2016 Iter Annual Report
2016 Iter Annual Report
JANUARY
¢ Scientist Fellow network launched
FEBRUARY
¢ Monaco-ITER International Fusion Energy Days (MIIFED), third edition
MARCH
¢ First components installed in Tokamak Complex basement
(water detritiation tanks)
APRIL
¢ ITER Council reviews independent assessment of the updated project
schedule in extraordinary meeting
MAY
¢ ITER Robots contest, fifth edition
JUNE
¢ Eighteenth ITER Council validates the updated schedule through
First Plasma
¢ Construction Management-as-Agent contract awarded to the
MOMENTUM joint venture (Amec Foster Wheeler, UK, in
partnership with Assystem, France, and KEPCO Engineering and
Construction, Korea)
¢ Main cranes installed in Assembly Building
JULY
¢ Project Team created for cryogenics
¢ First ITER Project Associate arrives
SEPTEMBER
¢ Cooperation Agreement signed with the Australian
Nuclear Science and Technology Organisation (ANSTO)
¢ Cryostat welding begins on site
¢ New organizational matrix for construction oversight
¢ ITER Games, sixth edition
OCTOBER
¢ First toroidal field winding pack completed in Europe
¢ Open Doors Day with 600 participants
¢ Two-day press event for international journalists
NOVEMBER
¢ Nineteenth ITER Council endorses updated project schedule to
Deuterium-Tritium Operation
DECEMBER
¢ 15,000 people visit the ITER construction site in 2016
¢ Immersive reality tour of site construction launched
¢ 19 of 20 ITER Council milestones achieved for the year
ITER ORGANIZATION
2016 ANNUAL REPORT
C oncluding a two-year effort by the ITER Organization
and the seven Domestic Agencies to establish a new
baseline, the overall project schedule was approved by
the ITER Council in November 2016. The project in its
entirety is now moving forward according to this very
detailed blueprint, which identifies the date of First
Plasma as December 2025 and lays out a staged
approach to full Deuterium-Tritium Operation in 2035.
CONTENTS
In June, the four large girders of the Assembly Hall’s overhead bridge crane are lifted to a
height of 43 metres and installed on rails.
US contractors complete the winding of the first central solenoid module in April. Six
modules – each made from approximately 6,000 metres of niobium-tin superconductor
supplied by Japan – will be stacked to form the 13-metre-tall central magnet. Photo: US ITER
I
t is my pleasure to introduce the 2016 ITER
Organization Annual Report, the first under my
tenure as ITER Council Chair.
The year that has passed has been one of transition, FOREWORD FROM THE
as the actors of the ITER Project came together around
a clear roadmap to ITER construction. In approving the CHAIR OF THE ITER COUNCIL
Overall Project Schedule in November, as well as the
won namkung
Overall Project Cost ad referendum, the ITER Council Saint-Paul-lez Durance
recognized the project-wide improvements that have July 2017
resulted from reforms carried out by the Director-
General in the framework of his Action Plan.
Although the implementation of these reforms is an
ongoing process, actions tailored to address the
difficulties identified in project management have
already made a difference. Reports received in 2016
from the ITER Council Review Group (ICRG) and the 2015
Management Assessment both confirmed the
reinforced capacity of the project to properly forecast,
manage and execute. Improvements in a number of
critical areas such as systems engineering and
integration, project control, decision-making processes,
and international coordination made the development
of a credible updated schedule and associated resource
estimates possible. against ITER Project Milestones as reported to the
We now have two distinct milestones ahead of us: a Council every two months has been steady. The original
clear date for the achievement of First Plasma (December list of milestones for 2016-2017 has been extended
2025) and a detailed approach to the start of Deuterium- through to the achievement of First Plasma, with each
Tritium Operation in 2035. incremental step bringing the project closer to
Without minimizing the challenges, I believe that the completion. The ITER Council will continue to closely
ITER Project is on the path to success. Performance monitor and support the project’s ability to achieve
these milestones as well as its capacity to anticipate and
mitigate eventual risks to delay in the schedule.
Maintaining performance in the years ahead will be
critical, as delay related to construction or manufacturing
– or even financial or political hurdles – will set off a ripple
of accompanying difficulties. I have no doubt about the
commitment of all ITER Members to supporting the
project’s momentum, with the common understanding
that each Member still needs to go through its domestic
process to secure support and financial resources for the
updated project baseline.
The construction of ITER, which can only be achieved
by overcoming monumental complexity, will be a
testimony to the scientific and technology capabilities
of all participating Members. Together, we are engaged
in one of the most thrilling human adventures of our
times and one that could permanently alter the course
of history.
I congratulate the entire team – from the Director-
General to every staff member at the ITER Organization
and the Domestic Agencies, plus contractors and suppliers
globally – for their commitment to effective collaboration
that has put the project on the path to success.
The pace of Tokamak Complex construction accelerated in 2016 due to an increase in the
number of workers and the introduction of a second shift. The main Tokamak Building
must be ready for early-access assembly activities in late 2018.
F
or the project to move forward, it was essential for
us to accomplish two objectives over the past two
years: first, to execute sweeping organizational
reform, fully addressing and correcting the problems FOREWORD FROM THE
identified in the 2013 Management Assessment report;
and second, while in the midst of this reform, to shift to DIRECTOR-GENERAL
full-paced construction and manufacturing in respect of
bernard bigot
milestones agreed with the ITER Council for the years Saint-Paul-lez Durance
2016 and 2017, even as the examination of our updated July 2017
long-term project schedule and associated resource
estimates was underway.
The successful achievement of this ambitious program
was critical to ensuring that the ITER Members, the ITER
Organization and the Domestic Agencies regain full
confidence in the project and in themselves. It was a
prerequisite for the pursuit of ITER and, finally, success.
Thanks to the joint effort of the management, staff and
contractors of the ITER Organization and the Domestic
Agencies, and the strong, continuous support of the ITER
Members, we have reached the goals we set for ourselves
and, today, the ITER Project has turned the page. More
remains to be done but I do believe that we have created
a new culture of collaboration, within which we candidly
face the challenges that arise and jointly seek the industrial expertise of the CMA as we enter a new
solutions that are in the best interest of the project. chapter of ITER construction.
In 2016, we successfully concluded a series of iterations And because I feel strongly that to exploit the
to develop an updated resource-loaded schedule, taking machine's potential and to optimize its performance
a comprehensive look at each Member’s technical, ITER will rely on major contributions from the
financial and political constraints to arrive at the best Members' fusion science communities, we are striving
compromise. Within the revised baseline schedule to reinforce interaction. There are now 45 international
endorsed by the ITER Council in November 2016, First organizations, national laboratories, universities and
Plasma is planned for December 2025, followed by a national schools from the ITER Members that have
staged approach to the development of machine and signed scientific or technical cooperation agreements
auxiliary system performance that culminates in the with the ITER Organization, and in 2016 we welcomed
transition to deuterium-tritium operation in 2035. the first non-Member entity – the Australian Nuclear
This intense collaborative work on the schedule has Science and Technology Organisation, ANSTO. The first
had important side benefits as – in order to successfully scientists accepting to participate in the new ITER
complete the exercise – we had to resolve pending Organization Scientist Fellow network and collaborate
questions related to design completion, project change with our specialists on simulation and theory in
requests, and technical issues. The project as a whole is support of ITER also met on site to confirm short- and
in a much stronger position due to this effort. long-term research objectives.
In parallel, we are completing ambitious milestones in It is not an exaggeration to say that thousands of
building construction and the fabrication of First Plasma people are working around the world to make ITER a
components as scheduled and preparing for the success. At the ITER Organization, in the Domestic
assembly and installation phase of the machine and Agencies, in factories, labs and universities our efforts are
plant. A new construction management organization – focused on building, commissioning, and operating a
based on construction teams with responsibility for unique scientific device – the only one on Earth capable
specific areas on the worksite – as well as the selection of producing a burning plasma in the next decades. With
of the ITER Organization’s principal assembly contractor, me, and you, they share the conviction that ITER will
the Construction Management-as-Agent (CMA), were show the way to a new, safe, environmentally responsible
two important steps to ensuring that the knowledge of and virtually inexhaustible energy source that is well
components and systems that exists within our worth the large investment of the seven ITER Members
respective organizations is successfully integrated with and the best joint efforts of our staff and industries.
Work on the Tokamak Complex is now evolving at or above ground level as European contractors
start on the first ground elevation of the ITER bioshield (circle) and Diagnostics Building (right).
EXECUTIVE
SUMMARY
O
n 21 November 2006, the government representatives of
the People’s Republic of China, the European Atomic Energy
Community (Euratom), the Republic of India, Japan, the
Republic of Korea, the Russian Federation and the United States
of America signed the constitutive document of the ITER
Organization in Paris. In the Preamble of the ITER Agreement, the
Members emphasized their belief that “ITER is the next important
step on the path to develop fusion energy” and affirmed the
significance of “genuine partnership in implementing this long
term and large scale project.”
Ten years later, the Members’ vision is crystallizing on the ITER site
in southern France, as the buildings of the scientific installation
emerge and components shipped from factories around the world
are stored for the start of assembly and installation. The stage is now
set for the world’s largest fusion reactor to enter operation in 2025.
The ITER Director-General welcomes H.S.H. Prince Albert II of Monaco to the site in
From design and early construction activities, the project has September. Through the Monaco-ITER Partnership Arrangement, signed in 2008, the
transitioned to full-paced construction and manufacturing. Broad Principality of Monaco has funded over 20 postdoctoral researchers at ITER for two-year
reform has increased the fundamental strength of the organization, assignments and hosted three international conferences.
its management, and the international collaboration that
underwrites all efforts. A detailed work plan defining project scope, level. Project Teams for buildings, the vacuum vessel, and
schedule and cost through First Plasma and Deuterium-Tritium cryogenics now focus cross-project resources on highly
Operation – the 2016 Baseline – has earned the approbation of integrated and/or schedule critical areas. Decision-
internal and external observers. making efficiency has been improved at the working
In an early sign that the ITER Organization and the Domestic level through the Central Team Management Board (ITER
Agencies have the capacity to meet the baseline schedule as Organization) and the Joint Project Coordination weeks
proposed, 19 out of 20 high-level technical and programmatic (ITER Organization/Domestic Agency).
milestones planned as a way to measure performance in 2016 were The proposed updated long-term schedule and
achieved, and the twentieth was delayed by only a matter of weeks. associated resource estimates as well as the ITER
Through organizational effectiveness and sustained physical Organization’s management of human resources were
progress, the project is demonstrating its capacity to complete the the object of rigorous review by the ITER Council
construction phase of the project with reliability and accountability. Independent Review Group (ICRG) beginning in February.
