 1
UNDERSTANDING PROJECT MANAGEMENT .............................................................................. 1
MICROSOFT PROJECT LANGUAGE ................................................................... 2
NON-CRITICAL TASKS ................................................................................... 2
CRITICAL TASKS ........................................................................................... 2
CRITICAL PATH............................................................................................ 3
TERMINOLOGY ............................................................................................ 4
GUIDE INFORMATION........................................................................................................... 7
INTRODUCTION ........................................................................................... 7
HOW TO USE THIS GUIDE............................................................................. 7
OBJECTIVES ................................................................................................ 7
INSTRUCTIONS ............................................................................................ 7
THE PROJECT SCREEN........................................................................................................... 8
PROJECT WINDOW COMPONENTS ................................................................ 10
GROUPS .................................................................................................. 12
TOOLBARS ............................................................................................... 12
STATUS BAR ............................................................................................. 14
TASK PANE .............................................................................................. 14
USING THE QUICK ACCESS TOOLBAR ..................................................................................... 14
ABOUT THE DEFAULT BUTTONS ................................................................... 15
ADDING BUTTONS ..................................................................................... 15
REMOVING BUTTONS ................................................................................. 16
ABOUT RIBBONS ............................................................................................................... 16
COMMAND TABS ...................................................................................... 17
CONTEXTUAL TABS .................................................................................... 18
FURTHER BUTTON OPTIONS ........................................................................ 19
THE FILE TAB.................................................................................................................... 19
SAVE....................................................................................................... 19
SAVE AS .................................................................................................. 20
OPEN ...................................................................................................... 20
PRINT ..................................................................................................... 21
-i -
Project 2010 Introduction Understanding Project Management
Page ii
Project 2010 Introduction Understanding Project Management
Page iii
Project 2010 Introduction Understanding Project Management
SETTING DURATIONS.................................................................................. 73
MILESTONES ............................................................................................ 73
LINKINGTASKS .................................................................................................................. 74
METHODS OF LINKING ............................................................................... 75
DEFINING THE SUMMARY TASKS .......................................................................................... 77
CREATE SUMMARY TASKS ........................................................................... 77
THE PLANNING WIZARD ............................................................................. 78
2010 METHOD FOR SUMMARY TASK ENTRY.................................................. 79
MOUSE ................................................................................................... 79
RESOURCES ...................................................................................................................... 80
DEFINE THE RESOURCES ............................................................................. 80
REVIEWING AND NAVIGATING THE RESOURCE SHEET ....................................... 81
ADDING RESOURCES TO THE RESOURCE SHEET ............................................... 81
THE RESOURCE INFORMATION DIALOG .......................................................... 83
PRACTICE ADDING RESOURCES..................................................................... 84
VIEW RESOURCES.............................................................................................................. 85
THE RESOURCE SHEET ................................................................................ 85
THE RESOURCE GRAPH ............................................................................... 86
ALLOCATE/ASSIGN RESOURCES .................................................................... 88
EDITING RESOURCE INFORMATION ....................................................................................... 90
EDITING DATA ENTERED BY THE USER .......................................................... 90
INSERTING AND DELETING RESOURCES .......................................................... 90
WORKING WITH RESOURCES ON THE FLY ...................................................... 91
UPDATING RESOURCE INFORMATION ON THE FLY ........................................... 92
OVER ALLOCATIONS ........................................................................................................... 93
RESOURCE LEVELLING................................................................................. 93
PLANNED TIME SCALE (BASELINES) ....................................................................................... 95
BASELINE ................................................................................................. 95
SET AND CLEAR A BASELINE ........................................................................ 95
USING GANTT CHARTS ....................................................................................................... 97
GANTT CHART PRINCIPALS .......................................................................... 97
CHANGING THE SPLIT BETWEEN CHART AND TABLE ......................................... 97
TIME SCALE.............................................................................................. 98
THE TIMELINE NEW FEATURE............................................................................................... 99
Page iv
Project 2010 Introduction Understanding Project Management
Page v
Project 2010 Introduction Understanding Project Management
Page vi
Project 2010 Introduction Understanding Project Management
In Microsoft Project, however complex your project may be, you can vary only
information regarding tasks or resources. The information you provide is fed into the
“Black Box” or algorithm, to provide you with a schedule in the form of a Gantt chart,
Network Diagram Chart, or Resource Graph. In summary, the seven or eight parameters
that you enter result in output that is a schedule displayed on various views and forms.
Non-Critical Tasks
In the illustration above, two tasks have a relationship. Task A is the PREDECESSOR TASK,
and Task B is the SUCCESSOR TASK. Both of these tasks are considered to be NON-CRITICAL
because they both have flexibility. Let’s focus on Task A. EA marks the earliest possible
time Task A can start. SS marks the scheduled start time for Task A. By default, all tasks
are scheduled to start at the earliest possible time, unless you specify otherwise. In the
example above, Task A is scheduled to start later and therefore has been delayed. SE
marks the scheduled end time for Task A, and LE marks the latest possible time Task A
can end. Both of these tasks have SLACK. (the amount of time a task can slip before it
affects another task’s dates or the project finish date.) FREE SLACK is the amount of time
Task A can be delayed before affecting the start time of Task B, and TOTAL SLACK is the
amount of time that Task A can be delayed before affecting the finish date of the
project.
The SUMMARY TASK summarizes Tasks A and B.
Critical Tasks
CRITICAL TASKS, not shown above, have no slack; therefore, delaying this type of task
would mean delaying the project.
Critical Path
A CRITICAL PATH is a series of critical tasks. All tasks on a critical path must be completed
on time for the project to finish on time. If one task on a critical path is delayed, then the
project is delayed. In Microsoft Project, a critical path is shown on the Gantt chart and
the Network Diagram Chart in red.
Terminology
Term Usage
ALAP Refers to a task that should be started ‘As Late As Possible’, using
all the free-float time available.
ASAP Used to indicate a task that should be started ‘As Soon As Possible’,
taking into account the start date of the project and its
predecessor tasks.
Baseline The original project plan, including the time schedule and resource
and cost allocations. The baseline is used for comparing projected
values to actuals, and facilitates the tracking and analysing of a
project’s progress.
Cost Variance A project tracking function recording the difference between the
budgeted cost of the work performed and the actual cost. Values
below the baseline show an overspend and positive values denote
cost savings.
Critical Path The sequence of tasks or activities whose schedules and durations
directly affect the date of overall project completion.
Float (slack) The amount of time by which a non-critical task can be delayed
before it affects another task’s schedule.
Hammock Task A task whose duration is calculated based on the time span
between its predecessor and successor activities.
Histogram A bar chart that shows resource workloads over a time period.
Lag The amount of time between the finish of a predecessor task and
the start of a successor task.
Lead The amount of time that a task is permitted to start before its
predecessor is finished.
Loading(back) A loading pattern that allocates resource usage as late in the task
as possible.
Loading (contour) The contour-loading pattern assesses which resources are left over
after allocation to the critical tasks and spreads these resources
among the remainder.
Loading(uniform) This loading pattern allocates the resource usage on a by day basis
in a task. This will usually be done without causing any one task to
be over committed.
Negative float Refers to an unscheduled delay before an actual task start time
that must be recovered if the project is not to be delayed.
Network Diagram Project Evaluation and Resource Tracking charts, also called
network diagrams. Network Diagrams are a graphical depiction of
task dependencies, and resemble flow charts. Dependencies are
shown by connecting lines or arrows indicating the work flow.
Resource Driven Task durations determined by the program and based on the
number of an allocation of resources, rather than the time 5
WBS codes Work Breakdown Structure codes are used to identify tasks in a
hierarchy. Many project management applications associate these
codes with an outline structure. WBS codes can be used to filter
the project schedule for tracking and reporting purposes.
Guide Information
Introduction
Project 2010 is a powerful application that allows you to plan, resource, manage and
report on a project no matter how large, it contains calculations, graphs. Project to web
data and SharePoint information is available to be built in to the project file so that the
project can be managed across continents via the internet or intranet allowing the use
of a central pool of common resources to enable the project managers to efficiently
interact and plan through project difficulties.
Objectives
Sections begin with a list of objectives each with its own check box so that you can mark
off those topics that you are familiar with following the training.
Instructions
Those who have already used a Project file before may not need to read explanations on
what each command does, but would rather skip straight to the instructions to find out
how to do it. Look out for the arrow icon which precedes a list of instructions.
Keyboard
Keys are referred to throughout the manual in the following way:
ENTER – Denotes the return or enter key, DELETE – denotes the Delete key and so on.
Where a command requires two keys to be pressed, the manual displays this as follows:
CTRL + [P] – this means press the letter “p” while holding down the Control key.
