Ee Estimate Final
Ee Estimate Final
Ee Estimate Final
II SURVEY WORKS
1 Staking and Layout 1.00 lot
2 Bench markimng and Reference Elevation 1.00 lot
SUBTOTAL II : SURVEY WORKS
IV STRUCTURAL WORKS
1 Earthworks
1.1 Excavation 3,192.00 cu.m.
1.2 Backfilling cu.m.
1.3 Disposal of unsuitable materials 2,553.00 cu.m.
1.4 Compaction cu.m.
1.5 Gravel Base 89.00 cu.m.
1.6 Boulders for Footing 135.00 cu.m.
1.7 Soil Poisoning 890.00 m²
1.8 Shoring 600.00 m²
2 Concreting Works ,3000 psi
2.1 Foundation 298.00 cu.m. 2,950.00
2.2 Retaining Wall 106.00 cu.m. 2,950.00
2.3 Footing 52.00 cu.m. 2,950.00
2.4 Footing Tie Beam 38.00 cu.m. 2,950.00
2.5 Columns 150.00 cu.m. 2,950.00
2.6 Slab on grade cu.m. 2,950.00
2.7 Second Floor Beams 71.00 cu.m. 2,950.00
2.8 Second Floor Slabs 70.40 cu.m. 2,950.00
2.9 Third Floor Beams 71.00 cu.m. 2,950.00
2.10. Third Floor Slabs 70.40 cu.m. 2,950.00
2.11 Fourth Floor Beams 70.20 cu.m. 2,950.00
2.12 Fourth Floor Slabs 70.40 cu.m. 2,950.00
2.13 Roof Beams 38.00 cu.m. 2,950.00
2.14 Roof Deck Slab 18.00 cu.m. 2,950.00
2.15 Stairs cu.m. 2,950.00
2.16 Elevator Pit and Frames cu.m. 2,950.00
2.17 Wall Footings cu.m. 2,950.00
2.18 Canopy Beams cu.m. 2,950.00
2.19 Concrete Ledges cu.m. 2,950.00
2.20. Cistern and Fire Tank cu.m. 2,950.00
2.21 Septic Tank cu.m. 2,950.00
2.22 Concrte Parapet cu.m. 2,950.00
2.23 Basement Slab 134.00 cu.m. 2,950.00
2.24 Ground Floor Beams 72.00 cu.m. 2,950.00
2.25 Ground Floor Slab 79.00 cu.m. 2,950.00
3 Reinforcement
3.1 Foundation
• Deformed bars , Grade 60 34,987.00 kgs 41.00
• 25mm dia x 6 m deformed bars , Grade 60
• 25mm dia x 9 m deformed bars , Grade 60
• 20mm dia x 6 m deformed bars , Grade 60
• 20mm dia x 9 m deformed bars , Grade 60
• 16mm dia x 6 m deformed bars , Grade 60
• 16mm dia x 9 m deformed bars , Grade 60
• Tie Wire 708.00 kgs 60.00
3.2 Footing
• Deformed bars , Grade 60 6,472.00 kgs 41.00
• 16mm dia x 6 m deformed bars , Grade 60
• 16mm dia x 9 m deformed bars , Grade 60
• 20mm dia x 6 m deformed bars , Grade 60
• 20mm dia x 9 m deformed bars , Grade 60
• 10mm dia x 10.5 m deformed bars , Grade 60
• Tie Wire 131.00 kgs 60.00
3.3 Footing Tie Beams
• Deformed bars , Grade 60 5,996.30 kgs 41.00
• Deformed bars , Grade 33 1,284.40 kgs 39.50
• 10mm dia x 6 m deformed bars , Grade 33
• 20mm dia x 6 m deformed bars , Grade 60
• 20mm dia x 7.5 m deformed bars , Grade 60
• 20mm dia x 9 m deformed bars , Grade 60
• 20mm dia x 10.5 m deformed bars , Grade 60
• 20mm dia x 12 m deformed bars , Grade 60
• Tie Wire 145.00 kgs 60.00
3.4 Retaining Wall
• Deformed bars , Grade 60 9,500.00 kgs 41.00
• Deformed bars , Grade 33 3,731.00 kgs 39.50
• 16mm dia x 6 m deformed bars , Grade 60
• 16mm dia x 9 m deformed bars , Grade 60
• 12mm dia x 6 m deformed bars , Grade 33
• 12mm dia x 9 m deformed bars , Grade 33
• Tie Wire 267.00 kgs 60.00
3.5 Columns
• Deformed bars , Grade 60 29,989.50 kgs 41.00
• Deformed bars , Grade 33 14,282.00 kgs 39.50
• 10mm dia x 6 m deformed bars , Grade 33
• 25mm dia x 6 m deformed bars , Grade 60
• 25mm dia x 9 m deformed bars , Grade 60
• 25mm dia x 12 m deformed bars , Grade 60
• 20mm dia x 6 m deformed bars , Grade 60
• 20mm dia x 9 m deformed bars , Grade 60
• 20mm dia x 12 m deformed bars , Grade 60
• Tie Wire 894.00 kgs 60.00
3.6 Ground Floor Beams
• 25mm dia x 6 m deformed bars , Grade 60
• 25mm dia x 9 m deformed bars , Grade 60 kgs 35.50
• 20mm dia x 6 m deformed bars , Grade 60
• 20mm dia x 9 m deformed bars , Grade 60 kgs 35.50
• 10mm dia x 6 m deformed bars , Grade 33 kgs 32.50
• Tie Wire kgs 32.50
3.7 Ground Floor Slabs
• 12mm dia x 6 m deformed bars , Grade 33 kgs 32.50
• 12mm dia x 9 m deformed bars , Grade 33 kgs 32.50
• Tie Wire kgs 32.50
3.8 Second Floor and Third Floor Beams
• 25mm dia x 6 m deformed bars , Grade 60
• 25mm dia x 9 m deformed bars , Grade 60 kgs 35.50
• 25mm dia x 12 m deformed bars , Grade 60 kgs 35.50