Its report, which provided the ITER Council with
ORGANIZATION external validation of the credibility of the proposal and
Completing reform its underlying assumptions as well as recommendations
The bulk of the Action Plan proposed to the ITER related to human resource management, was accepted
Council by Director-General Bernard Bigot at the start of by the ITER Council during an extraordinary meeting in
his mandate in March 2015 has effectively been April (IC-Ex/04.16). The ITER Council also convened for two
implemented. Three essential pillars of reform – regular meetings during the year on 15-16 June (IC-18)
management and organizational restructuring at the and 16-17 November (IC-19), during which it reviewed the
ITER Organization, improved collaboration between the continued development of the baseline and the
central team and the seven Domestic Agencies, and implementation of project reforms. The Management
improvements to project management practices – have Advisory Committee (MAC), the Science and
resulted in stronger control of schedule, cost and risk. Technology Advisory Committee (STAC) and the Test
The ITER Organization has reinforced the transversal Blanket Module Program Committee (TBM-PC) met
functions of engineering integration, configuration ahead of each Council session to provide support for
control, quality assurance, project control and human strategic issues. The results of the 2015 ITER Management
resources, and introduced the first phase of a new Assessment were reported to the ITER Council in June.
construction management organization to prepare for
the lead role that it will play in the assembly and BASELINE
installation of the machine and plant. The Executive First Plasma in December 2025
Project Board, introduced in 2015 to unite the top Concluding a two-year effort by the ITER Organization
management of the ITER Organization and the Domestic and the seven Domestic Agencies to update the baseline,
Agencies, is working well to resolve issues at the senior the overall project schedule was approved by the ITER
Just outside the three-metre-thick ITER bioshield (partially covered in blue), workers
pour the south side of the bioshield mezzanine. Photo: F4E
The 18 D-shaped toroidal field coils are among the largest components of the ITER
machine. The very first toroidal field winding pack (110 tonnes) is produced by European
contractors in October. Photo: F4E
2016 HIGHLIGHTS
BY DEPARTMENT
PROJECT CONTROL OFFICE (PCO) also the occasion to discuss and resolve identified
The Project Control Office ensures the coordinated action of technical issues and to escalate a small number of top
project controls, manages the ITER Baseline (scope, schedule, issues, with recommendations, for decision making by
cost, and risk), monitors schedule variation and response the Director-General.
actions, performs risk and opportunity analysis, and In November, the ITER Council (IC-19) commended
evaluates the efficiency of management systems. the ITER Organization and the Domestic Agencies for
The updated long-term schedule presented to the the successful development of the updated schedule,
ITER Council in November 2015 (the “reference the fruit of two years of integrated effort. All Members
schedule”) was the foundation for the establishment approved the project schedule and estimated cost
of the ITER Baseline in 2016. The Project Control Office including staff resources up to 2025, as well as the
was centrally involved in these efforts, preparing for indicative schedule and cost baseline up to the start of
meetings of the ITER Council and advisory bodies and burning plasma operations (2035) based on the staged
working to articulate a “staged approach” to plasma approach. The overall project cost was approved ad
operation with respect to the technical challenges and referendum, pending approval through each Member’s
financial constraints of the Members. specific governmental budget process.
Project progress was controlled and reported
throughout 2016 on the basis of high-level project or
Project progress is controlled and reported programmatic milestones approved by the ITER Council.
on the basis of high-level milestones Out of 20 ITER Council milestones planned for the year
approved by the ITER Council. 19 were achieved – with the last delayed by only a few
weeks without impact on the schedule. Similar high-
level “markers” have now been identified through First
The methodology and the preparation underpinning Plasma and will continue to be tracked and reported
the first year of schedule development were validated every two months as an important monitoring tool.
by an ITER Council Review Group in February and the To answer to the need for more precise statusing,
subsequent extraordinary meeting of the ITER Council; effective change control and more meaningful trend
based on this positive result and further analysis, the Project Control Office also introduced a
recommendations for optimization, a project-wide effort new schedule management tool during the year – a
was launched to complete integration activities. In parallel, simplified Master Schedule. Consistent with the
the ITER Organization and Domestic Agencies worked Detailed Work Schedules submitted by the Domestic
through several iterations to develop the staged approach Agencies in September, the Master Schedule formed
to operation – four distinct phases of operation from First the basis of the baseline schedule submitted to the ITER
Plasma to deuterium-tritium experiments, interspersed Council. The Detailed Work Schedules are still used to
with periods of assembly – that reduce funding monitor execution at the working level on a daily basis
requirements from the Members for the 2017-2019 and to provide forecast delivery dates, while the Master
period. The staged approach also lowers project risk by Schedule is used to monitor the rate of achievement
focusing on First Plasma and allows for a longer research against commitments. With ten times fewer activities,
program between First Plasma and fusion operation.
At the eighteenth ITER Council in June, representatives of
the ITER Members endorsed the updated resource-loaded
schedule to First Plasma (December 2025) and charged the
ITER Organization with extending the integrated schedule
through Deuterium-Tritium Operation.
Six months of tightly coordinated effort with the
Domestic Agencies ensued to establish the detailed
consistency of the full 2016 Baseline within the frame
of the staged approach. At two workshops held at ITER
Headquarters in July – the Configuration Workshop
and the Research Plan Workshop – lists of components
were established for each installation phase and need
dates defined in full compatibility with the Members’
In March, a water detritiation tank supplied by Europe becomes the first plant
financial constraints and the planned scientific
component to be installed in the Tokamak Complex.
research program. The Configuration Workshop was
quality and planning documents finalized. The Document and suppliers (650 in all), while continuing to monitor
Control Section was active in preparing for on-site outsourced work packages, CAD earned value
activities by establishing document control procedures, measurements, and key performance indicators to ensure
determining the criteria for handing over engineering the efficiency and quality of the work. The Office moved
documentation packages to the Construction to set up control groups, enhance quality control, create
Department, and improving the management of standardized technical documents, and develop industrial
radiographic material and as-built documentation. technical plateaus (schematics, drawings, plant design) in
The Project Information System Section/Division (IT) support of the tight schedule.
continues to manage computer services, databases and
networks, telecommunications, and the project’s internal
and external websites, adding 1,000 new computers to The ITER Organization has worked over the
its base in 2016, managing 4,500 video conferences and past two years to reinforce the transversal
treating 23,000 user requests. IT oversees some 40 functions of engineering integration,
outsourced contracts, seeking the best value for configuration control, quality assurance,
investment, and maintains the ITER Organization’s project control, and human resource
central applications and central infrastructure. management.
In 2016, the group upgraded the SAP solution for
administration, created new applications and interlinks
between software programs to reflect business needs, To efficiently support the construction phase,
supported the integration of the Construction improvements were launched or initiated in the area of
Management-as-Agent team, and continued to multi-CAD usage, advanced drafting capabilities, improved
collaborate on the use of the SmartPlant® suite for mass production tools, clarified documentation, and PLM
materials management and construction. Significant support; the new AVEVA plant design suite was also
resources were also devoted to the development and deployed and centrally administered. A workshop hosted
trial of the PLM project management tool, the in May in China with all Domestic Agencies brought users
reinforcement of cyber security, and the improvement together in the interest of improving collaboration.
of computing capacity. In October, a protocol for The Analysis Section/Division is charged with
massive data transfer developed in Japan was tested structural, seismic, nuclear and electromagnetic analysis
successfully with the participation of ITER IT experts. in support of project priorities, with emphasis on
In collaboration with IT, the Design Office Division interfaces and the design integration of the plant in
administers the project’s CAD infrastructure. In 2016 it collaboration with the Domestic Agencies. In 2016, team
supported the technical responsible officers in the members pursued the definition of interface loads
execution of the year’s full CAD work plan, in particular between buildings and equipment in the Tokamak
producing thousands of schematics and drawings in Complex for the sizing of embedded plates; performed
support of construction call-for-tenders. The Office treated calculations to confirm the interface load between the
requests for support and tickets for data exchange from cryostat bellow flanges and the bioshield in accidental
users at the ITER Organization, the Domestic Agencies conditions; collaborated with the Korean Domestic
Agency on the structural analysis of the sector sub-
assembly tool and assembly tool group B1; and
contributed to the completion of building design by
responding to requests for information. Twenty-five
additional system load specification reports were
finalized, bringing the number on record to 226.
