Constraints 2022-02-20
Constraints 2022-02-20
Constraints 2022-02-20
Artificial grass installation cannot proceed as the GE reply 30 Jan : Earthing material is already arrived.
WBS: WAS_ Internal_UP‐4.4.1.12 Artificial GE to provide earthing material ‐waiting for delivery
area was excavated (and still not backfilled) by ASC Constraint GE ‐E On‐hold by Elec. Team due to earthing resistance
Grass fixing on hold by GE ASC to install earthing and backfill
for grounding installation ( GE Hold on 21‐Feb‐21) issue
WBS: WAS_ Internal_UP‐4.4.1.5 Asphalt This refers to road works along west side of GE reply 30 Jan : Gate Area & East side of WHBO on‐
Constraint ASC ASC to complete the works on Warehouse Gate area
Road from Unloading gate to WHBO WHBO from Warehouse Gate to North of WHBO hold due to underground services to be introduced.
WBS: WAS_ Internal_UP‐4.6.19.5 1m wide gravel strip along patrol road work cannot Not a GE‐Elec. Grounding installation to complete and area GE reply 30 Jan : Area are open, if there is any holding
GE‐E / ASL
PB‐Parking‐03 East side of NGC proceed due to grounding installation constraint to be backfilled pl. specify the location.
WBS: WAS_ Internal_UP‐4.6.19.8 1m wide gravel strip along patrol road work cannot Not a GE‐Elec. Grounding installation to complete and area GE reply : There is no hold from GE, if there is any
GE‐E / ASL
PB‐Parking‐02‐East proceed due to grounding installation constraint to be backfilled hold then ALS need to send via mark up drawing.
WBS: WAS_ Internal_UP‐4.6.19.9 Access concern ‐ access can be diverted. Coordinate ALS 20‐Feb : Released area done, remaining engaged
Gravel installation works Constraint ALS /GE
PB‐parking‐01 the diverted access when applying for the permit. with other
WBS: WAS_ Internal_UP‐4.17.1 Process Area has been released to ALS to do the south side on
Asphalt road at Process area Constraint GE ALS 09‐Feb : Not released yet
area gate house 09 Nov. Once this is done, north side will be released
Activity ID Affected ALS work Status Action by Action Required Latest reply
WBS: WAS_ Internal_UP‐4.17.12 South side Access concern. This is currently the main access to
Not a ALS : Access released on 25‐Jan . The activity is
of Solar & east side of ASL Tank road Roadworks at south‐east of Solar Field ALS site. However, planning for road/access diversion to
constraint already started.
connection be proposed to get a permit.
Preliminary Inspection Checkpoint (PIC)east Not a excavation for our finished BoE. Done by other to GE reply 30 Jan : Grounding installation nearing
Asphalt road at PIC area & Walkway ALS
side constraint install grounding completion. Area will be released to ALS on 31 Jan
WBS: WAS_ Internal_UP‐4.4.1.11.11.1.2.4 Asphalt road And Walkway Warehouse area North
Constraint GE/Eng. Trench level not matching asphalt IFC Drawing. ALS 09‐Feb : New drawings not yet provided
Warehouse area North side side
Fire water pump station building Walkway west side Constraint GE portion on the walkway on hold need level clearance. ‐‐‐