Psoc Unit 1
Psoc Unit 1
The operation and control of the system should ultimately maintain the following:
Stability:
Continued intact of the system, following a disturbance.
This depends on the operating condition and the nature of the disturbance.
Security:
It is the degree of the risk in the power system's ability to survive contingencies
without interruption to the consumer.
It is related to the robustness of the system
Reliability:
It is the probability of satisfactory operation over a long period.
It denotes the ability of the system to supply adequate service on a nearly continuous
basis, with a few intermittent interruptions over an extended time period.
Various controls in a power system
Operating States of Power System
1. Normal state
2. Alert state
3. Emergency state
4. Inextremis state
5. Restorative state
Normal state:
A system is said to be in normal if both load and operating constraints are satisfied.
It is one in which the total demand on the system is met by satisfying all the operating
constraints.
Alert state:
A normal state of the system said to be in alert state if one or more of the postulated
contingency states, consists of the constraint limits violated.
When the system security level falls below a certain level or the probability of
disturbance increases, the system may be in alert state.
All equalities and inequalities are satisfied, but on the event of a disturbance, the system
may not have all the inequality constraints satisfied.
If severe disturbance occurs, the system will push into emergency state. To bring back
the system to secure state, preventive control action is carried out.
Emergency state:
The system is said to be in emergency state if one or more operating constraints are
violated, but the load constraint is satisfied.
In this state, the equality constraints are unchanged.
The system will return to the normal or alert state by means of corrective actions,
disconnection of faulted section or load sharing.
Inextremis state:
When the system is in emergency, if no proper corrective action is taken in time, then
it goes to Inextremis state.
In this regard neither the load or nor the operating constraint is satisfied, this result is
islanding. Also, the generating units are strained beyond their capacity.
So emergency control action is done to bring back the system state either to the
emergency state or normal state
Restorative state:
From this state, the system may be brought back either to alert state or secure state.
The latter is a slow process.
Hence, in certain cases, first the system is brought back to alert state and then to the
secure state. This is done using restorative control action.
Operating States of Power System
Functions
Tie-line
The area B represents an operating area of inter
connected power system in which sudden load
or generation change occurs, Area A forms the
rest of the power system.
Areas share a disturbance in proportion to their
generating capacity size and operating
characteristics.
Let the Area A overall generation frequency be
represented by curve GG
The shaft speed and consequently the electrical
line frequency changes with load reflected onto
the prime mover.
The generation – frequency characteristics
curve has a negative slope or droop.
Basic Equations
GA = G0 +10β1 (fact – f0) MW --------- (1)
LA = L0 +10β2 (fact – f0) MW --------- (2)
GA = Total Generation,
G0 = Base generation
LA = Total Load
L0 = Base load
fact = System frequency
f0 = Base frequency
β1 = Cotangent of generation-frequency characteristic, MW/0.1 Hz < 0
β2 = Cotangent of load-frequency characteristic, MW/0.1 Hz > 0
Isolated Operation in A – response to load change
Increase in load in ‘A’ moves the load frequency curve to position L’L’.
The new system frequency will now be defined by the intersection labeled as I1 at
49.9Hz.
Then it is desired to return the system frequency to 50.0Hz i.e., point I2.
Setting AGC in ‘A’- shifting of GG to G’G’ takes place to meet frequency demand of
50.0Hz – I2
Resulting combined characteristic is C’C’ In terms of increments,
ΔA = GA - G0 + L0 - LA = 10β1 (fact – f0) - 10β2 (fact – f0)
= 10BA XA (fact – f0)
= 10BA XA Δf MW ------------- (4)
Where,
BA - Natural regulation characteristic of area expressed in % gen for 0.1Hz
XA – Generating Capacity of Area A, MW
Thus The load increase, ΔA (or generation decrease) in area A leads to a Frequency
deviation.
Frequency deviation = Δf =
ΔA Hz ------- (5)
10BA XA
Define a real power tie-line flow, ΔTL as a power quantity out of area, the combined
effect on frequency for a load increase (or generation decrease) and positive tie flow on area.
Then, considering Tie line flow Frequency deviation
Δf =
ΔA + ΔTL Hz --------(6)
10BA XA
Where,
ΔA + ΔTL - Net Megawatt change
ΔTL = ΔGA - ΔLA
Frequency change due to disturbance B for a tie line power flow from A to B is
Δf =
ΔB - ΔTL Hz ------- (8)
10BB XB
Let, ΔAB = ΔB be the magnitude of disturbance that occurs in area B and ΔA = 0.
