Distribution Notebook CAD
Distribution Notebook CAD
Table of Contents
Ch_1 ............................................................................................................................................ 4
Introduction ...................................................................................................................... 4
AutoCADShortcut. ............................................................................................................. 4
Drawing Command ............................................................................................................ 7
Modify Command .............................................................................................................. 9
Layer ............................................................................................................................... 13
Ch_2 .......................................................................................................................................... 15
Concept Design ................................................................................................................ 15
Construction Field:............................................................................................................ 15
Electrical System ............................................................................................................... 18
▪ Internal coordination: ....................................................................................................... 22
Design Phases ................................................................................................................... 24
Load Estimation: .............................................................................................................. 26
Overall method: ................................................................................................................ 29
Load breakdown. .............................................................................................................. 30
Exact method: ................................................................................................................... 30
Feeding System:................................................................................................................ 33
Zoning: ............................................................................................................................ 35
Bulk Equipment Selection ................................................................................................ 37
Transformer: ................................................................................................................... 37
Principal: ........................................................................................................................... 37
Structure of Transformer: .............................................................................................. 38
Main Purpose: .................................................................................................................. 39
Transformer operation ..................................................................................................... 39
Types Of Transformers: ........................................................................................................... 40
Oil Transformer: ....................................................................................................................... 40
Dry Transformer:...................................................................................................................... 44
Classification according to ventilation method (Cooling) ................................................... 45
Important definitions ............................................................................................................. 45
Transformer Tests: ........................................................................................................... 46
Transformer Sizing ................................................................................................................... 47
1
Distribution notebook S’22 2
GENERATOR. ............................................................................................................................. 49
UPS ............................................................................................................................................ 55
Central battery.................................................................................................................. 60
End of Ch_2....................................................................................................................... 65
Ch_3 .......................................................................................................................................... 66
Switchgear ...................................................................................................................... 66
1. Low Voltage switchgears: ............................................................................................. 66
POWER FACTOR CORRECTION .......................................................................................... 86
Medium Voltage Switchgear ............................................................................................ 90
Distributer......................................................................................................................... 90
Layout: Distributer building (outdoor) ............................................................................. 96
Ring Main Unit (RMU): ..................................................................................................... 98
Ch_4 ........................................................................................................................................ 105
Lighting and small power design .................................................................................... 105
INDOOR LIGHTING DESIGN ............................................................................................. 105
How to specify the lux of applications? ......................................................................... 135
DIALux Red...................................................................................................................... 136
DIALux Evo ...................................................................................................................... 143
Lighting In CAD ............................................................................................................... 161
Small power .................................................................................................................... 164
Types of switches .......................................................................................................... 173
Disconnect Switch .................................................................................................................. 177
MEP .............................................................................................................................. 179
1. HVAC SYSTEM ......................................................................................................... 180
2. FIRE FIGHTING SYSTEM........................................................................................... 189
3. Plumping system .................................................................................................... 191
4. Low current............................................................................................................. 193
Practical on CAD: ............................................................................................................ 196
Ch.5......................................................................................................................................... 198
Power Cable & Circuit Breaker ....................................................................................... 198
1. Circuit Breaker: ....................................................................................................... 198
Sizing ............................................................................................................................... 204
2
Distribution notebook S’22 3
3
Distribution notebook S’22 4
Ch_1
Introduction
AutoCAD Shortcut.
AutoCAD is based on a set of orders to do the drawing
process and the most important of these orders is orders:
1. Drawing,
2. Modification,
3. Measure,
4. and layers.
4
Distribution notebook S’22 5
✓ Drawing Menu:
✓ Background:
▪ How to modify background?
1. Right click Option color
2. Write (OP) Enter color
5
Distribution notebook S’22 6
6
Distribution notebook S’22 7
Drawing Command
1-Line
✓ L Enter
✓ Home line
• Then specify start point and end point.
• To get to horizontal or vertical line:
1. Key F8
2-ARC
✓ A Enter
✓ Home Arc
7
Distribution notebook S’22 8
3-rectangular
✓ REC Enter
✓ Home Rectangular
4-Circle
✓C Enter
✓ Home Circle
5-Poly line
✓ PL Enter
✓ Home poly line
8
Distribution notebook S’22 9
Modify Command
1-Hatch
✓H Enter
1-Trim
✓ TR Enter
3-Extend
✓ EX Enter
4-Rotate
✓ Ro Enter
5-copy
✓ Co Enter
9
Distribution notebook S’22 10
6-Scale
✓ Sc Ente
7-Move
✓M Enter
8-Break
✓ Br Enter
9-Explode
✓ EX Enter
10-Aline
✓ AL Enter
10
Distribution notebook S’22 11
11-Filit
✓F Enter
12-Block
✓B Enter
13-Mirror
✓ MI Enter
11
Distribution notebook S’22 12
14-Offset
✓O Enter
15-Area
✓ AA Enter
16-Dimension
✓ DIME Enter
17- Text
✓T Enter
18-B Count
✓ BC Enter
12
Distribution notebook S’22 13
NOTES
Layer
13
Distribution notebook S’22 14
(Set layer) the layer with this signal is the layer you work in
14
Distribution notebook S’22 15
Ch_2
Concept Design
Construction Field:
Construction Field is an impressive free business theme for
construction, engineering, architecture, real estate, or building
companies. The theme is suitable for construction or real state
agency and overall construction and real estate sites.
➢ Stake Holders:
❖ Owner:
The first person to be responsible for the project, He has the idea
of the project, is the owner of the capital like the National Bank
of Egypt or Sheraton or CIB or City stars.
❖ Consultant:
The consulting office like Dar El- Handasa…etc., and he is
responsible for organizing and supervising the implementation of
the project, He converts the owner’s idea into an accessible
design on ground according to codes, standard and regulation
15
Distribution notebook S’22 16
❖ Contractor:
These are contracting companies and it is a central party such
as Orascom, Hassan Allam and Arab Contractor, and this is
the responsible body or the entity responsible for
implementation.
❖ Supplier:
Its role is to supply me with the tools and components that I as
a contractor will need in the implementation of my project and
there are companies that make and supply like Schneider
Electric or EL-Sewedy for cables or EL-Sewedy for
Electrometer or ABB and there is one of them Supplying and
only like a Siraj for lighting
❖ Commissioning team
And this is a little advanced after the contractor finishes the
project, maybe before I hand over the project to the consultant,
the third part comes away from the consultant, the owner, the
contractor, and has a technical degree to evaluate things very
well to make sure that the project in a specific system is
perfected.
16
Distribution notebook S’22 17
“Last
stage”
17
Distribution notebook S’22 18
Electrical System
18
Distribution notebook S’22 19
➢ Power Supply:
• Off Grid:
1. Conventional (Generator),
2. Green Power (New technology system).
• On Grid:
1. Local Authority Tie-In (MV, LV).
19
Distribution notebook S’22 20
➢ Applications:
• Indoor lighting:
▪ Hospitals, malls, offices…etc.
• Outdoor lighting:
▪ Street lighting, landscape, green app.
• Lighting control:
▪ Local Switch,
▪ Timer, photocell,
▪ Dimming,
▪ Sensors.
• Small power services:
▪ Single socket,
▪ Double socket,
▪ Power socket,
▪ Industrial socket.
• Conveying System:
▪ Vertical transportation
✓ Elevators
✓ Moving walks
✓ Escalators
➢ Protection:
o Lightening,
o Earthing.
20
Distribution notebook S’22 21
➢ Aspects, References:
1. Local regulation:
✓ Egyptian code,
✓ Electrical company regulation,
✓ Civil defense requirement.
2. International code, standards:
✓ IEC,
✓ IEEE,
✓ NEC,
✓ NFPA.
3. Additional requirements:
✓ Owner manuals,
✓ Code of practice.
