FDN Lesson 1 5 Merged
FDN Lesson 1 5 Merged
ENGINEERING
Introduction/ Definition
Lesson 1
• Foundation – is the part of an engineered system
which transmits to, and into, the underlying soil or
rock the loads supported by the foundation and its
self-weight.
• All engineered construction resting on the earth must be carried
by a foundation.
• Superstructure – is commonly used to describe the
engineered part of the system bringing load to the
foundation, or substructure.
• The term superstructure has particular significance for buildings
and bridges; however, foundations also may carry only machinery,
support industrial equipment (pipes, towers, tanks) ast as sign in bases,
and similar.
• It is better to describe foundation as that part of the engineered
system interfacing the load carrying components to the ground.
• It is evident on the basis of this definition of a foundation that it is
the most important part of the engineering sytem.
• Foundation Engineer – is the person who by
reason of training and experience is sufficiently
versed in scientific pricinples and engineering
judgment to design a foundation.
• The necessary scientific principles are acquired through
formal educational courses in geotechnical (soil mechanics,
geology, foundation engineering.) and structural (analysis, design in
reinforced concrete and steel, etc.)
• Steps in designing a foundation:
• 1. Locate the site and the position of the load.
• 2. Physically inspect the site for any geological, or other,
evidence of possible problems. Supplement this with any previously
obtained soil data.
• 3. Establish the field exploration program and on the basis
of discovery set up the necessary supplemental field testing
and the laboratory test program.
• 4. Determine the necessary soil design parameters based
on integration of test data, scientific principles, and
engineering judgment. Simple or complex computer analyses may be
involved. For complex problems, compare the recommended data with
published literatue or engage another geotechnical consultant to give an outside
perspective to the results.
• 5. Design the foundation using the soil parameters from step
4. The foundation should be economical and be able to to
be built by the vailable construction personnel. Take into account
practical construction tolerances and local construction practices. Interact
closely with all concerned (client, engineers, architect, contractor) so that the
substructure is not excessively overdesigned and risk is kept within acceptable
levels.
Classification of Foundation
1. Shallow Foundation – termed bases,
footings, spread footings, or mats. Where
depth is generally D/B < 1
Spread Footing- supports a single column.
Mat – is used to support several rows of
parallel columns and may underlie a portion, or the
entire building plan.
Bases – foundation supporting machineries.
2. Deep Foundations – piles, drilled piers,
or drilled caissons. D/B > 4.
• Pile – deep foundations are anlogous to
spread footings but distribute the load
vertically rather than horizontally. A
qualitative load distribution over depth for a
pile.
• Drilled Pier and Drilled Caisson – are for
the pile type member which is constructed
by drilling a hole 0.76m in diameter, adding
reinforcing, and backfilling the cavity with
concrete.
3. Retaining Structure – any structure used
to retain soil or other material; in a
geometric shape other than that naturally
occurring under the influences of gravity.
It may be constructed of a large number of
materials including wood and metal sheeting, plain or
reinforced concrete, reinforce earth, precast concrete
elements, closely spaced piling, inlocking wood or metal
elements (crib walls), and similar.
Sometimes it is permanent and in other cases it is
removed when no longer needed.
General Requirements in
Foundation Design:
• 1. Determining the building purpose, probable
service-life loading, type of framing, soil proflie,
construction methods and construction cost.
• 2. Determine the client/ owner’s needs.
• 3. Make the design but ensuring that it does not
excessively degrade the environment nand with
a margin of safety which produces a tolerable
risk level to all parties: the public; the owner; and
the designer
Foundations: Additional Considerations
The previous section outlined in general terms
requirements to be met in designing a foundation in
terms of settlement and soil strength. We will now
outline number of additional considerations which
may have to be taken into account at specific sites.
1. Depth must be adequate to avoid lateral squeezing of
material from beneath the foundation for footings and mats.
Similarly excavation for the foundation must take into
account that this can happen to existing footings on
adjacent sites and protection may be required for adjacent
buildings.
2. Depth of foundation must be below the zone of seasonal
volume changes caused by freezing, thawing, and plant
growth. Most local building codes will contain minimum
depth requirements.
3. The foundation scheme may have to consider expansive
soil conditions. Here the building tends to capture soil
moisture in the interior zone and allow normal evaporation
around the perimeter. The soil in a distressingly large
number of geographic areas tends to swell in the presence
of substantial moisture and carry the foundation up with it.