Commands
When a command is referred to in the manual, the following distinctions have been
made:
When Ribbon commands are referred to, the manual will refer you to the Ribbon –
E.G. “Choose HOME from the Ribbons and then B for bold”. 7
When dialog box options are referred to, the following style has been used for the text –
E.G. “In the PAGE RANGE section of the PRINTdialog, click the CURRENT PAGE option”
Dialog box buttons are emboldened – “Click OK to close the PRINTdialog and launch the
print.”
Notes
Within each section, any items that need further explanation or Points for extra
attention devoted to them are denoted by shading. For example:
“Project will not let you close a file that you have not already saved changes to
without prompting you to save.”
Or
“Project will not let you close a file that you have not already saved changes to
without prompting you to save.”
CLOSE BUTTONThis button is used to close a window. If you click the close button for a
document window you close the document. The last button will close the Project
application.
DIALOG BOX LAUNCHER this button launches dialog boxes specific to the part of the
ribbon you see them the category will be named such as FONT, CLIPBOARD, etc
BACKSTAGE VIEW – FILE RIBBON is the start of Project and has many important
commands and option. Such as Project settings, opening, saving, printing and closing
files. This will be looked into much further later in the manual.
Mouse
Click the left mouse button on the required tool.
Dialog Box
To open a dialog box use the DIALOG BOX LAUNCHER when the dialog box is open, make a
choice from the various options and click OK in the dialog box. If you wish to change your
mind and close the dialog box without making a choice then click on CANCEL. The dialog
box will close without any choice being applied. If you would like help while the dialog
box is open then click on the “?“In the top right hand corner this will bring up a help
window that will display the relevant topics.
10
Dialogue Box
Launcher
11
Groups
Look at a group type on the ribbon such as font and in the bottom right hand corner of
that group you may see a small box with an arrow, clicking this is the method to call up a
dialogbox as mentioned. Within the group clicking on a drop down arrow will give access
to a menu, any choice with three dots after it as in “more tables…” is another way of
opening a dialog box.
Toolbars
There are only two toolbars within the new version of Project 2010 there is the Quick
Access toolbar seen here next to the FILE tab, and there is the mini toolbar
Customising
menu for toolbar
Backstage View
(File Tab) Quick Access
Toolbar
Mini Toolbar
Whenever text is selected within Project a small formatting toolbar will appear above
the highlighted text it will disappear if the mouse cursor is moved away from the toolbar
and will reappear when the mouse cursor is moved over the highlighted text again.
12
13
Status Bar
The Status bar, across the bottom of the screen, displays different information at
different times. To the right is an indicator, which will display which view you are
currently in and there are quick options to see which views are available and to change
the view you are in E.G.Gantt chart, resource sheet, team planner etc..
The Status bar information about the status of Project, if any particular lock keys are
enabled on your keyboard, which view is currently active, and more.
Task Pane
A task pane is a window that collects commonly used actions in one place. The task pane
Generallyenables you to quickly create or modify a file, perform a search, or view the
clipboard the task pane is not used as much in Project as the needs of the application
are different. It is a Web-style area that you can either, dock along the right or left edge
of the window or float anywhere on the screen. It displays information, commands and
controls for choosing options.
A task pane is displayed automatically when you perform certain tasks, for example
when you choose Task Inspector from the TASK, Ribbon, to inspect your project for
problems.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-8: TASK PANE SHOWING TASK INSPECTOR
In the previous lesson, we introduced the new layout changes to Project 2010. In this
section, we will learn a little bit more about each part of the new interface and how it
works. This lesson will focus on features and customization options available with the
Quick Access toolbar, located in the upper left-hand corner of the screen:
Adding Buttons
As you become more familiar with Project you might find it handy to have another
command quickly available for use. Though the command tabs and ribbon significantly
reduce the number of clicks it takes to do something, you might want to have a
particular command always available. Project allows you to add the command to the
Quick Access toolbar.
For example, some of us have difficulty with spelling. Fortunately, many programs
(including Project) feature a spell checking feature. In Project 2010, the spell checking
feature is located in the PROOFING section of the PROJECT command tab:
15
Mouse
Right-click the SPELLING command and click 'ADD TO QUICK ACCESS TOOLBAR:'
The command (denoted by the small ‘ABC’ icon) will be placed in the QUICK
ACCESS toolbar:
Removing Buttons
If you no longer use a certain command or your Quick Access toolbar is getting a bit too
filled with icons, you can remove them easily at any time.
To Remove A Button
Mouse
Right-click on any icon you no longer use and click REMOVE FROM QUICK ACCESS
TOOLBAR:
About Ribbons
One of the biggest changes in Project 2010 is the removal of menus. Instead of having a
list of menu commands to choose from (including a number of options that are greyed
out and not Accessible), Project 2010 features a more intuitive control system of tabs.
16
Each tab contains a certain group of commands relevant only to the tab. The commands
are listed in the ribbon.
In the past, the Office package made use of menus that contained a listing of commands.
At their core, the command tabs are essentially the same thing as menus but with a few
big changes. For starters, the grouping of commands in tabs is much more intuitive. The
commands listed under each tab are also the only commands that are applicable to your
current view of the Project file.
Project 2010 takes this one step further with the addition of contextual tabs. The tab
labelled FORMATis a subset of the GANTT CHART TOOLS and appears only when you have
selected view with the Gantt chart. These tabs will contain even more specific
commands that can be used on a table being viewed and will only be visible when a
table is being viewed.
Consider the TASK ribbon tab that is selected in the diagram above. Beneath the tab is a
listing of all commands that are performed most often on the currently selected object,
contained in what Microsoft refers to as the ‘ribbon’:
The ribbon was designed to allow access to all functionality of a tab at once. Also, the
commands in the ribbon are only the commands that are available for use at the time.
We will learn in this lesson how the ribbon works and some of the tools that are
available.
Command Tabs
There are two main types of ribbons: general (or command) and contextual. The general
ribbons (and corresponding tabs) are always visible when you are viewing a Project file
in Project:
Along the top of the window are the command tabs:
The command tabs listed here include many of the most common commands you will
perform in Project. The Task ribbon contains the majority of the most common tasks
relating to your project.to switch views, formatting, and informational tools for the
tasks.
If you want to make a new Project file, Save it or open an existing one, click the File tab
and select what you wish to do. The views tab gives you control of the many ways you
17
may view your information in Project, Using tabs saves the need of remembering which
menu to choose.
Contextual Tabs
Contextual tabs appear only when a certain type of Project file object is selected (or
brought into context). For example, if you are looking at a Gantt chart and wish to
format it or adjust it in any way then use the GANTT CHART TOOLS, format tab:
When using a command in the ribbon, simply click it with your mouse. The command
will be performed, or the appropriate tool or dialog box will appear to help you perform
the task.
18
Save
19
Saves any modifications you have made to the current database object.
Save As
Opens the save as window and allows you to save the currently open Project under
another name. This is useful if you want to perform a major revision or update to a
particular Project file. (Figure 1-23)
Open
Opens a dialog box allowing you to search your computer or network for a file.
20
Blank Project
At the Top of the window is a link to create a new Blank Project. Use this link to make
your own Project from scratch.
21
Available Templates
In the main part of the Project window are the accessible Template panes: Project has a
number of templates built right into the program. To access those click on the sample
templates. The different categories of templates are from office online and will show
those templates you can download from the internet, simply click a category to see the
available template files.
22
Mouse
Select my templates. A dialog box will open.
Select a previously downloaded or created template from the available choices.
Click OK to create a new file based on that template.
The bottom of the Project window is a special area that extracts content from Microsoft
Office Online (a service provided over the Internet). Microsoft Office Online provides
quick links to different templates, training material, and other downloads. It also
provides links directly to Office Online where you can read about updates to Office 2010
as they become available.
23
Recent Files
The left-hand side of the window lists any recently opened Project files, just like the Old
File menu (2003) or office menu (2007: Click one of the Project files to open the file. Or
click on the recent link on the left to show even more of your recently used files. If you
want to open a Project file stored somewhere else on your computer or on another
network, using the pushpin to the right of the file will fix this files availability in the
recent files list and it will not disappear when the list fills and pushes older used files
from it.
24
SaveAndSend
Send As Attachment
Save and send the current project as an email attachment
Save to SharePoint
Allows the publishing to websites using SharePoint services
25
File Types
Save the current project as a different kind of project file many options to allow your
project to be as another type of file compatible with as many platforms as possible
Info
This menu option gives you three choices:
ProjectInformation
Following the link on the top right allows you to modify and view characteristics specific
to your Project:
Help
In File Tab
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-29: HELP OPTIONS FROM FILE TAB
The Help here allows you to check on the status of the Project product and check for
updates it also gives you another point to connect with the help window as well as using
the Help button.
27
Help Button
The HELP button, located directly under the title bar on the far right, launches the Project
help screen:
ToolTips
If you are unsure what a certain command does, point to it, but do not click it after a
quick moment a description will appear. This is true for most of the commands:
28
Mouse
From the FILE tab, choose OPTIONS
In the OPTIONS dialog choose PROOFING on the left and from the options on the
right, choose AutoCorrect options a dialog will appear.
