WEMINE MIDDLE EAST CRYPTOCURRENCY MINING -LLC
Executive
Summary
Whoa!
Discover the unparalleled
expertise of Wemine,
a premier crypto mining hosting provider
in the dynamic landscape of the Middle East.
Our seasoned professionals navigate the
challenges of escalating global electricity rates,
ensuring your business thrives.
Tailored to perfection, our solutions forge enduring
partnerships, propelling mutual success. Dive into
our proposal and unlock the limitless potential for
your business with Wemine.
Introduction
When it comes to hosting or investing in Crypto Mining
farms, we offer our customers solid and flexible solutions
with different portfolio size scalable to the client’s needs.

● Build and manage multiple mining farms from ground.


● Offering one of the best rates per KW In the Industry.
● Sustainable, renewable long-term contract.
- Leading Bitcoin mining and ASIC hosting provider
- Robust infrastructure across 20 locations in the
UAE, utilizing 10 MW for hosting services
- Specialization in hydro cooling solutions
- Sold 2500 ASIC machines
- Maintaining a total terahash rate of 300,000 TH
- Expertise in critical ASIC chip repair, including
exclusive service for IceRiver ASICs outside of
China
- Reliable, innovative, and customer-centric
cryptocurrency mining solutions provided by
WeMine
Project Overview

● Having experience in crypto mining and holding a crypto


mining license along with the eligibility to provide the power
puts us in the top position to offer hosting solutions in the
UAE which is one of the few countries legalizing crypto
mining, and one of the safest destinations for investment
worldwide.
● Our tailor-made and customizable solution will provide a
complete crypto mining site, taking care of the land lease,
bringing necessary power to the facility, building the mining
facility with Its required cooling system , power , Internet and
surveillance system , as well as arranging a professional team
ready and equipped to manage the whole business if
necessary.
● Our company will support and sustain itself by making a
margin by selling power to the facility, as a local company in
the UAE with crypto mining license we have access to very
low power cost in the Emirate of Abu Dhabi.
Challenges

• We recognize the challenges faced by our


clients in the Crypto Mining sector, including:

• High global electricity costs

• Concerns regarding security, safety, and legality


of mining
0pportunities

However, where there are challenges, there are also


opportunities:

• We offer access to low-cost electricity in a crypto-


friendly state with excellent infrastructure and a
supportive regulatory environment for foreign
investment.

• Our tailored services are designed to ensure your


mining operations thrive and stay ahead of the
market. We take the time to understand your
company and specific needs, aligning our strategy
to achieve your unique goals. Expect ongoing
support, regular performance reviews, and
opportunities for continuous improvement.
Scope of work
Budget
NAME PRICE QTY SUBTOTAL

$250,000
Land and farm Rental $50,000 5 years

Power substation, Transformer and cable


$3,000,000 20 MW $3,000,000
+the fee to the power company
Facilities constructions (including a 4000+
$1,604,150 $1,604,150
RepairCentre + Storage) miners
Hydro
Cooling systems $2,383,300 $2,383,300
Cooling

Internet, ethernet and power wiring $88,000 Fiber Optic $88,000

CCTV equipment and Installation + Full


$45,000 $45,000
Gate pass System
Tax will be inclusive through USDT Subtotal $7,370,450
Payment
Tax(5%) $368,522.5

Total $7,738,972.5
Payment schedule

Payment amount Payment Due Date


(40%) of The Total Should be initial $3,328,300
paymentto start processing the project.

(30%) of The Total after 30 Days from $2,496,225


thecontract date.
supporting the project progress
(30%) of The Total after 180 Days from
thecontract date $2,496,225
Project goals
Using the above Infrastructure to mine btc with own machines 03
Operational infrastructures

Parameter Value

Hosting Charge for 20 MW Facility $612,000 (Monthly)


Number of Bitmain S21 335T
3,500
Machines
Total Bitcoin Mining Power
1.1725
(ExaHash)
Financial analysis

Parameter Value

Cost of 3,500 Bitmain S21 335T


$19,932,500
Machines (one time)
$7,738,972.5
Infrastructure Expense (one time)

Operational Expense (Electricity &


Maintenance) (monthly) $612,000 (monthly)

Total cost without operational


$27,671,472
expense
Break-even period

Bitcoin Price Break-even Period


$50,000 13 months

$69,000 9 months

Considered Halving
Cryptocurrency investments, including Bitcoin, carry market risks; past performance doesn't ensure
future results
Predicted results

$150,000
With the recent Bitcoin ETF approval, akin
to gold, Bitcoin is forecasted to surpass a
minimum value of $150,000 in the near
future.
$69,000
At its previous peak of $69,000, Bitcoin was
not acknowledged as an asset class. This
value serves as a realistic worst-case selling
point for BTC miners. Cryptocurrency investments, including Bitcoin, carry market risks; past performance doesn't ensure
future results
Yearly BTC
production
Considering the
halving effect

500 BTC
largest bitcoin
mine in US

Click this hyper link


Our team

Marwan Qasqoos Rinshin Kizhakkethil Janisker Jelastin


Head of operations Operations manager Sales manager
Thanks!
Do you have any questions?
[email protected]
+971 585955317 | wemine.ae

Credits: This presentation template was created by


Slidesgo, and includes icons by Flaticon, and infographics &
images by Freepik

You might also like