4. In addition to compressive strength considerations, the
foundation system must be safe against overturning,
sliding, and any uplift (flotation}.
5. System must be safe against corrosion or deterioration
due to harmful materials present in the soil. This is a
particular concern in reclaming I reclaimingsanitary
landfills bdt has application where chemical agents
present can corrode metal piling,cause adverse reactions
with Portland cement in concrete footings or piles, etc.
6. Foundation system should be adequate to sustain some
later changes in site or construction geometry and be
easily modified should changes in the superstructure and
loadingbecome necessary.
7. The foundation should be buildable with
available construction personnel.
8. The foundation and site development must
meet local environmental standards.
• Exploratory holes into the soil may be made by hand tools, but
more commonly mounted power tools are used.
Hand Tools
The earliest method of obtaining a test hole was to excavate test
pit using a pick and shovel. Because of economics, the current
procedure is to use power-excavation equipment such as a
backhoe to excavate the pit and then to use hand tools to
remove a block sample or shape the site for in situ testing. This
is the best method at present for obtaining quality undisturbed
samples or samples for testing at other than vertical orientation.
Mounted Power Drills
• For numerous borings to greater depths and
to collect samples that are undisturbed, the
only practical method is to use power-driven
equipment.
1. Wash boring – a term used to describe one
of the more common methods of advancing
a hole into the ground. A hole is started by
driving a casing to a depth of 2 to 3.5m.
Casing is simply a pipe which supports the
hole, preventing it from caving in.
2. Rotary Drilling – is another method of
advancing test holes. This method uses
rotation of the drill bit, with the simultaneous
application of pressure to advance the hole.
Rotary drilling is the most rapid method of
advancing holes in rock unless it is badly
fissured; however, it can also be used for
any other type of soil.
3. Continuous-flight augers – with a rotary drill
are probably the most popular method of soil
exploration at present in North America and
Europe. The flights act as a screw conveyor
• Execution of soil borings
• General safety instructions
• Before performing any drilling it is important to make sure
that:
or qa = qult(RQD)2
SF
Bearing Capacity Equation by Terzaghi
qult = cNcsc + qNq + 0.5gBNgsg
where:
Nc = (Nq-1)cotf
Nq = ____a2______
2 cos2 (45 + f/2)
a = e(0.75p – f/2) tanf
Ng = tanf (Kpg/ cos2f – 1)
2
For: strip round square
sc = 1.0 1.3 1.3
sg = 1.0 0.6 0.8
• Example Prob 3-1:
Compute the allowable bearing pressure
using the Terzaghi Equation for the footing
and soil parameters given below. Use safety
factor of 3 to obtain qa.
g = 110 pcf
f = 250
c = 300psf
D = 4 ft (depth of footing from ground
surface)
B x L = 2 ft X 2 ft (footing size)
Req’d: qa
Sol’n:
qult = cNcsc + qNq + 0.5gBNgsg
From Terzaghi Table:
for f = 250
Nc = 25.1 Nq = 12.7 Ng = 9.7
for square footing:
sc = 1.3 sg = 0.8
therefore:
qult = (300)(25.1)(1.3) + 110(4)(12.7) + .5(110)(2)(9.7)(0.8)
qult = 16230.6 psf or 16.23 ksf
qa = qult/SF
qa = 16.23/3
qa = 5.41ksf
a = e(0.75p – f/2) tanf
a = e(0.75p – ((25)/2)*p/180) tan(25)
a = 2.7101
Nq = ____a2______
2 cos2 (45 + f/2)
Nq = ____(2.7101)2______
2 cos2 (45 + (25)/2)
Nq = 12.72
Nc = (Nq-1)cotf
Nc = (12.72-1)cot(25)
Nc = 25.13
Ng = tanf (Kpg/ cos2f – 1)
2
Ng = tan(25) ((35)/ cos2(25) – 1)
2
Ng = 9.70
• Effect of water table on Bearing Capacity
The effective unit weight of the soil is
used in the bearing capacity equations for
computing the ultimate capacity.
ge=(2H –dw)dw gwet + g’(H – dw)2
H2 H2
Where:
H = 0.5B tann(45 + f/2)
dw = depth to water table below base of
footing
gwet = wet unit weight of soil in depth dw
g’ = submerged unit weight below water
table = gsat - gw
• Example Prob 3-2:
A square footing vertically and concentrically loaded is
to be placed on a cohensionless soil as shown. The
soil and other data are as shown:
qa = qult(RQD)2
SF
Example Prob. 3-3: We have a drilled pier
with a diameter = 3 ft to be founded at a
depth of 10 ft in a rock mass to get through
the surface irregularities and the weathered
zone as determined by coring to a depth of
25ft. From the cores the average RQD =
0.50 (or 50 percent) below the pier point.