➢ Design Tools:
✓ Lighting calculations:
• DIAlux, olyse…. etc.
✓ Network Analysis:
• Etap, Semaris, Ecodial etc.
✓ Generator sizing:
• GEN Size.
✓ Cable tray sizing:
• Tray Cad.
✓ Drafting & MTO:
• AutoCAD (2D), Revit (2D, 3D)
21
Distribution notebook S’22 22
➢ Earthing Calculations:
• Excel
➢ Lightening protection assessment.
• Excel
➢ Design Output:
• Drawing:
• BOQ(Bill of Quantity)
• Calculations:
1. Open-source drawing,
2. Pdf.
➢ Coordination with all trades:
▪ Internal coordination:
22
Distribution notebook S’22 23
▪ External coordination:
➢ Importance of coordination:
✓ Encourages team spirit,
✓ Leads to higher quality,
✓ Gives proper direction,
✓ Helps to achieve their missions quickly.
23
Distribution notebook S’22 24
Design Phases
25
Distribution notebook S’22 26
Load Estimation:
o Why load estimation is essential?
✓ Determine the spaces required for electrical substation and
rooms,
✓ Determine the rating of required bulk equipment and
switchgear,
✓ Apply for the permits of the project by providing the
assigned electricity company with total project load,
✓ Determine the primary electrical work cost.
26
Distribution notebook S’22 27
➢ Area:
✓ Plot area, A
✓ Footprint area, B
✓ Built up area. C
➢ Power Density:
✓ Power density: is a value that is multiplied by the area of a
room, space, or a building to transform this area into an
electrical load (KVA, KW) that to estimate the load
required for the project at the primary phase of design
before having the final load.
✓ Common Units: (VA/m2), (W/m2), (VA/ft2), (W/ft2).
✓ Power density value is obtained from code, standard,
regulation, (experienced electrical consultants).
27
Distribution notebook S’22 28
❖ Types of loads:
✓ Connected load:
• The sum of the continuous ratings of the power-
consuming apparatus connected to the system or any
part thereof in watts, kilowatts, or horsepower.
✓ Demand load:
• The electrical load at the receiving terminals averaged
over a specified interval of time, demand is expressed in
KW, KVA.
✓ Demand factor:
• The ratio of the maximum demand of a system to the
total connected load of the system.
• From NEC Table 220.42 Lighting Load Demand Factors
• Table 220 56 Demand Factors for Kitchen
Equipment. And so on...
https://drive.google.com/file/d/1q180dnYlZYSX7z0y_ZDdtof
xbFWmTytD/view?usp=sharing
✓ Diversity factor:
• The ratio of the sum of the individual maximum
demands of the subdivisions of the system to the
maximum demand of the complete system
28
Distribution notebook S’22 29
Overall method:
• Calculate the gross interior area of the building,
• Determine the load density according to type of the
building from tables (IEEE 241 Table 4, 5) link above.
• Multiply gross interior area by its load density to get the
estimated electrical load for this building.
* Note: Don`t Forget other discipline loads.
❖ Applying Egyptian code (chapter 3):
https://drive.google.com/file/d/1W7u1qhmIUWWl4Fsp5xlaCQ9zjfov
XZq4/view?usp=sharing
❖ Applying electrical companies’ regulation:
29
Distribution notebook S’22 30
Load breakdown.
• Divide the building into different spaces based on its
function (for example, office, storage, mechanical, and
corridor),
• Calculate the gross interior area of each space,
• Determine the load density for each space (from tables),
• Multiply each space gross interior area by its load density
to get the estimated electrical load for this space,
• Sum all the estimated electrical loads for all spaces to get
the total preliminary electrical load for the whole building.
Exact method:
• Divide the whole building loads into different types (for
example, Lights, Power, mechanical).
• Calculate the gross interior area of each building
• Determine the load density based on the building type
(from tables).
• Multiply gross interior area by each load type density to get
the estimated electrical load for this building.
➢ Very important note:
✓ “HVAC load equal to 60% of the building loads” means
if you have HVAC loads given from other discipline,
you must multiply the power density by 60%.
30
Distribution notebook S’22 31
✓ overall method:
✓ load breakdown:
31
Distribution notebook S’22 32
➢ Other discipline:
32
Distribution notebook S’22 33
Feeding System:
✓ According to Cairo Electric Distribution Company
(CEDC) there are four types of feeding systems according
to the load rating divided as follow: -
✓ 1st type – Used for loads less than 200 KVA so most usage
1st type to feed The Residential Areas.
✓ 2 Nd type – Used for 200 < loads < 1 MVA
✓ 3 rd. type – Used for 1 MVA < Loads < 5 NVA
✓ 4 th type – Used for loads > 5 MVA
33
Distribution notebook S’22 34
34
Distribution notebook S’22 35
Zoning:
It depends on
• Sufficient Electrical Rooms
• Branch Circuit Maximum Permitted Length
• Voltage Drop
❖ The building type and the area of the building
❖ Selection the number of electrical rooms and it is
position.
❖ The max voltage drop from transformer to the load is
5%
35
Distribution notebook S’22 36
36
Distribution notebook S’22 37
37
Distribution notebook S’22 38
Structure of Transformer:
• The transformer consists two inductive coils, these are
electrically separated but linked through a common
magnetic circuit. These two coils have a high mutual
induction,
• One of the two coils is connected to a source of alternating
voltage. This coil in which electrical energy is fed with the
help of source called primary winding(P), as shown in
figure,
• The other winding is connected to a load. The electrical
energy is transformed to this winding drawn out to the
load. This winding is called secondary winding(S), also as
shown in
figure
38
Distribution notebook S’22 39
Main Purpose:
• Step up: used to raise the value of the voltage to transmit to large
distance, we use it to also reduce the current to reduce cross section
area and power losses.
• Step down: used to reduce the value of the voltage to the amount
can consumers use it safely
• Isolated: used to make protection between two circuits if any fault
or damage in one of two circuit the other circuit still the same
without that damage
• we used core in limitations to reduce the Eddy current and
Hysteresis losses
Transformer operation
When applied voltage on primary side which make induced emf in other
side by the ratio E1/E2 =N1/N2.
39
Distribution notebook S’22 40
Types Of Transformers:
− Generally the transformer classify accordingly
transformation ratios are:
I. Step-up Transformer,
II. Step-down Transformer
1. Power transformer,
2. Distribution Transformer,
3. Isolated Transformer,
4. Autotransformer,
5. Leakage transformer,
6. Resonant transformer,
7. Earthing Transformer,
Oil Transformer:
➢ The figure shows the construction of distribution
transformers, which are as follows:
40
Distribution notebook S’22 41
42
Distribution notebook S’22 43
43
Distribution notebook S’22 44
Dry Transformer:
• Cast risen,
• Open ventilation.
44
Distribution notebook S’22 45
Important definitions
✓ Utilization factor: gives me number with it I can turn
on transformer continues without being problem in it,
oil 80%, dry 90%
45
Distribution notebook S’22 46
• IP (ingress protection):
✓ IP00: transformer has low protection because its
environment not wet or dusty (not common),
✓ IP21: commonly used in street, IP33: commonly used
in street, IP65: used in factors
• Per unit impedance: Z% total impedance of transformer
per unit value is very useful in short circuit calculation
• Vector Group (DYN11): delta star connection with
neutral with angle 11
Vector group gives us details we needed to know to can
connect parallel transformers together
• K factor: it is factor related to harmonics which
transformer can hold it, Harmonics is kind of
deformation happen in sin wave of voltage and
harmonics happened by power electronics which in
electrical equipment.
