Activity ID Affected ALS work Status Action by Action Required Latest reply

‐ For W‐beam guardrail activities ALS 20‐Feb : Foam shelter 20m


WBS: WAS_ Internal_UP‐4.4.1.1.5 116 ‐ ALS purchased the quantity of W‐beam as per ALS to provide Drawing Number/Structure where the east of Helipad 86m provided 15‐Feb
Constraint GE
meter as per P.O misc. BOQ and there are 116mtrs excess after all required W‐beams are installed and respective quantity. 106 of 116m provided
W‐beams are installed

MOT permit required We requested Al Soli to provide all the requirements


SEC to secure MOT permit. from MOT to issue the permit along with their
WBS: WAS_ Internal_UP‐4.4.1.13 Phase Backfilling of 15 nos. lighting poles at curve area at
Constraint GE/SEC SEC will not ask MOT for permit if the concrete slope quotation but till now quotation not yet received, Al
‐ 02 Single Pole Main Access Road
protection and cat eyes are not provided by GE Soli not take it seriously to close the subject.
‐ Management to resolve Quotation received under evaluation ‐ 1st Feb

Artificial grass installation cannot proceed as the GE reply 30 Jan : Earthing material is already arrived.
WBS: WAS_ Internal_UP‐4.4.1.12 Artificial GE to provide earthing material ‐waiting for delivery
area was excavated (and still not backfilled) by ASC Constraint GE ‐E On‐hold by Elec. Team due to earthing resistance
Grass fixing on hold by GE ASC to install earthing and backfill
for grounding installation ( GE Hold on 21‐Feb‐21) issue

WBS: WAS_ Internal_UP‐4.4.1.5 Asphalt This refers to road works along west side of GE reply 30 Jan : Gate Area & East side of WHBO on‐
Constraint ASC ASC to complete the works on Warehouse Gate area
Road from Unloading gate to WHBO WHBO from Warehouse Gate to North of WHBO hold due to underground services to be introduced.

WBS: WAS_ Internal_UP‐4.4.1.8.6 Gas Level/scope of slope protection as shown on


Not a
buffer and Helipad South side Slop Urbanization drawing cannot be done as is. ALS Construction to clarify with Engineering ALS 09‐Feb : DMS issued 06‐Feb
constraint
protection and gravel Engineering Support required

Level/scope of slope protection as shown on


WBS: WAS_ Internal_UP‐4.4.1.8.5 between
Urbanization drawing cannot be done as is. Constraint ALS /GE Construction to clarify with Engineering ALS 20‐Feb : Released area done
drainage swale west side of Solar field
Engineering Support required

WBS: WAS_ Internal_UP‐4.6.19.5 1m wide gravel strip along patrol road work cannot Not a GE‐Elec. Grounding installation to complete and area GE reply 30 Jan : Area are open, if there is any holding
GE‐E / ASL
PB‐Parking‐03 East side of NGC proceed due to grounding installation constraint to be backfilled pl. specify the location.

WBS: WAS_ Internal_UP‐4.6.19.8 1m wide gravel strip along patrol road work cannot Not a GE‐Elec. Grounding installation to complete and area GE reply : There is no hold from GE, if there is any
GE‐E / ASL
PB‐Parking‐02‐East proceed due to grounding installation constraint to be backfilled hold then ALS need to send via mark up drawing.

WBS: WAS_ Internal_UP‐4.6.19.9 Access concern ‐ access can be diverted. Coordinate ALS 20‐Feb : Released area done, remaining engaged
Gravel installation works Constraint ALS /GE
PB‐parking‐01 the diverted access when applying for the permit. with other

The existing perforated drain pipe where the


ALS 20‐Feb : from GE 12‐Feb : provide geotextile on
Not a walkway has to be constructed need to be relocated
South Admin Annex South Admin Annex ‐ walkway construction ASC the gravel fill over the perforated drain below and
constraint as per DMS 4011‐DRA‐ABE‐065‐ 350‐0001 Rev.11,
backfill the area to the required level for the walkway
DMS013

It was clarified to ALS that where there is slope


WBS: WAS_ Internal_UP‐4.6.19.3 Along Not a GE reply 30 Jan : GE don’t see any problem here.
Gravel laying along patrol road east of Helipad ALS protection, no gravel along the road side to be done.
patrol road to helipad constraint Please clarify the issues.
Rest of the roadside to have 1m wide strip of gravel.

