Feng Shun - Daily Report (31!05!2024)
Feng Shun - Daily Report (31!05!2024)
Feng Shun - Daily Report (31!05!2024)
Trail trench No-22B Hacking the concrete pavement and excavation Management Staff 4
Reach to 1.2 m from ground level.found LT cable. Project Director 1
MH-E21A & Turf reinstate works has done at MH-E20A and MH-E21A Project manager 1
Phase 2
20A Project Engr 1
Cage Ladder standing Platform plate cutting and welding works WSH Coordinator 1
in progress
Site Staff 10
Site Supervisor 1
Asst Site Foreman - Trial Trench Excavation - MH-E21A -TT22
Machine Operator 1
Lifting Sup. 1 Picture
Rigger/signalman 3
Banksman 0
Land Surveyor -
welder 2
General Workers 2
C. Material Excavated
Hard soil Excavated - cum 1.83 Dumped near the site,later backfill
Cum