RICS Case Study Example Quantity Surveying
RICS Case Study Example Quantity Surveying
Critical Analysis
_____________________________________________________________________
1 Introduction
1.2 Declaration
Candidate: Date:
Supervisor: Date:
Supervisors Name: Simon Wilson Membership number:
Counsellor: Date:
Counsellor’s Name: Maria Govorusa MRICS Membership number:
2
Royal Institution of Chartered Surveyors
Page
Case Study
_____________________________________________________________________
2.0 Project Overview
Project Details:
I was involved in the project during the design development stage and
attended design team meetings to suggest value engineering options
and review the contractor’s proposals. I liaised with the design team to
obtain information on the condition of the existing building shell in order
to generate a scope of works and updated the cost plans accordingly.
3
Royal Institution of Chartered Surveyors
Page
Case Study
_____________________________________________________________________
Once the design was complete and cost plans finalised, the client
approved the project for tender. I was involved in negotiating tenders
on behalf of my client using approved suppliers listed under a JCT
2011 framework agreement.
Capital
Expenditure Value of Initial
Bid Received vs
Scope of Works Budget (Cost Tenders
Capex %
Estimate) Received
4
Royal Institution of Chartered Surveyors
Page
Case Study
_____________________________________________________________________
appeared inflated by firstly reviewing quantities against the drawings
and checking to see if any front loading or competence errors were
apparent. It was obvious that detection and sprinkler equipment for
installation within the ceiling void were abnormally high. I subsequently
forwarded the contractor’s design onto the client’s Fire Safety
Consultant who confirmed that the high levels of sprinkler and fire
detection equipment within the void were necessary as the ceiling void
depth was in excess of 800mm due to an irregular layout of structural
beams above the sales floor.
The ceiling height shown at 3200mm above FFL creates a void depth of 1350mm.
5
Royal Institution of Chartered Surveyors
Page
Case Study
_____________________________________________________________________
High quantities of void protection above the sales floor were proposed due to the void
depth being in excess of 800mm. This caused both tenders for fire alarm and
sprinkler protection to be significantly in excess of the feasibility.
3.1 Key Issue 1 - What options are available in order to reduce the
cost of the Fire Alarm and Sprinkler protection works?
3.3 Option 1 – The works would be re-tendered under the NJCC code of
procedure for Single Stage Selective Tendering with six contractors
shortlisted by myself and sent to the client for approval.
6
Royal Institution of Chartered Surveyors
Page
Case Study
_____________________________________________________________________
Option Summary
Reason rejected
Whilst this option would have provided competitive tender prices and a
potential discount on the tenders initially received, an impending
commencement date did not afford sufficient time to conduct the
necessary pre-qualification and tender interviews in order to add
additional suppliers onto the RETAILER Framework and negotiate a
contract sum. This option was therefore not practical and was quickly
dismissed.
3.4 Option 2 – Omit the suspended grid ceiling above the sales floor to
negate the need for fire sprinkler void protection and reduce the
quantity of fire detection equipment.
Option Summary
Omitting the suspended grid ceiling above the sales floor would have
eradicated the ceiling void, meaning that all void sprinkler equipment
could be omitted and less fire detection equipment would be required.
The exposed services above the sales floor would need to be sprayed
out for decorative purposes but the cost savings achieved by omitting
7
Royal Institution of Chartered Surveyors
Page
Case Study
_____________________________________________________________________
the suspended grid ceiling and void protection equipment would have
achieved a nett saving of circa £24,500.
Reason Rejected
Omission of the suspended grid ceiling would have left mechanical and
electrical services exposed above the sales floor in the line of sight of
customers. Whilst we proposed that these services were sprayed out to
match the structural soffit for decorative purposes, this design was not
in keeping with RETAILER’s standard store specification and despite
the prospect of achieving significant savings was rejected by
RETAILER’s design team.
3.5 Option 3 – Increase the ceiling height to reduce the void depth to less
than 800mm in order to omit the sprinkler void protection and reduce
fire detection equipment required.
