15.1 Reliability Studies

Download as pdf or txt
Download as pdf or txt
You are on page 1of 27

ETAP Workshop Notes

Reliability Analysis
Theoretical Concepts:
Need for Reliability Studies:
The fundamental planning in system planning is the correct determination of reserve capacity. Too low
a value means excessive interruption, while too high a value results in excessive costs. The greater the
uncertainty regarding the actual reliability of any installations, the greater is the investment cost wasted.

System behaviour is stochastic in nature and therefore it is logical to consider that the assessment of
such systems should be based on techniques that respond to this behaviour i.e. probabilistic techniques.
Definition of Reliability:
Probability whether a device does its task adequately in the given intended time, for a particular
operation (given operating conditions) with adequate performance. It therefore is a function of time.

Fig 1.1 Bath-Tub curve


ETAP Workshop Notes

Reliability Analysis
The factors that affect the system reliability studies are:
1. Failure rate: The failure rate of a component at time (t) is the probability of a component
failing at time (t) if the component is still functioning at time (t).
2. Failure intensity: It is the anticipated number of times an item will fail in a specified time
period, given that it was as good as new at t=0 and is functioning at time t. In ETAP, the failure
rate per year  of which there are two rates, a Active Failure Rate and p Passive Failure
Rate.
3. Failure density: It is defined as the probability per unit time that the component experiences
its first failure at time t, given that the component or system was operating at time (t) =0.
4. Mean time to failure (MTTF): It is the expected time the component will take to fail from the
state of being healthy.
5. Mean time to repair (MTTR): It is the expected time the component will take for a failure to
be repaired.
6. Availability of a component: Probability that the component or system is operating at time t,
given that it was operating at time (t) = 0.
7. Unavailability of a component: Probability that the component or system is not operating at
the time t, given that it was operating at time (t) =0.

For the ease of understanding the system and conducting the reliability studies, the system is reduced
and studied under the following configurations:
1. Series Configuration: A system whose subsystem or components form a series network. For the
system to fail, only 1 components/subsystem needs to fail.
 For a series system consisting on ‘n’ identical components, as the component reliability
increases, the system reliability also increases.
 However for a system reliability decreases as the number of identical series
components increases.
2. Parallel Configuration: A system whose subsystem or components form a parallel network. For
the system to fail all the components /subsystem must fail.
 For a parallel system consisting of ‘n’ components, as the number of components
increases (in parallel connection), reliability increases.
 However, increasing the number of components increases:
 Weight
 Cost
 Volume of the system
 Required maintenance.
ETAP Workshop Notes

Reliability Analysis

(A) (B)
Fig: (A) Series System Configuration (B) Component reliability v/s system reliability
graph

(A) (B)
Fig: (A) Parallel System Configuration (B) Component reliability v/s system
reliability graph.

The formulae required are:

a is the active failure in (failures/year)

p is the passive failure in (failure/year)


MTTR is the mean time to repair in hours

s or i is the overall or net failure/year


Us is the overall annual system outage in hours/year

rs =Us /s. Overall System Outage Rate (Comprising many components in series)

sis the Overall System Failure Rate per year.


The basic formulae for series and parallel system are discussed in the next section.
ETAP Workshop Notes

Reliability Analysis
FUNCTION & FORMULAE

For series elements

For parallel elements


(general)
ETAP Workshop Notes

Reliability Analysis

For 2 parallel elements

For 3 parallel elements

Unavailability (FOR) Availability

𝜆
U=
𝜆+µ
ETAP Workshop Notes

Reliability Analysis

Below table shows ETAP default values of the parameters for Grid, CB, Bus, Transformer and cable defined
above.

a in p in ri = MTTRi in
Component
Failures/year Failures/year
hours

GRID 0.643 0 2
CB 0.003 0.0045 50
BUS 0.001 0 2
Transformer 0.015 0 200
Cable 0.02 0.02 25

CASE 1:

1) Drag and drop Grid, CB and bus as shown below (default values as per Table1)

2) Go to Reliability Assessment module and click on Study Case and check the following options.