Transformer Tests:
1- General Checks,
2- Voltage /Turn Ratio,
3- winding resistance measurement,
4- Vector Group Test,
5- Insulation Resistance Test,
6- Short Circuit Test,
46
Distribution notebook S’22 47
Transformer Sizing
− Firstly, we will check the load estimation of the building
and if it’s greater than 250 KVA we calculate it as medium
voltage, and if it’s lower than 250 KVA we calculate it as
medium voltage and, in this case, the consumer will
purchase a transformer and ring main unit himself.
− Secondly, we multiply the connected load by the Diversity
factor which is chosen according to the type of the project.
− Third, we take the value equal to multiplying the diversity
factor by the connected load and we divide it by the
Utilization factor.
− Finally, we choose the suitable transformer from supplier
catalog, and we can also know the dimensions of the
transformer from the catalog as well.
47
Distribution notebook S’22 48
48
Distribution notebook S’22 49
GENERATOR.
✓ Principle:
• The principle of working of a generator is such that the
flow of electric charges can be induced by moving an
electrical conductor in a magnetic field.
• A DC generator operates on the principle of Faraday’s
laws of electromagnetic induction. According to
Faraday’s law, whenever a conductor is placed in a
fluctuating magnetic field (or when a conductor is moved
in a magnetic field) an EMF is induced in the conductor.
• If the conductor is guided with a closed path, the current
will get induced. The direction of the induced current
(given by Fleming’s right-hand rule) changes as the
direction of movement of the conductor changes.
49
Distribution notebook S’22 50
➢ Components:
• Diesel Engine: One of the significant parts of the
generator that produces mechanical energy is the engine.
Then enter to the Alternator and convert it to electrical
energy.
• Automatic control:
Automatic Generation Control (AGC) Is A System
for Adjusting the Power Output of Multiple Generators
at Different Power Plants, In Response to Changes in
The Load.
• Base:
Base Used in To Prevent Motion and Vibration in The
Generator Body.
• Water Tank Radiator:
Used To Dissipate the Heat Carried by The Cooling Water
into The Atmosphere to Lower the Temperature of The
Cooling Water.
➢ Classification:
o Stand By:
It’s a backup (Spare / Stand by) generator for the building
and its main function is that if the utility is cut off ’If the
main transformer is cutoff ‘.
o Loading Rate:
At average operation (70%) in the catalogues we have to
turn it on 200 hr. /year for lifetime warranty.
50
Distribution notebook S’22 51
o Prime:
Usually used as Primary ‘there’s no transformer’ so it
become the main source such as “project in desert like oil
field, remote agricultural area”.
o Loading Rate:
At Rated operation (100%) in the catalogues we have to
turn it on 500 hr. /year for lifetime warranty, and if we
want (110%) in catalogues we have turn it on 25 hr. /year
and for a day only two hours.
o Continuous
Used in a constant load ‘Critical usage’.
o Loading Rate:
o Frequency Dip:
Frequency dip is when the engine cannot supply enough
power (kW) to support the load demand, causing a reduction
in engine RPM. When frequency dips occur, the generator
will sense a need for more fuel to increase RPMs and will
bring it back up to speed (typically 1800 rpms for 60 Hz or
1500 rpms for 50 hertz). The lag time to recover as well as a
drop in hertz is referred to as a frequency dip. Most loads are
tolerant of a frequency dip up to 10 Hz, but some
technologies can be more sensitive.
51
Distribution notebook S’22 52
S
pace Program and Selection for Generator:
• First, we calculate the total loads and dividing by the
utilization factor.
52
Distribution notebook S’22 53
53
Distribution notebook S’22 54
AutoCAD plan
54
Distribution notebook S’22 55
UPS
− UPS is an acronym for "Uninterruptible power supply",
it is a panel whose source of supply in the normal case is
the transformer, and if it is in the building, it works
instantaneously when the electricity is cut off and becomes
the main source of nutrition in this case until the generator
enters.
− The concept of making this type of panel is that the first-
time alternating current is converted into direct current, the
second time, the constant current is used to charge several
batteries, and then the direct current from the battery is
converted to alternating current again.
− The advantage of using UPS is the Continuity of work
during a power outage, where in the event of a power
outage; the user can achieve any work he does without
wasting any saved data for a specified period.
55
Distribution notebook S’22 56
➢ Types of UPS:
a) Offline,
b)Hybrid,
c) Online,
d)Line Interactive Ups.
➢ UPS components:
• Rectifier: Where it converts the AC current coming from
the main supply source into a DC current to charge the
batteries.
• Batteries: Used to store DC current.
• Inverter: it converts the DC current into AC current for
feeding the load again.
• Switch: to switching between two sources when detecting
that no power Pass through the line switch from AC supply
switching to UPS system.
a) Offline Ups:
56
Distribution notebook S’22 57
58
Distribution notebook S’22 59
59
Distribution notebook S’22 60
Central battery
60
Distribution notebook S’22 61
➢ Function.
• A Central Battery System has a couple of advantages
over a self-contained Emergency Lighting System. Firstly,
because there are no batteries or super capacitors in the
luminaires themselves, there are fewer components to
maintain and service. This truly pays off, when the natural
life span of the batteries is coming to an end. With a
Central Battery System, the replacement of the batteries
can be done in one location, in contrast to Self-Contained
Emergency and Exit Lights, where the batteries must be
replaced one-by-one, in each luminaire.
61
Distribution notebook S’22 62
62
Distribution notebook S’22 63
➢ Sizing of UPS
• First, we should know the total demand load for UPS, and
then, we divide the value of the total load by diversity
factor = 0.8, and finally from the catalog, we get the width
& weight of UPS.
• For example: we have ups total critical load=40.455 kVA
• Then, we will divide the total load by 0.8
= 50.568 kVA
63
Distribution notebook S’22 64
64
Distribution notebook S’22 65
➢ Catalogs:
✓ Transformer:
• https://drive.google.com/file/d/1pUm0gjXd1ndJFnrLCHiC
g8-YXb7b4eCt/view?usp=sharing
✓ Generator
• https://drive.google.com/file/d/1mXklsA-
fYnaGeBCFPNkLozHT_OScNrUB/view?usp=sharing
✓ UPS
• https://drive.google.com/file/d/1rd-
VPSO3PaOsMl1Dovcc0YeuBZfr2JzC/view?usp=sharing
End of Ch_2
65
Distribution notebook S’22 66
Ch_3
Switchgear
1. Low Voltage switchgears:
➢ What is meant by switchgear?
• Switching/protection Point at different voltage levels to
provide security and privacy.
• Any electrical panel provides switching or protection or
control or both is switchgear, also P.F correction or
transition panel all this considered as switchgear.
➢ Switchgear components:
• Protection elements
- Overload
- Short circuit
• Switching elements
- Manual
- On load (LBS) & no load
(Isolators) disconnection
• Control elements
- Relay for control circuits (lower
rating than contactors) &
contactors for power circuits
- Selector switch & pushbutton
change the operation (on or
off...etc.)
- CT & VT transfer the high ratings to low ratings for the
relay of the C.B to take a decision (in MVSGs)
- Drives (mcc panels)
66
Distribution notebook S’22 67
• Measurements
- Calculate some features like (current, volt, P.F...)
and get these values from (CT & VT) measurements
• Indications
- Benefit to know if there is fault or power supply on or off
• Bus bars, cables, and wires
- Exist in any enclosure
• Terminal blocks and ducts
- Terminals for in and out cables
- Ducts for collecting internal wires to provide easy
maintenance
• Enclosure
- Outer frame that collects all previous elements
NOT NECESSARY FOR SWITCHGEARS TO HAVE ALL
THESE ELEMENTS
AND RATINGS WILL BE DIFFERENT FROM MV AND LV
BUT FOR MEASUREMENTS AND INDICITION NOTHING
WILL BE DIFFERENT
67
Distribution notebook S’22 68
• Construction
- Incoming cell W×D×H
(600*600*2000) mm
- Outgoing cell
(600+400) *600*2000 mm
- General section (can be p.f
correction)
(600/800/1000) *600*2000 mm
68
Distribution notebook S’22 69
Incoming
cell
Outgoing cell
• Main purpose
- Switching/protection point at different voltage level to
provide security and privacy
• Location
- MDB, SMDB, MCC, ATS, PFC (ACC. TO RATING)
• Rating
- 400/230 V, 6300 A(max)
• Connection
- Incoming cell: cable compartment can be up or down acc.
