0% found this document useful (0 votes)
35 views3 pages

Zonal Work Order

Uploaded by

raulbiswas007
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
35 views3 pages

Zonal Work Order

Uploaded by

raulbiswas007
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

WORK ORDER UNDER ZONE CONTRACT

Work order No. 00864100083247/Zone-1/2023-24/22 dated 17/05/2024


Under contract LOA No. 00864100083247 dated 01/08/2023.

Name of work: Petty repairs, color washing, painting etc. of RRI Cabin Howrah, RPF Yard Post
Howrah, Ganghut at Pilgrim Platform, and Strengthening of Bankim setu protection guard etc. at
Howrah Station Old Complex in Zone No-01 under AEN/HQ/Howrah.
(Site) Howrah Station Old Complex
Schedule of Drawings
Survey Sheet
Authority ADRM INFRA
Allocation 04-410-32

The Contractor ARINDAM GHOSH-KOLKATA is/are hereby ordered to carry out the following
works at percentage(s), above/below/At par the Schedule of Rates of Eastern Railway Corrected
upto latest correction slips of Howrah Division under Zone Contract Agreement here-in before
referred to:

The Works herein mentioned are required to be completed on or before 30/06/2024 (Date).The
quantities provided herein are approximinate and subject to variation under Clause 42 of the
Standard General condition of Contract corrected upto latest correction slips.

Railway :Sr.DEN/HQ/HWH
(For President of india)

I agree to complete the works herin set forth on or before the date specified under the Zone
Contract Agreement herin before referred to in conformity with the drawings hereto annexed and
in accordance with the General and Special (if any ) Conditions of Contract Corrected upto latest
Correction Slips and the Standard Specification of Eastern Railway with up-to-date Correction
Slips.
I also agree to maintain such works for the period specified below from the date of
completion:
(a) Repair and maintaince work including white/color washing: three calendar months
from date of completion.
Signature(b)NotAll
Verified
new works except earth work: Six calendar months fromSignature Not Verified
date of completion.
Digitally signed by ARINDAM GHOSH Digitally signed by MUKESH KUMAR
Date: 2024.05.24 18:58:18 IST JHA RAKESH
Reason: For sanction of zonal work Date: 2024.05.30 11:33:33 IST
order Reason: For sanction of zonal work
order

Contractor: ARINDAM GHOSH-KOLKATA Railway:


(For President of India)
Address:48/1A Dr.SURESH SARKAR ROAD , KOLKATA, West
Bengal-700014 India
Signature Not Verified
Digitally signed by MANOJ KUMAR
SAHU
Date: 2024.05.23 18:46:36 IST
Reason: For sanction of zonal work
order
Schedule - A
Bid
Basic SOR Tender
SL Amount rate/Unit Bid Amount (Rs.)
value Rate(%) rate
01 9000000.0 0.0 % At 9000000.0 null null 5711400
Par
Description : Schedule items covered under all chapters of USSOR-2011 which includes (i) New
works addition & alterations to existing structures, special repair works and
supply of building materials subject to the contract value of each such work order
not exceeding Rs.5.00 Lakhs (Rupees five lakhs) (ii) All ordinary repairs and
maintenance works and (iii) Conveyance of materials e.g. bricks, lime, sand etc.
which are likely to be required in a zone during the year. Note:-Approximate
Distribution of the proportion of cost will be as under: General civil works: 70% of
overall basic cost. Wood works:10% of overall basic cost. Sanitary works: 20% of
overall basic cost. The above distribution of cost may be varied with the approval
of DEN/Sr. DEN within the overall cost of the Zonal Contract.
Item No Item Code Qty. Unit Agmt. Rate Amount (Rs.)
1 031023 1.0 cum 1475.66076 1475.66
4
Description : 1:2:4 (1 cement : 2 sand : 4 graded stone aggregate 20mm nominal size)
2 033063 0.5 Tonne 4342.2505 2171.13
Description : PPC
3 041012 0.6 cum 1906.47801 1143.89
2
Description : All work in buildings above plinth level upto floor two level.
4 042013 3.0 Sqm 148.724856 446.18
Description : Suspended floors, roofs, landings, balconies, FOB slabs, walkway slabs and access
platform
5 045016 30.0 Kg 44.015856 1320.48
Description : Thermo-Mechanically Treated bars
6 051014 0.3 cum 1401.55852 420.47
2
Description : Cement mortar 1:4 (1 cement : 4 fine sand)
7 111071 5.0 Sqm 47.525194 237.63
Description : 1:3 (1cement: 3fine sand)
8 115060 1500.0 Sqm 15.966536 23949.8
Description : Applying one coat of cement primer of approved brand and manufacture on wall
surface
9 115080 1350.0 Sqm 52.982754 71526.72
Description : Finishing walls with Deluxe Multi surface paint system for interiors and exteriors
using Primer as per manufacturers specifications with two or more coats applied @
1.25ltr/10 sqm over and including one coat of Special primer applied @ 0.75
ltr/10sqm
10 117091 1500.0 Sqm 51.770668 77656.0
Description : Two or more coat, to give an even shade
11 121150 150.0 Sqm 30.23869 4535.8
Description : Painting two coats (excluding priming coat) with chocolate, red, grey or buff ready
mixed paint of approved quality, on steel or wood work
12 171012 20.0 Sqm 65.61764 1312.35
Description : With cement mortar 1:4 (1cement: 4coarse sand)
Total 186196.11
Summary Rupees
Schedule - A 186196.11
Schedule Total 186196.11
Amount (Rs.)
Rebate (0.0 %) 0.00
Amount (Rs.)
Total Amount 186196.11
(Rs.)