Type the name of the entry in the REPLACE text box.
Type the name of the replacement in the WITH text box.
Choose ADD.
Choose OK.
29
dialog box to turn AutoFit settings off. Also, for single-column layouts, you can change to
a two-column layout, start a new slide to accommodate the text, or split the text
between two slides.
31
Charts
Charts can be either Gantt Charts or Network Diagram Charts both of which are a
diagrammatic representation of the project data.
Network Diagram
Resource Graph
32
Forms
Forms contain the data relevant to a single specific task or resource.These display as
dialog boxes.
Resource form
Sheets
Sheets are a table of all the Tasks or all the Resources that are part of the Project these
appear in a spreadsheet manner.
Resource sheet
The previous views can be displayed separately or in any combination of the two e.g.
You can combine any two single-pane views on the screen to create a combination view.
In a combination view, the information in the bottom relates only to the task or
resources in the top view. The reason for having combination views is to make the job of
entering and analysing information easier.
34
Mouse
Double-click on the Microsoft Project icon.
Or
Click the START button, select Programs, and select the PROJECT icon.
The Programme will start and display an empty project.
35
Tool Bars: The Quick Access and Mini toolbars enable a speedy route to the
most common commands, The Quick Access toolbar can be
customised
Status Bar: At the bottom of the screen showing the current status and to
change zoom and views.
Scroll Bars: When using a mouse to scroll the views and to move the
boundary between two views.
36
The STATUS BAR displays the current mode of operation and warning messages and
indicates when special key control modes, such as Num Lock mode, are on it Also allows
you to change View and zoom in and out on your project in the Gantt chart as already
mentioned. Resizing at the join between the Gantt chart and the Table allows more
columns to be seen and worked with. But less of the Gantt obviously.
A view is the format of the way that project data is displayed on the screen and there
are a considerable number of different permutations that can be used.
37
The Drop down arrow on theVIEW BUTTONon the TASK tab or on the VIEW tab is the first
place where the view that is required is selected. The basic selection is between a Chart,
a Form, or a Sheet. Some of the options in this menu can provide a split view to show
two different displays for the same Task or Resource.
You can also use the View buttons, located on the bottom right of the Status Bar.
As well as the standard views achieved with the View menu or View bar, you can select
More Views to see more detailed and complex views and forms.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-39: THE VIEW MENU OPTIONS
Gantt Chart: A diagrammatic view of the Tasks and their time scale. This
chart can also show the relationship between Tasks and the
Critical Path. It usually shows the task entry form alongside
the Gantt chart.
on the chart and the lines that link the boxes represent the
structure of the project.
Task Usage: The Task Usage view displays project tasks with their
assigned resources grouped underneath them.
Tracking Gantt: The Tracking Gantt view displays two task bars, one on top of
the other, for each task. The lower bar shows baseline start
and finish dates, and the upper bar shows scheduled start
and finish dates (or if the task has already started, meaning
that the percentage complete is greater than zero, the upper
bar shows the actual start and finish dates).
Resource Usage: This is a view that shows the use in hours per day for each
resource.
View Bar: Activates the View bar, located vertically on the left of the
screen.
Team Planner A new view in 2010 which allows you to reassign work
amongst team members to more efficiently use their time.
39
The baseline bars and the scheduled or actual bars are synchronized. However, if the
start date of task slips by, say, 2 days, the red scheduled bar will extend 2 days beyond
the lower baseline bar.
Because the tasks are linked, the slipping of task 2 will cause a ripple effect, making its
successor tasks slip by 2 days as well.
The Resource tab contains all the commands pertinent to working with resources such
as levelling assignment of resources, addition of resources etc
The main choices here are Change Working Time, project information, reports and
Multiple Projects.
The view Tab has the functionality to change views and manage aspects of your project
with these new appearances.
42
Layout: Allows you to customise the way links are shown. Format
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-47: THE GANTT CHART TAB
Gantt Chart Change the selected Gantt Bar style Gantt Chart
Style: Style
Layout: Change the way the bars are displayed including Format
links.
43
The skills of project management are gathered from a wide range of experiences.
Consciously or sub consciously we all apply these skills in the daily administration of our
work.
Where a major undertaking has to be completed, these skills are not only brought into
focus but must be applied in a much more structured format.
We must take on the jargon and techniques of the Project Manager as well as become
familiar with the "Tools of the trade".
To review the skills those are relevant to project management
The ability to define the Goal, Objective, Specifications and Limitations of a project.
The ability to define the individual tasks in sufficient detail and sequence to meet the
objective with the minimum of problems, and within the defined time scale.
Task attributes should include some or all of the following
Objectives
Time constraints
Milestones
Task(s) on which this Task is Dependant
Estimated Duration: -
Task(s) that are dependent on this task
(Optimistic estimate)
Itemised task Budget
(Pessimistic estimate)
Resources required completing the Task.
The ability to manage the progression of the tasks in terms of their resources,
start times and finish times.
The production of appropriate progress reports.
As the complexities of these undertakings increase so the importance of discipline and
structure increase and the Project Manager must look to the tools that can help which is
where Microsoft Project comes into the picture. 44
Implementation
A leap into the void!
Notes: A poorly planned project will take three times longer than the original plan. A well-
planned project will only take twice as long.
A project that will be completed without changes, on time and within budget has never
been known in the past and will never happen in the future.
Microsoft Project will help!
Evaluation.
As the project progresses and when it has been completed the process of evaluation
should be used to learn the lessons for the next time.
Highlights 45
Gantt charts to show project schedules graphically on a time scale (with scaling
from minutes to years).
Network Diagrams to show task relationships.
Outlining to group and arrange project tasks in hierarchical order.
Filters to view selected information.
Resource usage and Graph views and reports to quickly identify resource
availability and costs.
Split views to see any two screens simultaneously.
Custom fields so you can track additional information unique to your project.
The Goal
This is a short statement of what the project should achieve in the broadest terms. For
example if the project is to build a new road to divert traffic away from a shopping
centre the goal would be: -
To make Project to the shopping centre easier for pedestrians and improve the shopping
amenities for local residents.
The Objectives
The objectives can be more specific and there can be any number of them as required.
To continue the example from above the following are examples: -
To build a road for through traffic that does not use any existing residential areas.
To design the road and the route to allow for the projected traffic flow for the next 20
years.
The Specification
This section will provide more detailed areas for the project, for example it may specify
the broad sections of the project and at what points approvals are required before
proceeding. There may be a section concerning where resources should come from. It
may also specify the management team.
The Limitations
These are the restrictions that will affect the project, for example there may be a cost
limit, there could be a set of regulations that must be adhered to, and time may be a
vital factor. 46
When these areas are clearly specified before the project starts there is a much greater
chance of the project succeeding and major pitfalls being avoided. (In theory!)
Project Title:
(File Name)
Start Date:
Goal:
Objectives:
Specification:
Limitations:
Project Planning
This is where the experience and skill of the Project Manager must be used. At this
point the project is broken down into a series of tasks and you must ensure you have all
the necessary information for each task.
The Project Manager must be confident that it will be possible to control the task as
listed, if there is any doubt then the task should be broken down into a number of
smaller tasks, each of which will be easier to control.
When defining a task the following is a guide to the information required.
The Title
The Objective of the Task 47
At this point it will be possible to SET THE PLAN, this will become the base line
against which progress can be measured.
48
49
Mouse
Select FILE tab, OPEN to open the OPEN dialog.
Navigate to project file location and select project file
Click OK to open the project file
Viewing A Project
There are various tools as mentioned to navigate and change the view of your project.
Zoom Section
controls
Scroll Bars
Resize Handle
50
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-49: THE PROJECT INFO DIALOG BOX
51
Choosing the STATISTICS button opens the PROJECT STATISTICSdialog box, below. This dialog
box displays information on project start and finish dates, duration, work, and cost. It
also provides comparative statistics you can use to measure the progress of your
project.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-50: THE PROJECT STATISTICS DIALOG BOX
Mouse
Choose NEWfrom the FILE Tab,
Select BLANK PROJECT, click CREATE.
52
53
Mouse
In the PROPERTIES group of the PROJECT ribbon select PROJECT INFORMATION a dialog
opens.
The PROJECT INFORMATIONdialog box allows the selection of the start or end date
of the Project.
To view project STATISTICS, choose STATISTICS.
Once you have viewed the necessary information, choose CLOSE to close the
STATISTICS dialog.
Click OK to close and set the start date of the project.
Tab Function
General Provides information about the project, including project name, file
type and size, file location, dates and times of file creation, most
recent modification, and most recent Project.
Custom Allows you to enter project properties by which you can search and
define links to actual values in your project.