Option Summary
By raising the ceiling height over the sales floor to 3822mm from
3200mm, a ceiling void space of less than 790mm would be formed.
With the advice of RETAILER’s fire safety consultant this would mean
that the sprinkler protection within the ceiling void could be omitted and
fire detection equipment reduced.
8
Royal Institution of Chartered Surveyors
Page
Case Study
_____________________________________________________________________
Revised Elevation Drawing
The revised ceiling height shown at 3822mm above FFL creates a void depth of
728mm. On approval with RETAILER’s fire consultant this meant that sprinkler void
protection could be omitted.
9
Royal Institution of Chartered Surveyors
Page
Case Study
_____________________________________________________________________
It was thought that this option provided the best outcome in terms of
delivering improved value for money, the correct RETAILER store
layout and also mitigated any delays and risks if the work had been re-
tendered with local but unfamiliar suppliers. RETAILER were satisfied
with this solution
and the savings achieved of £7,710.00 and £21,474.19 on sprinkler
and fire detection tender prices respectively.
Value of
Value of Negotiated
Initial Tender
Scope of Works Saving
Tenders following Ceiling
Received Height
Adjustment
10
Royal Institution of Chartered Surveyors
Page
Case Study
_____________________________________________________________________
4.0 Key Issue 2 Background
The second key issue I encountered was managing the post contract
cost control of the project. Due to the high frequency of variations and
lack of understanding of the change control procedure, it was
extremely difficult to monitor and raise change requests in a timely
manner. This impacted on the accuracy of cost reports and did not
provide RETAILER with the levels of cost certainty required.
When variations were submitted by the contractor, they were not priced
in accordance with the agreed framework rates or supported with
substantiation. Variations were often submitted by e-mail without a
breakdown which meant that rates from the framework had to be
identified in addition to requesting further information and drawings.
This prolonged negotiations in respect of agreeing variations and
caused the cost reporting of the project to be less accurate. In some
cases instructions had been made directly to the contractor from an
appointed building control consultant. Despite these instructions having
no contractual validity, the contractor had acted on them and requested
that a change request was raised.
11
Royal Institution of Chartered Surveyors
Page
Invalid Instruction Pathway
4.1 Key Issue 2 - How can the change control and cost reporting of
the project be improved?
Option summary
Reason rejected
_____________________________________________________________________
instructions from the appointed certifier despite them not being
permitted to do so. This option would not have supported the contractor
through this issue as the appointed certifier may have continued to
issue instructions.
Option Summary
14
Royal Institution of Chartered Surveyors
Page
Case Study
_____________________________________________________________________
raised and agreed in a timely manner. I reminded the team that any
instructions other than those issued by the contract administrator would
hold no contractual validity and that in future they needed to be
authorised by the contract administrator within 48 hours of becoming
apparent.
15
Royal Institution of Chartered Surveyors
Page
Valid Instruction Pathway incorporating standardised process document
5 Reflective Analysis of Key Issue 1
The initial site visit was undertaken by a colleague who had previously
left the company; when reporting findings from the visit, the irregular
nature of the structural beam layout was not mentioned within their
report. The structural beam layout caused the need to allow provision
for additional fire protection and caused higher than anticipated tender
prices. The tendering contractors were based in mainland UK and were
entitled to a percentage uplift to cover the additional costs of working
within the Republic of Ireland. These costs would not have been
incurred had the contractors been based in the Republic of Ireland. The
lack of time apportioned to undertaking the tendering process meant I
was unable to competitively tender the works which could have
delivered further savings.
If additional time had been allocated for the tendering process, the
works could have been competitively tendered in accordance with
NJCC single stage guidance. By tendering the works with suppliers
based in the Republic of Ireland, the need to pay an uplift to suppliers
based in mainland UK would have been negated.
Case Study
_____________________________________________________________________
18
Royal Institution of Chartered Surveyors
Page
Case Study
_____________________________________________________________________
offer an opportunity to address any queries rather than assuming they
were aware of the process.
7 Lessons learnt
19
Royal Institution of Chartered Surveyors
Page