SAP Report 2
SAP Report 2
• Introduction
The July 2012 India blackout was the largest power outage in
history, occurring as two separate events on 30 and 31 July
2012. The outage affected over 620 million people, about 9%
of the world population, or half of India's population, spread
across 22 states in Northern, Eastern, and Northeast India.
An estimated 32 giga watts of generating capacity was taken
offline in the outage.
• Prior disaster-proofing-
• Before the grid collapse, the private sector spent $29 billion
to build their own independent power stations in order to
provide reliable power to their factories. The 5 biggest
consumers of electricity in India have private offgrid supplies.
Indian companies have 35 GW of private off-grid generation
capacity and plan to add another 33 GW to their off-grid
capacity.
• Some villages that were not connected to the grid were not
affected, such as Meerwada, Madhya Pradesh which has a 14
kW solar power station built by US-based firm for $125,000.
• Aging power equipment –
• older equipment have higher failure rates, leading to
customer interruption rates affecting the economy and
society; also, older assets and facilities lead to higher
inspection maintenance costs and further repair/restoration
costs. Hence they need to be changed.
• Obsolete system layout – older areas require serious
additional substation sites and rights-of-way, that cannot be
obtained in current area and are forced to use existing,
insufficient facilities. So amendments need to be made in this
area.
• Outdated engineering – traditional tools for power delivery
planning and engineering are ineffective in addressing
current problems of aged equipment, obsolete system
layouts, and modern deregulated loading levels. So it needs
to be reformed.
SOLUTIONS