ALS 20‐Feb : 1st layer of aggregate base course was


completed and tested while in the same area, the
WBS: WAS_ Internal_UP‐4.6.4.2 Patrol
Patrol road axis 3.2 between Mosque & Admin Bldg. Constraint GE Missing elevation. activity of other contractors was noticed. Any
Road axis‐3.2 on hold
damages or rework due to rain or else to be repaired
prior to handover to us for further progress

ASC scaffolds for GRC installation obstructing the


WBS: WAS_ Internal_UP‐4.17.7 Mosque walkway area. ASC to complete the GRC installation
Walkway around the Mosque Constraint ASC ALS 09‐Feb : Not released yet
area and scaffold to be removed to allow construction of
walkway

WBS: WAS_ Internal_UP‐4.17.1 Process Area has been released to ALS to do the south side on
Asphalt road at Process area Constraint GE ALS 09‐Feb : Not released yet
area gate house 09 Nov. Once this is done, north side will be released
Activity ID Affected ALS work Status Action by Action Required Latest reply

ASC working on this area to complete the duct bank


WBS: WAS_ Internal_UP‐4.17.10 Gasoline
Concrete works at Gasoline Station Constraint GE / ASL installation. Once this work is done, ASC to backfill ALS 20‐Feb : partially released on 25‐Jan
Station
the area up to ‐0.50m from TOC.

WBS: WAS_ Internal_UP‐4.17.12 South side Access concern. This is currently the main access to
Not a ALS : Access released on 25‐Jan . The activity is
of Solar & east side of ASL Tank road Roadworks at south‐east of Solar Field ALS site. However, planning for road/access diversion to
constraint already started.
connection be proposed to get a permit.

Preliminary Inspection Checkpoint (PIC)east Not a excavation for our finished BoE. Done by other to GE reply 30 Jan : Grounding installation nearing
Asphalt road at PIC area & Walkway ALS
side constraint install grounding completion. Area will be released to ALS on 31 Jan

WBS: WAS_ Internal_UP‐4.4.1.11.1


detail section of between ditch & channel detail,
Existing Swale and executing connection Between ditch & channel detail Connection in Yard Constraint GE ALS 20‐Feb : Not yet provided
moreover solution for the Hindrance.
with Concrete Drainage channels

Road Marking After the Finalize manhole level &


WBS: WAS_ Internal_UP‐4.4.1.4 Marking Constraint ALS After the Finalize manhole level & final Inspection ALS 20‐Feb : already explained
final Inspection

WBS: WAS_ Internal_UP‐4.4.1.11.11.1.2.4 Asphalt road And Walkway Warehouse area North
Constraint GE/Eng. Trench level not matching asphalt IFC Drawing. ALS 09‐Feb : New drawings not yet provided
Warehouse area North side side

Not a ALS 09‐Feb : Approved by SEC on 09‐Feb, now in


Sun shelter Gate Sun shelter Gate ALS Shop Drawing Submitted on 03‐11‐2021 for approval
constraint production

installation of signage post are located on the


GE walkway in some areas to avoid blockage in the ALS 09‐Feb : New coordination submitted on 08‐Jan
signage Installation of signage Constraint
Site/Eng. walkway the same will be shifted to edge the not yet approved
walkway

Security DG area(Cat04) 1. As per drawing fence is Type‐B(Galvanized) but


material submittal is PVC coated.
Installation of the Chain link Fence CAT‐IV fence Not a 2. AS per drawing, gate should be industrial type
ALS ALS 20‐Feb : Gates received on 12‐feb
with Doors constraint to be controlled from Control Room. Please provide
SAS confirmation that proposed gate is acceptable.
Cat‐04 DG of Solar(Cat04)

Fire water pump station building Walkway west side Constraint GE portion on the walkway on hold need level clearance. ‐‐‐