54
The Calendar
The Default Working Calendar is used by Microsoft Project to calculate all Timescales
and Resource costs. It defaults to a working day of 8 hours with the working hours 0800
to 1200 and 1300 to 1700.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-57: PROJECT CALENDAR (CHANGE WORKING TIME)
You can create your own calendar with your own particular times. If this is not a
standard 8-hour day you must remember to tell Microsoft Project what the standard day
is. Each resource you add will be based on the calendar you select when you start your
project.
Depending on the nature of your project you may find that the base calendar and
standard 8-hour day is satisfactory. A full day’s work is considered as two shiftsone in
the morning and one in the afternoon. You can use the From and To text boxes in the
Working Time area to specify up to three shifts. Selecting Default restores selected days
and working hours to their default settings.
Resource calendars deal specifically with resourcesthat is, working hours, working
days, and vacations on an individual basis. Resource calendars are created automatically
when a resource is added to the pool. Users do not create resource calendars. It is up to
the user to attach a resource to a specific base calendar.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-58: CHANGE WORKING TIME BUTTON
56
Mouse
Go to the PROPERTIES group on the PROJECT ribbon
Click the CHANGE WORKING TIME button to open the CHANGE WORKING TIME dialog
box.(figure 3-7)
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-59: CREATING A NEW BASE CALENDAR
Mouse
Access the CHANGE WORKING TIME dialog
Choose CREATE NEW CALENDAR.
In the NAME text box, type the new calendar’s name.
Select either the CREATE NEW BASE CALENDAR or MAKE COPY OF calendar option
button if the latter select a calendar to copy from the drop down box choices.
Choose OK.
57
Edit A Calendar
In a calendar for the project you must define the working and non-working hours and
days as these will affect the costing and the duration of the project. Please understand if
your project runs 24 hours a day your workers will only maybe work 8 hours so a task
taking a working project day will take a worker 3 days to complete increasing the cost
etc. If your project day is running for 16 hours and you have two teams working shifts (at
8 hours a day) 1 days project work will entail the two teams working a day each. It is
very important to ensure the entire project work calendar is set correctly especially
weekend or holidays where the project cannot function. You must select days, weeks or
the entire calendar to set the working hours and non-working times for the project NOT
the workers.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-60: ADJUST PROJECT WORK TIMES
Select the days your work week will include and change (if necessary) the
working hours choose whether the days for the selected dates will be non
working times.
Click OK to enter the work times.
Your project may run longer in the summer months and shorter during the
winter months due to light, weather or absence of staff select the start and end
dates that the time periods you selected in the previous step will run from and
to.
Select another row and repeat the previous procedure for another block of time.
On the exceptions tab (figure 3-10) select a row and click the DETAILS button and
enter any exceptions to the rule (for example half day holidays. Or days when the
project will run longer than normal due to site clearance etc) click ok to enter the
exception.
Choose OK
Mouse
Open or create a blank project
Create and edit your project calendar as previously described
Open the PROJECT INFORMATION dialog box from the PROPERTIES group on PROJECT
tab.
In the CALENDAR drop down box select the previously created Project Calendar.
You can also save (EXPORT) your project in formats that other programs can read. For
example, you can export your project file with an .XLS extension for use in an Excel
spreadsheet, a .DBF extension for use in a FoxPro or dBase Project file, or an .MPX
extension for use in other project management applications. To export a file, in the File
Savedialog box, select the desired extension from the SAVE AS TYPE drop-down list, type
the filename, and choose SAVE.
61
Mouse
From the FILE Tab (Backstage), choose SAVE.
OR
On the Quick Access toolbar, click the SAVE button.
Mouse
From the FILE Tab (Backstage), choose SAVE& SEND.
From the displayed choices in the central window area under file types select
SAVE PROJECT AS FILE.
On the right a number of options appear select the version of project file you
wish to save as.
Click the SAVE AS button the SAVE AS dialog will open.
Enter a file name, select a location
Click SAVE to complete the save.
Mouse
Open the project file created in an earlier version of Microsoft Project.
Your file will be in COMPATIBILITY MODE which may not allow the saving of 2010
features.
Go to the FILE tab SAVE command.
A dialog will open warning you which version you may be saving in click YES to
convert to 2010 project file type.
Closing A Project
Once you have finished working with an existing project, you will close it. When you do
this, Project asks whether you need to save the changes.
To Close A Project:
From the FILE Tab (Backstage), choose CLOSE.
Choose YES to save the changes.
OR
Choose NO to close the file without saving the changes.
Exit Project
Select FILE tab, CLOSE to close the existing project file.
Select FILE tab, EXIT to close Microsoft project and the file that is currently open.
You will be prompted to save changes to any open and unsaved project files.
63
Mouse
Go to the FILE tab and click OPTIONS In the OPTIONS window on the left go to
SCHEDULE option
About half way down is the option for how you wish tasks to be scheduled it says
NEW TASKS CREATED.(figure 3-18)
If you desire the default to be changed to automatic scheduling then click the
drop down arrow and select the option from the list. Click OK to save and apply
the setting.
Remember every task as it is created will have the option to change back to
manual or vice versa this is merely the default.
64
Entering Tasks
This is the main activity in setting up a new project. The tasks which have been
identified at the Design Stage must be entered.The system will hold task information in a
task Project file, which we cannot access directly but is used by the system whenever we
view task data. This is one of two Project files the system uses the other being the
resourceProject file.
It is important to understand that the system checks the data that it holds and where
the data does not cross check then the system will generally update the Project file to
make it right. It is important to keep an eye on this process; this will be discussed in a
later section.As each entry is made the system will update the appropriate data and
views to reflect the entries.The order of entry should be in the logical progression but
this is not essential as it can be changed.
Normal Task entry will be by using the standard Task Sheet. The Gantt View shows the
Gantt Chart in the right part of the window with the Task Sheet in the left part.
65
The Task entry sheet is a view of the tasks with information shown in the columns as
follows: -
Duration: The time the Task will take including the time units.
Start: This is the current Scheduled Start date for the Task. Not the
Planned or Actual Start.
Predecessors: The ID numbers for the preceding Tasks that are linked to this
Task.
Add New Column New to 2010 a quick way to add new columns to your task entry
sheet this column will appear on any table that you show
66
Navigate
Navigating the sheet is much the same as working in a excel spreadsheet enter your
information within a cell and use the arrow keys to move left or right.
Select
Select columns or rows by clicking on the column or row label enabling you to format
delete or drag to another location.
Enter some information in the following fields to start building your project.
IMPORTANT: Do NOT enter any dates at this time
Duration: The time the Task will take including the time units.
As the entries are made, the Gantt Chart will automatically be updated to display the
tasks. All tasks initially will run from the project start date, this is expected and no
problem.
Note:Pressing SHIFT+TAB moves to the previous cell without deselecting the range.
Clicking your mouse inside or outside the range will deselect the range. 67
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-70: THE TASK INFORMATION FORM
If using the Task Information FORM it will be possible to enter and/or view many other
pieces of information that is not normally shown in the task entry table think of the
information as hidden columns within the task entry sheet.
Mouse
Select a task in the task entry sheet. (click On Row label)
Double click on the desired task to open the TASK INFORMATION form for that task.
Or
On the TASK tab in the PROPERTIES group select the INFORMATION button the dialog
will open
68
Mouse
Move to an empty row where you wish the task to appear in your task list.
Click on the Information button in the properties section of the task ribbon. The
dialog will appear.
Enter the desired information.
Click OK to create the task.
Mouse
Select the task BELOW where you wish your new task to be created for instance if
you want a task after Plaster in the above diagram and before floorboards select
floorboards. As the task will be pushed down when a new task is created.
Click on the TASK button in the INSERT group to create a new task.
69
Enter the task name to create the Task it is not necessary to complete all the
fields at entry time, as more information is added so the system will update the
boxes. It is only necessary to enter the data that has been determined in the
design stage.
Task Mode
The task mode is a new 2010 feature it allows us to specify whether we want Project to
automatically calculate start and end date changes to our tasks as we adjust aspects of
the project or whether we manually schedule our task changes ourselves. From
experience although some tasks should have fixed dates (specific meetings and such)
many of the tasks should be left to automatic scheduling
Mouse
Entering our tasks a new column should appear before the TASK NAME with a
pushpin and a question mark called TASK MODE.
All tasks are created undefined at first and may not appear in the Gantt chart
Click in the cell in the TASK MODE column for a created task a drop down arrow
will appear
From the drop down options select MANUALLY SCHEDULED or AUTO SCHEDULED.
The task has been set and should now appear on the Gantt chart. It can be
changed at any time by changing the option.
70
In the following picture tasks 1 and 2 are auto scheduled and task 3 and 4 are manually
scheduled notice how they appear in the task mode column and on the Gantt Chart.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-75: DEFINED TASK MODE EXAMPLES
Or
Instead of using the task mode column you may use the ribbon
Mouse
Select a task
On the TASK ribbon in the TASKS group choose a button to MANUALLY SCHEDULE or
AUTOMATICALLY SCHEDULE your task.
Note: When you try to make a link that is not logical or possible, Project will warn
you about this (see illustration below).