Assume: f = 450, and c = 0.5 ksi, SF = 3.
Estimate the allowable bearing capacity for
the pier base.
• Req’d: qa
• Solution:
Nc = 5tan4 (45 + f/2)
Nc = 5tan4 (45 + 45/2)
Nc = 170
Nq = tan6 (45 + f/2)
Nq = tan6 (45 + 45/2)
Nq = 198
Ng = N q + 1
Ng = 199
For: round base/ footing
sc = 1.3
sg = 0.6
Since:
qult = cNcsc + qNq + 0.5gBNgsg
qult = 0.5(144)(170)(1.3) + (0.160)(10)198 +
0.5(0.160)(3)(199)(0.6)
qult = 16257 ksf
Therefore:
qa = qult(RQD)2
SF
qa = 16257(0.5) 2
3
qa = 1355 ksf
Assign:
Prob 1: What is the allowable bearing capacity
using Terzaghi methods for the assigned
problem in the following data set. Other data:
Use B = 5ft or 1.52m, D = 0.75B. The
average unit weight in the zone of interest is
110 pcf or 17.3 KN/m3 and water table is not
a problem.
a.) f = 200, c = 0.30 ksf (15kPa)
b.) f = 300, c = 0.10 ksf ( 5kPa)
c.) f = 380, c = 0.0
Prob 2:
A square footing vertically and concentrically loaded is
to be placed on a cohensionless soil as shown. The
soil and other data are as shown:
LESSON 4
THE SETTLEMENT PROBLEM
Foundation settlements must be
estimated with great care for buildings,
bridges, towers, power plants, and similar
high cost structures. The settlement for
structures such as fills, earth dams, levees,
braced sheeting, and retaining walls can
usually be estimated with a great margin of
error.
Soil settlement computations are, except for
occasional happy coincidences, only best estimates
of the deformation to expect when the future load is
applied. During settlement we have the soil
transitioning from the current body (or self-weight)
stress state to a new one under the additional
applied load. The stress change Dq from this added
load produces a time dependent accumulation of
particle rolling, sliding, crushing, and elastic
distortions in a limited influence zone beneath the
loaded area. The statistical accumulation of
movements in the direction of interest is the
settlement. In the vertical direction the settlement
will be defined as DH.
The principal components of DH are the
particle rolling and sliding which produces a change
in the void ratio, and crushing which alters the
material. Only a very small fraction of DH is from
elastic deformation of the soil grains. As a
consequence, if the applied stress were to be
removed, very little of the settlement DH would be
recovered. Even though DH has only a very small
elastic component it is convenient to treat the soil as
a pseudoelastic material with “elastic” parameters of
Es, G’, m and ks to estimate settlements. This would
appear reasonable since a stress change causes the
settlement and it is observed that larger changes
produce larger settlements.
Es = stress-strain modulus or modulus of
deformation of soil
G’ = shear stress-strain modulus of soil or
other material
m = Poisson’s ratio
= strain perpendicular to applied stress
strain in direction of applied stress
ks = modulus of subgrade reaction either
vertical or horizontal
There are two major problems with soil
settlement analyses:
1. Obtaining reliable values of the “elastic”
parameters. Problems of recovering
“undisturbed” soil samples means laboratory
values are often in error by 50 percent or
more. There is now a greater tendency to
using in situ tests, but a major drawback is
they tend to obtain horizontal values. Since
anisotropy is a common occurrence the
vertical value (usually needed) is often
substantially different. Because of these
problems, correlations are commonly used
particularly for preliminary design studies.
2.Obtaining a reliable stress profile from the
applied load. We have both the problem of
numerical values and the effective depth of
the influence zone. Theory of elasticity
equations are usually used for the stress
computations with the influence depth H
below the loaded area taken from about 2B
to H - infinity.
The values from these two problem areas are then
used in some form of
H
DH = e dh
0
where e = strain = Dq/Es but Dq = f(H, load) and H as
previously noted is the estimated influence depth.
It is not uncommon for the ratio of measured versus
computed DH to range 0.5- to 2+. Most values are
in the 0.8 to 1.2 range, however . We might note,
too, that a small computed DH of, say, 10mm
where the measured value is 5 or 20mm has a
large “error” but most practical structures can
tolerate, either the predicted or measured value.