To the cell
- Outgoing cell: cable compartment can go up for cable trays
or down for cable trenches
• Rear access or Dead front
- Needs maintenance from behind or not (if main bus bar from
behind so it must be rear access)
“To make suitable sizing for LVSG you must know about LV
C.Bs which is installed in LVSG”
69
Distribution notebook S’22 70
LV C.Bs:
- MCB (up to 125A)
1pole=2cm*11c
m
Fixed size (no. of
poles=same size)
• Accessibility
- Dead front: main bus bar takes a place in top of the cell (no
need for back space)
Rear access: main bus bar takes a place in the back, so you
must take a back space for your maintenance needs
71
Distribution notebook S’22 72
• Form of separation
- This shows the separation of dropper bus bar and live parts
for
protection
• Form 2a
• Form 2b (Type 1 & Type 2)
72
Distribution notebook S’22 73
▪ Form 3
• Form 3a
• Form 3b (Type 1 & Type 2)
▪ Form 4
73
Distribution notebook S’22 74
• Layout
- Incoming MCCB
74
Distribution notebook S’22 75
- Front plate (cover the wires and mounting plate but not the
C.Bs)
75
Distribution notebook S’22 76
- Fish bone
i. Fixed width,
ii. Extension length
• Cut Sheet:
- Eaton Surface/Recessed Mounted Panel (fishbone example)
- Very important to know the depth of the wall in flush
mounting
76
Distribution notebook S’22 77
• Layout
-closet or room
“Area that is specified and safe for the operator for a safe
maintenance with no hazards”
-Influenced with main factors:
▪ Installation conditions
▪ Operating voltage to ground
78
Distribution notebook S’22 79
B. Dedicated Space
“Area specified for the electrical equipment”
-forbidden that any discipline gets in the dedicated space
even above the gypsum board if exist and not allowed to
get in the room anyway only if that discipline serves the
room
Note that the electric room and equipment must not be close to
wet areas from all directions.
C. Assembly Types:
✓ Dead Front
✓ Rear Access
79
Distribution notebook S’22 80
80
Distribution notebook S’22 81
➢ Condition_1
➢ Condition_2
➢ Condition_3
81
Distribution notebook S’22 82
wide
- Door Opening only 90 degrees
82
Distribution notebook S’22 83
- Overlapping
83
Distribution notebook S’22 84
84
Distribution notebook S’22 85
• Personal Doors:
- Opening Direction (to outside)
- Panic bars
- Self-latch
85
Distribution notebook S’22 86
86
Distribution notebook S’22 87
87
Distribution notebook S’22 88
• Example:
“A motor consumes 100 kW at a power factor of 0.75 (i.e.
tan ϕ = 0.88). To
Improve the power factor to 0.93 (i.e. tan ϕ = 0.4), the
reactive power of the
Capacitor bank must be:
88
Distribution notebook S’22 89
power
89
Distribution notebook S’22 90
Distributer.
90
Distribution notebook S’22 91
-Main Purpose.
Take The Power from two Sources (Stations) -To increase
reliability – and distribute this power to no. of RMU.
-Main Construction.
91
Distribution notebook S’22 92
92
Distribution notebook S’22 93
93
Distribution notebook S’22 94
94
Distribution notebook S’22 95
95
Distribution notebook S’22 96
• Rearcapture:
96
Distribution notebook S’22 97
Battery
Battery charger
Its use is to charge the batteries and feed the protective devices as
long as they are fed through the auxiliary transformer located in the
distributor building. If the auxiliary transformer is disconnected the
feeding will be from batteries.
• Indoor:
97
Distribution notebook S’22 98
-
Construction:
98
Distribution notebook S’22 99
-location:
99
Distribution notebook S’22 100
100
Distribution notebook S’22 101
-RMU Constructions:
(3-way-In/OUT/Feeder-)
101
Distribution notebook S’22 102
(4-way)
-Cut sheet:
*ABB (GIS-RMU):
102
Distribution notebook S’22 103
-Layout:
(GIS)
103
Distribution notebook S’22 104
(AIS)
End of Ch_3
104
Distribution notebook S’22 105
Schematic Design
Ch_4
Lighting and small power design
INDOOR LIGHTING DESIGN
➢ What is light?
Light are Electromagnetic waves having a specific
wavelength between 380 and 750 nm which is visible to the
human eye.
➢ Why we light up the place:
To lighting and show the beauty of the place.
105
Distribution notebook S’22 106
106
Distribution notebook S’22 107
✓ Illuminance (E)
• quantity of light falling on a unit of surface,
• Unit: lm/m² (lux)
✓ Types of Illuminance:
• Horizontal Illuminance: when the surface on which
the light falls is horizontal, as the case with desks and
floors
107
Distribution notebook S’22 108
✓ Luminance (L)
• Luminance is the amount of light that the eye perceives
after it strikes a given surface. Measures the brightness of
a light source after it strikes,
• Unit:
cd/m2
✓ Luminous Efficacy:
108
Distribution notebook S’22 109
✓ Glare :
• Caused by excessive and uncontrolled brightness between
two different surfaces. It can be disabling or simply
uncomfortable.
❖ There are two forms of glare:
• Disability glare is the reduction in visibility caused by
intense light sources in the field of view
• discomfort glare is the sensation of annoyance or even
pain induced by overly bright sources
109
Distribution notebook S’22 110
✓ Color Temperature :
• color temperature describes the light color of an
artificial light source,
• Unit: (°K)
110
Distribution notebook S’22 111
➢ Beam angle
• The beam angle of a lamp is the angle at which the light is
distributed or emitted.
• Equal to double the angle between the max. Luminous
intensity and half the max Luminous intensity
111
Distribution notebook S’22 112
➢ Classifications of Luminaires
✓ Surface Mounted Luminaire :
• Surface mounted lights are mounted directly on the
ceiling
112
Distribution notebook S’22 113
• Suspended Luminaire:
114
Distribution notebook S’22 115
115
Distribution notebook S’22 116
• Hay bay
➢ Used in a large area with high ceilings at range of 20
feet to 45
• Up light :
➢ Used for decoration in public areas, have a high Ik to avoid
shocks
116
Distribution notebook S’22 117
• Flood Light :
➢ Usually use in stadiums and open areas .
117
Distribution notebook S’22 118
118
Distribution notebook S’22 119
❖Surface:
• This is the conventional type of ceiling.
• Used in homes
❖Recessed.
• Recessed ceiling used to hide ducts and cables in case of
using central air conditioning.
• Consists of slabs usually 30x60 or 60x60 cm
• It usually used in factories and any places have central air
conditioning
• Built in a distance between (0.6:1) m from concrete
119
Distribution notebook S’22 120
120
Distribution notebook S’22 121
121
Distribution notebook S’22 122
122
Distribution notebook S’22 123
Filament lamps
➢ Incandescent
➢ Halogen (tungsten)
Gas discharge lamps
➢ Fluorescent
➢ High pressure sodium
➢ Low pressure sodium
➢ High pressure mercury
➢ Metal halide
LED
123
Distribution notebook S’22 124
• Filament lamp:
➢ Theory of operation
• Contains a thin coil of wire called the filament. This heats
up when an electric current passes through it and produces
light as a result.
