Project Name : Response to Drought Crisis in Somalia
Area / Village: Balli x.Diriye village, Odwayne district , Togdheer Region-Somaliland.
BILL OF QUANTITY FOR REHABILITATION OF HAFFIR DAM- 10,000m3
# Description Unit Qty Rate US$ Amount US$ 1 Dam desilting, removing the old craked HDPE geomembrane sheets,+ siltrap desilting. 1.1 Mobilization and demobilization Lum 1.00 1.2 Romove the silt accumulated (desilting) above Job 1.00 the HDPE geomemebrane sheets in the main Hafir pan and remove the old geomemebrane sheets with dimensions of( 80mx50m). keep the Dam side slopes of the embakments with ratio of 1:2. maintain the bottom depth hight of the dam with 2.5m minimum. Maintain a minimum 5m berm between and the reservoir and the embankment as directed by by Supervisor Engineer. 1.3 Desilt the existing silt trap champer with m³ 390.00 dimmensions of 13m*15*2m deep.
1.4 Excavation of the outlet and inlet channels - m³ 150.00
100x3x0.5m Sub Total 1- Pan desilting and siltrap works 2 HDPE Geo membrane Dam Liner Material 2.1 Supply and instal 1.5mm Thick approved m2 4,000.00 quality Geosynthetic water proof sheets (HDPE smooth Geomembrane plastic liner) laid over well compacted soil bed bottom and sides of entire dam.(80mx50m)
2.2 excavate/dug atrench of (0.4mdeepx0.3 m3 26.00
thick)x 220m, 1m away from the pan pond edge, to secure the HDPE Membrane from shrinking edges. After excavation, make sure to trap the plastic sheet in the trench by backfilling with rubble stone and sand.
Sub Total 2- Dam Lining with HDPE Geoembranes.
3 INLET/GALLERY, SILT TRAP AND OUTLET/SPILLWAY 3.1 Construct and lay riprap stones with cement m3 40.00 mortar, mix ratio of 1:4, along the bed from inlet to siltrap, siltrap to water pan, and from water pan to spillway with thickness of 0.25m, 40m logn and 4m width, as directed by site engineer. 3.2 Cast 5mm thick plain/lean concrete with mix m³ 8.00 ratio of 1:2:4, over the riprap bed from inlet to siltrap, siltrap to water pan, and from water pan to spillway with thickness of 0.05m, 40m logn and 4m width, as directed by site engineer.
3.3 Construction of rubbl stone plinth wall along m³ 12.00
the two side of inlet and out let channels with dimension of ( 0.4m widht, 0.5m high) 60
3.4 desilt and rehabilitate the circular conrete job 1.00
intake water pump champer with diameter of 2.4m and 1.2 high.
Sub-total 3- INLET/GALLERY, SILT TRAP AND
OUTLET/SPILLWAY 4 External Works ( Fencing ) 4.1 Rehabilitation and remove the old chain mesh LM 360.00 fencing by replacing new mesh 2.10m high, and keep the 6mm angle posts to be vertically eracted by replacing the bended broked ones. make sure to clippe to 3 line horizontal straining wire of barbed wire to cranked tops of posts: Total Perimeter -360m. make sure during installing chain mesh wire fence to be 20cm below the ground level and approperiately backfilled. 4.2 Construct new Steel gate size 3000mm wide x item 1.00 2100mm high in two equal leaves: comprising of 0.3cmx0.3m concrete columns casted titly to the gate with 0.6*0.6*0.4m concrete footing. 4.3 Provide and install Trash screen for the inlet Item 1.00 channel 2 m X 1 m. (Heavy Gauge Mesh) as directed by site engineer. Sub Total 4 - External works -Fencing. 5 Rehabilitation of Animal troughs ,Watchman room and elevated fiber glassed tank.