• 20mm dia x 6 m deformed bars , Grade 60
• 20mm dia x 9 m deformed bars , Grade 60 kgs 35.50
• 20mm dia x 12 m deformed bars , Grade 60 kgs 35.50
• 10mm dia x 6 m deformed bars , Grade 33 kgs 32.50
• Tie Wire kgs 32.50
3.9 4th Floor Beams
• 20mm dia x 6 m deformed bars , Grade 60
• 20mm dia x 9 m deformed bars , Grade 60 kgs 35.50
• 20mm dia x 12 m deformed bars , Grade 60 kgs 35.50
• 25mm dia x 6 m deformed bars , Grade 60
• 25mm dia x 9 m deformed bars , Grade 60 kgs 35.50
• 25mm dia x 12 m deformed bars , Grade 60 kgs 35.50
• 10mm dia x 6 m deformed bars , Grade 33 kgs 32.50
• Tie Wire kgs 32.50
3.10. Roof Beams
• 20mm dia x 6 m deformed bars , Grade 60
• 20mm dia x 7.5 m deformed bars , Grade 60
• 20mm dia x 9 m deformed bars , Grade 60 kgs 35.50
• 20mm dia x 10.5 m deformed bars , Grade 60 kgs 35.50
• 20mm dia x 12 m deformed bars , Grade 60 kgs 35.50
• 10mm dia x 6 m deformed bars , Grade 33 kgs 32.50
• Tie Wire kgs 32.50
3.11 Ground Floor Slabs
• 12mm dia x 6 m deformed bars , Grade 33 kgs 32.50
• 12mm dia x 9 m deformed bars , Grade 33 kgs 32.50
• Tie Wire kgs 32.50
3.12 2nd and Third Floor Slab
• 12mm dia x 6 m deformed bars , Grade 33 kgs 32.50
• 12mm dia x 9 m deformed bars , Grade 33 kgs 32.50
• Tie Wire kgs 32.50
3.13 4th and Roof Deck Floor Slab
• 12mm dia x 6 m deformed bars , Grade 33 kgs 32.50
• 12mm dia x 9 m deformed bars , Grade 33 kgs 32.50
• Tie Wire kgs 32.50
3.14 Concrete Gutters
• 10mm dia x 6 m deformed bars , Grade 33 kgs 32.50
• 12mm dia x 9 m deformed bars , Grade 33 kgs 32.50
• Tie Wire kgs 32.50
3.15 Stairs
• 10mm dia x 6 m deformed bars , Grade 33 kgs 32.50
• 12mm dia x 9 m deformed bars , Grade 33 kgs 32.50
• Tie Wire kgs 32.50
3.16 Elevator Frame /Beams
• 2 1/2 x 2 1/2 x 1/4 Angle Bar kgs 32.50
• 10mm dia x 6 m deformed bars , Grade 33 kgs 32.50
• 12mm dia x 9 m deformed bars , Grade 33 kgs 32.50
• 16mm dia x 6 m deformed bars , Grade 60 kgs 32.50
• Tie Wire kgs 32.50
3.17 Elevator Pit
• 20mm dia x 6 m deformed bars , Grade 60 kgs 32.50
• Tie Wire kgs 32.50
3.18 Concrete Ledges
• 10mm dia x 6 m deformed bars , Grade 33 kgs 32.50
• Tie Wire kgs 32.50
3.19 Cistern and Fire Tank
• 16mm dia x 6 m deformed bars , Grade 60 kgs 32.50
• 12mm dia x 9 m deformed bars , Grade 33 kgs 32.50
• Tie Wire kgs 32.50
3.20. Septic tank
• 10mm dia x 6 m deformed bars , Grade 33 kgs 32.50
• 12mm dia x 9 m deformed bars , Grade 33 kgs 32.50
• Tie Wire kgs 32.50
3.21 Concrete Parapet
• 10mm dia x 6 m deformed bars , Grade 33 kgs 32.50
• 12mm dia x 9 m deformed bars , Grade 33 kgs 32.50
• Tie Wire kgs 32.50
3.22 Basement Slab
• 10mm dia x 6 m deformed bars , Grade 33 kgs 32.50
• Tie Wire kgs 32.50
3.23 Structural Steel Works
• 1.5 x 1.5 x 1/4 Angle Bar lgths 32.50
• 2 x 2 x 3/16 Angle Bar lgths 32.50
• 2 " x 6" x 1.2 Cee- Purlins lgths 32.50
• 12mm dia Sagrod lgths 32.50
• 12mm dia Cross Brace lgths 32.50
• 12 mm dia Turn Buckle pcs 32.50
• Welding Rods boxes 32.50
• Welding Outfit set 32.50
• Primer Paints gals 32.50
• Steel Ledges m² 32.50
4 Formworks and Scaffolds
4.1 Foundation 186.00 m² 400.00
4.2 Footing 69.00 m² 400.00
4.3 Footing Tie Beams 203.00 m² 400.00
4.4 Retaining Wall 1,055.00 m² 400.00
4.5 Columns 1,228.00 m² 400.00
4.6 Ground Floor Beams 533.00 m² 400.00
4.7 Second Floor Beams 537.00 m² 400.00
4.8 Third Floor Beams 537.00 m² 400.00
4.9 Fourth Floor Beams 542.00 m² 400.00
4.10. Roof Deck Beams 327.00 m² 400.00
4.11 Roof Beams - m² 400.00
Ground Floor Slabs 711.00 m² 400.00
4.12 Second Floor Slabs 640.00 m² 400.00
4.13 Third Floor Slabs 640.00 m² 400.00
4.14 Fourth Floor Slabs 640.00 m² 400.00
4.15 Roof dedck Slab 1,165.00 m² 400.00
4.16 Concrete Gutters - m² 400.00
4.17 Stairs - m² 400.00
4.18 Elevator Pit and Frames - m² 400.00
4.19 Wall Footings - m² 400.00
4.20. Canopy Beams - m² 400.00
4.21 Concrete Ledges - m² 400.00
4.22 Cistern and Fire Tank - m² 400.00
4.23 Septic tank - m² 400.00