What we do not want is to estimate 25mm and
have the structure settle 100mm. If we err in
settlement computations it is preferable to have
computed values larger than the actual (or
measured) ones – but we must be careful that the
“large“ value is not so conservative that expensive
(but unneeded) remedial action is required.
Settlements are usually classified as:
1. Immediate, or those which take place as
the load is applied or within a time period of
about 7 days.
2. Consolidation, or those which are time-
dependent and taking months to years to
develop. The “Leaning Tower of Pisa” in
Italy has been settling unevenly (causing
the “lean”) for over 700 years . This,
however, is an extreme case with the
principal settlements for most projects
occuring in 1 to 5 years.
Immediate settlement analyses are used
for all fine-grained soils including silts and
clays with a degree of saturation S < 90
percent (approximately) and for all coarse
grained soils with a large coefficient of
permeability.
Consolidation settlement analyses are
used for all saturated, or nearly saturated,
fine-grained soils where the consolidation
theory applies. This is because for these
soils we want estimates of both settlement
DH and how long it will take for the
settlement to occur.
Both types of settlement analyses are in the
form of
DH = eH = Dq H
Es
Stress in Soil Mass due to Footing Pressure
Dq = qv = ___Q____
(B + z)(L+z) or
Dq = qv = _Q___
(B + z)2
This method compares well with theoretical methods from z = B
to about 4B, but should not be used for qv in the depth z = 0
The BOUSSINESQ Method for Dq
Dq = qv = _3Q_ ___1____
2pz2 (1+ (r/z)2)5/2
Dq = qv = Q Ab
z2
Since the Ab term is a function of only the ratio
of r/z, it may be tabulated in several values as
follows:
• Example Prob 4-1:
What is the vertical stress beneath a point load
Q = 50kips at depths z = 0, 2ft, 4 ft and 10ft?
Example Prob 4-2:
What is the vertical stress qv at point A of
figure shown below for the two surface loads
Q1 and Q2?
IMMEDIATE SETTLEMENT COMPUTATIONS
The settlement of the corner of a rectangular base of
dimension B’ x L’ on the surface of a elastic half-space can
be computed from an equation from Theory of Elasticity as
follows:
DH = qoB’ [1-m2] 4IsIf
Es
where:
qo = intensity of contact pressure in units of Es
B’ = least lateral dimension of contributing base area in units
of DH
Ii = influence factors which depend on L’/B’, thickness of
stratum H, Poisson’s ratio m, and embedment depth D.
Es, m = elastic soil parameters
Is = I1 + [1 – 2m] I2
1-m
The DH equation is strictly applicable to flexible bases on the
half-space. In practice, most foundations are flexible – even
very thick ones deflect when loaded by the superstructure
loads. Some theory indicates that if the base is rigid the
settlement will be uniform (but may tilt) and the settlement
will be about seven percent less. On this basis if your base
is “rigid” you should reduce the Is factor by about seven
percent (that is, Isr = 0.931 Is).
For best result, equation should be used as follows:
1. Make your best estimate of qo.
2. For round bases, convert to an equivalent square.
3. Determine the point where the settlement is to be computed
and divide the base so the point is at the corner or common
corner of the contributing rectangles.
4. Note that the stratum depth actually causing settlement is not at
H/B to infinity but is either:
a. Depth z = 5B (B= least total lateral dimension of base), or
b. Depth to where a hard stratum is encountered. Take “hard”
as that where Es in the hard layer is about 10Es of adjacent
layer.
5. Compute your H/B’ ratio. For a depth H = z = 5B and for the
center of the base we have H/B’ = 5B/0.5B = 10. For a corner
5B/B =5
6. Enter Table below and obtain I1 and I2 and with your best
estimate for m compute Is.