72
Setting Durations
If you are using Project 2010 and entering a manually scheduled task, you can enter a
valid duration value, such as 1d or 2w, or you can enter text such as TBD or unknown. A
manually scheduled task is considered a placeholder task until two of the three
scheduling factors—start date, finish date, and duration—contain valid schedule
information.
As you enter durations bars will appear on your Gantt chart showing the duration in a
graphical format.
MANUALLY SCHEDULED TASK: This type of task can be placed anywhere in the
schedule without Project rescheduling it; it does not move as related information
about the task changes.
To Enter Durations
Keyboard
Navigate to the duration column
Enter a value and the suffix hrs, wks, d, mths, mins to define the duration type.
The task duration will be reflected in the Gantt Chart. Zoom in or out to better
see the durations in relationship to one another.
Milestones
A Milestone reference point marking a major event in a project and used to monitor the
project's progress. Any task with zero duration is automatically displayed as a milestone;
you can also mark any other task of any duration as a milestone.
73
To Create A Milestone
Mouse
Enter a task name for an important marking point in your project (such as signing
a contract, Handover of keys etc)
If a task has duration of zero, it is identified as a milestone so enter the duration
as zero. This will be reflected in the Gantt chart
Or
Select the task,
Open theTASK INFORMATION dialog
Click the ADVANCED tab, and then select the MARK TASK AS MILESTONE check box.
If you don't want the task to appear as a milestone, even if its duration is zero,
clear the MARK TASK AS MILESTONE check box.
LinkingTasks
In order that the system is able to display the overall time aspects of the project, each
Task must be defined in terms of the Tasks on which it is dependent and in turn those
Tasks that are dependent on it. It is also possible to define in what way these
dependencies exist.
Methods Of Linking
There are two main methods for Linking tasks, using the buttons on the task ribbon and
using the predecessors column on the task entry sheet. We will look at both.
75
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-80: LINK AND BREAK LINK BUTTONS
Mouse
Select two or more tasks as described earlier
Click on the LINK button in the SCHEDULE section of the TASK ribbon.
The tasks will become linked as described in the previous table using the default
FINISH TO START link this can be edited as you will see in later sections.
The tasks should appear on the Gantt chart linked
Keyboard
Navigate to the predecessors column for a successor task
Enter the task number of the preceding task
Enter FS, SS, FFSF following the task number as necessary because by default all
tasks will have a FS type link (even though the FS does not show in the
predecessors column.)
If the task you are on depends on more than one task completing enter the task
numbers separated by a comma
The tasks should appear on the Gantt chart linked
To Break Links
Mouse& Keyboard
Select the task you wish to break the link for and click the BREAK LINK button in
the SCHEDULE group of the TASK ribbon (figure 4-9)
76
Or
Delete the predecessors from the PREDECESSORS column
The links will be broken
Mouse
Select ALL Subtasks below the BUILD HOUSE task and indent them using the INDENT
button in the SCHEDULE group
They all become subtasks of build house.
Select all tasks between PREPARATION and BUILD FOUNDATIONS (not including) and
using the INDENT button indent them further. Preparation and build foundations
become summary tasks as well
77
Create further summary tasks as in the diagram.
This is a good manner in which to lay out your project using the + and – buttons
next to a summary task you may collapse or expand that group of tasks see
picture below.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-84: THE PLANNING WIZARD DIALOG
Mouse
When the Wizard appears READ THE INFORMATION then decide whether you wish
to continue receiving this message in the future by ticking the box (or not) click
on the OK button.
Select all the tasks you wish to enter the same information for.
Open the TASK INFORMATION box from the PROPERTIES group
Set the values that you wish to apply to the selected tasks and click OK
78
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-85: SUMMARY BUTTON ON TASK RIBBON
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-86: SUMMARY TASK CREATION (ONE SUBTASK)
Mouse
Place your mouse cursor in the task sheet above where you wish the summary
task to appear.
On the TASK ribbon in the INSERT group click the SUMMARY button a summary task
will appear the next task down will be indented all other tasks will remain at the
same level.
Enter the summary task name
Indent any other tasks necessary below the new summary task.
Or
79
Before clicking the SUMMARY button select all tasks you wish to be subtasks of the
new summary task.
When the SUMMARY button is clicked all selected tasks are now indented and
have become subtasks of the new summary task.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-87: MULTIPLE SUBTASKS AT ONE CLICK
Resources
The management of resources is a major feature of Microsoft Project. It is possible to
see how each one is being used and determine the times when they are under or over
utilised. The system can adjust the project to eliminate over allocation of a resource.
We can think of resource data being stored in a Project file, which is the partner to the
task Project file. The Microsoft Project system merges the data in the two Project files
to provide the facilities that are available.
There are a number of ways we can view the resources, as the following topics will
show.
Resource types
There are only 2 types of resources -material- and –work-.
Material
These are physical resources that you need to complete your project such as tables
chairs, bricks and Mortar once they are bought they are used in the project there is no
further cost accruing to them (unless they need maintenance which would be a separate
resource)
Work
However, if the tables and chairs are rented they may become a work resource because
they need regular payments on an hourly, daily, weekly basis as you pay for staff. All
items or people you pay for on a regular basis would really be entered as work to enable
the proper costing’s to be carried out
80
There are two separate stages in adding Resources to be managed by the system. They
first must be entered in the RESOURCE SHEET to identify them as being available. Secondly
the available resources are associated with the respective tasks.
Field Description
Std. Rate The standard cost of the resource per hour, week, or month.
Ovt. Cost The overtime cost of the resource per hour, week, or month. 81
Field Description
Cost/Use A special cost of the resource every time it is used like a call
out charge.
Accrue At This field identifies when the cost of the resource is added to
the running total of the project. The options are at the "Start",
at the "End" or "Prorated" which means updated at the end of
each time unit as the resource is used.
Base Calendar The base calendar to which you assign the resource.
Mouse
From the VIEWbutton on the TASK ribbon, choose RESOURCE Sheet.
In the RESOURCE NAME cell, type the Resource Name.
Press TAB
Enter the TYPE and Press TAB
Enter the label in the material COLUMN if it is a material resource and continue
across the row until you have entered all the information needed for the
resource as described previously.
Press ENTER this brings you to a new row
Press HOME this brings you to the beginning of that row to start again for a new
resource.
Repeat steps 2 through 7 for each resource.
82
Mouse
Double click on a desired resource the dialog will open for that resource.
Or
Select the resource you wish to open the dialog for
Click on the information button in the properties group on the resource tab the
dialog will open.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-90: THE PROPERTIES GROUP FOR RESOURCES
There are four tabs in the resource information dialog the notes button in the properties
group will open the same dialog but at the tab for notes the details button we will look
at in a later section.
83
The Max units default value of 100% is very important equate this as if they have a
40 hr work week for example then they are devoting 100% of that time to this
project.
Entering the group of builders as 600% means that you have the availability of 6
builders use multiples of 100% to specify how many individuals you have it will
help with costing and allocations.
If someone can only apply half their time to the project then enter them at only
50% (meaning 20hrs) enter the percentage dependent on the amount of time
they can devote to the project.
View Resources
As with Tasks there are a number of ways that the Resources can be seen in addition to
viewing the Resource Sheet.
85
One great value of this view is that it shows you when a resource is over-allocated. See
below, where Chris is over-resourced.
86
If the resource sheet is at the top then it will show only the resource selected. If the
Gantt is at the top then it will relate to whatever single resource was selected in the
resource sheet but as you click on the tasks he is assigned to it will move to the selected
task showing the time allocations. If shown alone then it will show for the last selected
resource.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-93: OVERALLOCATIONS IN RESOURCE GRAPH/RESOURCE SHEET
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-94: OVERALLOCATIONS IN RESOURCE GRAPH/TASK SHEET
87
Allocate/Assign Resources
There are a number of methods of allocating a resource to a task. The most direct
method is to select a view in which a task can be selected and then call up the ASSIGN
RESOURCES box using the ASSIGN RESOURCES button in the ASSIGNMENTS group on the
RESOURCE tab.
In the ASSIGN RESOURCES box a list of the resources can be viewed and the required
selection made.There are other views in which a resource can be allocated to a task and
it does not matter which is used, the preference is up to of the user.
To Assign Resources
Mouse
Select the GANTT CHART view from the VIEWbutton.
Select the first task.
Call up the ASSIGN RESOURCES box using the ASSIGN RESOURCES button in the
ASSIGNMENTS group on the RESOURCE tab
Select a resource you wish to assign and click the ASSIGN button.
The resource is assigned
Select another task and repeat to assign resources to different tasks
For each task that needs resources allocated place the pointer on the task scroll
down the list of resources and select as appropriate.
If you wish to assign multiple resources to a task select them in the dialog using
the CTRL key before clicking the ASSIGN button.
88
By default a resource is assigned at 100% which means that he will use all his
available time on this task. If he has say two tasks running concurrently you may
wish to assign him at 50% for each task.