In an important milestone for the project, Division staff
completed work begun last year to update design floor
response spectra for the Tokamak Complex. These key
input documents – critical to the design of all
components located in this area – have now been
approved as part of the technical baseline. A more
accurate model of the building and all internal equipment
was developed in close collaboration with the European
Engineers at ITER use virtual renditions of the machine’s systems to verify integration
agency and reconciliation has started to implement
issues, interfaces and assembly sequences.
changes in the impacted equipment. In parallel, the
Series production is underway in Japan on the building blocks of the toroidal field coils –
double pancake windings. Each winding is insulated by glass and polyimide tapes and
impregnated with cyanate-ester and epoxy resins to harden the assembly. Photo: ITER Japan
evaluation of floor response spectra for SL-3-rated seismic QUALITY ASSURANCE & ASSESSMENT DIVISION (QAA)
events is underway for the Tokamak Complex. The Quality Assurance & Assessment Division’s objectives are
To ensure a consistent and fully integrated nuclear to specify project quality requirements, perform independent
engineering approach in the project, compliant with assessments and audits on requirement compliance, and
project and regulatory requirements, the Director-General coordinate the integrated management system through the
created a Nuclear Integration Unit in 2016. Staffed with Management and Quality Program. The Division ensures that
experts from the ITER Organization and the Domestic the processes needed for the quality management system are
Agencies and under the functional responsibility of the properly established, implemented and maintained; reports to
CIO Department, the Unit was effective immediately – top management on the performance of the quality
producing a radiation transport model for the buildings of management system; and works to promote awareness of
the Tokamak Complex; assessing the issue of toroidal field ITER Organization or stakeholder requirements throughout
coil heating; performing nuclear analyses (for example on the organization.
dust filtering, in-vessel viewing systems, neutral beam Strong progress on the central database for processing
cell/neutral beam injection, and equatorial bioshield non-conformities means that this quality assurance
plugs); creating the first shut-down dose rate maps based management tool will be ready for launch in 2017. Until
on global analysis; and generating nuclear radiation maps then, temporary measures were employed during the
to provide a comprehensive view of the potential effect of year to track non-conformities and to alert responsible
radiation on Tokamak components. The Unit also parties in order to reduce the average duration from
works with the Environmental Protection & Nuclear Safety detection to closure.
Division on responses to questions from the French
nuclear safety authority.
The list of electronics exposed to nuclear radiation was In order to prepare for the lead role that it will
kept current in 2016 to reflect the results of radiation map play in the assembly and installation of the
studies, and basic countermeasures were selected for ITER machine and plant, the ITER
each system; discussions underway at ITER and with the Organization has introduced a new matrixed
Domestic Agencies on the standardization of needed organization for construction management.
radiation hardened electronics will continue into the next
reporting period. The Analysis Section/Division also issued
a document on the chemical composition and Through the joint effort of the Quality Assurance &
impurity requirements for steels and alloys in ITER – an Assessment Division and a specially created Management
area formerly missing from the technical baseline. and Quality Program (MQP) Working Group, the structure
The ITER electromagnetic integration team created of the ITER MQP program has been simplified – resulting
an analysis model for locked and rotating vertical in improved logic, clearer hierarchy and ownership, and
displacement events based on interpretation of results the elimination of process duplication. During monthly
obtained on the European tokamak JET: this working group meetings, participants carried out a
electromagnetic analysis model was extensively comprehensive review of MQP documents and begin
discussed by fusion community physicists and is implementing an improvement plan, including the
considered the best existing interpretation. A global update of more than 200 documents. Two of the three
model was completed for the test blanket systems and highest level documents – the Project Management Plan
delivered to users for the detailed analysis of each system. and the Quality Assurance Program – are in revision.
Large electromagnetic systems (magnet coils, passive Safety & Quality responsible officers from all
structures, power supply, busbars) will benefit from Domestic Agencies and the ITER Organization met as
integrated modelling and analysis capabilities made part of the SQAWG (Safety and Quality Assurance
possible by a new tool for operative dynamic simulations, Working Group). Through this forum information is
developed using specialized software. The geometrical shared on requirements and design conformity,
configuration of the magnetic system source currents supervision planning and inspections, procurement
was also described during the year in a standardized quality requirements, the non-conformity mechanism,
parametric specification developed from the 3D CAD and other safety and quality issues.
models for manufacturing design. Finally, the team During the reporting period, the Division verified the
provided detailed technical documents in support of effective implementation of the ITER Organization
material procurement, material test certificates, quality assurance program through 14 Domestic Agency
manufacturing reports, technical issues related to quality audits, and 15 supplier/subcontractor quality
welding, and material properties under radiation. audits covering 14 Procurement Arrangements. Through
distillation of the safety culture across the entire scope of for ITER, mockups are planned for assembly process
the project, including design and manufacturing; non- qualification and technical staff training.
conformity management; protection important The effort to procure 88 kilometres of niobium-tin
components, activities and defined requirements; the (Nb3Sn) superconductor for ITER’s toroidal field coils
compliance matrix for safety requirements; came to an end in December as the last unit length left
manufacturing and inspection plans; release notes; and the production line. The fabrication of the final coils –
as-built files. Members of the Department continue to be each made up of a conductor winding pack (seven
a regular presence at the public meetings of the Local stacked double pancakes) and stainless steel coil case –
Information Commission (CLI). is now in the hands of Europe and Japan. In a major
As part of the Safety Department, the Division for achievement, Europe completed its first winding pack in
Security, Health & Safety is responsible for the protection October; following final verification, this 110-tonne
of people and property, the protection of nuclear component will be transferred to the coil manufacturer
materials, the protection of data, and the health and for cold testing and insertion into a coil case. Headway
safety of workers. In fulfilling these missions, the Division was also made in Japan, where the first winding pack
maintains close relations with security and occupational will be finalized early next year and manufacturers are
safety Host state representatives. All occupation health on schedule to complete the first full set of toroidal field
risks are now grouped in a centralized database, which coil cases and intercoil structures. An insert coil built
lists the risks according to plant system or machine from ITER toroidal field conductor was tested in a
function and identifies mitigation measures. A tool for specialized facility in Japan under ITER-like conditions.
the management of chemical products on the ITER site Initial results are under investigation as they show some
was added in 2016. degradation under prolonged electromagnetic cycling.
The Division also manages general emergency The first series element of the poloidal field coil
procedures, keeping intervention plans updated for procurement program (a production double pancake)
every building, verifying emergency materials on a was manufactured in Russia for ITER’s smallest poloidal
monthly basis, and organizing occupational safety and field magnet. Series manufacturing is also slated to
security exercises. For the worksite area, induction safety begin in China for poloidal field coil #6 and at ITER for
training is managed centrally for all staff and contractors, coil #5 following the successful qualification of winding,
regardless of employer. helium inlet and joint welding processes for these coils
that are under European procurement. In the on-site
TOKAMAK ENGINEERING DEPARTMENT (TED) facility where Europe will manufacture the four
The Tokamak Engineering Department is in charge of the largest coils (#2-5), equipment was installed in 2016
design, procurement, acceptance, installation, commissioning, for the later-phase manufacturing steps; in addition, a
and operation of all core tokamak systems (blanket, divertor, final contract was awarded for the full fabrication and
vacuum vessel, cryostat, thermal shields, magnets, in-vessel cold testing process.
coils, port plugs and diagnostics, heating and current drive)
plus the Test Blanket Module program and system
instrumentation. In preparing for the assembly and installation
of components on site, the Department coordinates
increasingly with the Construction Department and dedicated
teams for Tokamak and Tokamak Complex assembly.
Nine years into the campaign to produce ITER’s large
superconducting magnet systems, collaboration
between the six procuring Domestic Agencies and the
ITER Organization continues to produce results: the
principal components are on schedule; technical issues
are dealt with on a day-to-day basis; and quality control
remains a top priority. With the first large magnet – a
toroidal field coil from Japan – expected on site in 2019,
planning has begun for the assembly phase, as teams
work to define specific handling and installation tools,
develop installation processes, and finalize
A European contractor practices one important step in poloidal field coil manufacturing
magnet/vacuum vessel and magnet/tooling interfaces.
– the creation of helium inlets in the conductor unit lengths.
At the CEA MIFI magnet infrastructure facilities created
for the first time to realize a poloidal segment sub- shaping was examined by a panel of experts in
assembly. The first activities have begun on sector #4. September. The panel underlined the importance of
A recovery plan was implemented in 2016 to achieving challenging tolerances in the vertical target
mitigate slippage in the manufacturing and delivery region where the plasma strike point is expected and
schedule for European vacuum vessel sectors. As part recommended further qualification activities on heat
of this plan, the responsibility for sectors #7 and #8 load and tungsten material specifications. The current
was transferred from Europe to the ITER Organization baseline shaping (toroidal bevel) was retained for the
for fabrication in Korea – a swap that does not modify inner vertical target, while a more complex shaping
the overall cost sharing. Other measures include the (planar bevel) was preferred for the outer vertical target
reinforcement of the European manufacturing to protect both the toroidal and poloidal edges. These
consortium through an additional subcontractor and recommendations will now be addressed by the ITER
improvements in the way oversight is managed. team and the International Tokamak Physics Activity
Manufacturing is underway on port extensions and (ITPA) group on divertor and scrape-off layer physics.
stub extensions for the lower and upper ports in Korea
and Russia respectively – when completed and tested,
these elements will be transferred to the vacuum vessel The first welding and radiographic testing
sector manufacturers for welding onto sectors. As part of activities for the ITER cryostat begin in a
the neutron shielding of the vacuum vessel, thousands dedicated workshop on site in 2016.
of in-wall shielding elements are in production in India.
The sustainment of the production throughput for these
schedule-critical items – needed for the completion of Two European companies are in the process of
vacuum vessel sectors – is being closely monitored. In realizing full-scale divertor cassette body prototypes
Korea, the manufacturing of the vacuum vessel thermal and delivery is expected next year after a series of
shield has now reached the half-way milestone and factory acceptance tests. Manufacturing is also
other 2016 highlights included the completion of the underway on prototypes of the divertor dome in
thermal shield silver coating facility, the qualification Russia, where the ITER Divertor Test Facility is already
of helium leak test procedures, the start of fabrication simulating the demanding heat loads expected during
on the cryostat and support thermal shields, and the operation in ITER. Small-scale mockups with tungsten
close-out of final design reviews for instrumentation monoblocks have been manufactured by three different
and piping manifolds. companies in Europe as part of the pre-qualification
The full tungsten divertor is a high-value component phase of the inner target. Following high heat flux
and the one that must withstand the highest heat load testing in Russia, pre-qualified companies will be asked
of the machine. As part of an ongoing effort to minimize to manufacture a full-scale inner target prototype. A last
the risk of damage or degradation during the annual highlight – with direct relevance for the ITER
operational phase, the question of divertor monoblock divertor program – was the successful first plasma of
the Tore Supra/WEST project in December. Updated
with an ITER-like tungsten divertor, WEST will be able to
test tungsten technology, acquire data on metal fatigue,
and explore the boundary conditions of components in
its operational program that kicks off in 2017.