3) Run Reliability Assessment.


ETAP Workshop Notes

Reliability Analysis

4) Change from the display option to view Average Outage Duration (hours) or Annual Outage
Duration (Hours/year) and select Buses, Sources and Load Points in order to view the complete
results.
ETAP Workshop Notes

Reliability Analysis

5) ETAP results are found to match with the excel results shown below:
ETAP Workshop Notes

Reliability Analysis
CASE 2:

1) Connect as shown below.

2) Go to Reliability Assessment module and click on Study Case and check the following options.

3) Run Reliability Assessment.


ETAP Workshop Notes

Reliability Analysis
ETAP Workshop Notes

Reliability Analysis
4) ETAP results are found to match with the excel results shown. (In the excel factor for passive
failure is zero for all outgoing CBs).
ETAP Workshop Notes

Reliability Analysis
CASE3-1: WITHOUT FORCED REPLACEMENT TIME

1) Connect as shown below.

2) Go to Reliability Assessment module and click on Study Case and check the following options.
ETAP Workshop Notes

Reliability Analysis
3) Run Reliability Assessment.

Average Outage Duration (hr)

Annual Outage Duration (hr/yr)


ETAP Workshop Notes

Reliability Analysis
4) ETAP results are found to match with the excel results shown. (In the excel factor for passive
failure is zero for all CBs except the 1st link i.e. for CB91, CB92, CB93 & CB94 p is 0).
ETAP Workshop Notes

Reliability Analysis
CASE 3-2: WITH FORCED REPLACEMENT TIME

1) Go to transformer, click on Reliability page and check availability of replacement with a


faster repair time (because of easily replaceable spare or a changeover switch).

2) Run Reliability Assessment. It can be noted that the results are different from Case 3-1 since,
the lowest of the repair times are taken to compute rs (overall outage time in hours)
ETAP Workshop Notes

Reliability Analysis

3) ETAP results are found to match with the excel results shown. (In the excel factor for passive
failure is zero for all CBs except the 1st link i.e. for CB91, CB92, CB93 & CB94 p is 0).
ETAP Workshop Notes

Reliability Analysis
CASE 3-3: WITH ALTERNATIVE SUPPLY TIME LESS THAN MTTR

1) Go to transformer, click on Reliability page and check availability of replacement with a


faster repair time (because of easily replaceable spare or a changeover switch).

2) Run Reliability Assessment. It can be noted that the results are different from Case 3-1 since,
the lowest of the repair times are taken to compute rs (overall outage time in hours)

3) ETAP results are found to match with the excel results shown. (In the excel factor for passive
failure is zero for all CBs in the 1st link i.e. CB90, CB95 & CB96).
ETAP Workshop Notes

Reliability Analysis
CASE 3-4:

1) Go to transformer, click on Reliability page and check availability of replacement with a


faster repair time (because of easily replaceable spare or a changeover switch).

2) Run Reliability Assessment. It can be noted that the results are different from Case 3-1 since,
the lowest of the repair times are taken to compute rs (overall outage time in hours)

3) ETAP results are found to match with the excel results shown. (In the excel factor for passive
failure is zero for all CBs in the 1st link i.e. CB90, CB95 & CB96).
ETAP Workshop Notes

Reliability Analysis
CASE4:
1) Connect as shown below.

2) Run Reliability Assessment

3) ETAP results are found to match with the excel results shown. (Results for Bus 32)
ETAP Workshop Notes

Reliability Analysis
Length 30 km
For Bus 32 1 year= 8760 hours
CASE 4
Factor for λ
 a in  p in N ET  i in ri = MTTRi
Component  i * ri
Failures/year Failures/year
λ afactor λ pfactor Failures/year in hours

GRID U6 0.643 0 1 1 0.643 2 1.286


CB29 0.003 0.0045 1 1 0.0075 50 0.375
BUS31 0.001 0 1 1 0.001 2 0.002
O/g CB34 0.003 0.0045 1 1 0.0075 50 0.375
Cable1 0.6 0.6 1 1 1.2 25 30

