Feng Shun - Daily Report (31!05!2024)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Weather:

Project Title: Fine a


(A) SITE CLEARANCE AND EARTHWORKS (PHASE II) AT ANG
MO KIO N8 Rain r
(B) CONSTRUCTION OF ANG MO KIO STREET 81 (Part I), ANG
MO KIO STREET 82 & ANG MO KIO DRIVE (PRT I)
(C)CONSTRUCTION OF TRUNK SEWERS (PART I) AT ANG MO
KIO N8
Rain start :
Proj. Ref.No.: E4480-00009-2023 Date: 31/5/2024
Company : Feng shun construction Pvt Ltd working Time : 8 am to 7 pm

Locations A. Activites Description / Particulars Manpower

Trail trench No-22B Hacking the concrete pavement and excavation Management Staff 4
Reach to 1.2 m from ground level.found LT cable. Project Director 1
MH-E21A & Turf reinstate works has done at MH-E20A and MH-E21A Project manager 1
Phase 2
20A Project Engr 1
Cage Ladder standing Platform plate cutting and welding works WSH Coordinator 1
in progress

Site Staff 10
Site Supervisor 1
Asst Site Foreman - Trial Trench Excavation - MH-E21A -TT22
Machine Operator 1
Lifting Sup. 1 Picture
Rigger/signalman 3
Banksman 0
Land Surveyor -
welder 2
General Workers 2

Site Vehicle (with


Excavator 1 Gen Set with pump 1 1
license plate)
10T Roller - 4'' cutting machine 1 shoring materials As required
Site Vehicle
ECM Plant 1 (without license 0 Electrical breaker 1
plate)

Good Soil excavated Cum

C. Material Excavated
Hard soil Excavated - cum 1.83 Dumped near the site,later backfill

Cum

Consultant C&S (ECAS)


D. Visitor(s) at Site Consultant M&E (GIMS)
Client (HDB)

E. Comments Trial Trench Excavation - MH-E20A -Turf reinstate


F. Name & Signature of RTO: Arunachalam

Note: This form serves as a guideline only

You might also like