5.1 Casting Rcc Concrete for footing around the m3 2.28
animal troughs base foundation with 2m length in all sides of 3 troughs.( 45m*2*0.05m thick) with concrete mix ratio 1:2:4, for Y12mm@ 20mm C/C. this inluding plastering for cracking areas and applying cement slarry finish for beds of the troughs as antiseepage control. this will be done as directed by engineer. 5.2 supply and instal new cealing sheets of 4mm m2 25.00 thick in the watchman room. 5.3 Apply 2 coats of internal and external m2 120.00 disptempering and painting to entire building 5.4 room. Apply anti-leage glue inside the fiber glass job 1.00 elevated tanke with dimension of( 2.6m*2.6m*1.5m high). 5.5 Supply and Erect name board size 1.2m wide x Item 1.00 .90m erected about 2.1 m high above existing ground level : fixed with concrete class 20 to ground ( Note: The writing on the Name board will be provided by Concern Worldwide and conform to Concern's requirements)
Sub Total 5- Rehabilitation of Animal troughs ,Watchman room and
elevated fiber glassed tank. GARAND TOTAL - HAFFIR PAN REHABILITATION Project Name : Response to Drought Crisis in Somalia Area / Village: Balli x.Diriye village, Odwayne district , Togdheer Region-Somaliland.
Construction of Pump-house (2.5mx3m)and Two Water kiosks (Water Points).
# Description Unit Qty Rate Amount US$ US$ 1 Pump house Construction. Excavation of foundation trench ( 40cm wide x 1.1 50cm deep) 11m Cu.m 2.2 Construction of rubble stone foundation. All the joints between stones filled with cement/sand mortar (1:4) with minimum foundation height 1.2 of 40cm. Cu.m 4.4
Cast 15cm thick and 40cm wide R.C foundation
beam of 1:2:4 mix ratio @12mm bars, 6mm 1.3 stirrups with 200mm c/c. Cu.m 0.7 Sub-total 1. 2 Floor Construction Back filling, watering and compacting the back 2.1 filled material. Cu.m 5 Laying 10cm thick lean concrete for floor fill 2.2 with ration of 1:2:4 Cu.m 0.8 Over laying Ceramic tiles ( indian 40x40cm) with Cement Screed mortar with 1:3 mixture of cement and sand ( cement should made in 2.3 oman) . sqm 7.5 Sub-total 2. 3 Wall Construction Construction of 20cmx20x40cm hollow bock walls by joined walls with mortar of 1:4. water curing should not less than 4 days. This 3.1 including ram step with sloping 1:2. sm 33
Construction of 15cm thick continuous lintels
beam on door and window opening running through all walls. And ring roof beam 15 cm thick on external walls only. 1:2:4 mix ratio. Bars at 12mm dia and stirrups 6mm @200mm 3.2 c/c. Cu.m 0.4 Sub-total 3. 4 Roof Construction. Roofing with # 28 gauge iron corrugated sheets and timber roof trusses c/c 2m. All roof trusses anchored with 6mm dai. Bars casted in the roof lintel. And all joints of roof trusses and purloins to be tied to gether with a flat metal strip. Dimension tie beam 2"x6", rafter 2"x4", purloins 2"x3", king post 2"x6", Brazing 2"x3". All timber should be single pieces with no joints 4.1 created by smaller pieces fastened together. sm 7.5
Fixing 4mm laminating ceiling board whole the
4.2 building including verandah. sm 7.5
Fasten 20cm fascia board with paints around
entire building. Joints to be attached by 4.3 wooden joint or metal strap. Including painting. Lm 11 Sub-Total 4 5 Plastering and Painting. 2 coats of minimum 12mm cement/ sand plastering on all interior wall faces and exterior 5.1 with ratio 1:4 sm 66 2 coats of white wash and distemper on all faces and ceiling. All interior wall surfaces to be smoothed. Interior wall should be applied with 5.2 stucko. sm 66 Sub-Total 5. 6 Finishing. Provide and install paneled regular steel doors (2.1 highx0.9m width)m with their hinges and 6.1 frames. No 1