7. From the Figure estimate If.
8. Obtain the weighted average Es in the depth z = H. The
weighted average can be computed as
Es(ave) = H1Es1 + H2Es2 + …. HnEsn
H
Example Prob:
Estimate the settlement of the raft (or mat) foundation given the
data as follows:
qo = 134KPa; B x L = 33.5 x 39.5m;
Soil is layered clays with 1 sand seam from ground surface
to sandstone bedrock at -14; mat at -3m
Es from 3 to 6m = 42.5MPa; Es from 6 to 14m = 60MPa; Es
for sandstone >= 500MPa
Solution:
For clay estimate m = 0.35
Compute Es(ave) = 3x42.5 + 8x60 = 55MPa
11
H = 14 – 3 = 11m (from base to sandstone)
B’ = 33.5/2 = 16.375m (for center of mat)
H = 11__ = 0.66 (0.70) L = 39.5 = 1.18 (1.20)
B’ 16.75 B 33.5
Interpolating from the table:
I1 = 0.0815, I2 = 0.086
Is = I1 + [1 – 2m] I2
1-m
Is = 0.0815 + [1 – 2(0.35)] (0.0865) = 0.121
1-0.35
D/B = 3/33.5 = 0.09, from the figure If = 0.82
Therefore:
DH = qoB’ [1-m2] IsIf = 134(16.75) [1-(0.35)2] 4(0.121)(0.82)(1000)
Es 55(1000)
DH = 14.21mm
Module 5
IMPROVING SITE SOIL FOR
FOUNDATION USE
LEARNING OBJECTIVES
At the end of the lesson, the students will be able to:
• Know the different soil improvement techniques.
OVERVIEW
The centuries-old problem of land scarcity in the vicinity of existing urban areas
often necessitates the use of sites with soils of marginal quality. In many cases
these sites can be utilized for the proposed project by using some kind of soil
improvement. This module will focus on several of the more widely used methods
of improving soils for bearing capacity
Of principal interest in this moduler is the identification of means to obtain
a significant increase in the bearing capacity of a soil. This can be achieved by
altering the soil properties of ∅, cohesion c, or density 𝜌. Usually an increase in
density (or unit weight 𝛾) is accompanied by an increase in either ∅ or c or both
(assuming the soil is cohesive). Particle packing (compaction) always increases
the density, with a resulting decrease in void ratio, and reduces long-term
settlements. Particle packing usually increases the stress-strain modulus so that
any "immediate" settlements are also reduced
COURSE MATERIALS
1.0 INTRODUCTION
When the site soil is marginal (e.g., not enough bearing capacity, excessive
settlement, or high permeability), soil improvement may be more economic than
other means.
Soil improvement refers to a technique to improve the engineering properties
of soil. It involves changing soil characteristics by physical action such as
compaction, vibration (to reduce void ratio) or by inclusion or mixing of
stronger material (injecting admixture) in the soil.
The scope of application of the various techniques depends mainly on the type
and grading of the soils that requires improving. (see Figure 1).
Figure 1. Soil Improvement Techniques for Various Types and Grading of
Soil
Source: www.bachy-soletanche.com/SBF/sitev4_uk.nsf/technique/soil-
improvement13
A. Densification
a. Consolidation (Preloading and Vertical Drains)
b. Compaction
c. Deep Dynamic Compaction
d. Vibrocompaction (Vibroflotation)
e. Vibro-Replacement Method
f. Stone Columns
g. Compaction Grouting
h. Blasting
B. Adhesion
a. Chemical stabilization
b. Slurry grouting, jet grouting
c. Thermal stabilization
C. Reinforcement
a. Soil and rock anchors
b. Mini-piles
c. Soil nailing
d. Soil mixing
D. Physico-chemical alteration
a. Electro-osmosis
b. Lime columns
c. Vitrification
d. Soil mixing
E. Biological transformation
3. CONSOLIDATION: PRELOADING
1) Preloading Methods
a. Simply place a surcharge fill on top of the soil that requires
consolidation.
b. Once sufficient consolidation has taken place, the fill can be
removed and construction takes place.
c. Surcharge fills are typically 10-25 feet thick and generally produces
settlement of 1 to 3 feet.
3) Advantages of Preloading
a. Requires only conventional earthmoving equipment
b. Any grading contractor can perform the work
c. Long track record of success
4) Disadvantages of Preloading
a. Surcharge fill must extend horizontally at least 10 m beyond the
perimeter of the planned construction, which may not be possible at
confined sites
b. Transport of large quantities of soil required
c. Surcharge must remain in place for months or years, thus delaying
construction
Vertical drains are installed under a surcharge load to accelerate the drainage of
impervious soils and thus speed up consolidation. These drains provide a shorter
path for the water to flow through to get away from the soil. Time to drain clay
layers can be reduced from years to a couple of months.
A. Sand Drain
In general, typical sand drains have a diameter from 20 to 45 cm and
spacing from 1.5 to 6 m. Sand drains can be installation with several
procedures: mandrel-driven pipes, driven pipes, rotary drill, or continuous-
flight hollow auger. The design is based on the time of preloading. Figure
2 shows a typical sand drain.
