Objective of Network Analicis
Objective of Network Analicis
Network analysis is a powerful tool for planning, scheduling, and control of project
It shows a simple way of the inter relationship of the various activities constituting a project
The main objective of the network analysis is the minimization of the total cost
Network Tek nicks were developed to facilitate planning scheduling the project in an integrated manor.
So that, those could be completed with in the constraints of desired time, cost, and performance.
2 most popular of this Teknik are the critical path method (cpm) and the program evaluation and revie
technic (pert).
Network
Network diagram
It is a diagram which represents the activities and events of a network, their sequence and relationship.
Activity
An activity is represented by an arrow with an event (node) at the biggening and at the end indicate the
start and finish of the activities.
Events are denoted by circles, and the direction indicate the progress of the activity.
The initial and terminal nodes of the activities are also called tail and head events.
If an activity “B” can start immediately after an activity “A” then it is denoted by
Note
Predecessor activity
An activity which must be completed before one or more other activities start is known as predecessor
activity
Successor activity
Activities that can’t be started until one or more of the other activities are completed but immediately
succeed them are called successor activity
events
Merge event
An event which represents the joint completion of more than one activity is known as merge event.
Burst event
An event represents the initiation or beginning of more than one activity is known as burst event.
The arrow represents an activity with the head indicating the direction of the progress in the project
A network should have only one initial and one terminal node.
The length of the arrow has no significance in network the diagram should flow from left to right
Events by those of marking the completion of activities are called head events
All activities proceeding an activity is to be completed in respects
i.e., a network should be developed on the bases of logical or technical dependencies dependences
between various activities of the project
looping is to be avoided
When the project contains group of 2 or more jobs which have common predecessor.
CPM networks are activity-oriented diagram. It is a network technic involved in the preparation of the
network in the form of arrow diagram
After preparing the network diagram, we can locate the various possible path from that, we can
determine the critical path.
Path
It refers to unbroken or continues chain of activity from start event to end event in the network diagram
Critical path
It is a longest path starting from first to the last event and it is shown by the thick line or double lines in
the network diagram
Critical activities
It is the sum of individual times of all critical activities laying on it defines the minimum time required to
complete the project
To determine the duration of the individual activities in CPM for activity times are to be computed
LST
it is the latest time by which an activity can be started without delaying the completion of the project
It is the latest time by which an activity can be finished without delaying the completion of the project
The float (slack) or free time is the length of time in which a non-critical activity or an event can be
delayed or extended without delaying the total project completion time
Total float
Total float is the duration by which an activity can be delayed without delaying the project
Free float
Independent float
Pert assist a business manager in planning and controlling a project. So, it is a management technic it
allows a manager to calculate the expected total amount of time required for completing the entire
project at the stage of formulation and planning of the project.
At the same time, it helps to highlight the critical activities of the project
Identification of critical activities helps the manager either to allocate more resources for them or keep a
careful watch on such activities as the project progresses
It is the short possible time in which an activity can be completed under ideal conditions if everything
goes well.
It refers to the estimate of the normal time that the activity would take
It is the maximum time that an activity would take if everything goes wrong and abnormal situations are
prevailed.
Note, from the above 3-time estimates, the expected time of each activity could be calculated by using
formula TE=TO+4TM+TP/6
Step 1, locate activities and events of a project on the bases of this, a network diagram is to be drawn
Step 5, by using expected time estimates of each activities find the earliest event time and latest event
time for each activity
Step 7, various time estimates for activities of the critical path to be added together
Step 8, standard deviation, and variants for each activity can be found by the following formula
( )
2
2 TP−¿
σ =
6
Standard deviation
Sum of the variants of time estimates of all activities are the critical activities
tasks a b C D e f g h i
TO 5 18 26 16 15 6 7 7 3
TP 10 22 40 20 25 12 12 9 5
TM 8 20 33 18 20 9 10 8 4
Determine the following: expected task time and their variants, earliest and latest expected time to each
event, and the critical path