Supply and install steel windows size 1mx1 m
having 2 leafs , complete frames. The outer 6.2 frame cover should be steel box 4inch. pcs 1 Sub-total. Total Cost of pump house. 7 Construction of Two Water points (kiosks). Excavation of base foundation trench 7.1 (2.4x2.8x0.3m deep) Cu.m 2 Supplying and laying 250 mm approved hardcore filling spread well rammed and 7.2 compacted Cu.m 1.7 Supplying and laying 50 mm approved lean concrete above the hardcore, spread well and 7.3 smoothed. Cu.m 0.36 Construct a rubble massonary wall of 1.2m*1.6m and 0.55m high, with mortar mix 7.4 ratio 1:4. Cu.m 1.1 Casting 10cm thick RCC top cap above the massonary cubicle foundation with mix ration 1:2:4, and Y 12@20cm c/c for both ways. 7.5 (1.2*1.6*0.1m) Cu.m 0.2
Casting of Vertical RCC wall above the base
water point with dimension (1.6m widht*0.7m high* 0.2m thick), mixing ration 1:2:4, 7.6 Y12mm@20cm c/c with 6mm stirups. Cu.m 0.22 Plumping work, including fixing Gi pipe 1", 6 7.7 peeckoks, elbows, Gi tee and gate valve. job 1 Excavate Soak away pit located 4meters from the structure. The drainage channel to be linked with soak away pit with a 2" PVC drainage pipe. The Soak pit to have 1m Diameter and 1.5metres deep, filled with 7.8 Construct Hardcore. two sun-shades roofings for the two job 1 water points. This is consisting, supplying and eracting 8no Gi pipe post, (4no in each shade roof) with 3m high and base dimensions of 3m*3m square in each shade. Then install corrugated iron sheet roof with timber roof trusses c/c 3m. All roof trusses anchored directly with Gi posts. And all joints of roof trusses and purloins to be tied to gether . Dimension tie beam 2"x6", rafter 2"x4", 7.9 purloins 2"x3", king post 2"x6", Brazing 2"x3". m2 18 Sub-total of One point (kiosk.)
Sub-total of the two point(kiosks). 2
8 Water supply and transmission system.
Excavation and backfill of 180m pipeline trench - 300mm wide and 400mm deep, from the storage tank to the new water points (kiosks) in 8.1 village as directed by engineer. M 180 Supplying and laying Rising main 2" dia HDPE/PPR Pn 10 pipe, including fittings. and 8.2 backfilling appropriately after instalations. m 180 construct Valve chambers measuring 0.5x0.5 m and 0.5m depth., and having lockable steel cover door (25cm*25cm). champers will be located on the rising main next to the pump house, at the water points, and at the junction of the lines to the animal water troughs, and at next to the tank, at the outlet pipe to the distribution lines. and then install 2" gate 8.3 Ckeck and replace if eny dameges on the other pcs 6 valves in each champer to conrol water. Gi 2" pipe line from Dam to wate tank, from 8.4 tank to animal troughs. job 1
Sub-Total-8- Water supply system
9 Solar power and surface pump system
Grundfos Surface pump (CRIF3-5), 2HP DC & 9.1 AC, up to 100mtrs head, 3500LHP. pcs 1
9.2 Solar power panels, 400W made in UAE. pcs 6
9.3 Solar structure mounting stand. set 1
9.4 Grundfos pump switch/controler. pcs 1
9.5 Cable solar 10mm. meter 40
9.6 Cable submercible 3c-2.5mm meter 150
accessories, connectors JM4CC male and 9.7 female lum 1
Sub-Total-9- Solar power system.
Grand Total of ( pump house, water kiosks, water transmission system and solar power) Project Name : Response to Drought Crisis in Somalia Area / Village: Balli x.Diriye village, Odwayne district , Togdheer Region-Somaliland.
BILL OF QUANTITIES - SUMMARY COSTS
Item Description Unit Qty Rate (USD) Amount (USD)
1 Annex-1 Dam Rehabilitations No. 1
Annex-2 construction of pumphouse, kiosks, water trasmission lines and solar 2 power system. No. 1 GRAND TOTAL.