BUS 33
0.001 0 1 1 0.001 2 0.002
(terminal box)
T4 0.015 0 1 0 0.015 200 3
O/g CB35 0.003 0 1 0 0.003 50 0.15
Bus32 0.001 0 1 1 0.001 2 0.002


n

 i
i
i
i .r i

1.879 35.192
(failures/year) failure-hours/year

Calculated value ETAP results


Overall systemfailure=NET λi=λs in failure/year 1.879 1.879
Overall annual system outage (hours/year)=Us 35.192 35.19
Overall outage time (system rs i.e., MTTR) in hours=Us/λs 18.72911123 18.8

4) ETAP results are found to match with the excel results shown. (Results for Bus 33)
For Bus 33 1 year= 8760 hours
CASE 4
Factor for λ
 a in  p in N ET  i in ri = MTTRi
Component  i * ri
Failures/year Failures/year
λ afactor λ pfactor Failures/year in hours

GRID U6 0.643 0 1 1 0.643 2 1.286


CB29 0.003 0.0045 1 1 0.0075 50 0.375
BUS31 0.001 0 1 1 0.001 2 0.002
O/g CB34 0.003 0.0045 1 1 0.0075 50 0.375
Cable1 0.6 0.6 1 1 1.2 25 30
BUS 33
0.001 0.0045 1 1 0.0055 2 0.011
(terminal box)

T4 0.015 0 1 0 0.015 200 3


O/g CB35 0.003 0 1 0 0.003 50 0.15
Bus32 0.001 0 1 1 0.001 2 0.002


n

 i
i
i
i .r i

1.8825 35.199
(failures/year) failure-hours/year

Calculated value ETAP results


Overall systemfailure=NET λi=λs in failure/year 1.8825 1.88
Overall annual system outage (hours/year)=Us 35.199 35.199
Overall outage time (system rs i.e., MTTR) in hours=Us/λs 18.69800797 18.7
ETAP Workshop Notes

Reliability Analysis
CASE 5: SINGLE AND DOUBLE CONTINGENCY

Cut-sets are considered here for performing the Single Contingency and Double
Contingency calculations.

The following circuit can be considered as three cut-sets as shown below:

Cut-set 1: series

Cut-set 2: parallel

Cut-set 3: series

For Single Contingency only the series cut-sets are considered, while for Double
Contingency, both series and parallel cut-sets are considered.
ETAP Workshop Notes

Reliability Analysis

1) Connect as shown below and keep the CB41 in the open condition.

2) Single contingency and double contingency for the above circuit will be discussed.
Single Contingency
a. Go to Reliability Assessment module and click on Study Case and check the
following options.
ETAP Workshop Notes

Reliability Analysis

b. Run Reliability Assessment

c. Excel results
ETAP Workshop Notes

Reliability Analysis
Single contingency
Length 30 km
1 year= 8760 hours
CASE 5
Factor for λ
 a in  p in N ET  i in ri = MTTRi in
Component  i * ri
λ afactor λ pfactor
Failures/year Failures/year Failures/year hours

GRID U6 0.643 0 1 1 0.643 2 1.286


CB29 0.003 0.0045 1 1 0.0075 50 0.375
BUS34 0.001 0 1 1 0.001 2 0.002
O/g CB37 0.003 0.0045 1 1 0.0075 50 0.375
Cable2 0.6 0.6 1 1 1.2 25 30
BUS 36 (terminal box) 0.001 0 1 1 0.001 2 0.002
T5 0.015 0 1 1 0.015 200 3
O/g CB38 0.003 0.0045 1 1 0.0075 50 0.375
Bus 35 0.001 0 1 1 0.001 2 0.002


n

i
i
i
i .r i

1.8835 35.417
(failures/year) failure-hours/year

Calculated value ETAP results


Overall systemfailure=NET λi=λs in failure/year 1.8835 1.879
Overall annual system outage (hours/year)=Us 35.417 35.19
Overall outage time (system rs i.e., Rp) in hours=Us/λs 18.80382267 18.8