As part of blanket first wall qualification, beryllium-
tiled “fingers” designed and manufactured in China
performed well in high heat flux tests – an achievement
which opened the way for the signature in November of
the First Wall Procurement Arrangement with the
Chinese Domestic Agency. In other programmatic
achievements, planning is underway in China and Korea
for the challenging series fabrication of blanket shield
blocks and their 200 design variants; Europe is qualifying
three first wall suppliers in expectation of a Procurement
At the PRIMA neutral beam test facility in Italy, a full size ion source – equivalent to the one Arrangement signature next year; Russia is manufacturing
that will be used on the heating neutral beams at ITER – will be developed on the SPIDER test
a new first wall semi-prototype; and the last activities were
bed. In 2016, Europe delivers the ion source and extraction grid power supply. Photo: OCEM ET
carried out to close-out the final design of the blanket
Korea is responsible for manufacturing all vacuum vessel equatorial and lower ports. In
2016, work begins on the first lower port stub extension (pictured) and port extension.
Photo: ITER Korea
manifold system. Conceptual design reviews were held for Arrangement was signed in April with Russia on the port
the protective structures that will be temporarily installed plug structures for lower port 8.
inside the vacuum vessel during first-phase assembly (First The diagnostics team has clarified diagnostic delivery
Plasma protection components) and for operational schedules in line with the ITER assembly phases, adding
instrumentation required to monitor the loads on internal some new systems in relation to specific First Plasma
components. Finally, the Beryllium Management requirements. System designs are advancing in all ITER
Committee continues to meet regularly to pursue the safe Members and the earliest-need diagnostics have
implementation of beryllium handling and storage at ITER. entered the manufacturing phase. Completed CER coils
It is envisaged that six technological solutions for a
tritium breeding blanket system will be operated and
tested for the first time in ITER; these solutions are The principal ITER magnets – the toroidal
under development now by the ITER Members. Five and poloidal field magnet systems, the
systems have concluded the conceptual design phase – central solenoid, and the correction coils –
China’s helium-cooled ceramic breeder, Korea’s helium- are all in production.
cooled ceramic reflector, Japan’s water-cooled ceramic
breeder, and Europe’s helium-cooled lithium-lead and
helium-cooled pebble bed systems – and kick-off (for “continuous external Rogowski” coils) are ready for
meetings have been held to launch the preliminary factory acceptance testing in Europe, mineral insulated
design phase in both China and Korea. Test Blanket cables were produced in Japan for the micro fission
Module (TBM) Leaders are also developing compliance chambers, and start of manufacturing is imminent for
strategies with European regulations on nuclear the outer vessel magnetic coils and the neutron flux
pressure vessels (ESP/ESPN), preparing for the trilateral monitor for equatorial port 7. R&D activities for technical
agreements that must be signed with the ITER issues common to many systems, such as loom
Organization and the Host country on the management attachments, welding to the vacuum vessel, mirror
of radioactive waste, and harmonizing inputs in view of cleaning, and the radiation environment, advance
reporting to the French safety authority in 2017. constructively and plans are maturing to launch
The need dates for the test blanket systems were framework contracts in several key program areas such
clarified during the year in relation to the staged as diagnostic instrumentation and control, remote
approach to assembly. To meet the deadline for the first handling, mirror cleaning and shutter engineering,
components due on site – the connection pipes for the optical diagnostics, and first wall fabrication.
test blanket systems – the design was advanced in-house Within the new staged approach to ITER operation the
before a contract was concluded for final design. second antenna of the ion cyclotron system and
Contracts were also awarded for safety studies on the test associated power supplies has been reintroduced into
blanket module port cells and for RAMI analysis of the the construction baseline and budget. Both antennas are
port plugs. All Members reported steady progress in the to be procured together by the European Domestic
R&D activities carried out in support of the test blanket Agency as the most economical path forward. The design
module program. of the antenna is progressing and a global analysis model
In pursuit of the joint tender approach adopted for the has been developed to evaluate the most stringent loads
procurement of diagnostic port plug structures – the on the components. In other R&D activities Europe tested
“containers” that will host ITER’s port-based diagnostic
systems – a common supplier was chosen in October.
Eight equatorial and 14 upper port plug structures will
be shipped by the manufacturer to the Domestic
Agencies for the integration of drawers with diagnostic
elements, shielding modules, and diagnostic first walls.
In other news, engineering teams are advancing the
standardization of port infrastructure looking – in
particular – at modular concepts to ease integration and
maintenance; work progressed on the development of a
prototype generic first wall; and electromagnetic
disruption loads were defined for the port plugs in order
This roots pump prototype – under development for ITER's vacuum system – has completed
to move forward with component design and port
the testing process in the US. Photo: US ITER
integration. A Complementary Diagnostic Procurement
small-size mockups of the Faraday screens, a cold spray have been installed and the first set of voltage holding
copper coating technique was trialled with success on tests is planned early next year. The high voltage bushing
titanium alloy, and tests have started on joining is also expected soon. Europe has awarded a preparatory
techniques between titanium and stainless steel. The contract for the MITICA beam source, with three potential
Indian Domestic Agency has developed two prototypes suppliers undertaking manufacturing designs.
for the system’s radio frequency sources and is testing To lay the groundwork for the heating and
them in order to decide on series fabrication. The US diagnostic neutral beams at ITER, a preliminary design
continues to validate the performance of different review was held for the largest all-metal valve ever
designed – the absolute valve that will connect each
neutral beam injector in the neutral beam cell to the
All planned milestones for the ITER vacuum vessel. Preparation is underway for the
cryogenic system were successfully signature of the European Procurement Arrangement
achieved, including the finalization of most that covers the heating neutral beam vessels, passive
of the components for the liquid helium and magnetic shielding, active correction coils, and front-
liquid nitrogen plants. end components. A proposal has been made to install
the large captive components for a third neutral beam
injector during early construction in order to maintain
transmission line subcomponent prototypes, and a plant an important potential for flexibility in the operation
control system prototype has entered the trial phase in of the ITER facility should an upgrade be decided.
ITER’s CODAC lab. The maturing design of the ion In advance of the operation of the neutral beam test
cyclotron system has permitted all requirements to be facility, the half-size ion source ELISE (IPP Garching,
defined for the on-site Radio Frequency Heating Building Germany) is producing results that are very important
and construction on that structure has started. to optimizing source performance and proving the
Five Domestic Agencies and the ITER Organization concept of large-scale negative ion caesiated sources.
are sharing in the design and procurement of ITER’s Important advances have been made in resolving high
microwave heating system – electron cyclotron power arcing issues that will allow operation at ITER-
resonance heating. Following lengthy qualification relevant power parameters. The experimental program
programs, series manufacturing started in 2016 for the for 2017 will concentrate on high power discharges
microwave sources (gyrotrons) in Russia and Japan, with a focus on controlling co-extracted electrons in
and for the first power supply unit in Europe. Two deuterium discharges.
diamond disks were also successfully produced for the The Indian Domestic Agency is developing a test
vacuum-tight window that will seal the vacuum vessel facility for the components and the design of the
but allow the system’s electromagnetic waves to reach diagnostic neutral beam for ITER. The vacuum vessel has
the plasma. US contractors completed mode purity been installed and manufacturing is now underway on
analysis on the full transmission line and pursued the the diagnostic neutral beam source and, more recently,
testing of prototype components; Japan has diagnostic neutral beam line components.
completed the first prototype body power supply; and
India is ready to award its first high voltage power
supply contract in 2017. A joint ITER Organization-US
ITER team is collaborating with industry to design an
isolation shutter valve that can ensure confinement at
each transmission line “point of entry” in the buildings.
The PRIMA neutral beam test facility at Consorzio RFX in
Padua, Italy, comprises the ion source testbed SPIDER and
the full-scale neutral beam injector MITICA. SPIDER is in its
final assembly phases and facility commissioning activities
have started, including the testing of components
procured by Europe (SPIDER vacuum vessel, high
voltage deck, gas and vacuum system) and India (beam
dump, 100 kV power supply). Integrated commissioning
of this test bed can begin once the beam source, the most The US Domestic Agency is testing electron cyclotron waveguide performance at Japan's QST,
the National Institute for Quantum and Radiological Science and Technology. The electron
critical component of the system, is delivered.
cyclotron system is one of three external heating systems at ITER. Photo: US ITER
For MITICA, the power supply components from Japan
Procuring parties Europe, Japan and the ITER management building in order to pre-assemble the first
Organization worked together to redefine the need wall components (water-cooled tiles) to be installed in the
dates for remote handling equipment in relation to the vacuum vessel in full respect of regulatory requirements.
staged approach to construction. This re-baselining The Tritium Plant is essentially a nuclear gas processing
exercise resulted in significant cost savings through plant – receiving deuterium-tritium-helium gases,
the elimination of one tool that had been under removing impurities, separating isotopes and helium, and
consideration (the multi-purpose deployer) and the returning gases back to the fuelling systems – but the
increased functionality of the blanket remote handling scale and processing demands of ITER make system
system. Projects were initiated with ASIPP (China) and
CCFE/RACE (UK) for the development and testing of
mockups for remote handling, tooling, and Electrical distribution will be the first ITER
component refurbishment; contracts have also been plant system to come on line, with the
established for support in the design, development planned energization of one portion of the
and planned operation of the remote handling steady state network next year.
transfer casks and systems planned for the ITER Hot
Cell. A conceptual design review was successfully held
for the maintenance and decontamination facilities designs challenging. The systems for storage and delivery,
that will be necessary for remote handling equipment. isotope separation, and analytics are the subject of
Work is underway to complete the conceptual design ongoing design and R&D studies; the tokamak exhaust
of the Hot Cell Complex (facility and processes) by the processing system has advanced to the preliminary
end of 2017; to this end, a large number of integration, design phase; and progress on the design of captive
design and safety activities have been launched. A piping for the atmosphere detritiation system means that
consortium was chosen for the design of the building, installation in the Tokamak Complex can be envisioned in
multiple contracts were signed for process development the near term. The atmosphere detritiation system is
(radwaste cutting station, liquid radwaste evaporator, entering the final design phase and key studies have been
tritium removal furnace, laboratory, in-vessel component completed on the efficiency of scrubber column tritiated
maintenance), and a framework contract was launched water collection. Six of the largest tritiated water storage
for the safety analysis of the Hot Cell Facility. The joint tanks for the water detritiation system were installed in
ITER Organization/Agence Iter France working group the basement of the Tokamak Complex and progress was
continues to think ahead to the issues of radwaste made on both the safety analysis of Tritium Plant
management and waste disposal in France. A workshop equipment and the atmosphere detritiation qualification
was held to raise awareness on decommissioning issues plan, which was presented to the Regulatory body.
that must be incorporated today in the design of systems The conceptual engineering of ITER’s fuelling system is
(handling, licensing issues) and collaboration has started also progressing. The US is testing a dual nozzle for the
with France’s permanent waste repository ANDRA on pellet injection system capable of delivering two types
storage issues such as packaging and acceptance criteria. of fuelling pellets, while in China – following the final
A beryllium facilities working group was also created to design review – the gas distribution manifold system is
develop technical options for a beryllium storage area and transitioning to the manufacturing readiness review
phase. The engineering design of a disruption mitigation
system based on hybrid shattered pellet injection for
deuterium-tritium operation and massive gas injection
for non-active operation advances in the US. Studies are
underway on port integration and support, and a task
agreement was signed to study shattered pellet
injection as a disruption mitigation technique at the
European tokamak JET.
All ITER vacuum systems are progressing to
manufacturing: the assembly of finalized torus pre-
production cryopump components is underway;
vacuum auxiliary system flanges are ready to ship from
Accurate dimension control is applied from component fabrication to final assembly at the US; testing has been concluded on the cryoviscous
ITER. Optical metrologists are already a common sight as they measure the as-built
compressor and a roots pump prototype; design and
locations of the systems.
build activities have started for the all-metal scroll
The Tokamak assembly pit is visible through the open end of the Assembly Hall. When
the building over the pit is completed, the assembly cranes will travel back and forth
delivering their loads.
pumps; and testing continues on dust filtering. The a) Tokamak machine assembly; b) systems installation
Procurement Arrangement covering cryopumps for in the Tokamak Complex; and c) conventional plant
ITER’s heating and diagnostic neutral beam systems as installation. Each of the teams integrates resources
well as for the MITICA neutral beam test stand was from engineering departments and offices as well as
signed with Europe in June. the Domestic Agencies and the CMA team in order to
As part of a standardization program that will make all- capture the working knowledge of components and
metal ultra-high valves available at reduced prices, a first systems that has accumulated across the project and
production batch was received from the manufacturer for to ensure the integrated organization of assembly and
testing. The procurement of vacuum pipework has been installation activities in specific zones on site.
launched following the award of a contract in April, and a In the new reorganization, the Tokamak Assembly
small batch of seamless stainless-steel piping has already Division has become the basis for the integrated team
been received for inspection. Contracts kicked off for the for Tokamak machine assembly and, as such, has full
manufacture of a full-size rig to test the sealing of the responsibility for all assembly-related activities in the
equatorial ports and test blanket module flanges, and for Tokamak Pit as well as the Assembly Hall and Cleaning
the manufacturing of double metallic seals. Facility (worksite 1). In 2016, the group revisited the
Complex installation contracts; these packages also basemat of the Tokamak Building were among the
transfer important constructability information to the milestones achieved. Progress was made on the final
CMA contractor. By thoroughly reviewing installation design and interfaces of the cryostat bearings, which is
sequences up to First Plasma, the Division identified an important prerequisite to starting civil work on the
captive equipment that might be needed by Tokamak concrete crown that will support the cryostat at B2 level.
Complex systems at a later phase and specified the The 60-metre-tall ITER Assembly Building has been
temporary infrastructure needed to optimize assembly equipped with handling cranes capable of lifting 1,500
activities. In interaction with design and engineering tonnes and dressed out in polished steel cladding – with
teams, the Domestic Agencies and the CMA contractor, the exception of the west wall, where a temporary cover is
the Division seeks to increase the efficiency of assembly in place until the completion of the Tokamak Building.
execution through its knowledge of sequences, access, Eight other building projects are also underway: European
and systems installation methodology. contractors completed the site service and cleaning
facilities; erected the skeletal structures of the cryoplant
and the building for radio frequency heating; launched
Work on ITER's main scientific facility – the excavation and preparatory work on the sites of magnet
Tokamak Complex – is now evolving at or power conversion and cooling towers; and advanced
above platform level. the underground technical galleries and electrical
switchyard infrastructure. The first transformer was
installed on the platform for the pulsed power electrical
The Construction Management Division forms the core network in October and three other beds are ready.
of the new Construction Management and Coordination In addition to hundreds of conventional loads, 23
Team, with responsibility for the coordinated procedures highly exceptional load convoys reached ITER in 2016
for the tendering and management of construction including those for the massive beams for the Assembly
contracts between the ITER Organization and suppliers. Hall cranes, large cryoplant components and segments
In 2016 the Division developed an optimized assembly of the ITER cryostat. As part of planning for the
procurement strategy that is compatible with the increased deliveries – and increased staff – expected in
updated project schedule and that, while dividing the the years ahead, the Facilities, Logistics & Materials
work into manageable packages, takes interfaces Division oversaw the completion of a new access road
between work areas into account. Nine contracts are to ITER’s largest storage warehouse, as well as a 200-
planned to cover all first-phase assembly and installation person office building and parking lot for construction
activities. As part of preparation activities, the Division staff. Two new warehouse areas will be added on site, an
has developed a code of safe practice in radiographic off-site warehouse – managed by ITER’s global logistics
testing that is applicable to contractors and staff alike. provider – is foreseen for bulk components, and an
The CST Department as a whole benefitted in 2016 from agreement signed with the Host Organization CEA will
interaction with the European organization CERN on provide additional local storage for some of the
its experience with the assembly and installation of extensive cooling water piping expected from India.
large scientific instruments. A workshop held at ITER in
September will be followed up next year by a visit of the
ITER construction assembly teams to CERN.
Due to an increase in workers and number of shifts on
site, the pace of building and infrastructure construction
accelerated in 2016 under the oversight of the European
Domestic Agency. Two elements of the Tokamak
Complex are now clearly visible above platform level –
the concrete bioshield, whose basement and ground
(L1) levels are in place, and the Diagnostics Building,
whose exterior walls are completely framed out at L1
level. Work also proceeds to complete the lower levels of
the Tritium and Tokamak buildings in order to make
them available for early-access assembly activities in
2018; the installation of the first captive components
The bioshield already rises over 20 metres, as construction teams advance on the third of
in the basement of the Tritium Building (six detritiation
six levels, L1.
tanks supplied by Europe) and the completion of the B1
FINANCE & PROCUREMENT DEPARTMENT (FPD) kind allocated value. In 2016, the Department assisted
The Finance & Procurement Department is charged with in the finalization and signature of two Procurement
sound financial and budget management, the preparation Arrangements, one Complementary Diagnostic
and management of the annual and lifecycle budgets, the Procurement Arrangement, and several transfer-of-
presentation of the annual ITER Organization accounts, the scope agreements from the Domestic Agencies to the
preparation of in-kind Procurement Arrangements, and the ITER Organization.
placement of in-cash contracts and task agreements The ITER Organization awarded the ten-year
through competitive process. Construction Management-as-Agent contract in June for
In 2016, the Budget Management Section worked Tokamak and support system assembly and installation.
closely with the Project Controls Office to finalize Several other major contract awards were concluded as
resource estimates in accordance with the revised a result of close collaboration with the Domestic
project schedule and to submit an updated baseline to Agencies, including arrangements for the common
the Members for the construction phase. It closely procurement of diagnostic port plug structures and the
monitored and reported on the implementation of the extension of the Logistics Service Provider framework
2016 ITER Organization commitments, payments, and contract. Further strategic contract signatures achieved
income budgets, overseeing the execution of fully 93 within deadline in support of the project include those
percent of the commitments budget and 86 percent of for vapour suppression tanks (manufacturing design
the payments budget. and procurement); sector sub-assembly tools; purpose-
In addition to these budgets, the Reserve Fund built tools and equipment; and Hot Cell Complex
continues to be maintained as a tool for addressing cost engineering services.
impacts due to changes in scope or design within the The Procurement & Contracts Division is closely involved
ITER Organization or Domestic Agencies. The use of this in preparations for the award of three major assembly and
common account is closely monitored and reported to installation packages for mechanical, electrical and
the Central Team Management Board and the ITER tokamak works. In general, it can be said that procurement
Council. The regular verification of commitments, activities and challenges are increasing in complexity as
invoices and other financial transactions; small-value the ITER Project prepares for the installation of the
purchase orders and invitation letters; and suspense machine and plant. Procurement & Contracts is moving
transaction management also contribute to sound toward a more strategic function through a leading role in
financial management at the ITER Organization. the construction procurement strategies.
The Accounting & Treasury Section produced the 2015
Financial Report, which includes the 2015 Financial
Statements, on which the Financial Audit Board –
composed of independent auditors nominated by the
seven Members – issued an unqualified audit opinion
in April 2017, noting the proactive initiatives taken to
improve accountability and transparency in financial
management, contract administration and budgetary
control. The expert group also conducted another
audit in September that covered the trial balance for
the period from 1 January to 30 June. During 2016, the
Treasury team managed to realize a financial income
of EUR .98 million, which represents an average rate of
return of 0.59 percent of the daily available cash balance
(invested only in secured deposits). In comparison, the
average 2016 Eonia® (Euro OverNight index Average)
index was -0.32 percent.
Recommendations from the Financial Audit Board
are tracked through a computer application until
solutions are validated and implemented.
Since 2007, the ITER Organization has signed a total of
108 Procurement Arrangements for the delivery of More than half of the space between the double walls of the vacuum vessel will be taken
up by in-wall shielding blocks designed to protect ex-vessel components from neutron
components, systems and buildings with the Domestic
radiation. Indian contractors are producing over 9,000 elements. Photo: ITER India
Agencies, representing 90.86 percent of the project’s in-
Tooling and testing activities are underway to prepare for the fabrication of ITER’s second-smallest
poloidal field coil (PF6) in China on behalf of the European Domestic Agency. Photo: ITER China
anti-dumping taxes, and electricity taxes. This type of issue officers on publications, contracts, Procurement
is increasing in frequency with the arrival of components Arrangements, non-disclosure agreements, and
and/or their transportation between Members. communication. Rules concerning rewards for inventors
Extensive support was provided on visa and work were issued in order to encourage directly employed
permit issues for contractors and Domestic Agency staff staff members to develop ITER Organization intellectual
members in order to prevent delay in contract execution. property; this new policy proposes awards for
Legal Affairs also interfaced with the labour inspectorate inventions that become the subject of a patent
and the French administration to clarify the administrative application, or developments that engender a royalty-
requirements for work on the construction site and in paying licensing agreement. At the annual meeting of
order to secure the social protection of workers. ITER Organization/Domestic Agency contact persons for
In 2016 Legal Affairs was responsible for drafting intellectual property, chaired by the ITER Legal Advisor
and negotiating 19 agreements, 9 license agreements, in November, participants worked to encourage the
numerous non-disclosure agreements, and 30 Memoranda widest appropriate dissemination of intellectual
of Understanding. It managed insurance claims and property generated in the course of activities for ITER.
insurance-related matters, and reviewed ITER Organization
contracts prior to signature by the Director-General. INTERNAL AUDIT (IAS)
Legal Affairs provided advice on the French laws and The work of the Internal Audit Service is aligned to the
regulations to be observed by the ITER Organization in business, financial and operational risks of the ITER
application of Article 14 of the ITER Agreement relative Organization and audits are conducted according to a
to public health, safety, licensing and environmental comprehensive risk-based plan that is updated periodically.
protection, in particular concerning working conditions The annual risk assessment exercise that was carried out in
on site and the management of beryllium handling and 2016 by IAS was comprehensive, and covered 92 major
storage issues. Legal Affairs is a participant to meetings processes of ITER Organization departments and divisions –
of the ITER Beryllium Management Committee and the including the Cabinet, Human Resources, Finance &
Beryllium Working Group. Procurement, Construction, the Design Office, IT, Document
Legal Affairs managed litigation cases in close Control and Project Control.
collaboration with the Human Resources Department, The results of the annual risk assessment exercise
and provided support and advice in the establishment of carried out by IAS were submitted to external auditors
the ombudsman process, activities of the ethic (the Financial Audit Board) as input for their audit
committee, the update of the ITER Project Associate planning. IAS also cooperated with the Financial Audit
scheme, and social security issues. Specific in-house Board auditors during their audit assignments at ITER.
training sessions were organized on the legal framework In 2016, IAS audited the accounting of assets, pre-paid
specific to the ITER Organization, the status of assets, and depreciation for the 2016 ITER Organization
international civil servants, and intellectual property in Financial Statements. Other important topics of audit
order to raise staff awareness. Legal Affairs also introduced included mission travel; the system of levy and
a new income tax assistance program for staff. computation of common facilities, services and amenities;
Legal Affairs coordinated the implementation of the operations pertaining to facilities management; suspense
legal framework for intellectual property within the ITER operations; and purchase and disposal of IT hardware.
Organization through the Intellectual Property Board, IAS performed advisory services as requested
advising line management and technical responsible periodically by management and carried out important
assignments related to human resource matters, budget
for salaries, and procurement issues. IAS also held
workshops to impart knowledge and skills to staff of the
Financial Control Office on matters relating to
computation and accounting of liabilities and provision,
and routinely advised the Head of Office with the aim to
further enhance the adequacy and effectiveness of
control functions at the ITER Organization. Similarly, in
collaboration with ORAP, IAS verified the effective
implementation of MQP process simplification following
As part of the semi-prototype qualification program in China for enhanced heat flux first a reduction-of-bureaucracy effort carried out last year.
wall blanket panels, pairs of beryllium-tiled "fingers" (pictured) have undergone testing
Lastly, IAS followed up on the implementation status of
at a dedicated facility in Russia. Photo: ITER China
its recommendations, of which a large number were
On a zone not far from the Tokamak Complex, contractors have started to erect the
infrastructure of the ITER cryoplant – 5,400 m² of covered buildings plus a large exterior
area for the storage of helium and nitrogen in liquid and gaseous forms.
STAFFING &
FINANCIAL TABLES
staFFing tables
67 512
TED 160 DG 8
38 CAB 20
36 QAA 14
32 CIO 178
SD 28
25
SCOD 55
CST 57
30
PED 145 FPD 39
PCO 20 HRD 16
Financial tables
Amounts in thousands of Euro
commitments execution – cash and short-term in Kind (task agreements and secondments)*
Total Commitment De-commitments and Total Actual Unused Commitment
Appropriations Transfers of previous years' Commitments Appropriations carried
2016 Total Commitments 2016 forward to 2017
Budget Headings 1 2 3 4=1+2-3
Title I Direct Investment (Fund) 158,242 9,583 153,121 14,704
Title II R&D Expenditure 3,682 88 2,431 1,339
Title III Direct Expenditure 167,127 3,754 157,742 13,139
TOTAL COMMITMENTS 329,051 13,424 313,294 29,181
* Excluding Reserve Fund
payments execution – cash and short-term in Kind (task agreements and secondments)*
Total Payment Total Actual Unused Payment
Appropriations Payments Appropriations carried
2016 2016 forward to 2017
Budget Headings 1 2 3=1–2
Title I Direct Investment (Fund) 96,817 75,250 21,568
Title II R&D Expenditure 6,776 5,958 818
Title III Direct Expenditure 173,332 145,887 27,445
TOTAL PAYMENTS 276,926 227,096 49,831
* Excluding Reserve Fund
45% 31%
9% 6%
9% 10%
9% 9%
9% 27%
9% 5%
9% 12%
3,000.00 3,000.00
MILLION €
2,500.00 2,500.00
2,000.00 2,000.00
1,500.00 1,500.00
1,000.00 1,000.00
500.00 500.00
0 0
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016
Cash Seconded staff and Task Agreements Procurement Arrangements
The pace of deferred contributions related to the achievement of
Procurement Arrangement milestones (in purple) continued its increase in
2016 (compared to 2015), reflecting an acceleration of construction and
component fabrication activities.
DOMESTIC AGENCY
PROCUREMENT HIGHLIGHTS
procurement arrangements*
Fourteen pas signed since 2007 representing…
...AND 100%
OF THE TOTAL
100% IN NUMBER VALUE
OF CN-DA IN-KIND
CONTRIBUTIONS.
77 design or fabrication contracts related to ITER procurement have been signed with
laboratories and industry.
CHINESE PROCUREMENT HIGHLIGHTS IN 2016 % OF ITER SYSTEM PROCURED BY CHINA
MAGNET SYSTEMS
Toroidal Field Conductor 7.5%
¢ All 11 conductor unit lengths completed and delivered (IC milestone)
Poloidal Field Conductor 65%
¢ All conductor fabrication completed for PF5 and PF2 (IC milestone)
¢ 6 of 16 PF3 unit lengths produced
¢ 8 of 16 PF4 unit lengths produced
¢ 9 conductor unit lengths delivered to EU-DA at ITER site
Magnet Supports 100%
¢ MRRs completed for gravity supports and poloidal field supports; some manufacturing underway
Feeders 80%
¢ Five MRRs successfully held, including for HTS current leads, coil terminal box (CTB/TS), and cryostat feedthrough
¢ Qualification completed for poloidal field HTS current lead prototype; series production started
¢ Start of fabrication on first cryostat feedthrough for poloidal field coil 4
Correction Coils 100%
¢ Contract signed for remaining manufacturing scope
¢ Bottom correction coil in fabrication
¢ Full-size U-shaped bottom correction coil case fabricated with satisfactory results
¢ Qualification prototypes progress for full manufacturing scope of bottom and side coils
Correction Coil and Feeder Conductors 100%
¢ All correction coil and feeder conductors manufactured and delivered in 2016
POWER SYSTEMS
Pulsed Power Electrical Network (PPEN) 100%
¢ All voltage transformers delivered to IO site
¢ Second batch of breakers, disconnectors, and current transformers delivered
¢ 3 main transformers delivered
AC/DC Converters 55%
¢ Successful FAT and delivery for first set of rectified transformers
Reactive Power Compensation 100%
First reactive power compensation (RPC) and harmonic filtering (HF) units manufactured
RPC and HF units installed at ASIPP-ITER platform for integrated tests
BLANKET
Blanket First Wall 12.6%
¢ High heat flux tests successfully passed on first-wall finger pairs for semi-prototype
¢ Enhanced Heat Flux Blanket First Wall Procurement Arrangement signed in November
Blanket Shield Block 50.2%
¢ Deep-hole drilling on full-scale prototype completed in December
¢ First hot helium leak test facility manufactured and under commissioning
FUEL CYCLE
Gas Injection System 100%
¢ Contract signed for manifold manufacturing
¢ Preliminary design of gas valve boxes ongoing; some physics requirements fixed as design input
Glow Discharge Cleaning 100%
¢ Preliminary design of temporary/permanent electrodes ongoing
DIAGNOSTICS
Diagnostics 3.22%
¢ Final design of neutron flux monitor (equatorial port 7) ongoing; FDR for support frame held
¢ PDR held for radial x-ray camera
¢ Preliminary design of equatorial port 12 integration ongoing
¢ Preliminary design of remaining neutron flux monitors ongoing
Abbreviations • ANB Agreed Notified Body • CDR Conceptual Design Review • DA Domestic Agency • FDR Final Design Review • I&C Instrumentation & Control • IO ITER Organization
• IC ITER Council • FAT Factory Acceptance Tests • MIP Manufacturing & Inspection Plans • MRR Manufacturing Readiness Review • PA Procurement Arrangement • PDR Preliminary Design Review
* Does not include Complementary Diagnostic Arrangements.
DELHI
ITER INDIA (IN-DA)
www.iter-india.org
procurement arrangements*
Fourteen pas signed since 2007 representing…
...AND 96%
OF THE TOTAL
93% IN NUMBER VALUE
OF IN-DA IN-KIND
CONTRIBUTIONS.
20 design or fabrication contracts related to ITER procurement have been signed with
industry and R&D organizations.
INDIA PROCUREMENT HIGHLIGHTS IN 2016 % OF ITER SYSTEM PROCURED BY INDIA
CRYOSTAT
Cryostat 100%
¢ Final segments of tier-1 base section delivered (IC milestone); start of tier-1 sub-assembly (fabrication/welding) and testing activities on site
¢ Manufacturing and FAT of tier-2 base section components completed; components delivered to Cryostat Workshop
¢ Progress on fabrication activities for lower cylinder tier-1 components in India
¢ FDR held for cryostat I&C
¢ Agreement reached to transfer vacuum vessel pressure suppression system (VVPSS) to IO
CRYOGENIC SYSTEMS
Cryolines & Cryodistribution 100%
¢ PDRs held for cryolines (Lot Y3, Lot X4, parts of Lot Y4 and Y5); and warm lines (Lots W1 and W2)
¢ PDR and FDR completed for cryoplant termination cold box (CTCB) of cryodistribution system
¢ PDRs held for auxiliary cold box and thermal shield cooling system for cryodistribution
¢ Manufacturing started for CTCB components
¢ FDRs held for cryolines (Lot Y1, Lot X3, parts of Lots Y4 and Y5) and warm lines (Lot W1) and completed for cryolines (Lot Y1, Lot Y2)
S
VACUUM VESSEL
In-wall Shielding Block Assemblies 100%
¢ Manufacturing and FAT completed for two vacuum vessel sectors (5 and 6)
¢ Manufacturing and FAT completed for the IWS support ribs and lower brackets of two vacuum vessel sectors (5 and 6)
¢ Batches shipped to EU-DA and KO-DA
¢ IWS component fabrication ongoing for vacuum vessel sectors 4 and 1
DIAGNOSTICS
Diagnostics 3.1%
¢ First-phase PDR held for XRCS-survey sight tube
¢ Most components for conventional X-ray source and optical setup procured and tested for IN-DA lab
¢ Fast-scanning Fourier transform spectrometer received at IN-DA lab after successful FAT; preliminary design and prototype works underway for electron cyclotron emission
¢ First phase system integration review completed for upper port integration
Abbreviations • ANB Agreed Notified Body • CDR Conceptual Design Review • DA Domestic Agency • FDR Final Design Review • I&C Instrumentation & Control • IO ITER Organization
• IC ITER Council • FAT Factory Acceptance Tests • MIP Manufacturing & Inspection Plans • MRR Manufacturing Readiness Review • PA Procurement Arrangement • PDR Preliminary Design Review
* Does not include Complementary Diagnostic Arrangements.
...AND 90%
OF THE TOTAL
72% IN NUMBER VALUE
OF JA-DA IN-KIND
CONTRIBUTIONS.
Over 800 design or fabrication contracts related to ITER procurement have been signed
with industry since 2007.
JAPANESE PROCUREMENT HIGHLIGHTS IN 2016 % OF ITER SYSTEM PROCURED BY JAPAN
MAGNET SYSTEMS
Toroidal Field Conductor 25%
¢ All conductor unit lengths completed in 2014
Toroidal Field Magnet Windings (9 out of 19) 47%
¢ Double pancake stacking of the first coil successfully performed
¢ Toroidal field coil series production underway
Toroidal Field Magnet Structures 100%
¢ Material procurement and coil structure series production underway
¢ Segments of first outer case section successfully connected
Central Solenoid Conductor 100%
¢ 37 conductors (six 613 m and thirty-one 918 m) manufactured, corresponding to 75% of required material
¢ 31 unit lengths shipped to US-DA, cumulative (63%)
REMOTE HANDLING
Blanket Remote Handling System 100%
¢ Contract awarded for package #2 (rail deployment equipment)
DIVERTOR
Outer Target 100%
¢ High heat flux testing of full-tungsten prototype plasma-facing units completed at RF-DA test facility (IC milestone)
¢ Discussion of Project Change Request related to design change to full-tungsten target (including financial issues) underway
¢ Amendment of Divertor Outer Target Procurement Arrangement due to this design change in provision
TRITIUM PLANT
Atmosphere Detritiation System 50%
¢ Progression of detritiation system qualification activities; performance test of modified water distributor completed
¢ Joint JA-DA/ITER Organization procurement activities proceeding
DIAGNOSTICS
Diagnostics 14.2%
¢ Manufacturing of mineral-insulated cables for micro fission chambers completed
¢ Contract awarded for prototyping and final design of edge Thomson scattering system, poloidal polarimeter, and divertor impurity monitor
¢ PDR closed for poloidal polarimeter
¢ PDR closed for edge Thomson scattering
Abbreviations • ANB Agreed Notified Body • CDR Conceptual Design Review • DA Domestic Agency • FDR Final Design Review • I&C Instrumentation & Control • IO ITER Organization
• IC ITER Council • FAT Factory Acceptance Tests • MIP Manufacturing & Inspection Plans • MRR Manufacturing Readiness Review • PA Procurement Arrangement • PDR Preliminary Design Review
* Includes Complementary Diagnostic Arrangements.
SEOUL
procurement arrangements*
eight pas signed since 2007 representing…
...AND 94%
OF THE TOTAL
80% IN NUMBER VALUE
OF KO-DA IN-KIND
CONTRIBUTIONS.
143 design or fabrication contracts related to ITER procurement have been signed with
universities, laboratories and industry since 2007.
KOREAN PROCUREMENT HIGHLIGHTS IN 2016 % OF ITER SYSTEM PROCURED BY KOREA
VACUUM VESSEL
Main Vessel (2 of 9 segments) 21.25%
¢ Agreement signed with IO for fabrication of sectors #7 and #8
¢ Fabrication activities underway for Sector 6 (55% completed) and Sector 1 (22% completed)
Equatorial Ports 100%
¢ Neutral beam port stub extension and in-wall shielding manufacturing launched
¢ Manufacturing design ongoing for neutral beam port extension
Lower Ports 100%
¢ Lower port stub extension and port extension manufacturing underway
BLANKET
Blanket Shield Block 49.82%
¢ Preparing to award contract for shield block material procurement and manufacturing
POWER SYSTEMS
AC/DC Converters 37.27%
¢ AC/DC converter (CCS-1) manufacturing completed
¢ AC/DC converter (CCU-1) and converter transformer (VS1-1) FAT completed
¢ Master controller manufactured for toroidal field coil power supply system
In-Vessel Coil Power Supply (busbars) 100%
¢ Design issues reviewed and configuration improvements implemented
MAGNET SYSTEMS
Toroidal Field Conductor 20.18%
¢ All conductor unit lengths completed in 2014 and delivered to JA-DA
THERMAL SHIELD
Vacuum Vessel Thermal Shield and Cryostat Thermal Shield 100%
¢ Final design for thermal shield manifold and instrumentation approved
¢ Manufacturing drawings of lower cryostat thermal shield (LCTS) cylinder and support thermal shield (STS) approved; manufacturing of LCTS cylinder and STS started
¢ Vacuum leak test system constructed
ASSEMBLY TOOLING
Machine Assembly Tooling 100%
¢ Start of assembly for first vacuum vessel sector sub-assembly tool (SSAT) for factory acceptance tests
¢ Start of manufacturing on SSAT #2
¢ FDR completed for first batch Group B2 tools
TRITIUM PLANT
Tritium Storage & Delivery 82.09%
¢ Storage and delivery system full scale getter bed design completed
¢ Storage and delivery system process flow diagram under development
¢ Tritium inventory calorimetry, helium 3 recovery process development ongoing
DIAGNOSTICS
Diagnostics 3.16%
¢ PDRs closed for vacuum ultra-violet (VUV) spectrometers and neutron activation system (NAS) transfer lines
¢ Ongoing prototype test of VUV spectrometer and NAS on KSTAR
¢ Development and testing of key components (DeMi system for first mirror protection, pipe feedthrough, rotary-type mechanical feedthrough …)
Abbreviations • ANB Agreed Notified Body • CDR Conceptual Design Review • DA Domestic Agency • FDR Final Design Review • I&C Instrumentation & Control • IO ITER Organization
• IC ITER Council • FAT Factory Acceptance Tests • MIP Manufacturing & Inspection Plans • MRR Manufacturing Readiness Review • PA Procurement Arrangement • PDR Preliminary Design Review
* Does not include Complementary Diagnostic Arrangements.
...AND 100%
OF THE TOTAL
100% IN NUMBER VALUE
OF RF-DA IN-KIND
CONTRIBUTIONS.
Over 800 design or fabrication contracts related to ITER procurement have been signed
with industry since 2007.
RUSSIAN PROCUREMENT HIGHLIGHTS IN 2016 % OF ITER SYSTEM PROCURED BY RUSSIA
POWER SYSTEMS
Switching Network, Fast Discharge Units, DC Busbar and Instrumentation 100%
¢ FDR-2 held for switching network resistors and power cables
¢ Second group of busbars, flexible links, rigid inserts, busbar boxes and supports manufactured, tested and delivered
¢ Prototypes of fast discharge unit resistor and fast make switch subjected to type testing
¢ Quality assurance documents uploaded and approved by IO, including new versions
¢ Engineering analyses completed and uploaded; R&D test reports issued
¢ Materials and components for future production purchased
¢ Manufacturing started on future deliveries
MAGNET SYSTEMS
Toroidal Field Conductor 19.3%
¢ All conductor unit lengths completed and delivered to EU-DA in 2015
Poloidal Field Conductor 20%
¢ Final conductor sample (PFRF4) tested at SULTAN
¢ Two unit lengths for PF1 conductor manufactured and accepted by IO
Poloidal Field Magnet No.1 100%
¢ First double pancake (of 8) wound
BLANKET
Blanket First Wall 40%
¢ Set of enhanced heat flux first wall fingers with beryllium armour manufactured and successfully tested
¢ New equipment prepared for induction brazing of beryllium armour to first wall panel
¢ Deep drilling technological process successfully developed and tested on enhanced heat flux first wall beam
Blanket Module Connectors 100%
¢ Pre-qualification tests completed for CuCrZr/316L bonded joint (diffusion bonding or HIP); post-HIP heat treatment procedure under development
¢ AS/LF coatings: first-phase pre-qualification program for plates completed; next step is performing experiments with coated bolts
DIVERTOR
Dome 100%
¢ Catia model of dome developed for full tungsten divertor; supporting analysis carried out on new design
¢ Update MIPs for full-scale new-design dome prototype
¢ Qualification of manufacturing process for dome
¢ Lower-level MIPs created for manufacture of dome prototype plasma-facing unit tiles
¢ RF-DA design review for inner particle reflector plate plasma-facing units
VACUUM VESSEL
Upper Ports 100%
¢ Series production continues on upper port components
¢ Final assembly and successful pressure and leak testing of the first upper port stub extension (PSE12)
¢ Participation in technical project management matters
Port Plug Test Facility 100%
¢ Designing and updating of Port Plug Test Facility for nuclear test stands continued for FDR finalization
DIAGNOSTICS 17%
¢ Diagnostic amendment signed for Lower Port Plug 8
¢ Procurement description completed for Upper Port Plug 7
Abbreviations • ANB Agreed Notified Body • CDR Conceptual Design Review • DA Domestic Agency • FDR Final Design Review • I&C Instrumentation & Control • IO ITER Organization
• IC ITER Council • FAT Factory Acceptance Tests • MIP Manufacturing & Inspection Plans • MRR Manufacturing Readiness Review • PA Procurement Arrangement • PDR Preliminary Design Review
* Does not include Complementary Diagnostic Arrangements.
US ITER (US-DA)
www.usiter.org WASHINGTON DC
procurement arrangements*
Fifteen pas signed since 2007 representing…
...AND 92%
OF THE TOTAL
83% IN NUMBER VALUE
OF US-DA IN-KIND
CONTRIBUTIONS.
The US has awarded over 600 contracts to US industry, universities, and national
laboratories in 44 states plus the District of Columbia since 2007.
US PROCUREMENT HIGHLIGHTS IN 2016 % OF ITER SYSTEM PROCURED BY THE US
MAGNET SYSTEMS
Central Solenoid Modules, Structure and Assembly Tooling 100%
¢ Completed winding of first module (IC milestone)
¢ Completed vacuum pressure impregnation and turn insulation of mockup coil
¢ Wound hexapancakes 4 and 5 for module 2
¢ Commissioned 9 of 10 fabrication work stations
¢ Last two contracts (of 7) for structures pending
¢ Completed lower key block assembly #1
¢ Manufactured first article tie plate
¢ Advanced fabrication of assembly platform
¢ Completed MRR for lifting fixture
Toroidal Field Conductor 8%
¢ Completed first 760-metre unit length by second integrator (IC milestone)
¢ Completed all conductor unit lengths; 7 of 9 deliveries completed to the EU-DA
¢ Toroidal field insert coil testing underway
DIAGNOSTICS
Port-Based Diagnostic Systems 14%
¢ Residual gas analyzer final R&D report completed
¢ Development test stand for motional stark effect mirror cleaning technology in progress
¢ Assembly underway for low field side reflectometer telescope test rig
FUEL CYCLE
Vacuum Auxiliary and Roughing Pump Stations 100%
¢ Delivery to ITER of vacuum test stand components
¢ Flanges ready to ship to ITER site (IC milestone)
¢ Further testing of cryoviscous compressor completed
Pellet Injection System 100%
¢ Pellet injection cask and system design ongoing
¢ Continued fabrication of fuel recirculation loop test unit
¢ Dual gun nozzle test unit in development
¢ Fabrication underway on latest iteration of twin screw extruder test unit
Disruption Mitigation System 100%
¢ Contract finalized for installation of shattered pellet injection unit on JET
TRITIUM PLANT
Tokamak Exhaust Processing System 88%
¢ Preliminary design contributions continued under IO Task Agreement
POWER SYSTEMS
Steady State Electrical Network 75%
¢ Delivery of power transformers to ITER site (IC milestone)
¢ Delivery of 6.6 kV switchgear to EU-DA
¢ 28 out of 35 planned shipments completed
¢ Contract awarded for fabrication of reactive power compensators
¢ Full contract scope now awarded
Abbreviations • ANB Agreed Notified Body • CDR Conceptual Design Review • DA Domestic Agency • FDR Final Design Review • I&C Instrumentation & Control • IO ITER Organization
• IC ITER Council • FAT Factory Acceptance Tests • MIP Manufacturing & Inspection Plans • MRR Manufacturing Readiness Review • PA Procurement Arrangement • PDR Preliminary Design Review
* Includes Complementary Diagnostic Arrangements.
FINLAND
SWEDEN
www.fusionforenergy.europa.eu LATVIA
IRELAND DENMARK
LITHUANIA
UNITED KINGDOM
CONTRIBUTIONS.
GREECE
The EU has awarded 595 research, design or fabrication contracts (89 in 2016) related to
ITER procurement to universities, laboratories and industry since 2007. MALTA CYPRUS
ITER will be the world's largest tokamak with a plasma volume of 840 m³ – nearly ten
times that of the largest machine in operation today. The experimental campaign that will
be carried out in this unique device is crucial to advancing fusion science and preparing the
way for the fusion power plants of tomorrow.
INTERNATIONAL COOPERATION
The following entities have signed Cooperation Agreements with the
ITER Organization as of 31/01/2017.
INTERNATIONAL ORGANIZATIONS
¢ CERN (European Organization for Nuclear Research) Switzerland
¢ ERIC (European Spallation Source European Research Infrastructure Consortium) Sweden
¢ IAEA (International Atomic Energy Agency) Austria
NATIONAL LABORATORIES
¢ Commissariat à l’Energie Atomique et aux Energies Alternatives, CEA France
¢ Dutch Institute for Fundamental Energy Research, DIFFER Netherlands
¢ Forschungszentrum Juelich GmbH, Institut fuer Energi und Klimaforschung, FZJ Germany
¢ Institute of Plasma Physics of the Academy of Science of the Czech Republic, IPP-Prague Czech Republic
¢ Institute for Plasma Research, IPR India
¢ Institute of Plasma Physics Chinese Academy of Sciences, ASIPP China
¢ Karlsruhe Institute of Technology, KIT Germany
¢ Max-Planck-Institut für Plasmaphysik, IPP Germany
¢ National Fusion Research Institute, NFRI Korea
¢ National Institute for Fusion Science, NIFS Japan
¢ United Kingdom Atomic Energy Authority, UKAEA-CCFE United Kingdom
UNIVERSITIES
¢ Seoul National University Korea
¢ The Eindhoven University of Technology, TU/e Netherlands
¢ The National Research Nuclear University (Moscow Engineering Physics Institute MEPhI) Russia
¢ Universitad Carlos III de Madrid (UC3M) Spain
¢ Université Aix-Marseille France
¢ University of Beihang (BUAA) China
¢ University of Durham United Kingdom
¢ University of Genoa (Department of Electrical, Electronic, Telecommunications Engineering and Naval Architecture, DITEN) Italy
¢ University of Ghent (Ughent) Belgium
¢ University of Illinois United States
¢ University of Keio Japan
¢ University of Kyoto Japan
¢ University of Liverpool United Kingdom
¢ University of Ljubljana Slovenia
¢ University of Manchester United Kingdom
¢ Universidad Nacional de Educación a distancia (UNED) Spain
¢ University of Oxford United Kingdom
¢ University of Pisa (Department of Civil and Industrial Engineering) Italy
¢ University of Rome-Sapienza Italy
¢ University of Tohoku (School of Engineering) Japan
¢ University of Science and Technology of China (USTC) China
¢ USTC School of Nuclear Science and Technology (SNST) China
¢ Università degli studi di Palermo (UNIPA) Italy
¢ University of Strathclyde United Kingdom
¢ University of York United Kingdom
NATIONAL SCHOOLS
¢ Ecole Centrale de Marseille (ECM) France
¢ Politecnico di Milano Italy
¢ Politecnico di Torino (PoliTo) Italy
¢ The Royal Institute of Technology (KTH) Sweden
NON-ITER MEMBERS
¢ Principality of Monaco Monaco
¢ Australian Nuclear Science and Technology Organisation (ANSTO) Australia
iter organization
Finance & Procurement Human Resources Project Control Office Central Integration Safety Department
Department (FPD) ¢ Department (HRD) ¢ (PCO) ¢ Office (CIO) ¢ (SD) ¢
Finance & Budget • Talent & Competencies Schedule Control Project Information System Security, Health & Safety
• Accounting, Treasury Development & Project Management Configuration Management Environmental
& Systems • Remuneration, Resource Control • Document Control Protection
• Budget Management Performance & & Performance & Nuclear Safety
• Financial Control Design & Construction
Employment Management Integration • Safety Analysis &
Procurement & Contracts • Design Integration Assessment
• Procurement Construction, • System Integration • Safety Control
Assembly and Logistics
• Procurement Engineering, Analysis Section
Plant and Support Design Office
• CAD Infrastructure
• CAD