Since the frequency is common for both systems,
Δf =
ΔTL = ΔAB - ΔTL Hz ------ (9)
10BA XA 10BB XB
Solving the equation (9) for tie-line flow ΔTL,
(10BA XA) ΔAB
ΔTL = MW ------ (10)
(10BA XA +10BB XB)
Equation (10) is the expression for Tie-line power.
ΔTL =372.41 MW
(10BBXB) ΔAB
Area B‘s share, ΔAB - ΔTL = MW
(10BAXA +10BBXB)
(10*0.01*4000)*400
ΔAB - ΔTL =
(10*0.015*36000+10*0.01*4000)
Frequency Deviation,
ΔAB
Δf (10BAXA+ 10BBXB)
Hz
400
Δf =
(10*0.015*36000+10*0.01*4000)
Δf = 0.0689 Hz
Parallel operation of Generators:
Tie line flows and frequency droop described for interconnected power areas are
composite characteristics based on parallel operation of generators. Each area could maintain
its speed w = 2f, then a load common to both areas, by superposition have the terminal voltage,
Vload = V1sinw1t + V2sinw2t,
Where, 1&2 represents areas and ‘t’ time in secs.
Generator speed versus load characteristics is a function of the type of the governor
used on the prime mover- type 0 – for a speed droop system and type 1 – for constant speed
system.
Therefore,
Unit speed regulation = R = Δf(pu)/ΔP(pu)
Load
Since the frequency is common to both units, they will share according to the ratio,
ΔP1 R2 P1 rate
-------------- (3)
ΔP2 R1 P2 rate
Initial Loads - P1 and P2, change in load
ΔL = ΔP1 + ΔP2
Δf P1 rate Δf P2 rate
ΔL = R1
+ R2
𝟏
Rsys =
P1 rate +
P2 rate
R1 R2
Problem: Two machines operate in parallel to supply a load of 400 MW. The capacities of
the machines are 200 MW and 500 MW. Each has a droop characteristic of 4%. Their
governors are adjusted so that frequency is 100% on full load. Calculate the load supplied by
each unit and the frequency at this load. The system is a 50Hz system.
Sol:
Problem:
Two generators rated 200 MW and 400 MW are operating in parallel. The droop
characteristics of their governor are 4%, and 5%, respectively from no load to fill load. The
speed set points are such that the generators operate at 50Hz when sharing the full load of 600
MW in proportion to their ratings:
(i) If lead reduces to 400 MW, who is the load shared, at what, frequency will system
Operate.
(ii) If speed changer arc reset so that load of 400 MW is shared at 50 Hz in proportion to
their rating what is the no load frequency now.
Sol:
Problem:
Two generators rated 200MW and 400MW are operating in parallel. The droop
characteristics of their governors are 4% and 5% respectively from no load to full load.
Assuming that the generators are operating at 50Hz at no load, how would a load of 600MW
be shared between them? What will be the system frequency at this load? Assume free governor
operation.
Sol:
Load shedding area lumped dynamic model
The model discussed so far is one macroscopic behavior because there is no effort made
to indicate instantaneous power flow within the system due to a tie line disturbance, magnitudes
of the internal line flows, the time history of generator phase angles and so on. The power
system macro model may be described by means of a block diagram as shown in the block
diagram.
SCADA – Supervisory Control and Data Acquisition:
One of key processes of SCADA is the ability to monitor an entire system in real time.
This is facilitated by data acquisitions including meter reading, checking statuses of sensors,
etc that are communicated at regular intervals depending on the system.
A well planned and implemented SCADA system not only helps utilities deliver power
reliably and safely to their customers but it also helps to lower the costs and achieve higher
customer satisfaction and retention.
SCADA - Architecture
Basic elements are sensors which measure the desired quantities
Current Transformers CTs – measure currents and Potential Transformers PTs-measure
voltages.
Today there is a whole new breed of Intelligent electronic devices (IEDs)
This data is fed to a remote terminal unit (RTU)
The master computer or unit resides at the control center EMS
SCADA - Process
Master unit scan RTUs for reports, if reports exist, RTU sends back the data and the
master computer places it in memory
In some new substation architectures, there could be significant local processing of
data which could then be sent to the control center.
The data is then displayed on CRTs and printed
SCADA - Logging
The SCADA provides a complete log of the system
The log could be provided for the entire system or part of the system
Type of information provided – Time of event
– Circuit breaker status
– Current measurements, voltage measurements, calculated flows, energy, etc.
– Line and equipment ratings
SCADA as a System
There are many parts of a working SCADA system. A SCADA system usually includes
signal hardware (input and output), controllers, networks, user interface (HMI),
communications equipment and software. Altogether, the term SCADA refers to the entire
central system. The central system usually monitors data from various sensors that are either
in close proximity or off site (sometimes miles away).