➢ Types of filament lamp
• Incandescent lamp
• halogen lamp
❖ incandescent:
➢ theory of operation:
• When an object is made hot, the atoms inside the object
become thermally excited. The outer orbit electrons of the
atoms jump to higher energy level due to the supplied
energy. The electrons on these higher energy levels are not
stable; they again fall back to lower energy levels. While
falling from higher to lower energy levels, the electrons
release their extra energy in a form of photons. These
photons are then emitted light.
✓ The filling gas (argon, nitrogen)
✓ Color: warm white (2600:2900) k
✓ Short Lifetime (1500)
➢ The advantages:
• Used as decorative lamps
• It is available in various shapes, sizes, and applications.
• It can be switched ON immediately.
124
Distribution notebook S’22 125
• It is not expensive
➢ disadvantages
• It is energy inefficient.
• It is warm source of light and hence requires air
conditioning to cool the room.
• It generates low lumen per watt. Ordinary incandescent
bulbs produce about 5 to 20 lumens per watt. This means it
has lower efficacy.
❖ Halogen lamp :
✓ Its theory of operation is same as the incandescent lamp,
but it’s painted by halogen to length its lifetime.
✓ Used in shops, landscape, and gallery
✓ Short lifetime 2000hrs
✓ Warm white (3200) k
➢ Advantages:
• Compact size: The small and varying shapes of halogen
bulbs makes them excellent choices for low smaller
fixtures, and they can direct light in spot beam angles.
• Dimmable: Halogen bulbs dim very well making them
excellent for homes and restaurants
• High CRI = 100
➢ Disadvantages
• More costly than incandescent
• Emit a LOT of heat. It can be very uncomfortable to sit
under halogen bulbs in a kitchen, workspace etc.
• Cannot be touched with hands
125
Distribution notebook S’22 126
Low-pressure Discharge
• Low-pressure lamps have working at pressure less than
atmospheric pressure. Like the fluorescent lamps, and the
sodium lamps. They have a long-life span
126
Distribution notebook S’22 127
✓ Fluorescent lamps
• Was the most common lamp in office lighting and many
other applications,
• Fluorescent lamps work by ionizing mercury vapor in a
glass tube. This causes electrons in the gas to emit
ultraviolet radiation and the pusher coating absorbs this
UV radiation and emit visible light.
• It produces up to 100 lumens per watt and operates at a
pressure about 0.3% of atmospheric pressure.
✓ Types of Fluorescent :
1. Taupe compact
127
Distribution notebook S’22 128
High-Pressure Discharge
✓ The working pressure of these lamps is higher than
the atmospheric pressure.
✓ There are Different categories in this type such as metal
halide lamps, high-pressure sodium lamps, and high-
pressure sodium mercury lamps.
1. High-pressure sodium
✓ More expensive than low pressure
✓ Color: yellow (has the ability penetrate fog)
✓ USED: - Street lighting, Commercial areas - plant growing
in green house
128
Distribution notebook S’22 129
129
Distribution notebook S’22 130
✓ This lamp type is the oldest high pressure lamp type, being
replaced in most applications by the metal halide lamp
✓ Light Color: white
✓ CRI: 40:50%
✓ Efficiency: Low Efficiency (30 to 65 lumen/Watt)
✓ Used (App): For outdoor areas/ parking, streets, farm light
and factories
✓ Lifetime: 8000:1000hrs
✓ Starting: take 4 min to reach to 80% of its light
The difference between high- and low-pressure
sodium
LOW HIGH
Energy Efficiency More efficient less efficient
CRI 0 20:80 %
Starting 10:20 2:4
Lifetime 15,000 to 20,000 6,000 to 24,000
Hours hours
130
Distribution notebook S’22 131
❖ LED
➢ Theory of operation
• The P-N junction emits light when electrical energy is
applied to it.
How??
✓ When a voltage is applied across the p-n junction from the
electrodes. electrons combine with holes at the p-n junction
✓ Thus, the energy level of the holes will be lesser than the
energy levels of the electrons. Some portion of the energy
must be dissipated to recombine the electrons and the holes.
This energy is emitted in the form of light.
131
Distribution notebook S’22 132
➢ Types of LED
1) Tube,
2) Compact
➢ advantages
• High efficacy (lumen/watt)
• High lifetime up to 70,000hr
• Low temperature
• Different colors (RGB)
• No maintenance
• Color Rendering up to 90%
• Small Size
132
Distribution notebook S’22 133
❖ Control Gear
Ballasts
✓ If you outfit your buildings with fluorescent, HID, or plug-
and-play linear LED lighting, you depend on a device
called ballast.
✓ Ballast is used to control, regulate, and ultimately stabilize
the light output of the lamp.
133
Distribution notebook S’22 134
❖ Type of ballast:
➢ Magnetic Ballast
❖ Electronic Ballast
❖ LED Drivers
➢ The LED driver used to drive the
power that is being given to the
LED.
➢ While LED work on DC power at
low voltage between (2:4) v. we use
drivers to convert AC into DC and
help to keep them protected from
any power surges that might occur.
134
Distribution notebook S’22 135
135
Distribution notebook S’22 136
DIALux Red
Steps for distributing lighting by the DIALux program.
1. Make sure that cad is saved in 2007 model and the building
is exploded.
2. Import the cad file to DIALux from file list then select
import dwg file (which refers to the cad file and select the
unit of cad file then press finish.
136
Distribution notebook S’22 137
137
Distribution notebook S’22 138
138
Distribution notebook S’22 139
139
Distribution notebook S’22 140
10.Then view the report which contains the average lux and
uniformity.
140
Distribution notebook S’22 141
141
Distribution notebook S’22 142
142
Distribution notebook S’22 143
DIALux Evo
❑ The difference between EVO and red
- In EVO we can see the whole building in 3D and with all
floors not only one floor
- There is interaction between indoor and outdoor scenes
- We can import IFC (for BIM tools as Revit)
- In EVO the standard of lighting is being set in setting
without returning to catalogs
• Note:
“Before inserting your plan on DIAlux Evo makes sure that
you do these following orders on AutoCAD:
1. Explode all blocks,
2. Purge all object,
3. Overkill all plan.”
143
Distribution notebook S’22 144
144
Distribution notebook S’22 145
145
Distribution notebook S’22 146
146
Distribution notebook S’22 147
• Set your
coordinates,
147
Distribution notebook S’22 148
148
Distribution notebook S’22 149
149
Distribution notebook S’22 150
• Draw your
rooms,
• From “space tap” can edit your rooms name, height, wall
zone, work plan height, room
application,
150
Distribution notebook S’22 151
• As you see
151
Distribution notebook S’22 152
• From “celling tap” you can draw celling if Evo can’t read
your plan celling
152
Distribution notebook S’22 153
153
Distribution notebook S’22 154
154
Distribution notebook S’22 155
155
Distribution notebook S’22 156
156
Distribution notebook S’22 157
•
• Light scene to make emergency or normal lighting fixture,
157
Distribution notebook S’22 158
• Note: You can control what layers that you need to appear in AutoCAD file.
158
Distribution notebook S’22 159
• Note: You can download any catalog for luminaires or furniture or any material in
DIALux from this tab.
159
Distribution notebook S’22 160
Note,
160
Distribution notebook S’22 161
Lighting In CAD
Legend:
161
Distribution notebook S’22 162
162
Distribution notebook S’22 163
163
Distribution notebook S’22 164
Small power
1. General use:
Such as: the normal use in normal conditions.
2. According to furniture
In places that we can’t but the normal sockets because of
furniture
3. Special uses:
In factories, kitchen, hospitals…...