If you have a group of people say builders then you may want to use more than
one of them on a job if they have been entered in the resource sheet at say 600%
(meaning 6 builders) assign as many as you wish as multiples of 100%
To Assign By Percentage
Mouse
Select the GANTT CHART view from the VIEWbutton.
Call up the ASSIGN RESOURCES box using the ASSIGN RESOURCES button in the
ASSIGNMENTS group on the RESOURCE tab
Select a task in your project that needs say two or more builders for example.
Select the builder’s resource in the ASSIGN RESOURCES box.
In the units box for that resource enter the number of individuals as multiples of
100% (6 builders = 600%)
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-96: ASSIGNING MULTIPLE INDIVIDUALS AND MATERIALS
If you assign an individual to a task and then assign another individual to the same task
the second operation seems like an edition to the project, and assigning another
individual to the same task can cause the calculation machine in Project to do some
strange things.
Think of the old adage about: “if it takes 1 man 2 days to dig a hole how many days
would it take two men.” Project calculates in this manner. So assigning a second
individual two a task can cause one of two things to happen.
The task could halve in duration
The individuals could have their units set to 50%
89
So the best thing to do to avoid this problem is to assign these individuals at the same
time.
Mouse
Call up the ASSIGN RESOURCES box using the ASSIGN RESOURCES button in the
ASSIGNMENTS group on the RESOURCE tab
Select a task in your project that needs say two or more individual resources.
Select the first resource in the ASSIGN RESOURCES box use the CTRL key then select
all the resources necessary while you hold the key down.
Click the ASSIGN button to assign them en masse.
OR
Double click the resource to open the RESOURCE INFORMATION dialog
In the dialog edit what information is necessary.
Click OK to enter the information and close the dialog
To Insert A Resource
Switch to the RESOURCE SHEET.
90
Select a cell in the row above the one where you want to add a resource.
OR
From the INSERTgroup, on the RESOURCE tab clickADD RESOURCES a menu will
appear.(figure 5-8)
From the choices make a selection of either WORK, MATERIAL or COST resource.
The resource will appear in your list enter the relevant information.
To Delete Resources
Select a cell in the row of each resource you want to delete.
Press [DELETE]
91
Mouse
Call up the ASSIGN RESOURCES box using the ASSIGN RESOURCES button in the
ASSIGNMENTS group on the RESOURCE tab
In the ASSIGN RESOURCESdialog box, select a blank NAME cell at the end of the
resource list.
Type the name of the resource and press ENTER
Mouse
Call up the ASSIGN RESOURCES box using the ASSIGN RESOURCES button in the
ASSIGNMENTS group on the RESOURCE tab
In the ASSIGN RESOURCESdialog box, double-click the resource for which you want
to add or update information the RESOURCE INFORMATION Dialog will open
In the RESOURCE INFORMATION dialog box, make the necessary changes and click
OK to save the changes.
92
Over allocations
As mentioned before resources that are have been assigned to many tasks to complete
within their work week are classed as over allocated. And these over allocations have to
be dealt with we will look at a couple of simple methods of dealing with over allocations
at a later stage in the advanced manual we will look at more precise ways of dealing
with them and assigning overtime.
View the Resource Graph and where there is an over allocation, consider these methods
of correcting them.
Resource Levelling
Levelling is the process of moving tasks in the time scale to redistribute the use of
resources where they are over allocated.
This may rearrange your tasks and lengthen the duration of your project.
This process can be set to automatic whenever there is a resource over allocation
or manually LEVELLING OPTIONS button in the LEVEL group on the RESOURCE tab.
Mouse
Go to the resource sheet to display your over allocations
Click the LEVEL RESOURCE button in the LEVEL group on the RESOURCE tab.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-99: LEVEL RESOURCE DIALOG (SINGLE RESOURCE)
Mouse
Go to the resource sheet to display your over allocations
Click the LEVEL RESOURCE button in the LEVEL group on the RESOURCE tab.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-100: LEVEL RESOURCE DIALOG(MULTIPLE RESOURCES)
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-101: LEVEL GROUP ON RESOURCE TAB
Or
Simply click on the LEVEL ALL button from the LEVEL group and all resources will be
levelled.
When a project involves levelling after a while certain things may change staff
coming and going new resources assigned etc you may even have decided to use
other methods to deal with your overallocations so uou may need to clear your
levelling and deal with the overallocations differently some may even no longer 94
apply.
To Clear Levelling
Mouse
Simply click on the CLEAR LEVELLING button from the LEVEL group and all levelled
tasks will returned to their former state if resource changes have taken place
some resources may no longer be over allocated those that are you may deal
with.
All of the data entered into the project at this time can be considered as the base
line for the project to be managed from and measured to. Microsoft Project will
hold this data by using the TRACKING, SAVE BASELINEcommand from the TOOLS
menu.
From this point, as the tasks are completed and the data updated it will be possible to
make comparisons with the plan and determine how late (or early!!!) the completion
date will be and where the problems are occurring.
This can be seen using the VIEW, MORE VIEWS, TRACKING GANTT. The Plan appears as
grey bars under the Gantt bars.
Baseline
A baseline is a very useful tool when working with your Project it uses hidden columns to
store information about the costs, and dates as your project stands at the moment for
example you have a start date and end date as soon as the baseline is saved you will find
that you will have a baseline start date and a baseline end date as well. The information
is transposed from the original columns to the baseline columns as you save the
baseline.
As your project is implemented and inevitable changes and refinements take place you
may use the tracking Gantt to compare the current state of play against the baseline
(original values) this will show you which tasks are ahead of schedule and those that are
behind schedule (slipping tasks) this enables you the opportunity to act on those tasks
that may delay your project or/and raise costs.
every six months to a year. Some projects are unending and a regular baseline may need
to be taken.
To Save A Baseline
Mouse
Open your project
Ensure all tasks have been entered, all durations and links set.
Select the SET BASELINE button from the SCHEDULE group on the PROJECT ribbon
Choose SET BASELINE from the options given a dialog will open.
To Clear A Baseline
Mouse
Open your project
Ensure all tasks have been entered, all durations and links set.
96
Select the SET BASELINE button from the SCHEDULE group on the PROJECT ribbon.
(Figure 4-16)
From the options displayed choose CLEAR BASELINE the CLEAR BASELINE dialog will
open.
Ensure the correct baseline is selected and click o the baseline will be cleared.
When further adjustments are made you may save the baseline again. Remember the
baseline is meant to be the final version of the plan before implementation to allow you
to monitor and effectively deal with the ensuing risks that may be realised in the
implementation of the plan.
It is also useful during the evaluation phase of the project to enable a better plan to be
formulated for the next project.
right arrows. If the left button is held down then the dividing line can be moved to the
left or right as required.
Time Scale
The time scale on the chart can be change to many different settings based on the
length of your project and which part of the project you wish to display on the screen.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-105: TIMESCALE AND ZOOM MENUS FROM THE ZOOM GROUP
Mouse
Ensure you are in Gantt view
Go to the VIEW ribbon, ZOOM group, ZOOM command.
From the menu make a selection of zooming in or out
Or
Use the zoom slider on the bottom right of the status bar as previously discussed.
Or
Go to the VIEW ribbon, TIMESCALEdrop down box and select a timescale.
Your timescale will adjust to the selection timescale
Go to the VIEW ribbon, TIMESCALEdrop down box and select the TIMESCALE
command a dialog will open.
From the SIZE box choose a percentage to zoom into and click OK
98
Change the timescale from the drop down box to an appropriate measuring
system again if necessary.
Where the timescale dialog is chosen, the dialog box will provide the ability to change
both the major and minor time scales and within each of these it will be possible to alter
the units, the label, the alignment, and the count of the interval between the unit labels.
Mouse
To view the timeline go to the VIEW ribbon, SPLIT VIEW group and tick the TIMELINE
check box. (un-ticking this will hide the timeline)
The timeline will appear beneath the ribbon and a new contextual ribbon will
appear called FORMAT in the TIMELINE TOOLS.The timeline will contain a scroll bar
beneath it to scroll left or right when zoomed in on any aspect of it.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-108: THE TIMELINE AND CONTEXTUAL RIBBON
Resize the timeline area by moving your mouse to just below the scroll bar a
double arrow will appear click and drag up or down to change the Timeline size.
Zooming
Zooming in and out on any part of the timeline is a useful thing to know when you have
added tasks.
Mouse
Select the timeline by clicking on the timeline label to the far left of the timeline
this changes the focus from any view you have displayed beneath it to the
timeline.
Or
Use the ZOOM control in the ZOOM group on the VIEW tab
100
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-109: INSERT GROUP, TIMELINE TOOLS
Mouse
Go the TIMELINE TOOLS, FORMAT tab, INSERT group and click on the EXISTING TASKS
button a dialog will open.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-110: ADD EXISTING TASKS DIALOG
From the dialog tick any tasks you wish to add to the timeline and un-tick those
you do not wish to see.