For the most part, the brains of a SCADA system are performed by the Remote
Terminal Units (sometimes referred to as the RTU). The Remote Terminal Units consists of a
programmable logic converter. The RTU are usually set to specific requirements, however,
most RTU allow human intervention, for instance, in a factory setting, the RTU might control
the setting of a conveyer belt, and the speed can be changed or overridden at any time by human
intervention. In addition, any changes or errors are usually automatically logged for and/or
displayed. Most often, a SCADA system will monitor and make slight changes to function
optimally; SCADA systems are considered closed loop systems and run with relatively little
human intervention.
SCADA can be seen as a system with many data elements called points. Usually, each
point is a monitor or sensor. Usually, points can be either hard or soft. A hard data point can
be an actual monitor; a soft point can be seen as an application or software calculation. Data
elements from hard and soft points are usually always recorded and logged to create a time
stamp or history
User Interface – Human Machine Interface (HMI)
A SCADA system includes a user interface, usually called Human Machine Interface
(HMI). The HMI of a SCADA system is where data is processed and presented to be viewed
and monitored by a human operator. This interface usually includes controls where the
individual can interface with the SCADA system.
HMI's are an easy way to standardize the facilitation of monitoring multiple RTU's or
PLC's (programmable logic controllers). Usually, RTU's or PLC's will run a pre-programmed
process, but monitoring each of them individually can be difficult, usually because they are
spread out over the system. Because RTU's and PLCs historically had no standardized method
to display or present data to an operator, the SCADA system communicates with PLC's
throughout the system network and processes information that is easily disseminated by the
HMI.
HMI's can also be linked to a database, which can use data gathered from PLC's or
RTU's to provide graphs on trends, logistic info, schematics for a specific sensor or Machine
or even make troubleshooting guides accessible. In the last decade, practically all SCADA
systems include an integrated HMI and PLC device making it extremely easy to run and
monitor a SCADA system.
Today’s SCADA systems, in response to changing business needs, have added new
functionalities and are aiding strategic advancements towards interactive, self-healing smart
grids of the future. A modern SCADA system is also a strategic investment which is a must-
have for utilities of all sizes facing the challenges of the competitive market and increased
levels of real time data exchange that comes with it (Independent Market Operator, Regional
Transmission Operator, Major C&I establishments etc). A well planned and implemented
SCADA system not only helps utilities deliver power reliably and safely to their customers but
it also helps to lower the costs and achieve higher customer satisfaction and retention. Modern
SCADA systems are already contributing and playing a key role at many utilities towards
achieving:
New levels in electric grid reliability – increased revenue.
Proactive problem detection and resolution – higher reliability.
Meeting the mandated power quality requirements – increased customer satisfaction.
Real time strategic decision making – cost reductions and increased revenue
The digital computers are usually employed in a fixed-cycle operating mode with priority
interrupts wherein the computer periodically performs a list of operation. The most critical
functions have the fastest scan cycle. Typically, the following categories are scanned every 2
seconds:
- All status points such as switchgear position (open or closed), substation loads and
voltages, transformer tap positions, and capacitor banks etc.,
- Tie line flows and interchange schedules
- Generator loads, voltage, operating limits and boiler capacity
- Telemetry verification to detect failures and errors in the bilateral communication links
between the digital computer and the remote equipment.
Q. What is SCADA (supervisory control and data acquisition) and how does it work?
(Or) What is a SCADA System, describe about the major components of SCADA
system.
SCADA (supervisory control and data acquisition) is a category of software
applications for controlling industrial processes, which is the gathering of data in real time from
remote locations in order to control equipment and conditions. One of the most commonly used
types of industrial control system, SCADA can be used to manage almost any type of industrial
process. SCADA systems include hardware and software components. The hardware gathers
and feeds data into field controller systems, which forward the data to other systems that
process and present it to a human-machine interface (HMI) in a timely manner. SCADA
systems also record and log all events for reporting process status and issues. SCADA
applications warn when conditions become hazardous by sounding alarms.
SCADA is a system of hardware and software elements that facilitate process control.
This central control system consists of communication equipment, network interfaces, input/
output devices and software. It allows organizations to carry out following functions:
Manage industrial processes remotely or locally.
Real-time data gathering, monitoring and processing.
Direct interaction with devices like valves, motors, pumps, valves using Human
Machine Interface (HMI) software.
Create a log file of events.
Basic Components of SCADA System
A basic SCADA system consists of following components: