Statcom Specification Rev-01
Statcom Specification Rev-01
Owner: The Owner (POWERGRID) is assumed to be responsible for the writing of the
specification, the execution of the contract, owning as well as the end user of the STATCOM
Stations.
PCC: Point of Common Coupling.
Power Module: Basic single power module of a Multi Module Valve. It includes H-Bridge,
DC Capacitor, Parallel discharge resistors, Bypass switch and associated accessories.
Valve Structure: Physical structure holding valve(s), which is insulated to the full system
voltage above earth potential.
Valve Section: Electrical assembly defined for test purposes, comprising one STATCOM
phase unit.
The requirement of reactive power compensation is defined in this section. The levels
guaranteed by the Bidder shall not be less than the levels specified hereunder.
The reactive power levels shall be determined by manufacturing tolerances of the components
and measurements carried out using metering accuracy instrumentation at the 400kV feed
points to the STATCOM Station. The reactive power capability shall also be determined by
calculations based on test values of appropriate quantities at the discretion of the owner.
In calculations of capability and availability, the owner shall assume the most unfavorable
combinations of control, manufacturing and measurement tolerances.
The rated capability of STATCOM, MSC(if applicable) & MSR(if applicable) shall be at 400
kV (Referred to as “Point of Common Coupling” or PCC) and in the steady state frequency
range of 48.5 Hz-50.5 Hz. Further the STATCOM Station including STATCOM Units,
MSCs and MSRs shall be designed to operate continuously under the worst possible
Technical Specification: Section-STATCOM Station, Rev01 Page 4 of 75
combination of steady state voltage and frequency range of 360- 440 kV and 47.5 Hz – 52 Hz
respectively and transient and temporary over voltages defined in Clause 6.1.3
1.1 Ambient conditions
STATCOM should be designed to perform under the ambient conditions as specified for each
location in Section-Project of Technical Specification.
2 Scope of work
This is a turn-key Technical Specification for the Contractor to supply according to this
specification, each complete STATCOM Station including STATCOM units along with
Mechanically Switched Capacitors (MSCs) (if applicable) and Mechanically Switched
Reactors (MSRs) (if applicable). Rating of STATCOM, MSCs and MSRs, shall be as
specified in for each location in Section-Project of Technical Specification. With the
exception of the equipment, material and services furnished by the Owner as defined in
Section-Project, the Contractor shall be responsible for the design, engineering, fabrication,
transport & delivery to site, civil works, erection, installation, testing, training,
commissioning, guarantees/warranties and field verification of the STATCOM station.
The Contractor shall also perform the system studies (steady state and dynamic), design
verification/validation, material procurement, type testing, quality management, factory
inspection/testing, site inspection, field testing, project management and interface
management with Other Parties and all associated Works and services until final handing over
of the STATCOM Station in a satisfactory working and operating condition along with the
necessary spare parts, consumables and documentation, to the Owner.
The STATCOM Station shall be installed at 400 kV sub-station of the Owner and connected
to 400KV Bus (Referred to as “Point of Common Coupling” or PCC). The STATCOM units
shall be required to provide specified reactive power at PCC to the 400 kV network of the
Owner. The Bidder shall decide the voltage of STATCOM Station MV Bus (Secondary
Voltage of Coupling Transformer) and shall provide necessary coupling transformer. The
switchgear provided on the secondary side shall be of standard voltage rating as per IEC. The
switchgear, structure, control, protection and substation automation on 400KV side shall be as
per applicable standard section of the Technical Specification.
2.1 Relevant Standard
STATCOM Station shall comply with the following standards:
3 Container for housing the equipments as above complete of: IEC 60071
- wall bushings for connection between converter phases IEC 60270
and decoupling reactors, IEC 60137
- piping and tubing connections of the cooling system to
converter
- connection of the control cabinet with the converter
through optical fibers
Technical Specification: Section-STATCOM Station, Rev01 Page 5 of 75
ITEM DESCRIPTION STANDARD
4 X kV, dry insulated, air core and air self-cooled decoupling IEC 60076
reactors. Mechanically Switched Reactors, half-reactors
stacked on above the other, Outdoor installation, Complete with
supporting structures
5 Power Capacitors (MSC etc.) IEC 60871-1
Note: Number of branches / units shown above shall be as per Section-Project of Technical specification
Figure 1: Conceptual Indicative Schematic diagram of STATCOM Station
The key components of STATCOM units and associated control & protection should be
designed, manufactured and tested by the Bidder itself. The bidder must also be
responsible for turn key delivery ensure availability and performance guarantees as well
as availability of follow up services and spare parts for running the STATCOM.
2.3 Performances Characteristic
a) When the steady state voltage is within 0.95 –1.05 pu, the Statcom output should be
zero or near zero for reduced losses. If the voltage is above 1.05 pu, then STATCOM
injects inductive current reaching full current at 1.1 pu voltage. If the voltage is above
1.05 pu then after about 5 seconds, MSL is switched in to bring STATCOM back to or
towards zero. If the voltage falls below 0.95 pu the STATCOM injects capacitive
current reaching 1 pu at 0.9 voltage. If the voltage falls below 0.95 pu then after about 5
seconds MSC is switched in to bring STATCOM back to zero or towards zero.
Furthermore the band of 0.1 pu (0.95-1.05) should be variable down to zero and
movable down to 0.9 pu by step of 0.01pu. If stability studies so indicate, STATCOM
should be able to operate in capacitive or inductive mode outside the band.
Protective levels of arresters connected to the 400 kV ac bus bars of the STATCOM Station
shall be coordinated with the insulation and surge arrester Characteristics of the 400 kV ac
SIWL LIWL
All equipment except Bus Post Insulator 1050 kVp 1425 kVp
Bus Post Insulator 1175 kVp 1550 kVp
Bushings of transformer 1050 kVp 1425 kVp
Winding of transformer 1050 kVp 1300 kVp
7.2 Valves
The requirement of insulation levels of the valves shall be provided by the bidder along with
the bid.
7.3 Air clearances
The air clearances shall be determined by the contractor based on the required withstand
levels for all waveforms in order to limit the probability of flashover within the STATCOM
Station to a target value of one flashover in 15 years.
7.4 Switchyard
The air clearances for switchyard equipment shall be equal to or greater than minimum values
as specified in IEC-60071. Altitude correction factor(if any) shall also be considered as per IEC
7.5 Leakage distances
The Creepage/leakage distance across insulation shall be determined by the contractor and
shall be adequate to ensure that under condition of heavy pollution, the probability of a flash
over of an insulator does not exceed one in 15 years. However, the leakage distance for all
AC insulators for outdoor installation shall not be less than 25 mm/kV of the maximum
operating phase to earth rms voltage at the insulator. The leakage distance of equipment
connected to 400 kV systems shall not be less than 10500 mm.
8 STATCOM Station Control Concept
The control system shall control the STATCOM, MSCs, MSRs required under this TS, as
well as any existing switchable capacitor and reactor banks as stated in the Section project of
Technical Specification.
The control system shall coordinate the operation of the STATCOM Station to regulate the
primary voltage (400kV bus). Operation logic for the breakers, disconnectors and earth-
switches in the STATCOM Station shall also be incorporated in the control system. The
control shall be programmable and have sufficient scope and flexibility (software
programming margin of at least 20%) to permit re-programming according to future changes
/ addition in the power system. The operator interface must be integrated in a latest version
of Windows environment. Major Control functions of the STATCOM Station shall include
the following:
11.6 As the sub-stations, where STATCOM Station shall be installed, are equipped with Sub-
station Automation System (SAS) conforming to IEC 61850, it is required that STATCOM
Station control and monitoring shall be integrated with SAS already provided at Sub-stations
by the Contractor. It is proposed to connect STATCOM Station SCADA with SAS through a
Gateway and the database, configuration etc. of existing SAS shall be upgraded to incorporate
STATCOM Station events, alarms, Controls (both switchgear and control functions of
14 Fault Recording
14.1 An integrated Transient Fault Recording (TFR) System shall be supplied, installed &
commissioned by the Contractor. This shall include trigger level settings for analog, etc.
subject to review and comment from the Owner. Disturbance and event recording facilities
are required for local monitoring of the STATCOM following a disturbance on the power
system or the STATCOM System. The following inputs are required:
• All analogue signals (output signals)
• All digital signals (control outputs, status indications, commands, alarms and
trip indications).
• Internal STATCOM Station control signals/variables to be selectable.
• The accuracy of the TFR for event inputs shall be at least 100 μs (sampling
rate of minimum 10 kHz).
• The TFR shall have provision for remote access and retrieval of recorded
information on to a PC. For this purpose, a communication link to the
Substation LAN shall be implemented.
• The remote software application for the data retrieval shall be included.
15 Radio Interference
The Contractor shall take necessary precautions in the form of shielding of valve hall and
building or Containers to meet its own requirement together with the following
a) With the STATCOM Station operating at any load upto rated value and within the design
range of firing angle, the radio interference level from electromagnetic or electrostatic
Technical Specification: Section-STATCOM Station, Rev01 Page 25 of 75
inductions generated by the STATCOM station shall not exceed 100 micro-volts/m, under
fair weather conditions, at any point outside the station fence. The RIL criteria shall be
achieved at all frequencies within the range of 150 KHz to 300 MHz and with the STATCOM
operation at any level upto and including rated value, the design shall provide correcting
measures, should the specified design not being realized in the final installation.
b) Measurements of actual RI at STATCOM Station shall be made by the contractor, at points
along the above defined contour and at other critical point.
c) RIV (RadioIinterference voltage) measured at a phase to ground voltage (266 kV rms) in
accordance to NEMA-107 shall not be more than 500 micro-volts for 400 kV system. For
other system voltages IEC/NEMA in the order of preference shall be applicable.
15.1 Interference with Power Line carrier & open wire carrier system
The Contractor shall take the necessary precaution in the form of noise suppression
techniques and filtering devices to prevent harmful interferences from STATCOM Station to
power line carrier (PLCC) system operating on connected AC transmission network.
The frequency spectra to be protected are:
System Frequency spectrum
Power Line carrier 30 kHz to 500 kHz
Open wire carrier 5 KHz to 30 kHz
The Contractor shall provide information on the noise spectrum at the termination of
STATCOM Station in the frequency from 5 kHz to 500 kHz.
16 Mechanically Switched Reactor (MSR): MSR is a fixed source of inductive reactive power
connected in shunt to the MV bus of STATCOM station and switched by means of Circuit
breaker (with control switching device) based on the command from STATCOM station
control system. The rated capability of MSRs shall be at 400 kV (Referred to as “Point of
Common Coupling” or PCC) and in the steady state frequency range of 48.5 Hz-50.5 Hz.
However, the individual components of MSR shall be able to withstand the onerous
condition imposed by system overvoltage and harmonics. The MSR consists of 3-ph Air
Core Reactor, 3-ph MV Circuit breaker (SF6/Vaccum type), associated current transformer,
3-ph Disconnector and associated safety grounding switch. The MSR area shall be fenced
and castle key interlock with safety grounding switch shall be provided for human safety.
The transformer should be designed & rated to carry 100% capacitive and inductive
reactive loading as specified including that of mechanically switched capacitor and
Reactors), as well as harmonic currents associated with the most onerous operating
conditions of STATCOM, without loss of life.
The coupling transformer shall be designed in accordance with the most upto date
experience in STATCOM application and shall incorporate the latest improvements of
design currently employed in the industry. The Comprehensive design review of
STATCOM transformer shall be carried out either by Owner or Owner’s Consultant
18.1 General Requirements
The coupling transformer shall be designed electrically and mechanically for operating
conditions peculiar to STATCOM operation, which shall include, but not be limited to
the following.
a) Electrical insulation problems resulting from the transformer being subjected to voltages of
distorted sinusoidal wave shape because of saturation, harmonics, trapped d.c. in capacitors
etc.
b) The cumulative effect of electro-dynamic forces produced during valve commutation or other
short circuit conditions imposed by valve design limitation and valve group operation.
c) Harmonic currents due to STATCOM operation, with particular reference to additional stray
losses resulting from these harmonic currents.
d) Stresses due to normal control operation and other onerous operations such as blocking and
de-blocking.
e) Stress due to fast response requirement of STATCOM for loading from 100% inductive to
100% capacitive and vice-versa.
f) Overvoltage stresses for which STATCOM shall be designed as per specification would apply
for transformer also.
g) All other stresses for which STATCOM shall be designed as per specification would apply for
transformer also.
h) The transformer and all its accessories like CTs etc. shall be designed to withstand, the
thermal and mechanical effects of any external short circuit to earth and of short circuit across
the terminals of any winding for a period of 3 seconds. The short circuit level of 400kV
system to which the transformer shall be connected as per the maximum short circuit level
mentioned in the section project. Short circuit level for HV bushing shall be 63kA for 1 Sec.
i) The transformer shall be capable of being loaded in accordance with IEC60076 or the
overload conditions as specified which is worst. There shall be no limitation imposed by
bushings during its terminal fault.
j) The transformer shall be capable of withstanding the mechanical, stresses caused by
symmetrical or asymmetrical faults on any winding.
Technical Specification: Section-STATCOM Station, Rev01 Page 30 of 75
k) The transformer should be designed to carry a certain level of direct current consistent with
the STATCOM design. To ensure minimum harmonic generation, the saturation flux density
of the transformer should be higher than the maximum flux density reached over the full
steady state range, and the bidder should state the margin by which it is exceeded. This
margin shall be at least 10%. This maximum flux density (over the full steady state range) is
obtained at the highest secondary voltage during any reactive power generation, highest
reference voltage, minimum slope, and minimum continuous frequency. The Contractor shall
submit B-H curve to substantiate this requirement. The flux density at the highest secondary
voltage shall lie in the linear portion of the B-H curve. Any harmonic generated by the
transformer should be considered by the design of the STATCOM.
l) Transformers shall be capable of operating under natural cooled condition up to the specified
load. The forced cooling equipment shall come into operation by pre-set contacts of winding
temperature indicator and the transformer shall operate as a forced cooling unit initially as
ONAF up to specified load and then as OFAF. Cooling shall be so designed that during total
failure of power supply to cooling fans and oil pumps, the transformer shall be able to operate
at full load for at least ten (10) minutes without the calculated winding hot spot temperature
exceeding 140 deg C. Transformers fitted with two coolers, each capable of dissipating 50 per
cent of the loss at continuous maximum rating, shall be capable of operating for 20 minutes in
the event of failure of the oil circulating pump or blowers associated with one cooler without
the calculated winding hot spot temperature exceeding 140deg C at continuous max rating.
The contractor shall submit supporting calculations for the above and the same shall be
reviewed during design review.
m) The transformer shall be free from any electrostatic charging tendency (ECT) under all
operating conditions when all oil circulation systems are in operation. In general, oil flow
speed shall not exceed 1.0 m/sec within winding in the oil flow system of the transformers.
The manufacturer shall ensure that there is no electrostatic charging tendency in the design.
b) HV and MV Bushing shall be RIP bushing with Polymer / composite insulator. Neutral
bushing shall be solid porcelain or oil communicating type.
c) Where current transformers are specified, the bushings shall be removable without disturbing
the current transformers.
e) Porcelain used in bushing manufacture shall be homogenous, free from lamination, cavities
and other flaws or imperfections that might affect the mechanical or dielectric quality and
shall be thoroughly vitrified, tough and impervious to moisture.
f) Polymer / composite insulator shall be seamless sheath of a silicone rubber compound. The
housing & weather sheds should have silicon content of minimum 30% by weight. It should
protect the bushing against environmental influences, external pollution and humidity. The
interface between the housing and the core must be uniform and without voids. The strength
of the bond shall be greater than the tearing strength of the polymer. The manufacturer shall
follow non-destructive technique (N.D.T.) to check the quality of jointing of the housing
interface with the core. The technique being followed with detailed procedure and sampling
shall be decided during finalization of MQP.
g) The weather sheds of the insulators shall be of alternate shed profile as per IEC 60815-3. The
weather sheds shall be vulcanized to the sheath (extrusion process) or moulded as part of the
sheath (injection moulding process) and free from imperfections. The vulcanization for
extrusion process shall be at high temperature and for injection moulding shall be at high
temperature & high pressure. Any seams / burrs protruding axially along the insulator,
resulting from the injection moulding process shall be removed completely without causing
any damage to the housing. The track resistance of housing and shed material shall be class
1A4.5 according to IEC60587. The strength of the weather shed to sheath interface shall be
greater than the tearing strength of the polymer. The composite insulator shall be capable of
high pressure washing.
i) The hollow silicone composite insulators shall comply with the requirements of the IEC
publications IEC 61462 and the relevant parts of IEC 62217. The design of the composite
insulators shall be tested and verified according to IEC 61462 (Type & Routine test).
k) Bushing turrets shall be provided with vent pipes, to route any gas collection through the
Buchholz relay.
m) Spare Bushing shall be specially packed suitable for long storage with non-returnable
packing, the details of which shall be provided to the purchaser
n) The terminal marking and their physical position shall be as per IEC: 60076.
18.4 Inhibited Insulating Oil
The insulating oil shall be virgin high grade inhibited, conforming to IEC-60296 & all
parameters specified at Annexure – A, while tested at oil supplier's premises. The contractor
shall furnish test certificates from the supplier against the acceptance norms as mentioned at
Annexure – A, prior to despatch of oil from refinery to site. Under no circumstances, poor
quality oil shall be filled into the transformer and thereafter be brought up to the specified
parameter by circulation within the transformer. The Unused inhibited Insulating Oil
parameters including parameters of oil used at manufacturer’s works, processed oil, oil after
filtration and settling are attached at Annexure – A. The oil test results shall form part of
equipment test report.
Sufficient quantity of oil necessary for maintaining required oil level in case of leakage in
tank, radiators, conservator etc. till the completion of warranty period shall be supplied.
Inhibited oil used for first filling, testing and impregnation of active parts at manufacturer's
works shall be of same type of oil (in line with IEC 60076-3) which shall be supplied at site
and shall meet parameters as per specification.
18.4.1 Particles in the oil
The particle analysis shall be carried out in an oil sample taken after completion of the oil
filtration at site. The procedure and interpretation shall be in accordance with the
recommendation of CIGRE report WG-12.17 - “Effect of particles on transformer dielectric
strength”.
b) The duration of the vacuum treatment shall be demonstrated as adequate by means of water /
dew point measurement with a cold trap or other suitable method. The vacuum shall be
measured on the top of the transformer tank and should be less than 1mbar.
c) Oil filling under vacuum at site shall be done with transformer oil at a temperature not
exceeding 65°C. Vacuum shall not be broken until the Transformer is oil filled up to the
Buchholz relay.
d) The minimum safe level of oil filling (if different from the Buchholz level) to which the
Transformer shall be oil filled under vacuum, shall be indicated in the manual.
e) The Ultra High Vacuum type oil treatment plant of suitable capacity (minimum 6000 litres
per hour) suitable for treatment of oil in EHV class Transformer shall be used in order to
achieve properties of treated oil. The plant shall be capable of treatment of new oil (as per
IEC 60296 and reconditioning of used oil (as per IS: 1866/IEC: 60422 for oil in service) at
rated capacity on single pass basis as follow:
f) Removal of moisture from 100 ppm to 3 ppm (max.)
g) Removal of dissolved gas content from 10% by Vol. to 0.1% by vol.
h) Improvement of dielectric strength break down voltage from 20 to 70 KV
i) Vacuum level of degassing chamber not more than 0.15 torr/0.2 mbar at rated flow and at
final stage. Machine shall have minimum of two degassing chambers and these should have
sufficient surface areas to achieve the final parameters.
j) Filter shall be capable of removing particle size more than 0.5 micron in the filtered oil.
k) Processing temperature shall be automatically controlled and have an adjustable range from
40°C to 80°C.
18.4.4 Transportation of Oil
The insulating oil for the transformer shall be delivered at site generally not before 90 days
from the date of commissioning, with prior information to the Employer.
Insulating oil shall be delivered to the site in returnable oil drums / flexi bag / tanker. The oil
drums / flexi bag / tanker shall be taken back without any extra cost to Employer within
generally 45 days after utilisation of oil but in any case before contract closing. However, the
spare oil shall be delivered in non-returnable drums.
i) A sufficient quantity of oil necessary for first filling of each tank, coolers and radiator at
the proper level, including spare units, along with 20% (of one complete transformer) extra
oil shall be supplied to site for Employer's later use. The 20% spare oil shall be supplied in
non-returnable containers suitable for outdoor storage.
i. The cooler shall be designed using radiator banks or tank mounted radiators. Design of
cooling system shall satisfy the performance requirements.
ii. In case of separately mounted radiator bank arrangement, the main tank shall have provision
such that cooler banks can be placed on either side of the main tank without the need of any
extra member/pipe maintaining the electrical clearances.
iii. The radiator shall be of sheet steel in accordance with IS 513 and minimum thickness 1 mm.
Each radiator bank shall be provided with the following accessories:
(a) Cooling Fans, Oil Pumps, Oil Flow Indicator (as applicable)
(b) Top and bottom shut off valve
(c) Drain Valve and sampling valve
(d) Top and bottom oil filling valves
(e) Air release plug
(f) Two grounding terminals for termination of two (2) Nos. 75x12 mm galvanised
steel flats.
(g) Thermometer pockets with captive screw caps at cooler inlet and outlet.
(h) Lifting lugs
iv. Each radiator bank shall be detachable and shall be provided with flanged inlet and outlet
branches. Expansion joint shall be provided on top and bottom cooler pipe connection.
v. Required number of standby fans of approximately 20% capacity shall also be provided with
each radiator bank.
vi. Cooling fans shall not be directly mounted on radiator bank which may cause undue
vibration. These shall be located so as to prevent ingress of rain water. Each fan shall be
vii. Two (2), 100% centrifugal or axial in line oil pumps, if applicable, (out of which one pump
shall be standby) shall be provided with each radiator bank. Measures shall be taken to
prevent mal-operation of Buchholz relay when all oil pumps are simultaneously put into
service. The pump shall be so designed that upon failure of power supply to the pump motor,
the pump impeller will not limit the natural circulation of oil.
viii. An oil flow indicator shall be provided for the confirmation of the oil pump operating in a
normal state. An indication in the flow indicator and potential free contacts for remote alarm
shall be provided.
ix. Valves shall be provided across the pump and oil flow indicator to avoid oil drain and long
outage during maintenance / replacement of pump and oil flow indicator.
x. Cooling fans and oil pump motors shall be suitable for operation from 415 volts, three phase
50 Hz power supply and shall conform to IS: 325. Each cooling fan and oil pump motors shall
be provided with starter thermal overload and short circuit protection. The motor winding
insulation shall be conventional class 'B' type. Motors shall have hose proof enclosure
equivalent to IP: 55 as per IS: 4691.
xi. The cooler pipes, support structure including radiators and its accessories shall be hot dip
galvanised or corrosion resistant paint should be applied to external surface of it.
xii. Butterfly valves shall be provided on either side of oil flow indicator and pumps for
maintenance and replacement of pump and oil flow indicator without removing the oils.
xiii. Air release device and oil plug shall be provided on oil pipe connections. Drain valves shall
be provided in order that each section of pipe work can be drained independently.
i. Automatic operation control of fans/pumps shall be provided (with temperature change) from
contacts of winding temperature indicator. The Contractor shall recommend the setting of
WTI for automatic changeover of cooler control over entire cooling option. The setting shall
be such that hunting i.e. frequent start-up operations for small temperature differential do not
occur.
ii. Suitable manual control facility for cooler fans and oil pumps shall be provided.
iii. The changeover to standby oil pump in case of failure of service oil pump shall be automatic.
v. Selector switches and push buttons shall also be provided in the cooler control cabinet to
disconnect the automatic control and start/stop the fans and pump manually.
vii. One potential free initiating contact for all the above conditions shall be wired independently
to the terminal blocks of cooler control cabinet and for single ph. unit connection shall be
extended further to CMB.
viii. The cooler control cabinet / Individual Marshalling box shall have all necessary devices
meant for cooler control and local temperature indicators. All the contacts of various
protective devices mounted on the transformer and all the secondary terminals of the bushing
CTs shall also be wired upto the terminal board in the cooler control cabinet/Individual
Marshalling box. All the CT secondary terminals in the cooler control cabinet shall have
provision for shorting to avoid CT open circuit while it is not in use.
ix. All the necessary terminations for remote connection to Purchaser's panel shall be wired upto
the Common Marshalling box.
x. Control and power supplies are to be given after suitable selection at Common Marshalling
Box. Necessary isolating switches and protective devices shall be provided at suitable points
as per Purchaser's approved scheme.
xi. The Contractor shall derive AC power for Cooler Control Circuitry from the AC feeder as
mentioned above. In case auxiliary power supply requirement for Cooler Control Mechanism
is different than station auxiliary AC supply, then all necessary converters shall be provided
by the Contractor. Details of station auxiliary power supply are mentioned in GTR.
a) Online Dissolved Gas (Multi-gas) and Moisture Analyser along with all required accessories
shall be provided with each transformer for measurement & analysis of dissolved gases and
moisture in the oil. Interpretations shall be as per IEC 60599-1999.
b) The equipment shall detect, measure and analyse the following gases:
d) Equipment shall havefacility to give SMS alert to at least three users whenever any fault gas
violates the predefined limit.
e) Equipment should work on station auxiliary supply. In case other supply is required for the
equipment then suitable converter shall be included. All the necessary power and control
cables, communication cables, cable accessories as required shall be provided by the supplier.
f) Online DGA shall be installed out door on transformer in harsh ambient and noisy condition
(Electromagnetic induction, Corona, and capacitive coupling). Equipment shall be mounted
separately to avoid effect of vibration. Suitable arrangement shall be provided support and
protect the inlet and outlet piping arrangement.The equipment shall be suitable for proper
operation in EHV substation (800kV) environment where switching takes place in the
EHV/HV System. The suitable indications for power On, Alarm, Caution, normal operation
etc. shall be provided on the front panel of the equipment. The equipment shall have IP55
Stainless Steelenclosure, suitable for 55 0C ambient temperature and EMI and EMC
compatibility.The Equipment must carry a minimum of two (2) years manufacturer’s
Warranty.
g) The equipment shall connect to the transformer's main body in two locations. One Connection
is for the supply of oil from the transformer. Second connection is for the return of the oil to
the transformer.The connecting oil lines must be of Stainless Steel rigid pipes or flexible
hoses.
h) The equipment shall be able to measure gas concentration and when downloaded should
immediately compare it with user selected alarm & caution level for immediate display. The
sampling rate shall be selectable as 2 or 4 or 6 or 12 hours etc. The equipment shall have
inbuilt memory to store these results for complete one year even if sampling is done at the
lowest interval.
i) The Equipment must have an automatic Calibration facility at fixed intervals. For calibration
if anything required including cylinder must be mounted with the Equipment.
j) The technical feature of the equipment shall be as under:
Accuracy + 10%
Repeatability +3% to 10% depending upon gases
Oil temperature range - 200 C to + 1200 C
External Temp. Range - 200 C to + 550 C
(External temp range of 550 C is important and should
not be compromise due to Indian ambient &
k) Software for fault indication and fault diagnostics shall include following:
Fault indication:
Fault Diagnosis:
i) Key gases
ii) Ratios (Rogers, IEC. etc.)
iii) Duval’s Triangle
l) The equipment shall be supplied with all necessary accessories required for carrying out DGA
of oil sample complete in all respect as per the technical specification. The following shall be
also form a part of supply.
i) Software
ii) Operation Manual (2 set for every unit),
iii) Software Manual and
iv) Compact disc giving operation procedures of Maintenance Manual & Trouble
shooting instructions.
Each Transformer unit shall be fitted with at least 16 numbers optical temperature sensors.
The optical sensors based temperature measuring system shall be of direct measurement non
calibrating type. All the sensors shall be brought out to separate optical sensor box mounted
on transformer tank to facilitate measurement of temperature during service life on each unit.
Temperature measuring unit/system housed in above box shall be suitable for satisfactory
operation with ambient conditions and IEC 61850 compliant to interface with Employer’s
SCADA system.
Location of optical temperature sensors inside the transformer shall be decided during design
review. Manufacturers are advised to provide few more optical temperature sensors (probes)
to take care of any damage during handling.
No. Test
1. Measurement of winding resistance Routine
2. Voltage ratio measurement Routine
3. Polarity test Routine
4. No-load loss and current measurement Routine
5. Magnetic balance test (for three phase Transformer only) Routine
6. Impedance and load loss measurement Routine
7. Measurement of insulation resistance & Polarization Index Routine
8. Measurement of insulation power factor and capacitance Routine
between winding and earth and Bushings
9. Chopped wave lightning impulse test for the line terminals Routine
(LIC)
Full wave lightning impulse test for the line terminals (LI) -
10. Measurement of transferred surge on LV (Tertiary) as Routine
applicable due to HV lightning impulse and IV lighting
impulse (as applicable)
11. Switching impulse test for the line terminal (SI) Routine
12. Line terminal AC withstand voltage test (LTAC) Type
13. Induced voltage withstand test (IVW) -
14. Applied voltage test (AV) Routine
15. Induced voltage test with PD measurement (IVPD) Routine
16. On-load tap changer test(Ten complete cycle before LV Routine
test)
17. Gas-in-oil analysis Routine
18. Core assembly dielectric and earthing continuity test Routine
Technical Specification: Section-STATCOM Station, Rev01 Page 44 of 75
19. Oil leakage test on transformer tank Routine
20 Appearance, construction and dimension check Routine
21. Short duration heat run test ( Not Applicable for unit on Routine
which temperature rise test is performed )
22. Measurement of no load current & Short circuit Impedance Routine
with 415 V, 50 Hz AC.
23. Frequency Response analysis (Soft copy of test report to be Routine
submitted to site along with test reports )
24. High voltage with stand test on auxiliary equipment and Routine
wiring after assembly
25. Tank vacuum test Routine
26 Tank pressure test Routine
27. Lightning impulse test for the neutral terminals (LIN) Type
28. Temperature rise test Type
29. Measurement of Zero seq. reactance Type
(for three phase Transformer only)
30. Measurement of harmonic level in no load current Type
31. Measurement of acoustic noise level Type
32. Measurement of power taken by fans and oil pumps Type
(Not applicable for ONAN)
1) Bushing (Type Test as per IEC:60137 including Snap back/Seismic test for
400 kV and above voltage class bushing)
2) Buchholz relay (Type Test as per IS: 3637 and IP-55 Test on terminal box )
3) Cooler Control cabinet, Individual Marshalling (IP-55 test)
4) Pressure Relief device Test
The pressure Relief Device of each size shall be subjected to increase in oil
pressure. It shall operate before reaching the test pressure specified in
transformer tank pressure test above. The operating pressure shall be
recorded. The device shall seal off after excess pressure has been released.
5) Magnetic Oil Level gauge & Terminal Box for IP-55 degree of protection.
6) Air Cell (Flexible air separator) - Oil side coating, Air side under Coating,
Air side outer coating and coated fabric as per IS: 3400/ BS: 903/ IS: 7016
7) OTI & WTI
8) Oil pump
Technical Specification: Section-STATCOM Station, Rev01 Page 45 of 75
9) Cooling fan and motor assembly
c) Tank Tests
i. Oil Leakage Test
All tanks and oil filled compartments shall be tested for oil tightness by being completely
filled with air or oil of a viscosity not greater than that of insulating oil at the ambient
temperature and applying a pressure equal to the normal pressure plus 35 kN/m2 measured
at the base of the tank. The pressure shall be maintained for a period of not less than 24
hours for oil and one hour for air during which time no leak shall occur.
ii. Vacuum Test
One transformer tank of each size shall be subjected to the specified vacuum. The tank
designed for full vacuum shall be tested at an internal pressure of 3.33 kN/m2 absolute (25
torr) for one hour. The permanent deflection of flat plate after the vacuum has been released
shall not exceed the values specified below:
Horizontal Length of flat plate Permanent deflection
(in mm) (in mm)
Upto and including 750 5.0
751 to 1250 6.5
1251 to 1750 8.0
1751 to 2000 9.5
2001 to 2250 11.0
2251 to 2500 12.5
2501 to 3000 16.0
Above 3000 19.0
23 VT & CT
The instrument transformers shall comply with the relevant IEC Standards. They shall
satisfy the general Technical Requirement specified in specification and shall be
designed to operate in the environmental conditions specified in this Specification.
-5 ~ +50Ԩ
21. Working
10 ~ 90%
Humidity
24.6 PTZ-Keyboards
The features of PTZ shall include:
• Fully functional dynamic keyboard/joystick controllers
• Controls all pan, tilt, zoom, iris, preset functions
• Control up to 255 units from a single keyboard
• Many preset options and advanced tour programming
• Compatible with all connected cameras
•
1. Key Application wired keyboard control operation of PTZ functions
for weatherproof dome cameras
2. Pan / Tilt / Zoom Protocol Selectable
Languages Supported
3. PTZ Data Transfer Baud selectable 1200 bps / 2400 bps / 4800 bps / 9600
Rates Supported bps
4. Additional Features dynamic joystick for smooth camera movements,
preset location option for quick access to
frequently monitored areas
26 MV Circuit Breaker
The MV Circuit Breaker shall comply with the IEC and all other relevant Standards, and as
specified in this specification. They shall satisfy the General Technical Requirements and
shall be designed to operate in the environmental conditions specified in this specification.
The Circuit Breaker offered should be of SF6 type /Vacuum type only and of class C2, M2 as
per IEC
26.1 The circuit breaker shall be complete with terminal connectors, operating mechanism, control
cabinets, piping, interpole cable, cable accessories like glands, terminal blocks, marking
ferrules, lugs, pressure gauges, density monitors (with graduated scale), galvanised support
structure for CB and control cabinets, their foundation bolts and all other circuit breaker
accessories required for carrying out all the functions the CB is required to perform.
26.2 All necessary parts to provide a complete and operable circuit breaker installation such as
main equipment, terminals, control parts, connectors and other devices whether specifically
called for herein or not shall be provided.
Technical Specification: Section-STATCOM Station, Rev01 Page 58 of 75
26.3 The support structure of circuit breaker shall be hot dip galvanised. Exposed hardware items
shall be hot dip galvanised or Electro-galvanised.
26.4 MV Circuit Breaker shall be equipped with controlled switching with consequent
optimization of switching behavior, when used in:
• Switching of Capacitor Bank
• Switching of shunt Reactor Bank
For Technical Requirement for controlled switching device refer Section-Switchgear of
Technical Specification.
26.5 The test reports of the type tests shall be submitted for Purchaser’s review:
26.6 The Circuit Breaker shall be capable of performing their duties for their intended application
under system operating conditions specified for STATCOM Station.
26.7 Routine tests as per IEC:62271-100 shall be performed on all circuit breakers.
29 Design Principles
The objective for the design of the STATCOM Station shall be to achieve high level of
availability and reliability as specified. Special attention shall be given to design the
STATCOM Station to avoid forced outages. The contractor shall conduct thorough design
Technical Specification: Section-STATCOM Station, Rev01 Page 60 of 75
reviews and submit a report explaining the measures taken to minimize the risk of such
outages. The Contractor shall give careful attention to related factors affecting STATCOM
Station performance such as subsystem & system testing, protective relays co-ordination and
proper setting of relays.