Click OK to apply the changes.
101
Zoom and scroll to view the tasks in the timeline. (notice the milestone)
Click on the DETAILED TIMELINE button in the SHOW/HIDE group to add or remove
the details from the timeline and just show the tasks.
Copy Timeline
Since the timeline could be useful for explanation or presentation purposes there is a
facility to copy it and print or present it.
To Copy Timeline
Mouse
Click on the COPY TIMELINE button on the far right of the FORMAT tab a menu will
appear.
The options in the menu allow for the quality of copy for when you paste it in
whatever document type you will use.
Choosing full size and pasting it into word will allow the object to be pasted as a
series of grouped drawing shapes and text boxes to allow further formatting
before printing.
102
Text styles
This opens the font format dialog for in depth text formatting
Font group
This allows quick access to text formatting actions
Show/Group
Change the appearance of the date and show or hide various aspects of the timeline
Mouse
Open your project to Gantt view
Go to the contextualFORMAT ribbon in the GANTT CHART TOOLS.
In the GANTT CHART STYLE group use the drop down arrow to the bottom right of
the style box a selection of styles appear. 103
Mouse
Select a task in the Gantt chart view either on the chart itself or on the task entry
sheet.
Go to the contextualFORMAT ribbon in the GANTT CHART TOOLS.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-115: FORMAT BAR OR BAR STYLES
Click on the FORMAT button and select the BAR command a dialog will open.
From this dialog the bar can be further formatted, including its shape pattern and
colour.
Text may also be added we will see this in the next section.
Mouse
Select the Gantt chart view.
104
Go to the contextual FORMAT ribbon in the GANTT CHART TOOLS.
Click on the FORMAT button and select the BAR STYLES command a dialog will open.
This dialog is used to maximise the information provided by the format of the bar
on the Gantt Chart. The appearance of the existing bars can be changed and
additional bars can be used. The full use of colour, shape and bar ending is also
possible.
Select a style in the top part of the box and in the bottom select the style you
want for that kind of task. Set a start, middle and end style.
Repeat or other bar types in the top most Boxes.
Mouse
Select the Gantt chart view.
Go to the contextualFORMAT ribbon in the GANTT CHART TOOLS.
Click on the FORMAT button and select the BAR STYLES command a dialog will open.
Ensure you have the correct bar type selected in the top part of the dialog such
as TASK.
In the bottom section of the dialog click on the TEXT tab
105
Choose where you would like your labels to appear and click in the box use the
drop down arrow on the right to select from all the fields in the project what
information you would like to appear.
Click ok to apply the selection and close the dialog
Try not to have too many labels on the Gantt as it can look untidy, use the FORMAT,BAR command to
add labels to just one specific bar
Mouse
Positioning the pointer at the beginning of a bar will change the pointer to
anarrowand % sign
The left mouse button is pressed and the symbol dragged to the right a box will
appear showing the amount of "percentage complete" that has been added. This
information will then be updated throughout the system.
Mouse
Place the pointer in the centre of the bar it will change to a four-way arrow
pointer.
The left button is held down it drag the bar to the left or right in time,
When the mouse is released the changing dates options will be shown in a dialog
box
Mouse
The pointer is positioned at the right end of the bar it will change into a right
pointing arrow.
The left button is held down it is then possible to change the length of the bar
and the respective change in duration is shown in a box.
Release the mouse and the duration will be changed.
107
Remember a non-critical task may become critical if it slips enough to affect other
critical tasks. (Compare the Gantts in the next pictures one showing the critical path the
other not, displaying how useful this feature is.)
Mouse
Go to the contextualFORMAT ribbon in the GANTT CHART TOOLS.
In the GANTT CHART STYLE group tick the box to allow critical tasks to be shown.
Change the style of the critical tasks as described in the previous lesson if you
wish.
The Gantt should like the following picture.
108
109
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-122: GANTT SHOWING CRITICAL TASKS
As you can see the red tasks display the critical path and the blue non-critical
tasks have room to slide a little before impacting upon a critical task.
110
To Apply Autofilters
Mouse
In the TASK ENTRY sheet move your mouse to the column label you wish to filter
and click on the drop down arrow to the right of the column label a menu will
appear.
As you move your mouse down the menu commands other options may appear
in a further menu (see picture)
111
Dependant on the column and the type of information the options will vary from
column to column
Make a selection from the displayed menu (disregard the lower part of the menu
involving the fields and check boxes for now)
The list will be filtered.
Or
When you have opened the menu move down to the checkboxes and only select
the tasks you wish to see in the task list.
To Clear Filters
In the TASK ENTRY sheet move your mouse to the column label and click on the
drop down arrow to make the menu appear.
Move down the menu and click the CLEAR ALL FILTERS option to remove all applied
filters to your data.
112
Mouse
Click on the VIEW ribbon
In the DATA group click on the drop down box on the middle right containing the
text “NO FILTER” a menu will appear
Make a selection to filter your data.
Repeat and select “NO FILTER” to remove the applied filter.
113
By default you can see that sorting is by id select from the drop down box
another field (column) to sort by you may sort by up to three levels as you can in
excel,
Do NOT tick the permanently renumber tasks unless you are still in the planning
and intial stages of setting up your project as all tasks will then have a different
ID and if the project is underway it will be very confusing when referring to ID
numbers which task is which.
Choose whether to sort ascending or descending
When you have finished your options click ok to apply your sort
Mouse
Open the SORT dialog from the DATA group
Click the RESET button (This will clear all sorts and the primary sort will revert to
ID)
Click OK to apply the default sort order.
Grouping
Grouping is a useful way of organising your data prior to printing. It is also useful to see
your project in a different light. For instance you could group by the stages of
completion so it is easier to see at a glance which tasks are in what stage of progress, or
you may wish to see the critical and non-critical tasks grouped or grouped by resource
usage. We will look at only the basic grouping options here and cover them in more
depth in the advanced manual.
114
Mouse
In the DATA group on the FORMAT ribbon of the GANTT CHART TOOLS click on the
drop down box on the bottom right containing the text “NO GROUP” a menu will
appear
To Remove Grouping
Mouse
In the DATA group on the FORMAT ribbon of the GANTT CHART TOOLS click on the
drop down box on the bottom right containing the text of the group type that
has been applied to access the menu
From the menu choose either no group or clear group.
115
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-128: GROUPED BY CRITICAL AND NON-CRITICAL TASKS
Grouping, sorting and filtering are useful tools to apply prior to printing your data. There
are many more options that will be covered in the advanced manual.
116
Tracking
An important part of implementing your project is marking when tasks are in progress or
complete this is an important part of monitoring your project because if a task has not
started yet it should not have incurred any material or work costs. And project uses this
to calculate the actual costs to your project and measures the progress of the work
against your baseline that you saved earlier.
Definitions
Slippage:
The amount of time that a task has been delayed from its original baseline plan. The
slippage is the difference between the scheduled start or finish date for a task and the
baseline start or finish date.
Start date:
The date when a task is scheduled to begin. This date is based on the duration,
calendars, and constraints of predecessor and successor tasks. A task's start date is also
based on its own calendars and constraints.
Finish date:
The date that a task is scheduled to be completed. This date is based on the task's start
date, duration, calendars, predecessor dates, task dependencies, and constraints.
Slack:
The amount of time that a task can slip before it affects another task or the project's
finish date. Free slack is how much a task can slip before it delays another task. Total
slack is how much a task can slip before it delays the project.
If you know where slack exists in your schedule, you can move tasks when certain
phases of the schedule have no slack and other phases have too much.
Slack values may also indicate a schedule inconsistency. For example, a negative
slack value occurs when one task has a finish-to-start dependency with a
successor task, but the successor task has a Must Start On constraint that is
earlier than the end of the first task. Negative slack can also occur when a task is
scheduled to finish after its deadline date.
117
Mouse
Select a task in your task list (not a summary task)
In the SCHEDULE group of the TASK ribbon select a percentage complete button to
mark the task as that much complete.
This should show on the Gantt chart.
If a task is marked as 100% then the task is marked as complete and a tick
appears in the information column of the task entry sheet.
118
Mouse
Another method of marking progress is to call up the task information dialog
from the properties group of the task ribbon.
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-131: PERCENTAGE COMPLETE IN TASK INFORMATION DIALOG
Type a percentage complete in the PERCENT COMPLETE box and click OK to apply.
Use this method if the percentage is not a standard figure on the ribbon
The system is dynamic in the sense that if a single element of a task is altered
that has a bearing on other elements, the changes will be calculated and the
other elements automatically updated.
To Updatetasks
Select the TASK Sheet from the VIEWbutton on the TASK tab.
Update individual tasks by selecting the tasks and clicking on the drop down
arrow next to the MARK ON TRACK button in the SCHEDULE group on the TASK ribbon
From the menu shown select UPDATE TASKS.A dialog will appear
119
From the dialog make the choices of how you want the task updated you may
change dates, percentage complete, the name, duration etc
To Updatethe project.