4.24 Concrete Parapet - m² 400.00
SUBTOTAL IV : STRUCTURAL WORKS
V ARCHITECTURAL WORKS
1 Masonry Works
1.1 4" Thick CHB pcs
1.2 6" Thick CHB pcs
1.3 Cement bags
1.4 Sand cu.m.
1.5 10mm dia x 6m deformed bars . Grade 33 lgths
1.6 Plastering Works ( Interior)
• Cement bags
• Sand cu.m.
1.7 Plastering Works ( Exterior)
• Cement bags
• Sand cu.m.
2 Railings, Handrails and Steel Gratings
2.1 Railings at main Stairs pcs
• 2 x 2 Vertical Tubular Steel bags
• 1 x 3" Stainless Tubular Horizontal bar bags
• 4" x 1 1/2 " Steel Tubular handrail bar bags
• Miscellaneous bags
2.2 Railings at Ledges pcs
• 2 x 2 Vertical Tubular Steel bags
• 1 x 3" Stainless Tubular Horizontal bar bags
• 4" x 1 1/2 " Steel Tubular handrail bar bags
• Paintings of railings bags
• Miscellaneous bags
2.3 Steel Gratings pcs
• 2 x 2 Vertical Tubular Steel bags
• 1 x 3" Stainless Tubular Horizontal bar bags
3 Floor Finishes
3.1 basement and Ground Floor
• basement ramp 8 x 8" Non Skid Concrete Tiles m²
• Smooth Cement Finish Parking Area m²
• Painted Smooth Cement Finish @ Utilities and maintainance m²
• 16" x 16" Ceramic tiles - Concoarse/ Pathways m²
• 12" x 12" Ceramic tiles - Stairways m²
• 16" x 16" Ceramic tiles - Pawnshop[ office m²
• 16" x 16" Ceramic tiles - Lounge Area m²
• Rough Finish at Rentable/ Commercial space m²
• Painted Smooth Cement Finish @ Utilities and maintainance m²
• Painted Smooth Cement Finish @ Utilities and maintainance m²
• 12" x 12" Ceramic tiles - Toilet Floor m²
• 8" x 10" Ceramic tiles - Toilet Wall m²
• Topping m²
• Tile Adhesive bags
• Tile Grout bags
3.2 Second Floor
• 12" x 12" Ceramic tiles - Toilet Floor m²
• 8" x 10" Ceramic tiles - Toilet Wall m²
• 12" x 12" Ceramic tiles - Stairways m²
• 16" x 16" Ceramic tiles - Offices m²
• 16" x 16" Ceramic tiles - Workshop Area m²
• 16" x 16" Ceramic tiles - Lobby area m²
• Painted Smooth Cement Finish @ Utilities and maintainance m²
• Brass Stair Nosing m²
• Topping m²
• Tile Adhesive bags
• Tile Grout bags
3.3 Third and Fourt Floor
• 12" x 12" Ceramic tiles - Toilet Floor m²
• 8" x 10" Ceramic tiles - Toilet Wall m²
• 16" x 16" Ceramic tiles - Lobby area m²
• Painted Smooth Cement Finish @ Utilities and maintainance m²
• Rough Finish at Rentable/ Commercial space m²
• Brass Stair Nosing m²
• Topping m²
• Tile Adhesive bags
• Tile Grout bags
3.4 Roofdeck Area
• Painted Smooth Cement Finish @ Utilities and maintainance m²
• Brass Stair Nosing m²
• Topping m²
• Tile Adhesive bags
• Tile Grout bags
4 Wall Finishes
4.1 basement and Ground Floor
• Painted walls at basement area m²
• Painted walls at stairways m²
• Painted walls at office / lobby area m²
• Painted walls at Utilities and maintainance area m²
• Primer paint to commercial / Rentable areas m²
4.2 Second Floor
• Painted walls office/ Lobby area m²
• Painted walls at stairways m²
• Epoxy Zinc Primer with aqua epoxy paint finish to steels m²
• Painted walls at Utilities and maintainance area m²
4.3 Third and Fourth Floor
• Painted walls at Lobby area m²
• Painted walls at stairways m²
• Epoxy Zinc Primer with aqua epoxy paint finish to steels m²
• Painted walls at Utilities and maintainance area m²
• Primer paint to commercial / Rentable areas m²
4.4 Roof deck
• Painted walls at Utilities and maintainance area m²
• Painted concrete parapet m²
4.5 Exterior Paintings
4.6 Painting of Steel fins m²
4.7 Painting of Steel ledges m²
5 Ceiling Finishes
5.1 6.0mm Hardin Davies Hardilite on Oven Baked T-runners
5.2 1/2" thk Boral Gypsum Board on Metal Furring Ceiling m²
Joist and hangers m²
5.3 Accoustic Ceiling on Matal frame joist and Hangers m²
5.4 Accoustic Ceiling obn Metal Frame m²
6 Doors, Windows and accessories
6.1 Louvered Steel Door ( Genset , Utilities and Maintainance)
6.2 Louvered Steel Door ( Storage) m²
6.3 Louvered Steel Door ( Stairway) m²
6.4 Frameless Aluminum Doors and Glass ( Lobby) m²