Figure 2. Sand Drain Installation
As shown in Figure 3, (a) Pore water pressure flows laterally to the wick
drain s and is carried vertically up to the ground surface. (b) Without
inserting PVD, dissipation of excess pore pressure is a slow process. (c)
With PVD, the excess pore pressure dissipates quickly through shorter
drainage paths.
(a)
(b) (c)
• Wick drains have almost totally replaced conventional sand drains for a
majority of application.
5.0 COMPACTION
Soil is excavated to a desired depth. Then it is filled with controlled lift thickness,
water content, and compaction effort. The backfill material can be modified by
mixed with an admixture (e.g. sand or gravel, cement, lime, or fly ash) or be
come from nearby borrow pit.
This is applied essentially to granular and non-coherent soils, such as sands and
gravels. The vibrations induce a temporary liquefaction of the soil around the
vibrator. In this case, the intergranular forces are temporarily nullified, and the
grains are rearranged in a more compact pattern offering better characteristics.
The induced vibration will reduce the void ratio and strengthen the soil.
This improvement method has been found useful to treat liquefiable soils.
This technique is often used on large works for the densification of hydraulic fills
for reclamation.
Site suitability
The vibro-compaction system is one of the most economical and
effective methods of densifying deep deposits of granular soils when the
soils having a maximum of about 20% fines (preferable for 10% fines), of
which not more than 3 % are active clay. The increase of fineness and
plasticity of the soil decreases the feasibility of using the vibro-compaction
method. Table 1 shows the summary of relative effectiveness of the
methodology in various soil types.
Method of Installation
1) First, the vibroflot penetrates the ground to the desired depth.
2) Granular material (sands or gravels) is then progressively introduced to
the hole, and the vibroflot is alternately raised and lowered to produce a
packed sand (stone) column.
3) This method works well when the soil contains a large amount of fine
contents.
4) The excellent candidates are fine sands and silty sands.
5) Only marginal success is reported for silts and clays.
6) This method can be used to form stone columns.
Grouting Methods
a. Intrusion grouting
- Consists of filling joints or fractures with grout
- Primary benefit is reduction in hydraulic conductivity
- Used to prepare foundation and abutments for dams
- Usually done using cementitious grouts
b. Permeation grouting
- Injection of thin grouts into the soil
- Once the soil cures, becomes a solid mass
- Done using chemical grouts
- Used for creating groundwater barriers or preparing ground before
tunneling
Figure 8. Grouting
c. Compaction grouting
- Used to repair structures that have excessive settlement and to
compact loose soil or to produce control displacement to lift
structure.
- When low-slump compaction grout is injected into granular soils,
grout bulbs are formed that displace and densify the surrounding
loose soils.
- Involves injection of low-slump (less than 2 inches) grout (soil-
cement mixture) which does not enter soil pores but remain in a
homogeneous mass.
- Grout material may consist of fine sand mixed with 12% cement
and water to produce stiff, mortar-like mixture.
- Grout pipe is installed to maximum treatment depth and grout is
injected at high pump pressure as the pipe is withdrawn
incrementally, forming a column of interconnected grout bulb
- Can be performed “stage down” or, more commonly, in a “stage up”
process, as follows:
▪ Advancing the grout pipe to the bottom of treatment depth
▪ Injecting the grout until refusal criteria is achieved, based on
injected grout volume, injection pressure, or ground heave
▪ Extracting the grout pipe to the next depth interval and
injecting the grout
▪ Repeat the process until reaching the upper limit of
treatment zone
d. Jet grouting
- It is developed in Japan.
- Uses a special pipe with horizontal jets that inject grout into the
ground at high pressures
- Jet grouting is an erosion/replacement system that creates an
engineered, in situsoil/cement product known as Soilcretesm.
- Effective across the widest range of soil types, and capable of
being performed around subsurface obstructions and in confined
spaces, jet grouting is a versatile and valuable tool for soft soil
stabilization, underpinning, excavation support and groundwater
control.
The most common admixture is Portland Cement. When mixed with soil, forms
soil-cement which is comparable to a weak concrete. Other admixtures include
lime and asphalt. The objective of this method is to provide artificial cementation,
thus increasing strength and reducing both compressibility and hydraulic
conductivity. This method is also used to reduce expansion potential of clays and
in surface mixing applications.
1) Reinforcement
3) Inclusion
4) Soil Mixing