Except where greater reliability requirements are specified in these specifications, the design
basis for STATCOM Station shall be such that no single contingency downstream from the
medium voltage bus shall cause a total outage of the STATCOM Station. The following
general criteria shall be followed for the design of the control system:
a) Use of components similar to those whose reliability has already been proved in use.
b) Use of good design practices, surge protection, filtering and interference buffers to assure
Immunity to sensitive component and circuits against damage and interference by induced
voltages and currents in the external cabling and cubicle wiring.
c) Use of fail safe and self-checking design features.
d) Use of component and equipment redundancy, by means of either duplication or triplication
with automatic transfer facilities wherever necessary to meet the requirement of these
specifications.
e) Design which in the event of component failures, provide for transfer to a less complex
operating mode.
f) Provision of alarm, fault diagnosis & indication
33 Testing Requirements: Below are basic requirements for STATCOM Station tests.
33.1 Site Pre-commissioning Testing
a) Dielectric and Insulation resistance checks on primary equipments consisting of Power factor
tests, high potential tests.
b) Resistance measurements of transformers, reactors, filter resistors & measuring equipment.
c) Ratio & polarity checks of transformers & measuring devices
d) Magnetization curves of current transformers
e) Insulating oil tests on transformers, reactors & other oil insulated equipment
f) Contact resistance checks of bus connections, jumpers, isolators and earths witches.
g) Functional tests on auxiliaries
h) Functional tests on control, protection, fault recorder, SCADA & alarm circuits including
protective relay settings and testing.
i) Mechanical balancing, alignment, capacity, vibration checks
j) Checks of Interlocks
k) Wiring continuity & insulation resistance tests
l) Power abnormality tests for electronic equipment
m) Power supply parameters for electronic equipment
n) Diagnostic software functional demonstration
o) Functional tests on Valve cooling system
33.2 Commissioning Tests
After successful completion of the pre-commissioning tests, all independent sub-system
shall be energized or started up in accordance with the relevant approved
commissioning procedures to be submitted by the Contractor. These tests shall
Technical Specification: Section-STATCOM Station, Rev01 Page 67 of 75
demonstrate the electrical & mechanical integrity of these sub-systems. During these
tests the Contractor shall make the initial adjustment to the equipment for satisfactory
operation.
Commissioning tests will be subject to mutual agreement between the Contractor & the
Owner.
33.3 Site Acceptance Test
After the satisfactory completion of pre-commissioning & commissioning tests the following
acceptance tests shall be carried out on each STATCOM Station. The Contractor shall furnish
the best procedure for carrying out the tests.
z STATCOM valves firing & supervision test
z STATCOM valves energizing test
z STATCOM Station power rating test
z MSC / MSR energizing test
z Harmonic performance test
z Complete Operating Characteristics & Slope Setting
z Static Characteristic of the Uncontrolled STATCOM
z STATCOM small Signal Response Test
z STATCOM Station Control system test.
z Heat run test
z Large disturbance test (Field testing)
33.4 Trial operation
After completion of system tests, trial operation for an uninterrupted period of normal
operation of not less than 10 days is required and during which the converter equipment shall
be fully operational. Interruptions attributable to connecting system requirements shall be
permitted during trial operation.
34 Commissioning Responsibilities
The equipment supplied for this Contract shall be commissioned at the Sites and
brought into Commercial Operation by the Contractor.
The Contractor shall provide a Commissioning Supervisor and other staff approved by the
Owner. The Contractor shall furnish commissioning procedures well in advance and details
of test equipment required and these procedures shall include, but not be limited to, the tests
specified above in this section.
The Contractor shall allow four weeks for the Owner to approve or comment on the
procedures received. The Owner reserves the right to have any additional tests carried out
which shall be mutually agreed to between the Owner and the Contractor
During the commissioning work the Contractor’s Commissioning Supervisor shall assume
charge and be responsible for the equipment being commissioned. Owner’s clearance and
safety procedures shall apply during the commissioning work and owner will nominate a
representative to coordinate with the Contractor’s Commissioning Supervisors on matters
relating to System operation and control.
The Contractor shall supply the testing equipment for the dielectric tests and all measuring
devices, including instrument transformers, oscillograph, etc., for tests performed at the Site.
These instruments and instrument transformers shall be previously calibrated against
accepted standards.
No inspecting, testing or operation which is required to take place or be done in, upon, or
about the Works which have been energized or existing equipment or facilities of Owner
Technical Specification: Section-STATCOM Station, Rev01 Page 68 of 75
which are or may be electrically charged or energized from any source, shall be permitted
unless and until a written “permit to work” has been issued for this purpose by the Owner.
When such inspecting, testing or operation has been completed, the Contractor shall give
written clearance to Owner of said completion. The “permit to work” shall apply and for
what period the said permit shall apply and the permit shall only be valid for such date and
such period of time.
35 Quality Control
The Contractor shall institute a quality assurance programme to ensure the quality of the
equipment. Such programme shall be geared to quality assurance at all manufacturing plants
of the Contractor and at the Site. The position of the programme related to the manufacture
of equipment by the Contractor shall be in accordance with the relevant international
Standards.
The contractor shall submit quality manual which shall be based on BS:5750 Part-I CSA:Z
299/national/international standard. Quality manual shall outline the comprehensive quality
management system of the contractor under various sections such as organization structure,
documentation control, deviation, disposal etc.
All details of the Contractor’s quality assurance programme shall be approved by Owner
prior to commencement of the Works.
The Contractor’s quality assurance programme shall include, but not be limited, to the
following items :
a) Appointment of Contractor’s representative for quality assurance
b) Performance of all inspection and testing
c) Calibration of measuring and testing equipment
d) Maintenance of quality records
e) Provide Owner access to Contractor’s or sub-contractor’s premises for the purpose of quality
surveillance and verification
f) Corrective action when non-conforming items are found in the quality assurance programme.
g) The Contractor shall comply with all the requirement of the approved quality assurance
programme.