6.5 Frameless Aluminum Doors and Glass ( Commercial) m²
6.6 Oven Baked Aluminum Windows
6.7 10mm Curtain Wall Glass in 2 x 4 " Aluminum Frame
6.8 Hinges
6.9 Door Closer
6.10 Door Stopper
7 Granite Countertop to Toilets
7.1 Granite Counter Top
8 Roofing
8.1 Ecofoam Poly Urethane Spray Insulation m²
8.2 Ribbed Metal Roofing with corresponding components m²
SUBTOTAL V : ARCHITECTURAL WORKS
VI. Plumbing / Sanitary Works
1 Plumbing Fixtures and Accessories
1.1 Water Closet with complete fittings and accessories sets
1.2 Lavatory with faucet and complete fittings and accessories sets
1.3 Urinal complete with fittings and accessories sets
1.4 Urinal Flush Valve sets
1.5 Stainless Steel Floor Drain 6"x6" pcs
1.6 Stainless Steel Floor Drain 4"x4" pcs
1.7 Tissue / Paper Holder pcs
1.8 Soap Holder pcs
1.9 PVC Toilet Partitions m2
2 Sanitary / Vent Lines / Aircon Drains
2.1 150mm dia UPVC Pipe Series 1000 lgths
2.2 100mm dia UPVC Pipe Series 1000 lgths
2.3 50mm dia UPVC Pipe Series 1000 lgths
2.4 150mm dia x 100mm dia UPVC WYE S 1000 pcs
2.5 100mm dia x 100mm dia UPVC WYE S 1000 pcs
2.6 100mm dia x 50mm dia UPVC WYE S 1000 pcs
2.7 50mm dia x 50mm dia UPVC WYE S 1000 pcs
2.8 150mm dia x 45deg UPVC Elbow S 1000 pcs
2.9 100mm dia x 45deg UPVC Elbow S 1000 pcs
2.10 50mm dia x 45deg UPVC Elbow S 1000 pcs
2.11 100mm dia x 90deg UPVC Elbow S 1000 pcs
2.12 50mm dia x 90deg UPVC Elbow S 1000 pcs
2.13 100mm dia UPVC Tee S 1000 pcs
2.14 50mm dia UPVC Tee S 1000 pcs
2.15 100mm dia UPVC P-Trap S 1000 pcs
2.16 50mm dia UPVC P-Trap S 1000 pcs
2.17 150mm dia UPVC Clean Out S 1000 pcs
2.18 100mm dia UPVC Clean Out S 1000 pcs
2.19 Insulation of Aircon Drains lm
2.20 6"x6" Floor Drain pcs
2.21 4"x4" Floor Drain pcs
2.22 Vulcaseal ga
2.23 Solvent Cement 400cc cans
2.24 Hangers and Supports lot
2.25 Others
3 Waterlines
3.1 2" dia Fusiotherm Pipe lgths
3.2 3/4" dia Fusiotherm Pipe
3.3 1/2" dia Fusiotherm Pipe
3.4 2"dia x 90deg Fusiotherm Elbow
3.5 3/4"dia x 90deg Fusiotherm Elbow
3.6 1/2"dia x 90deg Fusiotherm Elbow
3.7 2" x 3/4" dia Fusiotherm Tee Reducer
3.8 2" x 1/2" dia Fusiotherm Tee Reducer
3.9 3/4" x 1/2" dia Fusiotherm Tee Reducer
3.10 2" dia Fusiotherm Tee
3.11 3/4" dia Fusiotherm Tee
3.12 1/2" dia Fusiotherm Tee
3.13 2" dia Fusiotherm Coupling
3.14 3/4" dia Fusiotherm Coupling
3.15 1/2" dia Fusiotherm Coupling
3.16 2" dia Fusiotherm Union Gate Valve
3.17 3/4" dia Fusiotherm Union Gate Valve
3.18 1/2" dia Fusiotherm Union Gate Valve
3.19 2" dia Fusiotherm Check Valve
3.20 2" dia Foot Valve
3.21 2" dia Float Valve
3.22 Air Chamber
3.23 Water Meters
3.24 Installation of Constant Pressure Pumps (labor only)
3.25 Hangers and Supports
3.26 Others
4 Down Spout
4.1 100mm dia UPVC Pipes S1000
4.2 100mm dia x 90 deg UPVC Elbow S1000
4.3 Gutter Drains
4.4 Vulcaseal
4.5 Solvent Cement 400cc
4.6 Hangers and Supports
5 Drainage
5.1 2000mm dia PVC Pipes S 1000
5.2 200mm dia x 200mm dia UPVC WYE S 1000
5.3 Solvent Cement 400cc
5.4 Gravel base
5.5 CHB 6"
5.6 Plastering Works
SUB TOTAL VI : PLUMBING / SANITARY WORKS
VII Electrical Works
1. Panel Boards and Breakers
(Panelboards Enclosure By : LJ Industrial Fabrications)
(ABB/SQUARE D Circuite Breakers and Controls)
1.1 Generator Main Circuit Breaker set
Main: 1-2000AT / 2000AF, 3P, 240V, 100KAIC ACB Draw-out Ty
Meterings :
Digital Multi Metering
Current Transformer, Ring, Type, Ratio 1200:5A, 15VA
660V, Crompton Control CB, 3P, 10A, 6KA
w/ Grounding Terminals
1.2 ATS set
Main: 2-1200AT, 1200AF, 3P, 240V, 100KAIC ACB Draw out Typ
MECHANICAL INTERLOCK (ROD), FOR FIXED/DRAW-OUT TY
PILOT LIGHT,240VAC, Direct Type
Intelligence Circuit w/ Phase Protection (U/O & anti-1Phase)
Meterings :
Digital Multi Metering
Current Transformer, Ring, Type, Ratio 1200:5A, 15VA
660V, Crompton Control CB, 3P, 10A, 6KA
Terminal Lugs, Allen Type, 1x250mm2, 380A
Brn : 1-1000AT/AF,3P,240V,85KAIC MCCB w/ Micrologic 2.0
1-350AT/AF,3P,240V,50KAIC MCCB