Double contingency
For computation of double contingency, the above circuit has been divided into 3 sections:

1) Upper series section


a) Circuit

b) Excel
ETAP Workshop Notes

Reliability Analysis
Double contingency

Upper series section 1 year= 8760 hours


CASE 5
Factor for λ
 a in  p in N ET  i in ri = MTTRi in
Component  i * ri
Failures/year Failures/year
λ afactor λ pfactor Failures/year hours

GRID U6 0.643 0 1 1 0.643 2 1.286


CB42 0.003 0.0045 1 1 0.0075 50 0.375
BUS39 0.001 0 1 1 0.001 2 0.002
CB43 0.003 0.0045 1 0 0.003 50 0.15
CB 44 0.003 0.0045 1 0 0.003 50 0.15


n

i
i
i
i .r i

0.6575 1.963

(failures/year) failure-hours/year

Calculated value
Overall systemfailure=NET λi=λs in failure/year λs1 0.66
Overall annual system outage (hours/year)=Us Us1 1.96
Overall outage time (system rs i.e., Rp) in hours=Us/λs Rp1 2.9856

2) Middle parallel section


a) Circuit

b) Excel
ETAP Workshop Notes

Reliability Analysis
Double Contingency
Middle trafo parallel section
Length 30 km 1 year= 8760 hours

 p in Factor for λ
 a in N ET  i in ri = MTTRi in
Component Failures/yea  i * ri
λ afactor λ pfactor
Failures/year Failures/year hours
r

GRID U6 0.643 0 1 1 0.643 2 1.286


CB29 0.003 0.0045 1 1 0.0075 50 0.375
BUS34 0.001 0 1 1 0.001 2 0.002
O/g CB37 0.003 0.0045 1 1 0.0075 50 0.375
Cable2 0.6 0.6 1 1 1.2 25 30
BUS 36 (terminal
0.001 0 1 1 0.001 2 0.002
box)
T5 0.015 0 1 1 0.015 200 3
O/g CB38 0.003 0.0045 1 1 0.0075 50 0.375
Bus 35 0.001 0 1 1 0.001 2 0.002
n


n

i
i
i
i .r i

1.216 33.002
(failures/year) failure-hours/year

λ1 λ2 Up1 Up2 R1 R2 R1 R2
failure/year hours/year Years Hours
1.2160 1.2160 33.0020 33.0020 27.1398 27.1398 0.0031 0.0031

λp 0.0092
Rp 13.5699
Up 0.1243

3) Lower series section


a) Circuit

b) Excel
Double contingency

Lower series section 1 year= 8760 hours


CASE 5
 a in  p in Factor for λ
N ET  i in ri = MTTRi
Component Failures/y Failures/y  i * ri
λ afactor λ pfactor Failures/year in hours
ear ear

CB 38 0.003 0.0045 1 0 0.003 50 0.15


BUS35 0.001 0 1 1 0.001 2 0.002
CB 41 0.003 0.0045 1 0 0.003 50 0.15
n

  .r
n

i
i i
i i

0.007 0.302
(failures/year) failure-hours/year

Calculated value
Overall systemfailure=NET λi=λs in failure/year λs2 0.007
Overall annual system outage (hours/year)=Us 0.302
Us2
Overall outage time (system rs i.e., Rp) in hours=Us/λs Rp2 43.143
ETAP Workshop Notes

Reliability Analysis
4) Results of double contingency of Overall circuit

Note: the circuit breaker CB41 has to be kept closed while performing the double
contingency test.

Excel results
Units Upper series section Middle trafo parallel section Lower section Overall system results
Failurs/year λs1 0.66 λp 0.0092 λs2 0.007 0.674
Houys/year Us1 1.96 Up 0.1243 Us2 0.302 2.389
Hours Rp1 2.99 Rp 13.5699 Rp2 43.143 3.547

You might also like