35.1 Inspection
Inspection in Factory
In order to verify that all the manufacturing of equipment by the Contractor, or material and
equipment being procured and provided by the Contractor is all in complete conformance
with the requirements of the Contract, the Contractor shall ensure that the inspector or
Engineer, or any other agent or agency authorized by Owner in writing, shall at all times
have access to all facilities and premises where the manufacturing and supply of the
Equipment by the Contractor, or Sub-contractors is being carried out.
The Contractor shall provide detailed manufacturing schedules, quality control and non-
destructive testing procedures for approval of the Owner and shall keep such schedules up-
to-date. The Contractor shall notify the Inspector in writing at least fifteen (15) working days
in advance of each date any material or equipment becomes ready for inspection and shop
quality control tests. In addition, notice for tentative dates for type testing of major
equipment shall be given 90 days in advance.
In the case of material, certified copies of all such inspection and test reports for chemical
analysis and for mechanical and electrical properties shall be available to the Inspector.
Copies of the reports shall be given upon request.
Technical Specification: Section-STATCOM Station, Rev01 Page 69 of 75
Test reports of any and all tests performed in the supply shall be certified by the Inspector
unless specifically waived.
All inspections or tests carried out by the Contractor and to be witnessed by the Inspector
shall be scheduled and performed so as to avoid undue delay in the performance of the
equipment.
The Contractor shall provide without cost to Owner all facilities and assistance for the safety
and convenience of the Inspector in the performance of the Inspector’s duties.
The Contractor shall include in all orders to Subcontractors the requirement that any
equipment being supplied by Sub-contractors for incorporation in the equipment shall be
subject to inspection and testing by the Inspector or the Engineer or any other authorized
agent of Owner. Copies of such order blanked for prices shall be forwarded to Owner.
All of the required tests shall be made at the Contractor’s expense, including the cost of all
testing facilities, test samples and the like.
The Owner reserves the right to require special tests in addition to those specified in the
Contract and the Contractor shall perform such tests, which can be performed either in the
Contractor’s installations or in any other facilities chosen by Owner.
The Contractor will be advised in reasonable time at Owner’s discretion to permit the
preparation of facilities and specimens for such additional tests. Unless otherwise provided,
such tests shall be in accordance with the requirements of international accepted testing
standards and procedures.
The Inspector or the Engineer, or any other agent or agency authorized by Owner in writing,
shall carry out the testing and inspection of any part of the equipment in accordance with the
procedures herein below included:
a. Approval of the Contractor’s inspection plan and initial evaluation of the Contractor’s
inspection system.
b. Periodic checks of the manufacturing procedures to confirm effective application of the
inspection plan.
c. Inspection of matter and/or verification of inspection records at the Inspector’s
discretion including:-
compliance of raw materials with the requirements of Contract and the required standard;
compliance of manufactured parts and assemblies with the Contract, released drawings, and
good engineering practice and manufacturing practice;
check of packing lists to verify that all parts of the equipment listed is packed, including
identification and destination of shipments;
Periodic inspection of Contractor’s design and production, and preparation of progress
reports with regard to manufacturing process and procedures;
Witnessing of tests;
Verification of the Contractor compliance with the equipment delivery schedule, and releases
for dispatch;
Effectiveness of packing systems for shipment to ensure protection and handling of material
and equipment, and plant;
The Inspector shall have complete authority to accept or reject, on behalf of the Owner any
material, equipment or parts thereof considered unsatisfactory and not in accordance with the
Contract; failure to inspect and accept or reject materials, equipment or any components
thereof shall not relieve the Contractor of any of his obligations under the Contract, nor
impose any liability whatsoever on Owner.
Technical Specification: Section-STATCOM Station, Rev01 Page 70 of 75
The contractor shall furnish a detailed and comprehensive quality plan, in complete, to the
Engineer.
The quality plant shall relate the specific and objective manufacturing practices followed by
the contractor. Accordingly the quality plan shall be submitted broadly under the following
sub-heads :
a. Raw materials/bought out items and components
b. In process tests/checks to establish successful completion/accomplishment of the
process.
c. Final tests/checks in accordance with national international and POWERGRID
specification
The quality plan shall be submitted with all references documents to enable Engineer to
finalize quality plan. The Contractor shall proceed with manufacturing of the equipment
only once the quality plan is approved by the Engineer.
In order to ensure timely execution of the contract the Contractor shall ensure timely
submission/approval of quality plan.
36 Site Inspection
The Owner shall have the right to have Inspectors at the sites, on a regular basis or from time
to time as may be required within his sole description to monitor the quality and the progress
of the work.
The Inspectors shall have the right to order any special Sites tests deemed necessary to verify
the compliance of the equipment with the Contract.
The Contractor shall provide adequately furnished office space in his construction facilities
for the performance of an average of 5 people of the Owner throughout the execution of the
work.
37 Design Reports and Design Reviews
37.1 During detail engineering, the Contractor shall submit the following Design Reports for
All deviations from the technical specification shall be brought out separately as per the
format given in the first stage bid documents.
3. Total sulphur content BS 2000 part 373 or ISO 0.05 % (Max.) (before oxidation
14596 or ASTM D 2622 state)
5. Presence of oxidation IEC 60666 or ASTM D2668 0.08% (Min.) to 0.4% (Max.)
inhibitor or D4768 Oil should contain no other
additives .Supplier should declare
6. 2-Furfural content IEC 61198 or ASTM D5837 25 Microgram/litre (Max.)
C Performance
3. PCB content IEC 61619 or ASTM D4059 Not detectable (Less than 2
mg/kg)
E Oil used (inhibited) for first filling, testing and impregnation of active parts at
manufacturer's works shall be same type of oil which shall be supplied at site and shall
meet parameters as mentioned below:
1 Break Down voltage 70kV (min.)
(BDV)
F Each lot of the processed oil shall be tested prior to filling in main tank at site for the
following:
G After filtration & settling and prior to energisation at site oil shall be tested for following:
* Separate oil sample shall be taken and test results shall be submitted within 45 days
after commissioning for approval of Employer.