with Metering
1.3 MDP set
Main : 1-1000AT/AFD,3P,240V,85KAIC MCCB w/ Micrologic 2.0
Brn : 1-400AT/AF,3P,240V,50KAIC MCCB
1.4 Panel MDP set
Main : 1000AT, 3P, 240V, 60Hz, 85KAIC, MCCB
Brs : 1-175AT, 2P, 60Hz, 240V
2-125AT, 3P, 240V, 60Hz
5-100AT,3P, 240V, 60Hz
1-400AT,3P, 240V, 60Hz
Spare
w/ Grounding Bus Terminal
1.5 Panel ERDP set
Main : 1800AT, 3P, 240V, 60Hz, 85KAIC, MCCB
Brs: 11-125AT, 3P, 240V, 60Hz
1-Space
w/ Grounding Bus Terminal
1.6 Panel MPB set
Main : 1-200AT, 3P, 240V, 60Hz, 50KAIC, MCCB
Brs : 4-60AT, 3P, 240V, 60Hz
5-40AT, 3P, 240V, 60Hz
1-30AT, 2P, 240V, 60Hz
w/ Grounding Bus Terminal
1.7 Panel LPB set
Main : 1-100AT, 3P, 240V, 60Hz, 25KAIC, MCCB
Brs : 12-20AT, 2P, 240V, 60Hz
w/ Grounding Bus Terminal
1.8 Panel LP1 set
Main : 1-125AT, 3P, 240V, 60Hz, 25KAIC, MCCB
Brs : 1-50AT, 2P, 240V, 60Hz, 22 KAIC
13-20AT, 3P, 240V, 60Hz, 10KAIC
w/ Grounding Bus Terminal
1.9 Panel Board 101-103 (GF Rentable Space) Main is MTS Type set
Main : 2-125AT, 3P, 240V, 60Hz 25KAIC, MCCb (w/ mech'l
interlock/sliding bar)
Brs : 2-60AT, 1P, 240V, 60Hz, 22KAIC
2-30AT, 2P, 240V, 60Hz
6-20AT, 2P, 240V, 60Hz
w/ Grounding Bus Terminal
1.10 Panel Board LP2 set
Main : 1-70AT, 3P, 240V, 60Hz, 22KAIC, MCCB
Brs : 12-20AT, 2P, 240V, 60Hz
w/ Grounding Bus Terminal
1.11 Panel Board LP3 set
Main : 1-100AT, 3P, 240V, 60Hz, 25KAIC, MCCB
Brs : 10-20AT, 2P, 240V, 60Hz
2-30AT, 2P, 240V, 60Hz
w/ Grounding Bus Terminal
1.12 Panel Board ACU2 set
Main : 1-150AT, 3P, 240V, 60Hz, 25KAIC, MCCB
Brs : 9-40AT, 2P, 240V, 60Hz
3-30AT, 2P, 240V, 60Hz
w/ Grounding Bus Terminal
1.13 Panel Board PP2 set
Main : 1-125AT, 3P, 240V, 60Hz, 25KAIC, MCCB
Brs : 3-30AT, 2P, 240V, 60Hz
21-20AT, 2P, 240V, 60Hz
w/ Grounding Bus Terminal
1.14 Panel Board VRF set
Main : 1-200AT, 3P, 240V, 60Hz, 50KAIC, MCCB
Brs : 2-100AT, 3P, 240V, 60Hz, 25KAIC
10-20AT, 2P, 240V, 60Hz
w/ Grounding Bus Terminal
1.15 Panel Board DP2 set
Main : 1-400AT, 3P, 240V, 60Hz, 65KAIC, MCCB
Brs : 1-200AT, 3P, 240V, 60Hz
1-150AT, 3P, 240V, 60Hz
1-125AT, 3P, 240V, 60Hz
1-70AT, 3P, 240V, 60Hz
w/ Grounding Bus Terminal
1.16 Panel Board LP5 set
Main : 150AT, 3P, 240V, 60Hz, 22KAIC, MCCB
Brs : 2-60AT, 2P, 240V, 60Hz
1-40AT, 2P, 240, 60Hz
7-20AT, 2P, 240V, 60Hz
1.17 Panel Board PFP set
Main : 1-350AT, 3P, 240V, 60Hz, 65KAIC, MCCB
Brs : 1-300AT, 3P, 240V, 60Hz
1-60AT, 3P, 240V, 60Hz
1-40AT, 3P, 240V, 60Hz
1-50AT, 2P, 240V, 60Hz
w/ Grounding Bus Terminal
1.18 Panel Board 301 (3F Rentable Space) Main is MTS Type set
Main : 2-125AT, 3P, 240V, 60Hz 25KAIC, MCCb (w/ mech'l
interlock / sliding bar)
Brs : 2-60AT, 3P, 240V, 60Hz, 22KAIC
2-30AT, 2P, 240V, 60Hz
6-20AT, 2P, 240V, 60Hz
w/ Grounding Bus Terminal
1.19 Panel Board 302-304 (3F Rentable Space) Main is MTS Type set
Main : 2-125AT, 3P, 240V, 60Hz 25KAIC, MCCb (w/ mech'l
interlock / sliding bar)
Brs : 2-60AT, 3P, 240V, 60Hz, 22KAIC
2-30AT, 2P, 240V, 60Hz
6-20AT, 2P, 240V, 60Hz
w/ Grounding Bus Terminal
1.20 Panel Board 401 (4F Rentable Space) Main is MTS Type set
Main : 2-125AT, 3P, 240V, 60Hz 25KAIC, MCCb (w/ mech'l
interlock / sliding bar)
Brs : 2-60AT, 3P, 240V, 60Hz, 22KAIC
2-30AT, 2P, 240V, 60Hz
6-20AT, 2P, 240V, 60Hz
w/ Grounding Bus Terminal
1.21 Panel Board 402-404 (4F Rentable Space) Main is MTS Type set
Main : 2-125AT, 3P, 240V, 60Hz 25KAIC, MCCb (w/ mech'l
interlock / sliding bar)
Brs : 2-60AT, 3P, 240V, 60Hz, 22KAIC
2-30AT, 2P, 240V, 60Hz
6-20AT, 2P, 240V, 60Hz
w/ Grounding Bus Terminal
1.22 Panel Board LP4 set
Main : 1-100AT, 3P, 240V, 60Hz, 25KAIC, MCCB
Brs : 2-30AT, 2P, 240V, 60Hz
10-20AT, 2P, 240V, 60Hz
6-20AT, 2P, 240V, 60Hz
w/ Grounding Bus Terminal
1.23 Meter Center / Bus Bar Gutter set
1.24 ECB (Tenants) sets
Main : 1-125AT, 3P, 240V, 60Hz
BID AMOUNT :
AMOUNT IN WORDS :
BID SUMMARY
Materials Labor Equipment Indirect Cost
Amount Unit Cost Amount Unit Cost Amount Unit Cost Amount
150.00 478,800.00 20% 30.00 95,760.00
- 30% - - 20% - -
- 30% - - 20% - -
200.00 - 20% 40.00 -
- 30% - - 20% - -
- 30% - - 20% - -
- 30% - - 20% - -
- 70.00 42,000.00 20% - -
- 30% - - 20% - -
150.00 - 20% 30.00 -
200.00 - 20% 40.00 -
200.00 - 20% 40.00 -
200.00 - 20% 40.00 -
200.00 - 20% 40.00 -
200.00 - 20% 40.00 -
200.00 - 20% 40.00 -
200.00 - 20% 40.00 -
200.00 - 20% 40.00 -
- 30% - - 20% - -
150.00 - 20% 30.00 -
200.00 - 20% 40.00 -
200.00 - 20% 40.00 -
200.00 - 20% 40.00 -
200.00 - 20% 40.00 -
200.00 - 20% 40.00 -
200.00 - 20% 40.00 -
- 30% - - 20% - -
150.00 - 20% 30.00 -
200.00 - 20% 40.00 -
200.00 - 20% 40.00 -
- 30% - - 20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
- 20% - -
- 20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
- 20% - -
- 20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
- 20% - -
- 20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
- 20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
- 20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
20% - -
Total
Unit Cost Amount
-
-
-
-
-
-
-
-
-
-
-
180.00 574,560.00 574,560.00
- - -
- - -
240.00 - -
- - -
- - -
- - -
70.00 42,000.00 42,000.00
-
4,675.00 1,393,150.00 1,393,150.00
4,675.00 495,550.00 495,550.00
4,675.00 243,100.00 243,100.00
4,675.00 177,650.00 177,650.00
4,675.00 701,250.00 701,250.00
4,675.00 - -
4,675.00 331,925.00 331,925.00
4,675.00 329,120.00 329,120.00
4,675.00 331,925.00 331,925.00
4,675.00 329,120.00 329,120.00
4,675.00 328,185.00 328,185.00
4,675.00 329,120.00 329,120.00
4,675.00 177,650.00 177,650.00
4,675.00 84,150.00 84,150.00
4,675.00 - -
4,675.00 626,450.00 626,450.00
59.45 2,079,977.15
87.00 61,596.00
59.45 384,760.40
59.45 356,480.04
57.28 73,564.01
59.45 564,775.00
57.28 213,693.03
59.45 1,782,875.78
57.28 818,001.55
-
53.25 - -
-
53.25 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
-
53.25 - -
53.25 - -
-
53.25 - -
53.25 - -
48.75 - -
48.75 - -
-
53.25 - -
53.25 - -
-
53.25 - -
53.25 - -
48.75 - -
48.75 - -
-
-
53.25 - -
53.25 - -
53.25 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
48.75 - -
-
580.00 107,880.00 107,880.00
580.00 40,020.00 40,020.00
580.00 117,740.00 117,740.00
580.00 611,900.00 611,900.00
580.00 712,240.00 712,240.00
580.00 309,140.00 309,140.00
580.00 311,460.00 311,460.00
580.00 311,460.00 311,460.00
2,521,840.00
-
-
180.00 - -
- - -
- - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
-
180.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
180.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
180.00 - -
240.00 - -
240.00 - -
-
180.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
- - -
180.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
- - -
180.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
- - -
180.00 - -
240.00 - -
240.00 - -
- - -
-
180.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
180.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
180.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
180.00 - -
240.00 - -
240.00 - -
180.00 - -
240.00 - -
240.00 - -
-
180.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
-
180.00 - -
240.00 - -
240.00 - -
240.00 - -
240.00 - -
-
180.00 - -
-
180.00 - -
240.00 - -
-
-
-
-
-
-
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
-
-
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
-
-
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
-
-
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
-
-
-
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
-
-
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
-
-
- - -
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
- - -
-
- - -
-
-
- - -
- - -
- - -
-
-
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
-
-
- - -
- - -
- - -
- - -
- - -
- - -
- - -
-
-
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
-
-
- - -
- -
- -
- - -
- - -
- - -
- - -
-
-
- - -
- - -
- - -
- - -
-
-
- - -
- - -
- - -
- - -
- - -
-
-
- - -
- - -
-
-
#REF!
-
Project : PROPOSED 4-STOREY COMMERCIAL BUILDING
Location : J.P. LAUREL Avenue, Davao City
Contract Works : GENERAL CONSTRUCTION WORKS
Owner : HAI GLOBAL CORPORATION
Subject : BID BREAKDOWN
1.29 KW-HR METER, 3phase, 240v, CL200, Self Contained 11.00 sets 7,500.00
BID AMOUNT :
Plus 12% VAT for Labour & Profit Only:
AMOUNT IN WORDS :
BID SUMMARY
Materials Labor Equipment Indirect Cost
Amount Unit Cost Amount Unit Cost Amount Unit Cost Amount
4,339,950.00
928,000.00 15% 960.00 139,200.00 - - 20% 1,280.00 185,600.00
186,830.00 20% 1,099.00 37,366.00 - - 20% 1,099.00 37,366.00
37,824.00 20% 126.08 7,564.80 - - 20% 126.08 7,564.80
47,879.00 20% 736.60 9,575.80 - - 20% 736.60 9,575.80
9,960.00 20% 498.00 1,992.00 - - 20% 498.00 1,992.00
1,252.00 20% 62.60 250.40 - - 20% 62.60 250.40
84,280.00 20% 602.00 16,856.00 - - 20% 602.00 16,856.00
13,176.00 20% 329.40 2,635.20 - - 20% 329.40 2,635.20
4,080.00 20% 51.00 816.00 - - 20% 51.00 816.00
32,300.00 20% 380.00 6,460.00 - - 20% 380.00 6,460.00
3,412.00 20% 170.60 682.40 - - 20% 170.60 682.40
1,124.50 20% 22.49 224.90 - - 20% 22.49 224.90
599,720.00 20% 272.60 119,944.00 - - 20% 272.60 119,944.00
49,708.00 20% 115.60 9,941.60 - - 20% 115.60 9,941.60
6,361.80 20% 13.83 1,272.36 - - 20% 13.83 1,272.36
33,060.00 20% 228.00 6,612.00 - - 20% 228.00 6,612.00
4,932.00 20% 82.20 986.40 - - 20% 82.20 986.40
679.80 20% 11.33 135.96 - - 20% 11.33 135.96
36,656.00 20% 10.11 7,331.20 - - 20% 10.11 7,331.20
66,556.96 20% 16.10 13,311.39 - - 20% 16.10 13,311.39
2,275.20 20% 25.28 455.04 - - 20% 25.28 455.04
52,853.92 20% 36.83 10,570.78 - - 20% 36.83 10,570.78
1,045,415.00 20% 49.00 209,083.00 - - 20% 49.00 209,083.00
205,979.04 20% 60.10 41,195.81 - - 20% 60.10 41,195.81
43,991.04 20% 91.65 8,798.21 - - 20% 91.65 8,798.21
133,036.80 20% 216.32 26,607.36 - - 20% 216.32 26,607.36
2,235,552.00 20% 278.40 447,110.40 - - 20% 278.40 447,110.40
107,250.00 20% 330.00 21,450.00 - - 20% 330.00 21,450.00
55,000.00 20% 11,000.00 11,000.00 - - 20% 11,000.00 11,000.00
10,000.00 20% 200.00 2,000.00 - - 20% 200.00 2,000.00
4,400.00 20% 110.00 880.00 - - 20% 110.00 880.00
10,800.00 20% 360.00 2,160.00 - - 20% 360.00 2,160.00
1,700.00 20% 17.00 340.00 - - 20% 17.00 340.00
1,500.00 20% 6.00 300.00 - - 20% 6.00 300.00
6,500.00 20% 13.00 1,300.00 - - 20% 13.00 1,300.00
50,000.00 20% 10,000.00 10,000.00 - - 20% 10,000.00 10,000.00
35,000.00 20% 7,000.00 7,000.00 - - 20% 7,000.00 7,000.00
50,000.00 20% 10,000.00 10,000.00 - - 20% 10,000.00 10,000.00
6,199,045.06
1,001,494.08
12,619,785.14
Total
Unit Cost Amount
-
-
19.60
2,240.00 31,360.00 31,360.00
1,960.00 45,080.00 45,080.00
3,080.00 70,840.00 70,840.00
86,800.00 86,800.00 86,800.00
352.80 192,276.00 192,276.00
49.00 8,428.00 8,428.00
980.00 7,840.00 7,840.00
17,406,172.70
Project : PROPOSED 4-STOREY COMMERCIAL BUILDING
Location : J.P. LAUREL Avenue, Davao City
Contract Works : GENERAL CONSTRUCTION WORKS
Owner : HAI GLOBAL CORPORATION
Subject : BID BREAKDOWN
1.29 KW-HR METER, 3phase, 240v, CL200, Self Contained 11.00 sets 5,500.00
BID AMOUNT :
Plus 12% VAT for Labour & Profit Only:
AMOUNT IN WORDS :
BID SUMMARY
Materials Labor Equipment Indirect Cost
Amount Unit Cost Amount Unit Cost Amount Unit Cost Amount
3,892,178.00
928,000.00 15% 960.00 139,200.00 - - 20% 1,280.00 185,600.00
131,880.00 15% 824.25 19,782.00 - - 20% 1,099.00 26,376.00
37,824.00 15% 94.56 5,673.60 - - 20% 126.08 7,564.80
47,879.00 15% 552.45 7,181.85 - - 20% 736.60 9,575.80
9,960.00 15% 373.50 1,494.00 - - 20% 498.00 1,992.00
1,252.00 15% 46.95 187.80 - - 20% 62.60 250.40
78,260.00 15% 451.50 11,739.00 - - 20% 602.00 15,652.00
9,882.00 15% 247.05 1,482.30 - - 20% 329.40 1,976.40
4,080.00 15% 38.25 612.00 - - 20% 51.00 816.00
32,300.00 15% 285.00 4,845.00 - - 20% 380.00 6,460.00
3,412.00 15% 127.95 511.80 - - 20% 170.60 682.40
1,124.50 15% 16.87 168.68 - - 20% 22.49 224.90
545,200.00 15% 204.45 81,780.00 - - 20% 272.60 109,040.00
34,680.00 15% 86.70 5,202.00 - - 20% 115.60 6,936.00
6,361.80 15% 10.37 954.27 - - 20% 13.83 1,272.36
33,060.00 15% 171.00 4,959.00 - - 20% 228.00 6,612.00
4,932.00 15% 61.65 739.80 - - 20% 82.20 986.40
679.80 15% 8.50 101.97 - - 20% 11.33 135.96
33,060.00 15% 6.84 4,959.00 - - 20% 9.12 6,612.00
59,998.85 15% 10.88 8,999.83 - - 20% 14.51 11,999.77
2,052.00 15% 17.10 307.80 - - 20% 22.80 410.40
47,627.65 15% 24.89 7,144.15 - - 20% 33.19 9,525.53
929,352.60 15% 36.30 139,402.89 - - 20% 48.40 185,870.52
186,456.00 15% 40.80 27,968.40 - - 20% 54.40 37,291.20
120,540.00 15% 147.00 18,081.00 - - 20% 196.00 24,108.00
2,023,560.00 15% 189.00 303,534.00 - - 20% 252.00 404,712.00
99,000.00 15% 247.50 14,850.00 - - 20% 330.00 19,800.00
55,000.00 15% 8,250.00 8,250.00 - - 20% 11,000.00 11,000.00
10,000.00 15% 150.00 1,500.00 - - 20% 200.00 2,000.00
4,400.00 15% 82.50 660.00 - - 20% 110.00 880.00
10,800.00 15% 270.00 1,620.00 - - 20% 360.00 2,160.00
1,700.00 15% 12.75 255.00 - - 20% 17.00 340.00
1,500.00 15% 4.50 225.00 - - 20% 6.00 300.00
6,500.00 15% 9.75 975.00 - - 20% 13.00 1,300.00
40,000.00 15% 6,000.00 6,000.00 - - 20% 8,000.00 8,000.00
25,000.00 15% 3,750.00 3,750.00 - - 20% 5,000.00 5,000.00
35,000.00 15% 5,250.00 5,250.00 - - 20% 7,000.00 7,000.00
5,602,314.20
947,184.64
11,423,983.34
Total
Unit Cost Amount
-
-
18.90
1,890.00 26,460.00 26,460.00
1,890.00 43,470.00 43,470.00
2,430.00 55,890.00 55,890.00
78,300.00 78,300.00 78,300.00
340.20 185,409.00 185,409.00
40.50 6,966.00 6,966.00
810.00 6,480.00 6,480.00
15,423,229.01
Project : PROPOSED 2-STOREY COMMERCIAL BUILDING
Location : QUIMPO BLVD. DAVAO CITY
Contract Works : ELECTRICAL WORKS
Owner : DCLA
Subject : BID BREAKDOWN
1.24 KW-HR METER, 3phase, 240v, CL200, Self Contained 3.00 sets
1.25 KW-HR METER, 1phase, 240v, CL200, Self Contained 32.00 sets
BID AMOUNT :
AMOUNT IN WORDS :
BID SUMMARY
Materials Labor Equipment Indirect Cost
Unit cost Amount Unit Cost Amount Unit Cost Amount Unit Cost
322.00 18.90
3,920.00 1,890.00 26,460.00
6,440.00 1,890.00 43,470.00
8,280.00 2,430.00 55,890.00
11,600.00 78,300.00 78,300.00
27,468.00 340.20 185,409.00
1,032.00 40.50 6,966.00
960.00 810.00 6,480.00
5,763,696.69
Project : PROPOSED 2-STOREY COMMERCIAL BUILDING
Location : QUIMPO BLVD. DAVAO CITY
Contract Works : ELECTRICAL WORKS
Owner : DCLA
Subject : BID BREAKDOWN
1.24 KW-HR METER, 3phase, 240v, CL200, Self Contained 3.00 sets
1.25 KW-HR METER, 1phase, 240v, CL200, Self Contained 32.00 sets
BID SUMMARY
Materials
Unit cost Amount
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
15,000.00 45,000.00
3,500.00 112,000.00