➢ Sockets
• One of Electrical Outlets (Connection Devices) to connect
the machine into electricity
164
Distribution notebook S’22 165
• Surface mounted
• Flush mounted
• Normal
165
Distribution notebook S’22 166
• Switched
❖ In Egypt:
I. Past: using type C
II. Nowadays: using type F
4. Normal sockets
166
Distribution notebook S’22 167
6. POWER SOCKETS
167
Distribution notebook S’22 168
168
Distribution notebook S’22 169
8. INDUSTRIAL SOCKETS
169
Distribution notebook S’22 170
12. FURNATURE
BOX
170
Distribution notebook S’22 171
15. BHU
• It used in a
hospitals
171
Distribution notebook S’22 172
172
Distribution notebook S’22 173
Types of switches
1. One way one gang switch
The single pole switch is the general-purpose workhorse of
switches. Single pole switches turn a light, receptacle or device
on and off from a single location. A characteristic of a single
pole toggle switch is that
It has an on and off marking on the switch
173
Distribution notebook S’22 174
The following switches are some types but not used in low
medium voltage but uses in DC current
4. Single pole, single throw switch(SPST)
174
Distribution notebook S’22 175
175
Distribution notebook S’22 176
Pressure switch
Temperature switch
176
Distribution notebook S’22 177
Float switch
Disconnect Switch
Any machine needed to switch off the power on it for any reason
to clean it or to fix it, there are so many reasons to turn off power
so that we need to use Switch to connect or disconnect power,
Disconnect Switch (Insulator, Load break switch)
Insulator: mainly used as the main switch in low voltage and
isolating loads during maintenance only
Operation on: no load
No fuse inside it
Rated current: 16, 20, 25, 32, 40, 63, 80, 100, 125, 160A
Load Break Switch
Switches are designed to isolate an electrical circuit from power
source under load condition (can be closed or open on existing
energized line)
As insulator but can be switching from it because operates on
load, have Fused inside it
177
Distribution notebook S’22 178
178
Distribution notebook S’22 179
MEP
• In first, what does MEP refer to?
✓ In the construction world, it refers to “Mechanical,
Electrical, Plumbing”
179
Distribution notebook S’22 180
1. HVAC SYSTEM
“Heating Ventilation Air Condition”
180
Distribution notebook S’22 181
1.1.1 DX system
"Direct Expansion Systems"
➢ It consists of 3 categories:
- Split unit:
-Its application:
181
Distribution notebook S’22 182
- Package unit:
➢ Electrical feeding:
- VRF/VRV
182
Distribution notebook S’22 183
➢ System Components:
• Roof top condensing unit
• Indoor units
• Piping
➢ Electrical feeding:
183
Distribution notebook S’22 184
• Air cooled
• Water cooled
2-Absorption chillers (Gas Driven)
A) Air cooled:
The same cooling cycle but with the heat out of the condenser
➢ System components:
• Chiller
184
Distribution notebook S’22 185
• Water pump
• FCU or AHU for large space
➢ Electrical feeding:
B) Water cooled
• Same as air cooled but with
additional cooling tower to
increase system efficiency
➢ System components:
• Chiller
185
Distribution notebook S’22 186
• Water pump
• FCU or AHU for large space
• Cooling tower
➢ Electrical feeding:
186
Distribution notebook S’22 187
1.2 VENTILATION
• A general ventilation system may also be used to control
temperate and humidity within the workplace. General
ventilation is sometimes called dilution ventilation or fresh
air ventilation.
➢ Electrical feeding:
187
Distribution notebook S’22 188
188
Distribution notebook S’22 189
(LSF0H)
2.1 water
system
• Sprinklers: it detects
heat and then increase
pressure and it works
on the exit of water
and extinguishing the
fire.
189
Distribution notebook S’22 190
➢ System Components
• Primary pump (operation)
• Secondary pump (stand by)
• Jockey pump
➢ Electrical feeding:
190
Distribution notebook S’22 191
3. Plumping system
3.1 Domestic water supply
• we use it mostly for residential buildings and there are two
types of it:
191
Distribution notebook S’22 192
3.2 Drainage
Drainage pump:
192
Distribution notebook S’22 193
3.3 Irrigation
4. Low current
• It is a small current for some special systems inside
the building as
193
Distribution notebook S’22 194
4.3 CCTV
It is a “closed circuit television”
194
Distribution notebook S’22 195
➢ Practical on Revit:
✓ Distribute sockets as you see as a designer and
according to NEC code (single socket 180 VA, duple
socket 360 VA), furniture.
✓ Then call the circuit as (1R, 1Y, 1B, 2R, 2Y, 2B, and so
on) for single phase.
✓ Then call the circuit as (1R Y B, 2R Y B, and so on) for
three phases.
✓ Remember, according to the Egyptian code, that one
circuit is 2000 VA
✓ Remember; draw the legend on cad by symbol’s
definitions.
✓ MEP loads is feeding from LBS (normal, Emergency,
UPS according to other sections required)
✓ Then create the panel schedule and consider the
unbalanced percentage.
✓ Light current loads are feeding from power socket
(UPS).
✓ Pressurized fan, exhaust fan is feeding from
(Emergency).
✓ Fire pump is feeding from (Normal, Emergency by
ATS).
✓ Smoke fan is feeding from (Emergency).
195
Distribution notebook S’22 196
Practical on CAD:
1. Small power
1. We distribute sockets according to furniture, whether the sockets
are double or single.
According to NEC code (single socket 180 VA, duple
socket 360 VA), furniture.
LEGEND:
196
Distribution notebook S’22 197
End of Ch.4
197
Distribution notebook S’22 198
Ch.5
Power Cable & Circuit Breaker
1. Circuit Breaker:
• An electrical circuit breaker is a switching device that can be
operated automatically or manually for protecting and
controlling the electrical power system .it prevent situations
which simply cut off the remaining circuit such as short
circuit and overload
198
Distribution notebook S’22 199
❖ Trip curve.
199
Distribution notebook S’22 200
• Vacuum C.B,
• Oil C.B,
• Air C.B.
2- Low voltage
• MCB (Miniature Circuit Breaker),
• Air C.B.
200
Distribution notebook S’22 201
Types of MCB:
201
Distribution notebook S’22 202
• (3:4) poles
• May be adjustable
202
Distribution notebook S’22 203
203
Distribution notebook S’22 204
204
Distribution notebook S’22 205
❖ Selectivity:
➢ If selectivity is provided:
When a fault occurs (Overload or Short-circuit) The protection
device closes to the fault open,
➢ If selectivity is NOT provided:
When a fault occurs (Overload or Short-circuit) Both the
upstream & downstream protection devices could open.
According to IEC60947-2
• Total selectivity: over-current selectivity where, in the
presence of two over-current protective devices in series,
the protective device on the load side effects the protection
without causing the other protective device to operate,
•
• Partial selectivity: over-current selectivity where, in the
presence of two over-current protective devices in series,
the protective device on the load side effects the protection
up to a given level of over-current, without causing the
other protective device to operate.
2. Power Cable:
The function of Cable is
• Transmit power
• Distribute power
❖Classification of power cables
➢ Classification of MV cables:
✓ Conductor:
• AL
• CU
207
Distribution notebook S’22 208
• PVC, its contains & protect all cable layers and its
metallic part from corrosion
Classification of LV cables:
208
Distribution notebook S’22 209
✓ Conductor:
• AL
• CU
✓ Insulation or dielectric
• PVC (Polyvinyl Chloride)- “Thermoplastic”
• XLPE (Cross linked polyethylene) – “Thermoset”
✓ Assembly or filler
• PVC or polypropylene to fill spaces between cores to make
the round form of cable
✓ Bedding (inner jacket) (inner sheath)
• PVC bedding, are mandatory in case of armored cables
• Used under cable armoring to protect the laid-up cores and
as a separation sheath
✓ Armoring
• Is used for protection of cable against mechanical stresses
• Steal Tap or Steal Wire
✓ Outer jacket or outer sheath
• PVC, its contains & protect all cable layers and its metallic
part from corrosion
209
Distribution notebook S’22 210
210
Distribution notebook S’22 211
211
Distribution notebook S’22 212
212
Distribution notebook S’22 213
213
Distribution notebook S’22 214
relation:
214
Distribution notebook S’22 215
215
Distribution notebook S’22 216
216
Distribution notebook S’22 217
3. Fire Cables
❖ INTRODUCTION:
• In a fire accident some people die because of the fire,
but the majority dies because of the smoke.
• Halogen is added to the plastics used in conductor’s
insulation to give it the property of self-extinguish
such as PVC which contain chlorine atom. Chlorine is
one of halogens as Fluorine, Bromide, and Iodine.
But, in case of fire, halogens produce great amount of
smoke which contains that hamper visibility required for
escaping from a dangerous places or trying to find an exit
out.
• (HCI, CO & CO2) which are produced while a
conventional cable is burning out, dissolves in the fluids of
the human body organs like lungs, nose and eye causing
cell damage, shortage of oxygen and suffocation.
217
Distribution notebook S’22 218
➢ LSFH VS PVC:
218
Distribution notebook S’22 219
219
Distribution notebook S’22 220
220
Distribution notebook S’22 221
221
Distribution notebook S’22 222
222
Distribution notebook S’22 223
New
R BROWN
S BLACK
T GREAY
N BLUE
P. E YELLOW AND GREEN
Sizing of Cable:
You should apply this equation,
Where:
: load current at normal conditions.
224
Distribution notebook S’22 225
• According to NEC
The steps are same as IEC but this standard considers any load,
which is operated 3 hours or more daily, is a continuous load so,
it is necessary to load C.B with 80% by multiply the load current
by 1.25
So, we show now the summary of feeder sizing and voltage
drop calculations:
1. Calculate load current (Ib)
225
Distribution notebook S’22 226
And select the rated current which is directly greater this value.
226
Distribution notebook S’22 227
Panel schedule:
227
Distribution notebook S’22 228
228
Distribution notebook S’22 229
https://drive.google.com/drive/folders/1LQEdMbfMW0Z
qKcJUjVJnljC6VxdimK-f?fbclid=IwAR0cdif-
qugnQexluQb_M2lp3mFee8i_nRdJq9qMyzOJpPzuopxG
7m5uwgs
229
Distribution notebook S’22 230
➢ Types of Routing
✓ Cable tray:
• Used for power cables above false ceiling in corridors and
entrances but can also be exposed in service places like
electric rooms and garages.
✓ Cable Ladder:
• Used for large power cables and at building risers. More
stronger than trays, can hold more cables and also used for
heavu=y cable like MV cables from RMU to Transformer
✓ Wire basket:
• Keep cables cool by allowing air to flow freely, and
dissipate heat.Also known as datacenter trays.
✓ Cable trunk:
• Used for power and data cables above false ceiling at free
return HVAC system or under raised floor.
230
Distribution notebook S’22 231
✓ Cable Accessories:
231
Distribution notebook S’22 232
232
Distribution notebook S’22 233
233
Distribution notebook S’22 234
✓ After calculating the width and height for the cable tray, we
need to check a standard for the suppliers and get the next
value for my needs. As an example, if the width calculated
is 520 mm so I get a cable tray its width is 600mm and so
on.
✓ But what if I have 960 mm width and I need a cable tray fit
with it? Commonly width up to 800 mm but here I need
234
Distribution notebook S’22 235
235
Distribution notebook S’22 236
➢ Conduit Types
a. (UPVC) unrecycled Poly Vinyl Chloride: Used for
embedded routes or above false ceiling at ducted return
HVAC system.
236
Distribution notebook S’22 237
c. RGS -
Rigid Galvanized Steel: Used for exposed routes at damp or
wet areas like Electrical, Machine, water rooms
237
Distribution notebook S’22 238
PRACTICAL ON CAD
First after making sure that all bulk and switchgear in their final
location in the building and check the block diagram for SLD, we start to
predict and imagine the route of trays and ladders in building.
- first with the trenches coming from utility to RMU (orange arrow)
then continue to the transformer and take the cable up on a cable
ladder to the trans terminations (red arrow).
Do the same thing and check SLD to make a full vision for cable routing
for the whole building to know how many cables walk together in the
same tray and what accessories you need… and so on.
- SLD sample
238
Distribution notebook S’22 239
239
Distribution notebook S’22 240
pw2tv/view?usp=sharing
240
Distribution notebook S’22 241
Voltage Drop
241
Distribution notebook S’22 242
242
Distribution notebook S’22 243
❖ Where:
• V.D = Voltage Drop (v
• (mv/A/m) = specific voltage drops
• L = cable length (m)
• Ib = Base current or load current (A)
❖ NOTE:
✓ The previous lows are for individual V.D
✓ Accumulated V.D = Individual V.D + Up stream voltage
drop
243
Distribution notebook S’22 244
244
Distribution notebook S’22 245
Short Circuit
• A short circuit is an abnormal condition in an electrical
circuit where the electrical current flows through an
unintended, shorter pathway instead of following the
circuit.
➢ What Causes Short Circuits
Short circuits can be caused by:
245
Distribution notebook S’22 246
❖ Where:
• Vn.L = No load (L-N) secondary voltage of distribution
transformer (V)
• Zt = Total impedance contributing to s.c level (m.Ω)
246
Distribution notebook S’22 247
247
Distribution notebook S’22 248
➢ Cable Impedance:
❖ Where:
• Rc = Cable resistance (Ω)
• ρ = Resistivity constant of conductor material (mΩ.mm2
/M)
• 𝜌𝑐𝑢 = 23.69 mΩ.mm2 /M
• 𝜌𝐴𝑙 = 37.65 mΩ.mm2 /M
• L = Cable length (M)
• A = Cross sectional area (mm2)
248
Distribution notebook S’22 249
➢ Solved Example:
https://drive.google.com/file/d/1kBOOZTmClDwIL3WaRR0_tE
FGAMGIK-dm/view?usp=sharing
249
Distribution notebook S’22 250
ETAP
To create a new project:
1. Select “NEW”
2. Name the project and enter its location, and select
Metric system
250
Distribution notebook S’22 251
251
Distribution notebook S’22 252
252
Distribution notebook S’22 253
253
Distribution notebook S’22 254
254
Distribution notebook S’22 255
255
Distribution notebook S’22 256
15. On capacity:
-select the cable on tray or buried
- The operating temperature
NO. of circuit
256
Distribution notebook S’22 257
257
Distribution notebook S’22 258
258
Distribution notebook S’22 259
the calculation:
259
Distribution notebook S’22 260
the calculation:
260
Distribution notebook S’22 261
261
Distribution notebook S’22 262
262
Distribution notebook S’22 263
300 KVA to 500 KVA they negotiate with you if it’s able for
you to prepare the room and they get you the bulk equipment.
More than 500 KVA you will feed from MV tie-in.
➢ Important Definitions:
263
Distribution notebook S’22 264
Radial Ring
To speak about electrical equipment in infrastructure works,
we will highlight on each equipment.
264
Distribution notebook S’22 265
C. Main substations:
There are 3 types of substations to be mentioned.
1. Unit substation:
265
Distribution notebook S’22 266
(KIOSK):
RMU + Transformer +
LV
3. Room substation:
• Separate indoor substation (3 or 2 rooms) each room 5*4m
• It’s important about location to take
it in consideration, locate it in the
middle of zone, located in a main
road not less than 7 m.
D. RMU:
Connect the transformer on the MV loop.
- 2+1 way (most common)
- 2 incoming (LBS 630A) and 1 feeder
(LBS 630A + H.R.C.F) for Trans
*If transformer rating is higher
than 1.5 MVA it will be C.B
instead of fuse. *
266
Distribution notebook S’22 267
E. MV Distributer
(primary):
- 2 types (16 cell-14 cell)
- 22KV→30MVA ...
11KV→15MVA
- Distributer can have 5 loops
267
Distribution notebook S’22 268
268
Distribution notebook S’22 269
• Roads department:
- Signage and Road section with street lighting
269
Distribution notebook S’22 270
• Infra department:
- a coordination between all trades for the underground
corridors to divide it between them each section has his own
infrastructure need like utility, street lighting, irrigation, and
sewerage system.
270
Distribution notebook S’22 271
• Landscape department:
- Hardscape (sidewalk and walkway(
- Soft cape (trees and buried cables)
271
Distribution notebook S’22 272
Ch_6
EARTHING PROTECTION SYSTEM
&
LIGHTNING PROTECTION SYSTEM
1. EARTHING
- What is the meaning of earthing?
The process in which the instantaneous discharge of the
electrical energy takes place by transferring charges directly to
the earth through low resistance wire. Performed by a
connection of metal objects to a ground network through an
electrode and cable to provide a path for the leakage current
(caused by breakdown of insulation) and protect people from
electrical shock.
272
Distribution notebook S’22 273
ground?
- Importance of Earthing System:
• Provide a path for leakage current and protect people from
electric shock.
• Provide a path for the short circuit current to return to the
source and protect the equipment windings.
• It prevents the risk of fire hazards that could otherwise be
caused by the current leakage.
• Create a point with zero voltage (voltage of earthing
system).
• Protection against faults (Indirect Contact-Direct contact-
Over Current- Under Voltage-Over Voltage-Thermal
effects).
➢ Types of Electrical Shocks:
• Direct (touch line without insulation).
• Indirect (touch machine have electric charges ‘leakage’ on
it)
• Step (The difference in surface potential experienced by a
person bridging a distance of 1 meter with the feet without
contacting any other grounded object)
273
Distribution notebook S’22 274
➢ Definitions:
1. Step Voltage:
The difference in surface potential experienced
By a person bridging a distance of 1 M with the feet with
out
Contacting any other grounding object.
2. Touch Voltage:
The potential difference between the mesh and
A point in the surface. The grounded metallic masses are at
Mesh voltage, since they are jointed through connections
of
274
Distribution notebook S’22 275
Great section.
3. Metal to Metal Touch Voltage: The difference in
potential between metallic objects or structures within the
substation site that can be bridged by direct hand-to-hand
or hand-to-feet contact.
4. Transferred Voltage:
A special case of the touch voltage where a voltage is transferred
into the substation from a remote point external to the substation
site (through any metallic conductor).
- Don’t forget that earthing not only to make a path with low
resistance for leakage current but also to make an
equipotential between equipment either it carries current or
not
• Circuit protective conductor
276
Distribution notebook S’22 277
So, first we check the CSA of the power cable and then follow the
next tables:
277
Distribution notebook S’22 278
278
Distribution notebook S’22 279
279
Distribution notebook S’22 280
An air terminal rod is put next to every collection of equipment and check
that the
According to NFC102:
It is not necessary to put any additional rods, but at least the early steamer
must be
Notes
280
Distribution notebook S’22 281
281
Distribution notebook S’22 282
The higher the class is, the higher size of cone is. The
size of conical shape can be increased by lengthening
the rod or using two rods instead of one.
In this code, the mesh system is made on the roof and their slabs’
dimensions are determined according to the class of protection as shown
at the following figure:
It can be put air terminal rods on the mesh network and the distance between them is
15 m, if the rods’ height is 30 cm. The distance between them is 20 m, if the rods’
height is 50 cm. This system most used in gulf countries.
According to NFC102:
282
Distribution notebook S’22 283
In this code, one rod is used with a device at the top of the rod there is
a sensor sense the lightning and attract it. This rod covers the building
in a conical shape to protect all of the area under this conical shape
(zone of protection) as shown at the following figure.
283
Distribution notebook S’22 284
Earthing Systems:
284
Distribution notebook S’22 285
• Power Earthing
It is the grounding of the transformer's neutral point to provide a path for
the leakage current to return to the source and single line to ground current
fault.
1. Solidly: earthing the neutral point of transformer with just the main
earthing cable CU/PVC, this way is done in distribution transformers
(22KV/0.4KV or 11KV/0.4KV)
Keeps the Voltage of healthy phases of trans (for consumers in the
Y connection) is the same in case of line to ground fault happened then no V is
Changed in Neutral point when the fault current return to the source because
285
Distribution notebook S’22 286
In this way u will find that (Vn= I*R) voltage exist in neutral will
cause that voltage of healthy phases increase.
• Protective(safety) Earthing
First, we need to know some key letters to
understand how to describe the earthing system in the
source side and costumer side following this simple picture:
We have 5 different ways to provide safety
earthing
286
Distribution notebook S’22 287
1. TN-S
Source is earthed solidly and going from source to the consumer
with separate neutral plus protective earth (CPC). High cost because
you will get for each power cable a cable for earth.
2. TN-C
Source is earthed solidly and going from source to the consumer
with combined neutral and protective earth (PEN=N+CPC).
Neutral do the function of protective earth (it’s dangerous for the
neutral to have a leakage current in it but they do it for cost).
Also, BS7671 code forbids the use of RCDs in TN-C systems.
This is because the PEN conductor which in a TN-C system
would go through the RCD, so the RCD would not detect an
earth fault because the earth fault current would return down the
PEN and would not cause an imbalance in the RCD. The result
of this means that the RCD would not provide any protection.
287
Distribution notebook S’22 288
3. TN-C-S
Source is earthed solidly and going from source to the consumer with
combined neutral and protective earth (PEN), but get separated in the
consumer ‘having PE from neutral in building’s boundary’. This can be
done if the consumer wants more safety for the building and it’s also
economical.
4. TT
Source is earthed solidly but the consumer has his own earthing
network.
288
Distribution notebook S’22 289
5. IT
Best safety earthing because it’s almost having no leakage current (there
is open circuit in IT system). Used in airports and hospitals cause some
loads shouldn’t be off.
Steps:
289
Distribution notebook S’22 290
ways we mentioned).
2. Get the sizing main earth cable ( )
and choose the next rating from SWEDEY catalog table of
290
Distribution notebook S’22 291
getting R rod
getting R cable
291
Distribution notebook S’22 292
And don’t forget if you did not achieve the desired R ground,
there are some factors you can edit to reach a good earthing
system for your boundaries:
- Increase the length of the ground rod
- Increasing the diameter of the grounding rod
- Increasing the number of ground electrodes
Also if you have sandy soil or rocky with high resistivity, why
don’t you use the ‘GEM’?
BS7430 EARTHING CODE:
https://karbaladha.com/wp-content/uploads/2016/10/BS-
7430.pdf
292
Distribution notebook S’22 293
2. LIGHTNING
- What is the meaning of lightning and what causes it?
Lightning is a natural electrostatic discharge that forms during a thunderstorm,
electrical spark(bolt) forms as the electrons move from one object to another
discharging the excess electrons (ex: clouds to ground).
This occurs by the electric field which occurs by accumulation of negative
static
charges on clouds and positive static charges on buildings, so an electric field
occurs between them because of the difference of voltage. This represents a
capacitor. When the electric field exceed 30 KV, air is converted to be a
conductor and then the current, passing from the clouds to the building, appears
in a lightning form and the air temperature raises to 30000⸰c.
293
Distribution notebook S’22 294
• Air-termination system
• Down conductor
• Earth-termination system
-Risk Assessment
Calculations (Acc. To
NFC102-NFPA780):
295
Distribution notebook S’22 296
The (C3) coefficient that sees the contents within the structure.
The (C5) coefficient that sees the consequence of the loss of operations of
the structure.
And the result will show whether the LPS should be installed or not.
site captures:
According to NFC102:
At every early steamer, the down conductor is put from roof to an earthing
equilateral
triangle.
Note:
297
Distribution notebook S’22 298
298