Mouse
Go to the PROJECT tab, STATUS group and click on the UPDATE PROJECT button a
dialog will open.
Either use the dialog to update complete work through a series of dates or if
work has not been done reschedule uncompleted work to start after a specific
date.
Click ok to apply the update
As you may have noticed this will work on specific selected tasks as well as the
whole project
120
Mouse
On the TASK tab, click the arrow on GANTT CHART, then select TRACKING GANTT.
In the DATA group on the VIEW tab, click the arrow on TABLES, and then select
VARIANCE.
121
If the variance fields are not visible, adjust the view splitter for the Table/Ganttor
press TAB to move through the fields to display them.
Slippage
You can also see whether the start and finish dates for task assignments are slipping,
using the SLIPPING ASSIGNMENTS filter. This filter shows resources that are assigned to
tasks that are not yet complete and that have been delayed from the finish date of the
baseline. To use this filter, you must have saved a baseline plan.
To Show Slippage
Mouse
On the VIEW tab, click RESOURCE USAGE.
In the DATA group, in the FILTER list, select MORE FILTERS.
In the MORE FILTERS list, next to FILTERS, select Resources.
122
If you want to show only those assignments that are slipping, click APPLY.
Or
If you want to show all assignments with a coloured highlight on the slipping
assignments, click HIGHLIGHT.
Finding Slack
The amount of slacking your schedule tells you how much you can delay tasks before
other tasks or the project end date is affected.
To Find Slack
Mouse
On the VIEW tab, in the TASK VIEWS group, click the arrow on GANTT CHART, select
MORE VIEWS.
The MORE VIEWS dialog appears. In the VIEWS LIST, click DETAIL GANTT, and then click
APPLY.
In the chart portion of the view, slack appears as thin bars to the right of tasks,
with slack values adjoining the regular Gantt bars.
On the VIEW tab, in the DATA group, click the arrow on TABLES, and then click
SCHEDULE.
Press TAB to move to the FREE SLACK and TOTAL SLACK fields if they are not visible or
resize the Gantt/ sheet to show more of the sheet in the sheet portion of the
view.
123
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-138: DETAIL GANTT SHOWING SLACK
FIGURE ERROR! NO TEXT OF SPECIFIED STYLE IN DOCUMENT.-139: SCHEDULE TABLE SHOWING FREE SLACK
124
This view will list all the tasks as originally entered and the associated columns will
contain the cost data in terms of the Planned (baseline) cost, the Actual cost and how
much has been used so far.
This table is very useful in identifying those tasks that are causing the greatest pressure
on the total cost of the project.
125
Print (backstage)
All print options have now been put in one location to make it easier to handle printing
within Project 2010. To access the entire tools visit the FILE tab (backstage view) PRINT
option.
Page Setup
Before printing it is advisable to check the Page Setup which is in the middle of the
screen of the print options as a link.
Header: This box can hold a Header that will be printed on every page.
Footer This box can hold the footer for every page.
Legend: This is for printing Gantt and Network Diagram views only
In the Header, Footer, and Legend, buttons are available to enter specific information.
For example the following are available:
These include date, time, page number and number of pages.
The PAGE SIZE is available under the PRINTER,SETUP option.
Mouse
Ensure you are viewing the Gantt Chart.
Pull down the FILE Tab (Backstage).
Go to PRINT
Select PAGE SETUP.
Select LANDSCAPE in the Page box.
Check the other settings and change any that are not correct.
Click ok to close the dialog the Print Preview shows to the right of the backstage
window.
127
128
Before printing you may wish to set some other options available
To change settings
Mouse
In the PRINT section choose the number of copies you wish to print
In the PRINTERsection choose the printer you wish to print to.
The PRINTER PROPERTIES link opens the dialog to the printer to allow specific printer settings to be
adjusted not discussed here
In the SETTINGS section choose a date range that you may wish to print
Or
In the SETTINGS section choose a page range you would like to print
When clicking the button that says PRINT ENTIRE PROJECT a menu appears offering
even more print range options.
129
After making a selection here ensure the page or date range has been set.
The bottom three options are check boxes and allows the printing (or non-
printing) of aspects of your project.
When all options have been set and the preview looks as you wish it to click the
Print button to send your project to the printer.
If the PAGE SETUP has been completed for the views that are to be printed then it is only
necessary to bring the required view on to the screen and select the print command.
The settings in PAGE SETUP will align all the necessary settings for the printer and then
print the view in as many pages as it takes.
130
Reports
Reports Setup
MICROSOFT PROJECT has a number of pre-defined reports based on six principal types
which can be used directly, changed as required. Alternatively, completely new reports
can be created. The system is picture driven and simple to use.
To access reports
Mouse
Projectreports are accessed from the PROJECT tab, REPORTScommand.
A dialog box appears in which the following type of report can be chosen:
Overview: Summarizes the most significant project information, including
numbers of tasks and resources, task and schedule status, costs,
start and finish dates, and so on.
Current Activities: Displays information about top-level tasks for the entire project.
Includes summary tasks and task notes.
Costs: Shows critical tasks for the entire project. Includes summary and
successor tasks and task notes.
Workload: Shows working and nonworking times for resources for the
entire project duration.
131
After selecting one of the above you then choose SELECT and a second box will
appear that will have a number of pre-defined options depending on the base of
the report.
Select a subtype from the offered reports and click the SELECT button the report
will open in preview in BACKSTAGE view to make further printing options.
Once the options have been set click PRINT to print your report.
132
Mouse
Select PROJECT tab, REPORTS from the ribbon.
Select one of the reports group types and press the SELECT button.
Check one of the default reports subtypes and press the SELECT button. A preview
is shown.
ReportsByReport Type
To Print Use
The number of tasks and resources, the project Project Summary report
cost, the total amount of work, and the project (Overview reports)
start and finish dates.
Costing
To Print Use
The cost of each task per week, along with the Weekly Cash Flow report
total cost of all tasks per week and the total
(Cost reports).
cost of each task.
A list of resources whose costs are going to Over budget Resources report
exceed the baseline cost. (Cost reports).
A list of tasks showing whether you are ahead Earned Value report
of or behind schedule as compared with the (Cost reports).
actual costs incurred.
To Print Use
each task and the variance between budgeted (Cost reports).
costs and current costs.
A list of tasks whose costs are going to exceed Over budget Tasks report
the baseline cost. (Cost reports).
Gantt
To Print Use
A list of project phases (summary tasks) and Gantt Chart view,Entry table,
durations and a Gantt bar chart showing andSummary tasks filter
summary tasks.
A list of tasks and durations and a Gantt bar Gantt Chart view,Entry table,
chart showing tasks, durations, task andAll Tasks filter.
relationships, and assigned resources.
A list of tasks showing the actual start and finish Gantt Chart view,Tracking table,
dates, the percentage of each task completed, andAll Tasks filter.
and the actual and remaining task durations.
Calendar
To Print Use
Tasks
A list of tasks showing start and finish dates and Task Sheet view,Entry table,
assigned resources. andAll Tasks filter.
A flow chart, or network diagram, showing all Network Diagram Chart view.
tasks and task relationships.
Resource Graph
A graph showing cumulative cost per resource Resource Graph view with
over the life of the project. Cumulative Cost chosen from
Details submenu on Format
menu.
134
Resource/Task
To Print Use
A list of resources showing their assigned tasks, Who Does What report
the work scheduled for each task, the start and (Assignment reports).
finish dates, and additional
resourceinformation.
A list of resources showing their assigned tasks Who Does What report
and the daily work scheduled for each task. (Assignment reports).
A list of over allocated resources and the tasks Over allocated Resources report
to which they are assigned. (Assignment reports).
Work
To Print Use
Resource Usage
To Print Use
A list showing resource use over time, along Resource Usage view,Summary
with the cost, the work, and the pay rate of table, andAll Resources filter.
each resource.
A graph showing the amount of work assigned Resource Graph view and
to each resource over time. All Resources filter.
Resource Costs
To Print Use
Task Usage
To Print Use
Cost information broken down by task and Crosstab report with tasks
resource over time. selected under Row, Cost selected
under Column, and With
Resource Assignments selected in
Crosstab Report dialog box.
A list of planned and actual resource costs. Resource sheet view andCost
table.
Tasks
To Print Use
A list of tasks starting within a time period that Tasks Starting Soon report
you specify. (Current Activity reports).
A list of tasks that should have started by the Should Have Started Tasks report
date you specify. (Current Activity reports).
A list of the tasks that have been rescheduled to Slipping Tasks report
occur after their baseline start dates. (Current Activity reports).
A list of tasks showing the scheduled start and Task Sheet view,Variance table,
finish dates, the baseline start and finish dates, andAll Tasks filter.
and the difference between scheduled and
baseline dates.
136