Example of Gantt Chart For Small Building Construction Project

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
61 views2 pages

Example of Gantt Chart For Small Building Construction Project

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Example of Gantt Chart for Small Building Construction Project

Here's a breakdown of tasks with estimated durations for a small building construction project. The
Gantt chart visually represents the timeline for the tasks involved.

Project Overview:

Project Name: Small Building Construction


Duration: 6 months
Start Date: January 1, 2024
End Date: June 30, 2024

Task Breakdown and Timeline

Task Start Date End Date Duration

1. Planning and Design Jan 1, 2024 Jan 31, 2024 1 month

1.1 Site Survey Jan 1, 2024 Jan 5, 2024 5 days

1.2 Architectural Design Jan 6, 2024 Jan 20, 2024 2 weeks

1.3 Approval and Permits Jan 21, 2024 Jan 31, 2024 1 week

2. Site Preparation Feb 1, 2024 Feb 10, 2024 1.5 weeks

2.1 Site Clearing Feb 1, 2024 Feb 4, 2024 4 days

2.2 Excavation Feb 5, 2024 Feb 10, 2024 1 week

3. Foundation Work Feb 11, 2024 Mar 10, 2024 1 month

3.1 Foundation Laying Feb 11, 2024 Feb 20, 2024 10 days

3.2 Concrete Pouring and Curing Feb 21, 2024 Mar 10, 2024 2.5 weeks

4. Structure Construction Mar 11, 2024 Apr 30, 2024 1.5 months

4.1 Framing Mar 11, 2024 Mar 25, 2024 2 weeks

4.2 Walls and Roof Mar 26, 2024 Apr 30, 2024 1 month

5. Utilities Installation May 1, 2024 May 31, 2024 1 month

5.1 Electrical and Plumbing May 1, 2024 May 20, 2024 3 weeks

5.2 HVAC Installation May 21, 2024 May 31, 2024 1.5 weeks
Task Start Date End Date Duration

6. Interior and Finishing Jun 1, 2024 Jun 30, 2024 1 month

6.1 Interior Finishing (paint, flooring, etc.) Jun 1, 2024 Jun 20, 2024 3 weeks

6.2 Final Inspection Jun 21, 2024 Jun 30, 2024 1.5 weeks

Gantt Chart Visualization (sample description):

• January: Planning and design stages, including approvals and permits.

• February: Site preparation and starting foundation work.

• March: Completion of foundation and beginning of structure construction (framing and


walls).

• April: Completion of structural work and roofing.

• May: Installation of utilities like electrical, plumbing, and HVAC.

• June: Interior finishing and final inspections to wrap up the project.

You can visualize this using project management software like MS Project, or a simple spreadsheet,
with each task on the left and a timeline on the right representing the time required for each task.