0% found this document useful (0 votes)
33 views6 pages

DOMD Quiz

domd iim

Uploaded by

x24siddharthak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
33 views6 pages

DOMD Quiz

domd iim

Uploaded by

x24siddharthak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

Home ► My courses ► DOMDx-B-PGPX-2021-22 ► General ► DOMD Quiz

Started on Monday, 7 June 2021, 2:30 PM


State Finished
Completed on Monday, 7 June 2021, 2:45 PM
Time taken 15 mins

Question 1 The 'strategic service vision' provides a framework of developing a set of shared core values,
Complete practices, and measures as part of an overall strategy of the firm.

Marked out of 1.00 True or False?

Select one:
a. False

b. True

Question 2 The customer order decoupling point separates order driven activities from the forecast driven
Complete activities.

Marked out of 1.00 True or False?

Select one:
a. True

b. False

Question 3 The assembly line at SoChe Company operates a single shift of 480 minutes in a day. The
Complete desired daily output from the line is 100 units. What should be the cycle time of the line?

Marked out of 1.00


Select one:
A. Cannot be determined

B. 1.2 minutes /unit


C. 4.8 minutes/ unit

D. 0.208 minutes/ unit

Question 4 Smaller transfer batches give higher work-in-process inventory and slower product flow.
Complete True or False?
Marked out of 1.00
Select one:
a. True

b. False
Question 5 A simple project listing of five activities, their predecessors, and their respective time estimates
Complete are presented here
Activity Immediate Predecessor Time in days
Marked out of 1.00
A None 3
B A 2
C A 1
D B&C 3
E D 4

What activities have slack in this project?

Select one:
A. Activities B & C

B. Activity C
C. Activity D

D. Activity B

Question 6 In a job shop, Machine #1 has a twenty minute set-up time per batch and a two minute per unit
Complete run time. Machine #2 performs the identical function but has a set-up time of thirty minutes and a
one minute run time per unit. The job shop makes products in batches ranging from one unit to
Marked out of 1.00
one hundred units. Assuming capacity is not a limitation on either machine, on which batches
should Machine #2 be used?

Select one:
A. Batches with up to 25 units should be run on machine #2

B. All batches should be run on machine #2

C. Batches of fewer than 40 units should be run on machine #2

D. No batches should be run on machine #2

E. Batches of more than 10 units should be run on machine #2

Question 7 Given the following data for an assembly line, determine the percentage idle time on the line.
Complete
Cycle Time = 5 minutes/unit
Marked out of 1.00
Workstation # Activity Duration (in
minutes)
1 4.2
2 4.0
3 4.5
4 4.3

Select one:
A. 15%

B. 17%

C. 20%

D. Cannot be determined
Question 8 If the average aggregate inventory value is Rs. 500,000 and the cost of goods sold is Rs.
Not answered 1,000,000, which of the following is inventory turnover?

Marked out of 1.00


Select one:
A. 2

B. None of the other options


C. 10.5

D. 0.5

E. 50

Question 9 What type of plant layouts can more easily adapt to variations in product requirements?
Complete
Select one:
Marked out of 1.00
A. Product layout

B. Process layout
C. Fixed-location layout

D. cellular layout

Question 10 The term “servicescape” refers to which of the following?


Not answered
Select one:
Marked out of 1.00
A. The emergency exit plan from a service facility

B. The schematic diagram of the service flows of material, information and customers

C. The broadest concept of the service business


D. The physical surroundings in which the service takes place

E. The network of government rules regulating the service

Question 11 A simple project listing of five activities, their predecessors, and their respective time estimates
Complete are presented here
Activity Immediate Predecessor Time in days
Marked out of 1.00
A None 3
B A 2
C A 1
D B&C 3
E D 4

What is the minimum time required in days to complete the project?

Select one:
A. 11
B. 10

C. 13

D. 12
Question 12 An assumption of learning curve theory is which of the following?
Not answered
Select one:
Marked out of 1.00
A. Unit time will increase at a decreasing rate

B. Unit time will decrease at an increasing rate

C. Unit time will decrease at a decreasing rate


D. Unit time will increase at an increasing rate

E. Unit time will hold constant

Question 13 Low rates of capacity utilization in service organizations are never appropriate.
Complete True or False?
Marked out of 1.00
Select one:
a. True

b. False

Question 14 You have just determined the actual number of workstations that will be used on an assembly line
Complete to be 8 using the assembly-line balancing procedure. The cycle time of the line is 5 minutes and
the sum of all that tasks required on the line is 30 minutes. What is the resulting line's efficiency?
Marked out of 1.00

Select one:
A. 0.48
B. 0.75

C. 0.90

D. 0.6

Question 15 The minimum possible cycle time in a product layout is determined by the
Complete
Select one:
Marked out of 1.00
A. total task time

B. longest task time


C. shortest task time

D. average task time

Question 16 In the last financial year, the Karnavati Municipal hospital, a 250-bed hospital in Ahmedabad, had
Complete an average bed occupancy of 80%, and the average length of stay for patients was 4 days.
Assuming average bed (stay) charges of Rs 1000 per day, assuming 365 days in a year, what
Marked out of 1.00
was the annual revenue of the hospital (from the patient stay charges)?

Select one:
A. Rs. 1,00,00,000

B. Rs. 3,65,00,000

C. Rs. 8,00,00,000
D. Rs, 7,30,00,000
Question 17 The type of processing system which is deployd for highly standardized products is
Complete
Select one:
Marked out of 1.00
A. batch

B. job shop
C. intermittent
D. continuous

Question 18 Ola operates a fleet of 300 cars in Ahmedabad. On a typical evening, about 80% of the cars are
Complete in operation. If an average trip time (reaching the customer site, picking up the customer and
dropping off the customer at the destination site) is 40 minutes, how many trips are completed per
Marked out of 1.00
hour on an average?

Select one:
A. 240
B. 480

C. 360
D. 150

Question 19 Consider a car repair shop where the cars after arrival are first checked to ascertain the problem
Not answered associated with the car. These checks typically require 15 minutes per car. Then depending on
the problems, the repairs are classified as a major repair or minor repair. If it a major repair, the
Marked out of 1.00
car is taken to the major repair area for repair otherwise it is sent to the minor repair area. The
major repairs for a car typically require 20 minutes while the minor repairs for a car require 12
minutes. After the repair is complete, the car is cleaned in 5 minutes, and it leaves the premise.
From historical data, it is observed that 20% of the repairs are major and the remaining are minor.
What is the overall process capacity (in cars/hour) for the car repair shop?

Select one:
A. 5 cars/ hour
B. cannot be determined

C. 4 cars/ hour
D. 3 cars/ hour
Question 20 Consider a car repair shop where the cars after arrival are first checked to ascertain the problem
Not answered associated with the car. These checks typically require 15 minutes per car. Then depending on
the problems, the repairs are classified as a major repair or minor repair. If it a major repair, the
Marked out of 1.00
car is taken to the major repair area for repair otherwise it is sent to the minor repair area. The
major repairs for a car typically require 20 minutes while the minor repairs for a car require 12
minutes. After the repair is complete, the car is cleaned in 5 minutes, and it leaves the premise.
From historical data, it is observed that 20% of the repairs are major and the remaining are minor.

Which resource (or the process) is the bottleneck in the car repair shop?

Select one:
A. Car check

B. Minor repair Area


C. Major repair Area
D. Car cleaning